VA250-17-B-0970-019.pdf

PDF 10 MB Posted

Attached to
Building 26 Addition
Solicitation number
VA25017B0970
Issued by

About this file

VA250-17-B-0970 2018-04-24_B26_Re-Bid_Specifications.pdf

View the file

Other files

File Type Posted
36C25018C0186-003.docx DOCX document
VA250-17-B-0970-0004001.pdf PDF
VA250-17-B-0970-0004000.docx DOCX document
VA250-17-B-0970-0003001.pdf PDF
VA250-17-B-0970-0003000.docx DOCX document
VA250-17-B-0970-00002000.docx DOCX document
VA250-17-B-0970-00002001.pdf PDF
VA250-17-B-0970-00001000.docx DOCX document
VA250-17-B-0970-00001001.pdf PDF
VA250-17-B-0970-021.pdf PDF
VA250-17-B-0970-020.pdf PDF
VA250-17-B-0970-025.pdf PDF
VA250-17-B-0970-022.pdf PDF
VA250-17-B-0970-016.pdf PDF
VA250-17-B-0970-024.pdf PDF
VA250-17-B-0970-017.pdf PDF
VA250-17-B-0970-018.pdf PDF
VA250-17-B-0970-023.pdf PDF
VA250-17-B-0970-015.docx DOCX document
Show all 19

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CORRECT PRIVACY/SAFETY/ENVIRONMENTAL ISSUES ON BUILDING 26

DEPARTMENT OF VETERANS AFFAIRS, VA MEDICAL CENTER, CHILLICOTHE, OHIO

PROJECT NO. 538-115

00 01 10-1

DEPARTMENT OF VETERANS AFFAIRS

VHA MASTER SPECIFICATIONS

TABLE OF CONTENTS

Section 00 01 10

DIVISION 00 - SPECIAL SECTIONS DATE

00 01 15 List of Drawing Sheets 09-11

DIVISION 01 - GENERAL REQUIREMENTS

01 00 00 General Requirements 01 33 23 Shop Drawings, Product Data, and Samples 01 35 26 Safety Requirements 02-17 01 42 19 Reference Standards 05-16 01 45 29 Testing Laboratory Services 08-17 01 57 19 Temporary Environmental Controls 01-11 01 74 19 Construction Waste Management 09-13 01 81 13 Sustainable Construction Requirements 10-17 01 81 13.21 Sustainable Certification Requirements – Green Globes 09-15 01 91 00 General Commissioning Requirements 10-15

DIVISION 02 – EXISTING CONDITIONS

02 41 00 Demolition 08-17 02 82 11 Traditional Asbestos Abatement 09-15 02 82 13.13 Glovebag Asbestos Abatement 09-15 02 82 13.19 Asbestos Floor Tile and Mastic Abatement 09-15

DIVISION 03 – CONCRETE

03 30 00 Cast-in-Place Concrete 12-15 03 32 13 Stamped Concrete Finishes 03-11

DIVISION 04 – MASONRY

04 05 13 Masonry Mortaring 10-17 04 05 16 Masonry Grouting 02-16 04 20 00 Unit Masonry 08-17 04 26 00 Adhered Masonry Veneer 04 72 00 Cast Stone Masonry 02-15

DIVISION 05 – METALS

05 12 00 Structural Steel Framing 02-16 05 31 00 Steel Decking 02-16 05 36 00 Composite Metal Decking 10-15 05 40 00 Cold-Formed Metal Framing 05-16 05 50 00 Metal Fabrications 07-14

00 01 10-2

DIVISION 06 – WOOD,PLASTICS AND COMPOSITES

06 10 00 Rough Carpentry 10-17 06 16 63 Cementitious Sheathing 02-16 06 61 00 Fiberglass Reinforced Plastic Fabrications

DIVISION 07 - THERMAL AND MOISTURE PROTECTION

07 13 52 Modified Bituminous Sheet Waterproofing 08-16 07 21 13 Thermal Insulation 10-17 07 22 00 Roof and Deck Insulation 02-16 07 32 13 Clay Roof Tiles 02-16 07 53 23 Ethylene-Propylene-Diene-Monomer Roofing 02-16 07 60 00 Flashing and Sheet Metal 07-14 07 71 00 Roof Specialties 10-15 07 81 00 Applied Fireproofing 10-17 07 84 00 Firestopping 02-16 07 92 00 Joint Sealants 10-17 07 95 13 Expansion Joint Cover Assemblies 02-16

DIVISION 08 - OPENINGS

08 11 13 Hollow Metal Doors and Frames 08-16 08 14 00 Interior Wood Doors 02-16 08 31 13 Access Doors and Frames 02-16 08 44 13 Glazed Aluminum Curtain Walls 03-17 08 51 13 Aluminum Windows 02-16 08 71 00 Door Hardware 01-16 08 80 00 Glazing 10-15

DIVISION 09 – FINISHES

09 05 16 Subsurface Preparation for Floor Finishes 02-15 09 06 00 Schedule for Finishes 04-15 09 22 16 Non-Structural Metal Framing 05-16 09 24 00 Portland Cement Plastering 10-15 09 29 00 Gypsum Board 11-14 09 30 13 Ceramic/Porcelain Tiling 10-15 09 51 00 Acoustical Ceilings 12-16 09 65 13 Resilient Base and Accessories 02-16 09 65 43 Linoleum Sheet Flooring 09 68 00 Carpeting 10-15 09 91 00 Painting 01-16 09 91 45 Intumescent Coatings

DIVISION 10 – SPECIALTIES

10 11 13 Markerboards 10-15 10 11 23 Tackboards 10-15 10 21 16 Shower Compartments 08-16 10 21 23 Cubicle Curtain Tracks 05-15

00 01 10-3

10 28 00 Toilet, Bath, and Laundry Accessories 02-16 10 44 13 Fire Extinguisher Cabinets 08-14

DIVISION 12 – FURNISHINGS

12 24 00 Window Shades 08-17 12 32 00 Manufactured Plastic Laminate Casework 09-15 12 36 00 Countertops 12-15

DIVISION 14– CONVEYING EQUIPMENT

14 42 00 Vertical Platform Lift

DIVISION 21- FIRE SUPPRESSION

21 08 00 Commissioning of Fire Suppression System 11-16 21 13 13 Wet-Pipe Sprinkler Systems 06-15

DIVISION 22 – PLUMBING

22 05 11 Common Work Results for Plumbing 07-16 22 05 12 General Motor Requirements for Plumbing 09-15 22 05 19 Meters and Gages for Plumbing Piping 09-15 22 05 23 General-Duty Valves for Plumbing Piping 09-15 22 07 11 Plumbing Insulation 09-15 22 08 00 Commissioning of Plumbing Systems 11-16 22 11 00 Facility Water Distribution 09-15 22 11 23 Domestic Water Pumps 09-15 22 13 00 Facility Sanitary and Vent Piping 09-15 22 14 00 Facility Storm Drainage 09-15 22 35 00 Domestic Water Heat Exchangers 12-16 22 40 00 Plumbing Fixtures 09-15

DIVISION 23 – HEATING, VENTILATING, AND AIR

CONDITIONING (HVAC)

23 05 11 Common Work Results for HVAC 08-17 23 05 12 General Motor Requirements for HVAC and Steam

Generation Equipment 08-17

23 05 41 Noise and Vibration Control for HVAC Piping and Equipment

02-15

23 05 93 Testing, Adjusting, and Balancing for HVAC 02-15 23 07 11 HVAC and Boiler Plant Insulation 02-15 23 08 00 Commissioning of HVAC Systems 11-16 23 09 23 Direct-Digital Control System for HVAC 09-11 23 21 13 Hydronic Piping 08-17 23 21 23 Hydronic Pumps 08-17 23 22 13 Steam and Condensate Heating Piping 08-17 23 22 23 Steam Condensate Pumps 08-17 23 25 00 HVAC Water Treatment 02-15 23 31 00 HVAC Ducts and Casings 03-13

00 01 10-4

23 34 00 HVAC Fans 02-15 23 36 00 Air Terminal Units 02-15 23 37 00 Air Outlets and Inlets 02-15 23 40 00 HVAC Air Cleaning Devices 02-12 23 73 00 Indoor Central-Station Air-Handling Units 04-11 23 82 16 Air Coils 04-11

DIVISION 26 – ELECTRICAL

26 05 11 Requirements for Electrical Installations 01-16 26 05 19 Low-Voltage Electrical Power Conductors and Cables 01-17 26 05 26 Grounding and Bonding for Electrical Systems 01-17 26 05 33 Raceway and Boxes for Electrical Systems 01-18 26 05 41 Underground Electrical Construction 01-17 26 08 00 Commissioning of Electrical Systems 11-16 26 09 23 Lighting Controls 01-18 26 24 16 Panelboards 01-18 26 27 26 Wiring Devices 01-18 26 29 11 Motor Controllers 01-18 26 29 21 Enclosed Switches and Circuit Breakers 01-17 26 36 23 Automatic Transfer Switches 01-17 26 41 00 Facility Lightning Protection 01-17 26 43 13 Surge Protective Device 01-17 26 51 00 Interior Lighting 01-18 26 56 00 Exterior Lighting 01-18

DIVISION 27 – COMMUNICATIONS

27 05 11 Requirements for Communications Installations 06-15 27 05 26 Grounding and Bonding for Communications Systems 06-15 27 05 33 Raceways and Boxes for Communications Systems 06-15 27 08 00 Commissioning of Communications Systems 11-16 27 10 00 Control Communication and Signal Wiring 06-15 27 11 00 Telecommunications Room Fittings 06-15 27 15 00 Communications Structured Cabling 01-16 27 41 31 Master Antenna Television Equipment and Systems 06-15 27 51 23 Intercommunications and Program Systems 27 52 23 Nurse Call and Code Blue Systems 10-15

DIVISION 28 – ELECTRONIC SAFETY AND SECURITY

28 05 00 Common Work Results for Electronic Safety and Security 09-11 28 05 13 Conductors and Cables for Electronic Safety and

Security 09-11

28 05 26 Grounding and Bonding for Electronic Safety and Security

09-11

28 05 28.33 Conduits and Backboxes for Electronic Safety and Security

09-11

28 08 00 Commissioning of Electronic Safety and Security Systems 11-16 28 13 00 Physical Access Control System 10-11 28 13 16 Physical Access Control System and Database Management 09-11 28 23 00 Video Surveillance 09-11

00 01 10-5

28 31 00 Fire Detection and Alarm 10-11

DIVISION 31 – EARTHWORK

31 20 00 Earthwork 07-16

DIVISION 32 – EXTERIOR IMPROVEMENTS

32 05 23 Cement and Concrete for Exterior Improvements 08-16 32 90 00 Planting 07-16

DIVISION 33 – UTILITIES

33 40 00 Storm Sewer Utilities 12-17 33 46 13 Foundation Drainage 10-11

APPENDIX – ADDITIONAL INFORMATION

Subsurface Exploration Report Hazardous Material Assessment Report

TASK ORDER NO. 538-115

09-11

00 01 15 - 1

SECTION 00 01 15

LIST OF DRAWING SHEETS

The drawings listed below accompanying this specification form a part of the contract.

Drawing No. Title

GI001 TITLE PAGE

HAZARDOUS MATERIALS

HM101 HAZARDOUS MATERIALS ABATEMENT PLAN

HM102 HAZARDOUS MATERIALS ABATEMENT PLAN

HM103 HAZARDOUS MATERIALS ABATEMENT PLAN

SITE PLANNING

CD101 EXISTING CONDITIONS AND DEMOLITION PLAN

CG101 STORM & GRADING PLAN

CS101 SITE & UTILITY PLAN

STRUCTURAL

SS001 GENERAL STRUCTURAL INFORMATION

SS101 FOUNDATION PLAN

SS201 FOUNDATION DETAILS

SS301 FIRST FLOOR FRAMING PLAN

SS302 ROOF FRAMING PLAN

SS401 COLUMN SCHEDULE & STRUCT. DETAILS

SS501 STRUCTURAL DETAILS

SS502 STRUCTURAL DETAILS

SS503 STRUCTURAL DETAILS

ARCHITECTURAL

AS000 LEGEND

ASL01 LIFE SAFETY PLAN - BASEMENT

ASL02 LIFE SAFETY PLAN - FIRST FLOOR

ASL03 LIFE SAFETY PLAN - SECOND FLOOR

TASK ORDER NO. 538-115

09-11

00 01 15 - 2

AD01 DEMOLITION FLOOR PLAN - BASEMENT

AD02 DEMOLITION FLOOR PLAN - FIRST FLOOR

AD03 DEMOLITION CEILING PLAN - FIRST FLOOR

AS101 OVERALL FLOOR PLAN - BASEMENT

AS102 OVERALL FLOOR PLAN - FIRST FLOOR

AS103 OVERALL FLOOR PLAN - SECOND FLOOR AND ROOF

AS104 OVERALL FLOOR PLAN - PENTHOUSE AND ROOF

AS105 PARTIAL FLOOR PLAN - FIRST FLOOR AREA A

AS106 PARTIAL CEILING PLAN - FIRST FLOOR AREA A

AS107 PARTIAL FLOOR PLAN - FIRST FLOOR AREA B

AS108 PARTIAL CEILING PLAN - FIRST FLOOR AREA B

AS109 PARTIAL FLOOR PLAN - FIRST FLOOR AREA C

AS110 PARTIAL CEILING PLAN - FIRST FLOOR AREA C

AS111 PARTIAL FLOOR PLAN - FIRST FLOOR AREA D

AS112 PARTIAL CEILING PLAN - FIRST FLOOR AREA D

AS201 EXTERIOR ELEVATIONS

AS202 EXTERIOR ELEVATIONS

AS203 EXTERIOR ELEVATIONS

AS301 BUILDING SECTIONS

AS302 WALL SECTIONS

AS303 WINDOW SCHEDULE

AS304 EXTERIOR DETAILS

AS305 EXTERIOR DETAILS

AS400 TYPICAL DOOR SCHEDULE/DETAILS

AS401 BORROWED LIGHT DETAILS

AS402 ENLARGED TOILET ROOMS

AS403 ENLARGED PATIENT TOILETS - TYPE 1A AND 1B

AS404 ENLARGED PATIENT TOILETS - TYPE 1C AND 1D

AS405 ENLARGED PATIENT ROOM - TYPE 'A'

AS406 ENLARGED PATIENT ROOM - TYPE 'B'

AS407 ENLARGED PATIENT ROOM - SEM-PRIVATE

AS408 ENLARGED PATIENT ROOM - ISOLATION

AS409 ENLARGED NURSE STATION

AS410 ENLARGED NURSE STATION

AS411 ENLARGED NURSE STATION

AS412 ENLARGED NURSE STATION

AS413 ENLARGED EXAM ROOM

AS414 ENLARGED INTAKE ROOM

AS500 CASEWORK DETAILS

TASK ORDER NO. 538-115

09-11

00 01 15 - 3

AS500A CASEWORK DETAILS

AS501 INTERIOR ELEVATIONS

AS502 INTERIOR ELEVATIONS

AS503 INTERIOR ELEVATIONS

AS504 INTERIOR ELEVATIONS

AS505 INTERIOR ELEVATIONS

AS600 ROOM FINISH SCHEDULE

AS601 TYPICAL MOUNTING HEIGHTS

AS602 INTERIOR DETAILS

AS603 INTERIOR DETAILS

AS604 INTERIOR DETAILS

AS701 PARTIAL FLOOR FINISH PLAN - FIRST FLOOR AREA A

AS702 PARTIAL FLOOR FINISH PLAN - FIRST FLOOR AREA B

AS703 PARTIAL FLOOR FINISH PLAN - FIRST FLOOR AREA C

AS704 PARTIAL FLOOR FINISH PLAN - FIRST FLOOR AREA D

AS705 SIGNAGE SCHEDULE AND FINISH MATERIAL DETAILS

AS800 OVERALL FIRST FLOOR PLAN – ALTERNATES

AS801 ENLARGED PLANS AND DETAILS – ALTERNATES.

FIRE PROTECTION

FX000 FIRE PROTECTION LEGENDS AND DETAILS

FX100 BASEMENT FIRE PROTECTION PLAN

FX101 FIRST FLOOR FIRE PROTECTION PLAN

PLUMBING

P000 PLUMBING LEGENDS AND SCHEDULES

PD000 BASEMENT MED GAS DEMO PLAN

PD001 FIRST FLOOR MED GAS DEMO PLAN

PD100 BASEMENT PLUMBING DEMO PLAN

PD101 FIRST FLOOR PLUMBING DEMO PLAN

PL200 BASEMENT PLUMBING PLAN

PL201 FIRST FLOOR PLUMBING PLAN

PL202 SECOND FLOOR PLUMBING PLAN

PL501 PLUMBING DETAILS AND STACKS

PL502 PLUMBING DETAILS AND STACKS

TASK ORDER NO. 538-115

09-11

00 01 15 - 4

HEATING, VENTILATING, AIR

CONDITIONING AND REFRIGERATION

M000 HVAC LEGENDS & ABBREVIATIONS

MD100 BASEMENT HVAC DEMO PLAN

MD101 FIRST FLOOR HVAC DEMO PLAN

MD102 ATTIC HVAC DEMO PLAN

MH100 BASEMENT HVAC DUCTWORK PLAN

MH101 FIRST FLOOR HVAC DUCTWORK PLAN

MH102 SECOND FLOOR HVAC DUCTWORK PLAN

MH103 ATTIC HVAC DUCTWORK PLAN

MH200 BASEMENT HVAC PIPING PLAN

MH201 FIRST FLOOR HVAC PIPING PLAN

MH202 SECOND FLOOR HVAC PIPING PLAN

MH300 ENLARGED MECHANICA ROOM PLAN

MH500 HVAC DETAILS

MH501 HVAC HYDRONIC SCHEMATIC

MH600 HVAC SCHEDULES

MI101 HVAC CONTROLS (26-AHU3)E

MI102 HVAC CONTROLS 26-AHU5

MI103 HVAC CONTROLS CENTRAL PLANT

MI104 HVAC CONTROLS AIR TERMINAL UNITS

MI105 HVAC CONTROLS DDC NETWORK LAYOUT

ELECTRICAL

E000 ELECTRICAL LEGEND

E001 ELECTRICAL DETAILS

ED100 BASEMENT ELEC DEMO PLAN

ED101 FIRST FLOOR ELEC DEMO PLAN

ED102 SECOND FLOOR ELEC DEMO PLAN

ED103 ATTIC ELEC DEMO PLAN

EL100 BASEMENT LIGHTING PLAN

EL101 FIRST FLOOR LIGHTING PLAN

EP100 BASEMENT POWER PLAN

EP101 FIRST FLOOR POWER PLAN

EP101A FIRST FLOOR POWER CONDUIT PLAN

EP102 SECOND FLOOR POWER PLAN

EP103 ATTIC POWER PLAN

TASK ORDER NO. 538-115

09-11

00 01 15 - 5

EP501 ELECTRICAL SINGLE-LINE

EP601 ELECTRICAL PANEL SCHEDULES

TECHNOLOGY

T000 TECHNOLOGY LEGEND, ABBREVIATIONS, AND FACE PLATE

DETAILS

T001 TECHNOLOGY DETAILS

TD100 BASEMENT TECHNOLOGY DEMO PLAN

TD101 FIRST FLOOR TECHNOLOGY DEMO PLAN

TD102 SECOND FLOOR TECHNOLOGY DEMO PLAN

TD103 ATTIC TECHNOLOGY DEMO PLAN

T100 BASEMENT TECHNOLOGY PLAN

T101 FIRST FLOOR TECHNOLOGY PLAN

T102 SECOND FLOOR TECHNOLOGY PLAN

T103 ATTIC TECHNOLOGY PLAN

T201 ENLARGED TECHNOLOGY ROOM

T301 TECHNOLOGY AND SECURITY DETAILS

T302 VIDEO DETAILS

T303 SITE FIBER DETAILS

- - - END - - -

01 00 00 - 1

SECTION 01 00 00

GENERAL REQUIREMENTS

TABLE OF CONTENTS

1.01 SAFETY REQUIREMENTS

1.02 GENERAL INTENTION

1.03 STATEMENT OF BID ITEM(S)

1.04 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR

1.05 CONSTRUCTION SECURITY REQUIREMENTS

1.06 OPERATIONS AND STORAGE AREAS

1.07 ALTERATIONS

1.08 DISPOSAL AND RETENTION

1.09 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES,

AND IMPROVEMENTS

1.10 RESTORATION

1.11 PHYSICAL DATA

1.12 PROFESSIONAL SURVEYING SERVICES

1.13 LAYOUT OF WORK

1.14 AS-BUILT DRAWINGS

1.15 USE OF ROADWAYS

1.16 NOT APPLICABLE

1.17 TEMPORARY USE OF MECHANICAL AND ELECTRICAL EQUIPMENT

1.18 NOT APPLICABLE

1.19 NOT APPLICABLE

1.20 TEMPORARY TOILETS

1.21 AVAILABILITY AND USE OF UTILITY SERVICES

1.22 NOT APPLICABLE

1.23 TESTS

1.24 INSTRUCTIONS

1.25 NOT APPLICABLE

1.26 RELOCATED EQUIPMENT ITEMS

1.27 NOT APPLICABLE

1.28 NOT APPLICABLE

1.29 NOT APPLICABLE

1.30 NOT APPLICABLE

1.31 HISTORIC PRESERVATION

1.32 NOT APPLICABLE

01 00 00 - 2

01 00 00 - 3

PART 1 - GENERAL

1.01 SAFETY REQUIREMENTS

Refer to section 01 35 26, SAFETY REQUIREMENTS for safety and infection control requirements.

1.02 GENERAL INTENTION

A. Contractor shall completely prepare site for building operations, including demolition and removal of existing structures, and furnish labor and materials and perform work for PROJECT 538-115, Correct Privacy/Safety/Environmental issues on Building 26 at VAMC Chillicothe, Ohio as required by drawings and specifications.

B. Visits to the site by Bidders will be as outlined in the solicitation.

C. Offices of Dynamix Engineering Ltd., Columbus, Ohio, as Architect- Engineers, will render certain technical services during construction. Such services shall be considered as advisory to the Government and shall not be construed as expressing or implying a contractual act of the Government without affirmations by Contracting Officer or his duly authorized representative.

D. All employees of the general contractor and subcontractors shall adhere to the Chillicothe VAMC contractor identification process and obtain VA issued badges. All employees of general contractor and subcontractors shall comply with VA security management program , be identified by project and employer, and restricted from unauthorized access.

E. REQUEST FOR INFORMATION

In the event an explanation or interpretation of the drawings or specifications is necessary, submit the request using RFI (Request for Information) Form included in the EXHIBITS SECTION of the solicitation.

Such requests shall be submitted to the Contracting Officer soon enough to allow a reply so as to affect the project schedule as little as possible.

1.03 STATEMENT OF BID ITEM(S)

A. See Block 10, Standard Form (SF) 1442, and any continuation thereto, for a detailed list of Bid Items.

1.04 Alternate Descriptions

A. Alternate #1: DELETE all labor and materials associated with

Renovations to the North Side of the Center Wing, the current dining area consisting of rooms: Kitchenette 135, Patient Dining Room 134 and

Toilet 136. Existing rooms are to remain, no architectural renovation work to take place. See AS800 and AS801 for additional details. Existing fan coil units to be connected to the new distribution piping. Existing ventilation air ductwork to be connected to the new supply air ductwork through a 600cfm VAV box with a 2-row, 19MBH coil and connected to the

BAS system. Additional MEPT systems shall remain in place and be fed from new distribution systems. Plumbing: All piping passing through the existing space to serve other areas of work not serviced by existing

01 00 00 - 4 piping shall be installed as indicated on the contract documents. Refer to drawings for additional information.

B. Alternate #2: DELETE all labor and materials associated with Shell space in new addition, contractor shall Shell Visitor Room 136, Shared Work

Room 133 and Storage 133A,(eliminate wall between Visitor 136 and Shared

Work Room 133), Patient Room 111, and Patient Toilet 111A, Patient Room

109 and Patient Toilet 109A,Patient Room 108 and Patient Toilet

108A,Patient Room 107 and Patient Toilet 107A, Patient Room 167 and

Patient Toilet 167A, Patient Room 168 and Patient Toilet 168A,Patient

Room 169 and Patient Toilet 169A,Patient Room 170 and Patient Toilet

170A, and Toilet 162. Install doors 109 and 167, including frame and associated hardware. Shelled space shall consist of a completely enclosed exterior shell, but the interior shall remain unfinished. Arch:

For shelled spaces, do not provide gypsum wallboard or acoustical insulation. See Drawing AS800 and AS801 for additional information.

HVAC: For shelled spaces where the VAV terminal unit is located within the shelled space, the VAV shall be installed along with the associated ductwork and piping and accessories up to the VAV. Low pressure ductwork and associated air devices will not be installed. For shelled spaces where the space is served from a VAV installed in a non-shelled space, low pressure ductwork shall be extended into the shelled space a minimum of 4’ and left open to the space. All ductwork and piping passing through the space to serve other non-shelled spaces shall be installed as indicated on the contract documents. Electrical: Provide 20 chain hung 2 lamp industrial fixtures distributed per the COR’s direction throughout the shell spaces. Wire to the same circuits indicated on new work plans and provide one light switch for each room.

See plans for additional information. Plumbing: For shelled spaces where the plumbing fixtures were located, piping serving the fixtures will be stubbed up through the floor with shut-off valves at all branches from domestic water mains. All piping passing through the space to serve other non-shelled spaces shall be installed as indicated on the contract documents. Eliminate wall between Patient Room 164 and Quiet Room 165.

Eliminate door 165 and associated hardware and frame. Continue ceiling from Patient Room 164 into Quiet Room 165. Refer to drawings for additional information.

C. Alternate #3: DELETE all labor and materials associated with Renovations on the North side of the West wing, Rooms 118,118A, 119, 120, 121, 122, 122A, 123, 124, and associated corridor. Existing rooms

01 00 00 - 5 are to remain, no architectural renovation work to take place. Existing fan coil units to be connected to the new distribution piping. Existing ventilation air ductwork to be connected to the new supply air ductwork through a new 700cfm VAV box with a 2-row, 22MBH coil and connected to the BAS system. Additional MEPT systems shall remain in place and be fed from new distribution systems. Refer to Drawings for additional information. Tub/Laundry Room 117 to be demoed, but not fully rebuilt in this alternate. See Drawing AS800 and AS801 for further information.

Plumbing: All piping passing through the existing space to serve other areas of work not serviced by existing piping shall be installed as indicated on the contract documents.

D. Alternate #4: DELETE all labors and materials associated with Renovations on the North Side of the East Wing, Rooms 139,139A, 140, 141, 142, 143, 143A, 144, 145 and associated corridor. Existing rooms are to remain, no architectural renovation work to take place. Existing fan coil units to be connected to the new distribution piping. Existing ventilation air ductwork to be connected to the new supply air ductwork through a new 700cfm VAV box with a 2-row, 22MBH coil and connected to the BAS system. Additional MEPT systems shall remain in place and be fed from new distribution systems. Refer to plans for additional information. Rooms 147 and 146 are to be demoed, but not fully rebuilt in this alternate. Refer to Drawing AS800 and AS801 for further information. Plumbing: All piping passing through the existing space to serve other areas of work not serviced by existing piping shall be installed as indicated on the contract documents.

1.05 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR

Drawings and contract documents may be obtained from the website where the solicitation is posted. Additional copies will be at Contractor's expense.

1.06 CONSTRUCTION SECURITY REQUIREMENTS

A. Security Plan:

1. The security plan defines both physical and administrative security procedures that will remain effective for the entire duration of the project.

2. The General Contractor is responsible for assuring that all sub-contractors working on the project and their employees also comply with these regulations.

B. Security Procedures:

1. General Contractor’s employees shall not enter the project site without appropriate badge. They may also be subject to inspection of their personal effects when entering or leaving the project site.

01 00 00 - 6

2. No photography of VA premises is allowed without written permission of the Contracting Officer.

3. VA reserves the right to close down or shut down the project site and order General Contractor’s employees off the premises in the event of a national emergency. The General Contractor may return to the site only with the written approval of the Contracting Officer.

C. Not Applicable

D. Key Control:

1. Any keys necessary to gain entry to work areas or other spaces associated with performing work will be issued to the Contractor's representative on a daily basis. Keys will be signed out after 7:30 a.m.

and returned before 4:00 p.m. from the Engineering Office, Building 21, each day when necessary to gain access. Failure to return any issued keys may result in a charge to include costs to re-key areas associated with the keys involved.

2. The General Contractor shall provide duplicate keys and lock combinations to the Contracting officers representative (COR)for the purpose of security inspections of every area of project including tool boxes and parked machines and take any emergency action.

3. See Section 08 71 00, DOOR HARDWARE for permanent lock cylinder requirements.

E. Not Applicable :

F. Motor Vehicle Restrictions

Reference Chillicothe VAMC Policy Memorandum No. 07-29, Parking and Motor Vehicle Operations, and Designated Parking for Contractors and Contractor Employees exhibits.

1.07 OPERATIONS AND STORAGE AREAS

The following paragraphs are in addition to (FAR 52.236-10)

A. The Contractor shall confine all operations (including storage of materials) on Government premises to areas authorized or approved by the Contracting Officer. The Contractor shall hold and save the Government, its officers and agents, free and harmless from liability of any nature occasioned by the Contractor's performance.

B. Temporary buildings (e.g., storage sheds, shops, offices) and utilities may be erected by the Contractor only with the approval of the Contracting Officer and shall be built with labor and materials furnished by the Contractor without expense to the Government. The temporary buildings and utilities shall remain the property of the Contractor and shall be removed by the Contractor at its expense upon completion of the work.

C. The Contractor shall, under regulations prescribed by the Contracting Officer, use only established roadways, or use temporary roadways constructed by the Contractor when and as authorized by the Contracting Officer. When materials are transported in prosecuting the work, vehicles shall not be loaded beyond the loading capacity recommended by the manufacturer of the vehicle or prescribed by any Federal, State, or local law or regulation. When it is necessary to cross curbs or sidewalks, the

01 00 00 - 7

Contractor shall protect them from damage. The Contractor shall repair or pay for the repair of any damaged curbs, sidewalks, roads , or lawn areas .

D. Working space and space available for storing materials shall be as shown on the drawings , and as determined by the COR .

E. Workmen are subject to rules of Medical Center applicable to their conduct.

F. Execute work so as to interfere as little as possible with normal functioning of Medical Center as a whole, including operations of utility services, fire protection systems and any existing equipment, and with work being done by others. Use of equipment and tools that transmit vibrations and noises through the building structure, are not permitted in buildings that are occupied, during construction, jointly by patients or medical personnel, and Contractor's personnel, except as permitted by COR where required by limited working space.

1. Do not store materials and equipment in other than assigned areas.

2. Schedule delivery of materials and equipment to immediate construction working areas within buildings in use by Department of Veterans Affairs in quantities sufficient for not more than two work days. Provide unobstructed access to Medical Center areas required to remain in operation.

3. Where access by Medical Center personnel to vacated portions of buildings is not required, storage of Contractor's materials and equipment will be permitted subject to fire and safety requirements, and approval of the COR.

G. Phasing:

The Medical Center intends to fully vacate B26 during construction;

however, it is anticipated that the building will still be partially occupied when Notice to Proceed is issued. Notice to Proceed for this project will be issued with the following limitations:

• The contractor shall not be provided full access to the building until 60 days after issuance of the Notice to Proceed, during which time the Medical Center will complete evacuation of remaining occupants from the building.

• The contractor shall not commence with any construction activities, including mobilization, during this 60 day interim.

• The contractor is encouraged during this time to prepare and provide technical submittals, construction phasing plans, the schedule of values, construction schedules, safety plans, the commissioning plan, and all other relevant plans, schedules and submittals.

• The contractor will be provided, if requested, limited access during this time solely for the purpose of verifying existing conditions and taking measurements. Any access during this time, which will be limited, must be coordinated through the COR.

• At its sole discretion, the Medical Center may lift the restriction on full and complete access prior to the end of the 60

01 00 00 - 8 day period if the building is completely vacated of occupants at an earlier date.

The Medical Center must maintain its operation 24 hours a day 7 days a week. Therefore, any interruption in service must be scheduled and coordinated with the COR to ensure that no lapses in operation occur. It is the CONTRACTOR'S responsibility to develop a work plan and schedule detailing, at a minimum, the procedures to be employed, the equipment and materials to be used, the interim life safety measure to be used during the work, and a schedule defining the duration of the work with milestone subtasks.

To insure such executions, Contractor shall furnish the COR with a schedule of approximate phasing dates on which the Contractor intends to accomplish work in each specific area of site, building or portion thereof. In addition, Contractor shall notify the COR two weeks in advance of the proposed date of starting work in each specific area of site, building or portion thereof. Arrange such phasing dates to insure accomplishment of this work in successive phases mutually agreeable to COR and Contractor.

H. All building areas adjacent to this project will be occupied during performance of work.

Contractor shall take all measures and provide all material necessary for protecting existing equipment and property in affected areas of construction against dust and debris, so that equipment and affected areas to be used in the Medical Centers operations will not be hindered.

Contractor shall permit access to Department of Veterans Affairs personnel and patients through other construction areas which serve as routes of access to such affected areas and equipment. These routes whether access or egress shall be isolated from the construction area by temporary partitions and have walking surfaces, lighting etc to facilitate patient and staff access. Coordinate alteration work in areas occupied by Department of Veterans Affairs so that Medical Center operations will continue during the construction period. This may include evening or weekend work.

I. Construction Fence: Before construction operations begin, Contractor shall provide a chain link construction fence, six feet minimum height, around the construction area indicated on the drawings. Provide gates as required for access with necessary hardware, including hasps and padlocks.

Fasten fence fabric to terminal posts with tension bands and to line posts and top and bottom rails with tie wires spaced at maximum 375mm (15 inches). Bottom of fences shall extend to 25mm (one inch) above grade.

Details of fence construction and finish thereof shall be submitted to COR for approval. Remove the fence when directed by COR .

J. When a building and/or construction site is turned over to Contractor, Contractor shall accept entire responsibility including upkeep and maintenance therefore:

1. Contractor shall maintain a minimum temperature of 4 degrees C (40 degrees F) at all times, except as otherwise specified.

2. Contractor shall maintain in operating condition existing fire protection and alarm equipment. In connection with fire alarm equipment, 01 00 00 - 9

Contractor shall make arrangements for pre inspection of site with Chillicothe VAMC Fire Department required to respond to an alarm from Contractor's employee or watchman.

K. Utilities Services: Maintain existing utility services for Medical Center at all times. Provide temporary facilities, labor, materials, equipment, connections, and utilities to assure uninterrupted services. Where necessary to cut existing water, steam, gases, sewer or air pipes, or conduits, wires, cables, etc. of utility services or of fire protection systems and communications systems (including telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by COR .

1. No utility service such as water, gas, steam, sewers or electricity, or fire protection systems and communications systems may be interrupted without prior approval of COR . Electrical work shall be accomplished with all affected circuits or equipment de-energized. When an electrical outage cannot be accomplished, work on any energized circuits or equipment shall not commence without a detailed work plan, the Medical Center Director’s prior knowledge and written approval. Refer to specification Sections 26 05

11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS, 27 05 11 REQUIREMENTS FOR

COMMUNICATIONS INSTALLATIONS and 28 05 00, COMMON WORK RESULTS FOR ELECTRONIC SAFETY AND SECURITY for additional requirements.

2. Contractor shall submit a request to interrupt any such services to COR , in writing, 7 days in advance of proposed interruption. Request shall state reason, date, exact time of, and approximate duration of such interruption.

3. Contractor will be advised (in writing) of approval of request, or of which other date and/or time such interruption will cause least inconvenience to operations of Medical Center . Interruption time approved by Medical Center may occur at other than Contractor's normal working hours.

4. Major interruptions of any system must be requested, in writing, at least 15 calendar days prior to the desired time and shall be performed as directed by the COR .

5. In case of a contract construction emergency, service will be interrupted on approval of COR . Such approval will be confirmed in writing as soon as practical.

6. Access to Data Rooms requires escorts at all times. Access requests must be requested in writing a minimum of 7 days in advance of the proposed dates of work. Requests shall state reason, date, exact time of, and approximate duration of such work activity.

L. Abandoned Lines: All service lines such as wires, cables, conduits, ducts, pipes and the like, and their hangers or supports, which are to be abandoned but are not required to be entirely removed, shall be sealed, capped or plugged at the main, branch or panel they originate from. The lines shall not be capped in finished areas, but shall be removed and sealed, capped or plugged in ceilings, within furred spaces, in unfinished areas, or within walls or partitions; so that they are completely behind the finished surfaces.

01 00 00 - 10

M. To minimize interference of construction activities with flow of Medical Center traffic, comply with the following:

1. Keep roads, walks and entrances to grounds, to parking and to occupied areas of buildings clear of construction materials, debris and standing construction equipment and vehicles. Wherever excavation for new utility lines cross existing roads, at least one lane must be open to traffic at all times with approval.

2. Method and scheduling of required cutting, altering and removal of existing roads, walks and entrances must be approved by the COR .

N. Coordinate the work for this contract with other construction operations as directed by COR . This includes the scheduling of traffic and the use of roadways, as specified in Article, USE OF ROADWAYS.

O. Not Applicable

P. Hours of Work:

1. The work of this contract is to be executed between 7:30 a.m. and 4:00 p.m., Monday through Friday, except as required by the specifications and/or otherwise authorized by the COR. Submit in writing to the COR requests for proposed hours of work changes

2. Hours of work may vary depending on the area of work being performed.

Work in occupied spaces shall be scheduled at times convenient to the occupant and the Medical Center. Areas adjacent to the work area include urgent care which is open 24 hours, 7 days a week. No work will be performed on Government recognized holidays, except as required by the specifications and/or otherwise authorized by the COR.

3. Hot work shall stop prior to the specified end of work day at a minimum equal to the time required for final inspection.

1.08 ALTERATIONS

A. Survey: Before any work is started, the Contractor shall make a thorough survey with the COR and a representative of VA Acquisition and Material Management Service , of areas of buildings in which alterations occur and areas which are anticipated routes of access, and furnish a report, signed by all three, to the Contracting Officer. This report shall list by rooms and spaces:

1. Existing condition and types of resilient flooring, doors, windows, walls and other surfaces not required to be altered throughout affected areas of buildings.

2. Existence and conditions of items such as plumbing fixtures and accessories, electrical fixtures, equipment, venetian blinds, shades, etc., required by drawings to be either reused or relocated, or both.

3. Shall note any discrepancies between drawings and existing conditions at site.

4. Shall designate areas for working space, materials storage and routes of access to areas within buildings where alterations occur and which have been agreed upon by Contractor COR .

B. Any items required by drawings to be either reused or relocated or both, found during this survey to be nonexistent, or in opinion of COR and

01 00 00 - 11

Acquisition and Material Management Service Representative , to be in such condition that their use is impossible or impractical, shall be furnished and/or replaced by Contractor with new items in accordance with specifications which will be furnished by Government. Provided the contract work is changed by reason of this subparagraph B, the contract will be modified accordingly, under provisions of clause entitled "DIFFERING SITE CONDITIONS" (FAR 52.236-2) and "CHANGES" (FAR 52.243-4 and VAAR 852.236- 88).

C. Re-Survey: Thirty days before expected partial or final inspection date, the Contractor and COR together shall make a thorough re-survey of the areas of buildings involved. They shall furnish a report on conditions then existing, of resilient flooring, doors, windows, walls and other surfaces as compared with conditions of same as noted in first condition survey report:

Re-survey report shall also list any damage caused by Contractor to such flooring and other surfaces, despite protection measures; and, will form basis for determining extent of repair work required of Contractor to restore damage caused by Contractor's workmen in executing work of this contract.

D. Protection: Provide the following protective measures:

1. Wherever existing roof surfaces are disturbed they shall be protected against water infiltration. In case of leaks, they shall be repaired immediately upon discovery.

2. Temporary protection against damage for portions of existing structures and grounds where work is to be done, materials handled and equipment moved and/or relocated.

3. Protection of interior of existing structures at all times, from damage, dust and weather inclemency. Wherever work is performed, floor surfaces that are to remain in place shall be adequately protected prior to starting work, and this protection shall be maintained intact until all work in the area is completed.

4. Dampen debris to keep down dust.

5. Provide temporary construction partitions as described in Specification Section 01 35 26 paragraph Temporary Construction Partitions.

6. Block off ducts and diffusers to prevent circulation of dust into occupied areas during construction. Coordinate with COR.

7. See Specification Section 01 35 26 paragraph Infection Control for additional required measures.

1.09 DISPOSAL AND RETENTION

A. Materials and equipment accruing from work removed and from demolition of buildings or structures, or parts thereof, shall be disposed of as follows:

1. Reserved items which are to remain property of the Government are noted on drawings or in specifications as items to be stored. Items that remain property of the Government shall be removed or dislodged from present

01 00 00 - 12 locations in such a manner as to prevent damage which would be detrimental to re installation and reuse. The contractor shall secure and store the items until reinstallation. .

2. Items not reserved shall become property of the Contractor and be removed by Contractor from Medical Center .

3. Items of portable equipment and furnishings located in rooms and spaces in which work is to be done under this contract shall remain the property of the Government. When rooms and spaces are vacated by the Department of Veterans Affairs during the alteration period, such items which are NOT required by drawings and specifications to be relocated, reused, or demolished will be removed by the Government in advance of work to avoid interfering with Contractor's operation.

4. Not Applicable

1.10 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES, AND

IMPROVEMENTS

The following paragraph is in addition to FAR 52.236-9 Clause PROTECTION OF

EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES, AND IMPROVEMENTS

A. The Contractor shall preserve and protect all structures, equipment, and vegetation (such as trees, shrubs, and grass) on or adjacent to the work site, which are not to be removed and which do not unreasonably interfere with the work required under this contract. The Contractor shall only remove trees when specifically authorized to do so, and shall avoid damaging vegetation that will remain in place. If any limbs or branches of trees are broken during contract performance, or by the careless operation of equipment, or by workmen, the Contractor shall trim those limbs or branches with a clean cut and paint the cut with a tree-pruning compound as directed by the Contracting Officer.

B. The Contractor shall protect from damage all existing improvements and utilities at or near the work site and on adjacent property of a third party, the locations of which are made known to or should be known by the Contractor. The Contractor shall repair any damage to those facilities, including those that are the property of a third party, resulting from failure to comply with the requirements of this contract or failure to exercise reasonable care in performing the work. If the Contractor fails or refuses to repair the damage promptly, the Contracting Officer may have the necessary work performed and charge the cost to the Contractor.

C. Refer to Section 01 57 19, TEMPORARY ENVIRONMENTAL CONTROLS, for additional requirements on protecting vegetation, soils and the environment. Refer to Articles, "Alterations", "Restoration", and "Operations and Storage Areas" for additional instructions concerning repair of damage to structures and site improvements.

D. Not Applicable

1.11 RESTORATION

A. Remove, cut, alter, replace, patch and repair existing work as necessary to install new work. Except as otherwise shown or specified, do not cut, alter or remove any structural work, and do not disturb any ducts, plumbing, steam, gas, or electric work without approval of the COR .

Existing work to be altered or extended and that is found to be defective

01 00 00 - 13 in any way, shall be reported to the COR before it is disturbed. Materials and workmanship used in restoring work, shall conform in type and quality to that of original existing construction, except as otherwise shown or specified.

B. Upon completion of contract, deliver work complete and undamaged.

Existing work (walls, ceilings, partitions, floors, mechanical and electrical work, lawns, paving, roads, walks, etc.) disturbed or removed as a result of performing required new work, shall be patched, repaired, reinstalled, or replaced with new work, and refinished and left in as good condition as existed before commencing work.

C. At Contractor's own expense, Contractor shall immediately restore to service and repair any damage caused by Contractor's workmen to existing piping and conduits, wires, cables, etc., of utility services or of fire protection systems and communications systems (including telephone) which are not scheduled for discontinuance or abandonment.

D. Expense of repairs to such utilities and systems not shown on drawings or locations of which are unknown will be covered by adjustment to contract time and price in accordance with clause entitled "CHANGES" (FAR 52.243-4 and VAAR 852.236-88) and "DIFFERING SITE CONDITIONS" (FAR 52.236-2).

1.12 PHYSICAL DATA

A. Data and information furnished or referred to below is for the Contractor's information. The Government shall not be responsible for any interpretation of or conclusion drawn from the data or information by the Contractor.

The indications of physical conditions on the drawings and in the specifications are the result of site investigations by the Architect- Engineer.

(FAR 52.236 4)

B. Government does not guarantee that other materials will not be encountered nor that proportions, conditions or character of several materials will not vary from those indicated by explorations. Bidders are expected to examine site of work and logs of borings; and, after investigation, decide for themselves character of materials and make their bids accordingly. Upon proper application to Department of Veterans Affairs, bidders will be permitted to make subsurface explorations of their own at site.

1.13 PROFESSIONAL SURVEYING SERVICES

A registered professional land surveyor or registered civil engineer whose services are retained and paid for by the Contractor shall perform services specified herein and in other specification sections. The Contractor shall certify that the land surveyor or civil engineer is not one who is a regular employee of the Contractor, and that the land surveyor or civil engineer has no financial interest in this contract.

1.14 LAYOUT OF WORK

A. The Contractor shall lay out the work from Government established base lines , indicated on the drawings, and shall be responsible for all measurements in connection with the layout. The Contractor shall furnish, 01 00 00 - 14 at Contractor's own expense, all stakes, templates, platforms, equipment, tools, materials, and labor required to lay out any part of the work.

(FAR 52.236-17)

B. Establish and plainly mark center lines for each building and corner of column lines and/or addition to each existing building, and such other lines and grades that are reasonably necessary to properly assure that location, orientation, and elevations established for each such structure and/or addition are in accordance with lines and elevations shown on contract drawings.

C. Following completion of general mass excavation and before any other permanent work is performed, establish and plainly mark (through use of appropriate batter boards or other means) sufficient additional survey control points or system of points as may be necessary to assure proper alignment, orientation, and grade of all major features of work. Survey shall include, but not be limited to, location of lines and grades of footings, exterior walls, center lines of columns in both directions, major utilities and elevations of floor slabs:

Such additional survey control points or system of points thus established shall be checked and certified by a registered land surveyor or registered civil engineer. Furnish such certification to the COR before any work (such as footings, floor slabs, columns, walls, utilities and other major controlling features) is placed.

D. During progress of work, and particularly as work progresses from floor to floor, Contractor shall have line grades and plumbness of all major form work checked and certified by a registered land surveyor or registered civil engineer as meeting requirements of contract drawings. Furnish such certification to the COR before any major items of concrete work are placed. In addition, Contractor shall also furnish to the COR certificates from a registered land surveyor or registered civil engineer that the following work is complete in every respect as required by contract drawings.

1. Lines of each building and/or addition.

2. Elevations of bottoms of footings and tops of floors of each building and/or addition.

3. Lines and elevations of sewers and of all outside distribution systems.

E. Whenever changes from contract drawings are made in line or grading requiring certificates, record such changes on a reproducible drawing bearing the registered land surveyor or registered civil engineer seal, and forward these drawings upon completion of work to COR .

F. The Contractor shall perform the surveying and layout work of this and other articles and specifications in accordance with the provisions of Article "Professional Surveying Services".

1.15 AS-BUILT DRAWINGS

A. The contractor shall maintain one full size sets of as-built drawings which will be kept current during construction of the project, to include all contract changes, modifications and clarifications.

01 00 00 - 15

B. All variations shall be shown in the same general detail as used in the contract drawings. To insure compliance, as-built drawings shall be made available for the COR review, as often as requested.

C. Contractor shall deliver two approved completed sets of as-built drawings to the COR within 15 calendar days after each completed phase and after the acceptance of the project by the COR.

D. Paragraphs A, B, & C shall also apply to all shop drawings.

1.16 USE OF ROADWAYS

For hauling, use only established public roads and roads on Medical Center property and, when authorized by the COR , such temporary roads which are necessary in the performance of contract work. Temporary roads shall be constructed and restoration performed by the Contractor at Contractor's expense. When necessary to cross curbing, sidewalks, or similar construction, they must be protected by well-constructed bridges.

1.17 NOT APPLICABLE

1.18 TEMPORARY USE OF MECHANICAL AND ELECTRICAL EQUIPMENT

A. Use of new installed mechanical and electrical equipment to provide heat, ventilation, plumbing, light and power will be permitted subject to written approval and compliance with the following provisions:

1. Permission to use each unit or system must be given by COR in writing.

If the equipment is not installed and maintained in accordance with the written agreement and following provisions, the COR will withdraw permission for use of the equipment.

2. Electrical installations used by the equipment shall be completed in accordance with the drawings and specifications to prevent damage to the equipment and the electrical systems, i.e. transformers, relays, circuit breakers, fuses, conductors, motor controllers and their overload elements shall be properly sized, coordinated and adjusted. Installation of temporary electrical equipment or devices shall be in accordance with NFPA 70, National Electrical Code, (2014 Edition), Article 590, Temporary Installations. Voltage supplied to each item of equipment shall be verified to be correct and it shall be determined that motors are not overloaded.

The electrical equipment shall be thoroughly cleaned before using it and again immediately before final inspection including vacuum cleaning and wiping clean interior and exterior surfaces.

3. Units shall be properly lubricated, balanced, and aligned. Vibrations must be eliminated.

4. Automatic temperature control systems for preheat coils shall function properly and all safety controls shall function to prevent coil freeze up damage.

5. The air filtering system utilized shall be that which is designed for the system when complete, and all filter elements shall be replaced at completion of construction and prior to testing and balancing of system.

6. All components of heat production and distribution system, metering equipment, condensate returns, and other auxiliary facilities used in temporary service shall be cleaned prior to use; maintained to prevent

01 00 00 - 16 corrosion internally and externally during use; and cleaned, maintained and inspected prior to acceptance by the Government.

B. Prior to final…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it.