This is a Utility Information Sheet for the Allumbaugh Street, Franklin Road to Douglas Street project (Project #822042) in Boise, Idaho, coordinated by Ada County Highway District (ACHD). The project consists of roadway reconstruction, pedestrian and bike facility additions, bridge replacement over Ridenbaugh Canal, and railroad crossing preemption upgrades. Utilities require approximately 60 working days from the Notice to Proceed date to complete their relocations, adjustments, and installations following clearing, grubbing, and tree removal activities. The contractor must coordinate and accommodate utility work throughout all project phases, as utility windows may significantly impact the critical path schedule. ACHD General Conditions Section 26 applies to all utility coordination efforts.

Nine utility companies operate within the project area, each with designated contacts responsible for coordinating their respective relocations and installations: Sparklight, Lumen, West Boise Sewer District, City of Boise Street Lights, Idaho Power, Intermountain Gas, Marathon, Syringa Networks, Veolia, and Zayo. The contractor shall contact the ACHD Utility Coordinator, Scott Bennett, at (208) 387-6259, for coordination questions. Project phasing will significantly affect the schedule for utility relocations, adjustments, and installations, requiring the contractor to strategically schedule construction windows that accommodate multiple utility companies operating simultaneously across different project phases.

View the file

Other files

Show all 16

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Utility Information

Allumbaugh St, Franklin Rd to Douglas St

Project #822042

Utility Company Work Duration and Contact Information:

Utilities require approx. 60 working days from NTP date to complete their relocations, adjustments, and installations after clearing, grubbing, tree trimming and removal. These utility windows may impact the Contractor’s critical path schedule by that amount of time, and utilities may be working on site for every phase of the project. Project phasing may have a significant effect on the schedule for utility relocations, adjustments, and installations.

Contractor shall coordinate and accommodate work with utility companies and schedule required construction windows throughout the project.

ACHD General Conditions Section 26 applies. Contact ACHD Utility Coordinator, Scott Bennett, at (208) 387-6259, with questions.

Utilities within project:

• Sparklight – Kevin Wakagawa – (208) 954-9219 – kevin.wakagawa@sparklight.biz

• Lumen – Cody Hollenback – (208) 207-2346 – cody.hollenback@lumen.com

• West Boise Sewer District – David Filkins – (208) 375-8521 – david@westboisesewer.com

• City of Boise Street Lights – Tom Marshall – (208) 388-4719 – tmarshall@cityofboise.org

• Idaho Power – Dan Hammerquist – (208) 388-2629 – dhammerquist@idahopower.com

• Intermountain Gas – Jordan Garcia – (208) 793-1528 – jordan.garcia@intgas.com

• Marathon – Brandin Mann - (208) 954-4999 - bmann@marathonpetroleum.com

• Syringa Networks – Michael DeWitt - (208) 803-4000 - mdewitt@syringanetworks.net

• Veolia – Al Christy - (208) 617-9433 - Alan.Christy@veolia.com

• Zayo – Ryan Goins (3C) - (208) 590-6681 - 3c.ryang@gmail.com mailto:kevin.wakagawa@sparklight.biz mailto:cody.hollenback@lumen.com mailto:david@westboisesewer.com mailto:tmarshall@cityofboise.org mailto:dhammerquist@idahopower.com mailto:jordan.garcia@intgas.com mailto:bmann@marathonpetroleum.com mailto:mdewitt@syringanetworks.net mailto:Alan.Christy@veolia.com mailto:3c.ryang@gmail.com