SWPPP.pdf
PDF 208 KB Posted
- Solicitation number
- CT227-04
- Issued by
- Ada County, Idaho
About this file
This is a Stormwater Pollution Prevention Plan (SWPPP) information document supplied by Ada County Highway District (ACHD) for a road reconstruction project located on Allumbaugh Street between Franklin Road and Douglas Street in Idaho, specifically over Ridenbaugh Canal. The project involves reconstructing the roadway, adding pedestrian and bike facilities, replacing the bridge structure over Ridenbaugh Canal, and upgrading railroad crossing preemption systems, with contractor coordination required with Union Pacific for railroad-related work. The project site encompasses 1.3 acres of total disturbance. The document provides baseline environmental and compliance information to support the contractor's preparation of the SWPPP Report and Notice of Intent (NOI), including project coordinates (43°36'17.39" N / 116°15'58.65" W) and site-specific data necessary for stormwater management during construction activities.
The SWPPP documentation indicates that the project does not discharge stormwater into a Municipal Separate Storm Sewer System (MS4) and has no surface waters within 50 feet of construction disturbances. The site does not involve Indian country lands or properties of religious or cultural significance to Indian tribes. Regarding endangered species protection, the project qualifies under eligibility criterion C, with identified federally-listed species including Yellow-billed Cuckoo (Threatened) and Monarch Butterfly (Candidate), though no critical habitats exist at the location. The contractor is required to implement approved Best Management Practices (BMPs) to mitigate and manage stormwater runoff. Historic preservation consultation has been completed, with written indication that any adverse effects to historic properties from installation of stormwater controls can be mitigated through agreed-upon actions. The project will not require installation of ground-disturbing stormwater controls based on the documentation provided.
View the file
Other files
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ACHD Supplied SWPPP Information This information is provided to the Contractor to aid in the preparation of the SWPPP Report and NOI.
1. Project/Site Information
i. Project Name: Allumbaugh St, Franklin Rd to Douglas St
ii. Project Street/Location: Allumbaugh St over Ridenbaugh Canal
iii. Project Latitude/Longitude: 43º36’17.39” N / 116º15’58.65” W
i. Method for determining latitude/longitude:
USGS topographic map (specify scale: ) EPA Web site GPS Other (please specify): Google Earth
iv. Additional Project Information:
i. Is the project/site located on Indian country lands, or located on a property of religious or cultural significance to an Indian tribe? Yes No
ii. If yes, provide the name of the Indian tribe associated with the area of Indian country (including the name of Indian reservation if applicable), or if not in Indian country, provide the name of the Indian tribe associated with the property: NA
2. Discharge Information
i. Does your project/site discharge stormwater into a Municipal Separate Storm Sewer
System (MS4)? Yes No
ii. Are there any surface waters that are located within 50 feet of your construction disturbances? Yes No
iii. Names of Receiving Waters:
Name(s) of the first surface water that receives stormwater directly from your site and/or from the MS4 (note: multiple rows provided where your site has more than one point of discharge that flows to different surface waters)
1. N/A 2.
3.
Is this surface water listed as “impaired”?
If you answered yes, then answer the following:
What pollutant(s) are causing the impairment?
Has a TMDL been completed?
Title of the TMDL document
Pollutant(s) for which there is a
TMDL
1. YES NO YES NO
iv. Describe the method(s) you used to determine whether or not your project/site discharges to an impaired water: The map query at the bottom of the page on the following link. EPA.GOV/NPDES/EPAS-STORMWATER-DISCHARGE-MAPPING-TOOLS
v. Are any of the surface waters to which you discharge designated by the state or tribal authority under its antidegradation policy as a Tier 2 (or Tier 2.5) water (water quality exceeds levels necessary to support propagation of fish, shellfish, and wildlife and recreation in and on the water) or as a Tier 3 water (Outstanding Natural Resource
Water)? (See Appendix F). Yes No If yes, name(s) of receiving water(s) and its designation (Tier 2, Tier 2.5 or Tier 3): N/A
3. Nature of the Construction Activity
i. Size of Construction Project: What is the size of the property (in acres), the total area expected to be disturbed by the construction activities (in acres), and the maximum area expected to be disturbed at any one time?
1.3 Acres
4. Endangered Species Protection:
i. Eligibility Criterion: ☐A ☐B ☒C ☐D ☐E
ii. Include documentation supporting your determination of eligibility.
Supporting Documentation Provide documentation for the applicable eligibility criterion you select in Appendix D, as follows:
For criterion A, indicate the basis for your determination that no federally-listed threatened or endangered species or their designated critical habitat(s) are likely to occur in your site’s action area (as defined in Appendix A of the permit). Check the applicable source of information you relied upon:
Specific communication with staff of the U.S. Fish & Wildlife Service or National Marine Fisheries Service.
Publicly available species list.
Other source:
For criterion B, provide the Tracking Number from the other operator’s notification of permit authorization:
Provide a brief summary of the basis used by the other operator for selecting criterion A, B, C, D, E, or F:
For criterion C, provide the following information:
INSERT LIST OF FEDERALLY-LISTED SPECIES OR FEDERALLY-DESIGNATED CRITICAL HABITAT LOCATED IN
YOUR ACTION AREA
• BIRDS – Yellow-billed Cuckoo (Threatened)
• INSECTS – Monarch Butterfly (Candidate)
• NO CRITICAL HABITATS AT THE LOCATION
• POTENTIAL MIGRATORY BIRDS
o American White Pelican o Bald Eagle o California Gull o Cassin’s Finch o Evening Grosbeak o Lewis’s Woodpecker o Olive-Sided Flycatcher o Rufuous Hummingbird o Sage Thrasher
• Please visit page https://www.fws.gov/sites/default/files/documents/nationwide-standard-conservation-measures.pdf to assist in measures to reduce impacts to birds and their habitat.
Also, provide a brief summary of the basis used for determining that your site’s discharges and discharge-related activities are not likely to adversely affect listed species or critical habitat: There is no critical habitat within the vicinity of the project site. The listed species are not expected to be at or near the project site anytime during construction. Contractor is expected to use approved BMPs to mitigate and manage stormwater runoff during construction.
https://www.fws.gov/sites/default/files/documents/nationwide-standard-conservation-measures.pdf https://www.fws.gov/sites/default/files/documents/nationwide-standard-conservation-measures.pdf
For criterion D, E, or F, attach copies of any letters or other communication between you and the U.S. Fish & Wildlife Service or National Marine Fisheries Service concluding consultation or coordination activities.
5. Historic Preservation:
Step 1 Do you plan on installing any of the following stormwater controls at your site? Check all that apply below, and proceed to Appendix E, Step 2.
Dike Berm Catch Basin Pond Stormwater Conveyance Channel (e.g., ditch, trench, perimeter drain, swale, etc.)
Culvert Other type of ground-disturbing stormwater control: N/A
(Note: If you will not be installing any ground-disturbing stormwater controls, no further documentation is required for Section 3.2 of the Template.)
Step 2 If you answered yes in Step 1, have prior surveys or evaluations conducted on the site already determined that historic properties do not exist, or that prior disturbances at the site have precluded the existence of historic properties? YES NO
If yes, no further documentation is required for Section 3.2 of the Template.
If no, proceed to Appendix E, Step 3.
Step 3 If you answered no in Step 2, have you determined that your installation of subsurface earth-disturbing stormwater controls will have no effect on historic properties?
YES NO
If yes, provide documentation of the basis for your determination.
If no, proceed to Appendix E, Step 4.
Step 4 If you answered no in Step 3, did the State Historic Preservation Officer (SHPO), Tribal Historic Preservation Office (THPO), or other tribal representative (whichever applies) respond to you within 15 calendar days to indicate whether the subsurface earth disturbances caused by the installation of stormwater controls affect historic properties? YES NO
If no, no further documentation is required for Section 3.2 of the Template.
If yes, describe the nature of their response:
Written indication that adverse effects to historic properties from the installation of stormwater controls can be mitigated by agreed upon actions. N/A
No agreement has been reached regarding measures to mitigate effects to historic properties from the installation of stormwater controls. N/A
Other: N/A http://water.epa.gov/polwaste/npdes/stormwater/upload/cgp2012_finalpermit.pdf http://water.epa.gov/polwaste/npdes/stormwater/Stormwater-Pollution-Prevention-Plans-for-Construction-Activities.cfm http://water.epa.gov/polwaste/npdes/stormwater/upload/cgp2012_finalpermit.pdf http://water.epa.gov/polwaste/npdes/stormwater/Stormwater-Pollution-Prevention-Plans-for-Construction-Activities.cfm
File details come from the government source that posted it. Updated .