Preconstruction_Package.pdf
PDF 300 KB Posted
- Solicitation number
- CT227-04
- Issued by
- Ada County, Idaho
About this file
This is a Pre-Construction Meeting Packet prepared by Union Pacific Railroad (UPRR) for the Whatcom Yard Realignment project located at East Marginal Way in Seattle, Washington (MP 182). The project, proposed by the City of Seattle, involves realigning the Whatcom yard to accommodate a parallel trail on the east side of East Marginal Way. The pre-construction meeting was scheduled for Friday, March 8, 2024, at 8:00 AM PST. Prior to commencing any work on UPRR property, contractors must submit and obtain approval for nine critical items: a fully executed Construction and Maintenance (C&M) Agreement, a Contractor Right of Entry (CROE), a Certificate of Insurance, a monthly look-ahead project schedule, UP-Property Access Training (UP-PAT) certifications for all personnel, a Safety Action Plan, an Emergency Response Plan, approved design and construction submittals from the UPRR Project Engineer, and a Temporary Construction Crossing Agreement if applicable. The contractor bears responsibility for ensuring all subcontractors comply with UPRR requirements and safety standards.
The packet establishes stringent safety and operational requirements governing all work activities. Flagging is mandatory for any person or equipment within 25 feet of railroad tracks, and work windows are classified as either Conditional (with flagging and track clearance upon train approach) or Absolute (track inactive for train movements). Construction monitoring by UPRR representatives occurs routinely with little notice, and critical operations including girder erection, demolition, falsework installation, shoring, and concrete pours require full-time observation and pre-activity meetings. All personnel must comply with UPRR's Contractor Minimum Safety Requirements, including specified Personal Protective Equipment standards, and all injuries, incidents, and spills regardless of severity must be reported to UPRR's Railroad Operations Control Center (RMCC) at 1-888-877-7267 within 24 hours. Primary project contacts include Project Manager Nick Petersen, Construction Manager Jason Taylor, and Construction Coordinator Marianne OBagy, with detailed contact information and relevant UPRR design standards and guidance documents provided.
View the file
Other files
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PUBLIC PROJECT PRE-CONSTRUCTION MEETING PACKET
Whatcom Yard Realignment (East Marginal Way) Seattle Sub. – MP 182
Seattle, WA
“Statements made in the course of conversation may be hypothetical or dependent on other facts or circumstances and are not binding commitments of Union Pacific.”
Date: Friday, March 08, 2024, at 8:00am PST
SAFETY BRIEFING: -Know your address in case 911 is called.
-Know your headcount in the room in case of evacuation.
-What is your weather, evacuation/assembly location?
-Assign responsibility for:
• CPR – AED / First Aid / 911 -Active shooter Protocol: Run, Hide, Fight
INTRODUCTIONS: Review roles and responsibilities.
PROJECT DESCRIPTION: City is proposing re-alignment of Whatcom yard to accommodate a parallel trail on the
East side of E Marginal Way.
The contractor is responsible for ensuring their subcontractors comply with all UPRR requirements.
Union Pacific requires contractors to follow the same safety rules that govern Union Pacific Employees. These include, but are not limited to, requirements related to work gear, equipment, safety conduct, reporting, prohibitions against weapons, fires, drugs, and alcohol.
For Emergencies on/or affecting UPRR Property or Operations
Contact RMCC at:
(888) 877-7267 or
(888) UPRR-COP
npetersen Text Box npetersen Text Box
REQUIREMENTS FOR WORKING ON UPRR PROPERTY:
Work may not begin on UPRR property, nor adjacent to UPRR property if it has the potential to impact UPRR operations until the following items are submitted and accepted by UPRR.
1. Fully Executed Construction and Maintenance (C&M) Agreement:
The executed C&M Agreement should be obtained by the agency responsible for the project.
2. Fully Executed Contractor Right of Entry (CROE):
The CROE is an Exhibit of the C&M Agreement provided to the Prime Contractor, and any Consulting Firm representing the Agency, to perform any type of work on, under, or above UPRR property.
3. Certificate of Insurance (COI):
Required insurance information is an Exhibit within the CROE. Any additional information can be located online at:
https://www.up.com/real_estate/rrinsurance/index.htm
4. Look Ahead Project Schedule:
At a minimum the project schedule should be sent to the Benesch Team MONTHLY. Please add the Benesch Team to the email distribution list.
5. UP-Property Access Training (UP-PAT):
Property access training must have been completed by each person on UPRR property. A valid copy of the certification will be with the individual anytime they are on the job site. For guidance on completing the training visit the website provided at: http://www.up.com/up-pat
6. Safety Action Plan (SAP):
The safety action plan is not provided by UPRR but is designed and implemented by the contractor. This shall be posted at a visible location on the project site.
7. Emergency Response Plan (ERP):
The emergency response plan is not provided by UPRR but is designed and implemented by the contractor. This should however include Railroad contact information (include page 7 of the pre-con packet), project personnel contact information, directions to the site, and directions to the nearest emergency facility. This shall be posted at a visible location on the project site.
8. Applicable List of Design and Construction Submittals Approved by UPRR PE:
Project design must be 100% approved prior to any work beginning on property. Required construction submittals must have been submitted and approved by UPRR PE prior to the construction activity being performed. Examples include, but are not limited to, erection, demolition, shoring, falsework, work plan for all concrete pours, etc.
Construction submittals should be sent to the Benesch PM as early as possible. Allow for a minimum of 4–6-week review time.
9. Temporary Construction Crossing Agreement:
Any temporary crossing associated with the project must be covered under an agreement with insurance in place and payment made. For more information see sect 4.3.4 of the UPRR Public Project Manual.
Project Safety:
It is Union Pacific Railroad’s policy to conduct its business in a manner that addresses the safety of employees, contractors, customers, and the communities we serve. Union Pacific will strive to prevent all incidents, accidents, injuries, and occupational illnesses through the active participation of all stakeholders. The company is committed to continuous efforts to identify and manage safety risks associated with its activities. Housekeeping around the tracks and on UPRR right-of-way is a priority and shall comply with UPRR instructions. Walkway paths within 15 feet from the centerline of tracks shall always be free of debris and other walking hazards. All slip/trip/fall hazards and temporary excavation must always be protected. This should include temporary scaffolding, shoring, platforms, etc.
All injuries and incidents regardless of severity must be reported to RMCC and the Benesch PM immediately!
Reporting will be required by the contractor for any event on UPRR property and it must be completed within 24 hours of occurrence.
All spills, of any size, on UPRR property, must be reported to RMCC and the Benesch PM immediately.
Personal Protective Equipment (PPE):
The Licensee shall require its employees to wear personal protective equipment as specified by Railroad rules, regulations, or recommended or requested by the railroad representative. At a minimum this should include, but not limited to:
• Hard hat that meets the American National Standard (ANSI) Z89.1 – latest revision. Hard hats should be affixed with Licensee’s company logo or name.
• Eye protection that meets American National Standard (ANSI) for occupational and educational eye and face protection, Z87.1 – latest revision. Additional eye protection must be provided to meet specific job situations such as welding, grinding, etc.
• Hearing protection, which affords enough attenuation to give protection from noise levels that will be occurring on the job site.
• Orange ANSI Class II/III vest.
• Footwear that meets the requirements outlined in the Contractor Minimum Safety Requirements document.
Union Pacific’s “Contractor Minimum Safety Requirements” must be reviewed prior to access of UPRR property and adhered to throughout the project. A copy of this document can be found at the link provided below.
https://www.up.com/suppliers/contractor-safety/index.htm
Flagging Requirements:
Per the executed agreement, flagging is required for any person or equipment that will be within twenty-five (25) feet of any track or will be near enough to any track that any equipment extension (such as, but not limited to, a crane boom) will reach to within twenty-five (25) feet of any track.
No work of any kind shall be performed, and no person, equipment, machinery, tool(s), material(s), vehicle(s), or thing(s) shall be located, operated, placed, or stored within twenty-five (25) feet of any of Railroad's track(s) at any time, for any reason, unless and until a Railroad approved flagman is provided to protect against railroad movements. Any work equipment stored on UPRR Property must have a lockable battery disconnect as well as comply with the written requirements found in the “Contractor Minimum Safety Requirements” document.
Counterflow Traffic operations, if approved, may only be conducted while a Railroad Flagger and Roadway Flagger are present to coordinate the movement of trains and vehicles.
For information regarding UPRR’s third party flagging policy visit the web link below.
http://www.up.com/flagging
Job Briefings:
Job briefings must be conducted with all individuals involved in the task before work begins. These briefings will need to be repeated if task or conditions change and should include potential hazards, PPE requirements, scope of work, tools, and equipment to be used and any other railroad related requirements. These briefings will not be considered complete until verification of understanding is provided.
Railroad Operations:
Work windows for this project shall be coordinated with the Agency and the UPRR designated representatives. Types of work windows include Conditional Work Windows and Absolute Work Windows, as defined below:
Conditional Work Window
A Conditional Work Window is a period when railroad operations have priority over construction activities. When construction activities may occur on and adjacent to the railroad tracks within 25 feet of the nearest track center line, an UPRR flag person will be required. At the direction of the UPRR flag person, upon approach of a train, and when trains are present on the tracks, the tracks must be cleared (i.e., no construction equipment, materials, or personnel within 25 feet, or as directed by the UPRR Designated Representative, from the tracks). Conditional Work Windows are available for the Project.
Absolute Work Window
An Absolute Work Window is a period that construction activities are given priority over railroad operations. During this time frame the designated railroad track(s) will be inactive for train movements and may be fouled by the Contractor.
At the end of an Absolute Work Window the railroad tracks and/or signals must be completely operational for train operations and all UPRR, Public Utilities Commission (PUC) and Federal Railroad Administration (FRA) requirements, codes and regulations for operational tracks must be complied with. In the situation where the operating tracks and/or signals have been affected, the UPRR will perform inspections of the work prior to placing that track back into service.
UPRR flag persons will be required for construction activities requiring an Absolute Work Window. Absolute Work Windows will not generally be granted. Any request will require a detailed explanation for UPRR review.
No Interference with Operations of Railroad and Its Tenants
Contractor shall conduct its operation so as not to interfere with the continuous and uninterrupted use and operation of the railroad tracks and property of Railroad, including without limitation, the operation of Railroad’s lessees, licensees, or others, unless specifically authorized in advance by the Railroad Representative. Nothing shall be done or permitted to be done by Contractor at any time that would in any manner impair the safety of such operations. When not in use, Contractor’s machinery and materials shall be kept at least fifty (50) feet from the centerline of Railroad’s nearest track, or UPRR property (whichever is less), and there shall be no vehicular crossing of Railroads tracks except at existing open public crossings.
Construction Monitoring:
To promote the safety of the public and Railroad employees, to maintain quality rail service to the Railroad’s customers, and to protect its property and assets, the Railroad may require construction monitoring (which is in addition to flagging) of the project. The construction monitoring will be conducted by Railroad employees or railroad representatives hired by the Railroad.
Site Visits:
The project will be visited routinely to monitor safety and compliance. These visits will occur with little, or no notice and the frequency of these visits will be determined by the railroad or their representative.
Critical Observations:
Critical operations will require full-time observation of the operation as well as a pre-activity meeting for more intensive operations. These operations will be identified by the Benesch PM, or the Benesch CM. Critical observations include but are not limited to the following.
• Girder erection
• Demolition
• Falsework Installation
• Shoring
• Contingency plans for underpass structures
• Work requiring any track removed from service
• Concrete pours
For more information, review section 14 of the UPRR Public Project Manual at this link below.
https://www.up.com/cs/groups/public/@uprr/@corprel/documents/up_pdf_nativedocs/pdf_up_public_projects_manu al.pdf
Construction Clearances:
Temporary UPRR clearances for the track must be strictly adhered to – vertical 21 feet-6 inches, top-of-rail to structure, horizontal 15 feet from the centerline of the track to nearest obstruction. Refer to the final drawings that have been accepted by UPRR.
Soil Management/Drainage:
• Drainage shall not be altered or otherwise impacted without UPRR Engineering acceptance. Adequate positive drainage must always be provided adjacent to UPRR tracks and as required by UPRR Engineering.
• Storm water and regulatory compliance must be implemented per project specifications and permitting, any exceptions observed will be communicated by the Contractor.
• New Soil(s) or Other Fill Material: Agency/Contractor will adhere to and comply with Railroad specifications applicable to the import of new soils or other fill material to be used at the project site.
• Management of Removed and/or Disturbed Soils: Agency/Contractor shall manage all removed or disturbed soils or other fill material in accordance with the following provisions:
If soil is to be removed from, or brought onto UPRR property, contact the Benesch PM, or Benesch CM to review the process.
Project Coordination:
Railroad Contacts:
Whatcom Yard Realignment (East Marginal Way) Seattle Sub. – MP 182 Seattle, WA
Railroad Emergency Number (RMCC) 1-888-877-7267
Primary UPRR Point of Contact
Project Manager Nick Petersen
(402) 672-1463 npetersen@benesch.com
Primary UPRR Construction Contact
Construction Manager Jason Taylor
(254) 652-0774 jtaylor@benesch.com
Primary Construction Activities Contact
Construction Activities Luke Schweinsberg
(385) 228-2418 lschweinsberg@benesch.com
Construction Coordinator Contact
Construction Coordinator Marianne OBagy
(801) 815-2884 mobagy@benesch.com
UPRR Flagging Services and Track Work
Manager Track Maintenance (MTM) Vincent Ortegon
(971) 420-9348 vmortego@up.com
UPRR Manager Signal Maintenance
Manager Signal Maintenance (MSM) Jeremy Halbardier
(503) 249-2237 jhalbardier@up.com
Railroad Fiber Optic Line Locate https://www.up.com/aboutup/community/telecom/groups/index.htm npetersen Text Box npetersen Text Box npetersen Text Box npetersen Text Box
UP Design Standards & Guidance Documents:
UP and BNSF Guidelines for Temporary Shoring (12/7/2021) https://www.up.com/cs/groups/public/@uprr/@customers/@industrialdevelopment/@operationsspecs/@sp ecifications/documents/up_pdf_nativedocs/pdf_up_str_temp-shoring.pdf
UP and BNSF Guidelines for Railroad Grade Separation Projects (2016) https://www.up.com/cs/groups/public/documents/up_pdf_nativedocs/pdf_rr_grade_sep_projects.pdf
UP Demolition Guidelines (1998) https://www.up.com/cs/groups/public/@uprr/@realestate/documents/up_pdf_nativedocs/pdf_up_reus_ind ustry_demo.pdf
Guidelines for Contractor Material Delivery on Union Pacific Property https://www.up.com/emp/engineering/mapcontent/standards/GUIDELINES_FOR_CONTRACTORS_ON_UPRR_ PROPERTY.pdf
UPRR Public Project Manual https://www.up.com/cs/groups/public/@uprr/@corprel/documents/up_pdf_nativedocs/pdf_up_public_proj ects_manual.pdf
UPRR Safety Book/UPRR Contractor Minimum Safety Requirements https://www.up.com/suppliers/contractor-safety/index.htm
For information regarding UPRR’s third party flagging policy visit the web link here http://www.up.com/flagging
CBUD Reference Guide https://www.up.com/cs/groups/public/@uprr/@it/@telecom/documents/up_pdf_nativedocs/pdf_fiber_cbu d_reference.pdf
PROJECT DESCRIPTION: City is proposing re-alignment of Whatcom yard to accommodate a parallel trail on the East side of E Marginal Way.