This document is a Notification of Acceptance of Use of a General Permit issued by the Florida Department of Environmental Protection (FDEP) Central District Office for Seminole County Parks and Recreation. The permit (Number 0445102-001-DWC/CG) is for the Wekiva Golf Club Pump Station project, which includes constructing 633 linear feet of 8-inch PVC gravity main, a duplex lift station, 240 linear feet of 2-inch HDPE force main, and associated manholes, valves, and appurtenances. The permit was issued on February 13, 2024, with an expiration date of February 12, 2029, and is connected to the Wekiva Hunt Club Wastewater Treatment Facility.

The document outlines specific requirements for using the general permit, including obtaining clearance from FDEP before placing facilities into operation, reporting abnormal events, and adhering to specific notification procedures for placing new or modified collection/transmission facilities into service. The permit does not relieve the permittee of obtaining additional permits like dredge and fill, and requires reporting of unauthorized wastewater spills to the State Watch Office. The project is part of Seminole County's infrastructure improvements for the Wekiva Golf Club, with the engineering work being performed by CPH LLC, as indicated in the cc: section of the permit notification.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

NOTIFICATION OF ACCEPTANCE OF USE OF A GENERAL PERMIT

PERMITTEE: PERMIT NUMBER: 0445102-001-DWC/CG

Daniel Heacock, Project Manager II ISSUE DATE: February 13, 2024

Seminole County Parks and Recreation EXPIRATION DATE: February 12, 2029

500 W. Lake Mary Blvd COUNTY: Seminole

Sanford FL 32733 PROJECT NAME: WEKIVA GOLF CLUB PUMP

STATION

CONNECTED TO: WEKIVA HUNT CLUB

WWTF

Email: dheacock@seminolecountyfl.gov FACILITY ID: FL0036251

Dear Mr. Heacock:

This letter acknowledges receipt of your Notification/Application for Constructing a Domestic Wastewater

Collection/Transmission System for the subject project. Our office received the Notice on February 9, 2024. This project includes: A) 633 LF of 8 inch PVC gravity main, B) a duplex lift station, C) 240 LF of

2 inch HDPE force main, D) Associated manholes, valves, and other appurtenances.

This is to advise you that the Department does not object to your use of such General Permit.

Please note the attached requirements apply to your use of this General Permit for constructing the proposed domestic wastewater collection/transmission system.

You are further advised that the construction activity must conform to the description contained in your

Notification/Application for Constructing a Domestic Wastewater Collection/Transmission System and that any deviation will subject the permittee to enforcement action and possible penalties.

Sincerely, William Gillett

Environmental Specialist II

Permitting and Waste Cleanup Program cc: Jeremy Craig Morton, P.E. CPH LLC, jmorton@cphcorp.com

Nicholas Nida, CPH LLC, nnida@cphcorp.com

Sean Twomey President, Wekiva Hunt Club, Sean.Twomey@sunshinewater.com

FDEP: Charles LeGros; Allison Chancy; William Gillett

FLORIDA DEPARTMENT OF

Environmental Protection

Central District Office

3319 Maguire Blvd., Suite 232

Orlando, Florida 32803

Ron DeSantis Governor

Jeanette Nuñez

Lt. Governor

Shawn Hamilton

Secretary mailto:DHEACOCK@SEMINOLECOUNTYFL.GOV mailto:jmorton@cphcorp.com mailto:nnida@cphcorp.com mailto:Sean.Twomey@sunshinewater.com

REQUIREMENTS FOR USE OF THE GENERAL PERMIT FOR DOMESTIC

WASTEWATER COLLECTION/TRANSMISSION SYSTEMS:

1. This general permit is subject to the general permit conditions of Rule 62-4.540, F.A.C., as applicable. This rule is available at the Department’s Internet site at:

http://www.dep.state.fl.us/legal/Rules/shared/62-4/62-4.pdf [62-4.540]

2. This general permit does not relieve the permittee of the responsibility for obtaining a dredge and fill permit where it is required. [62-604.600(6)(b)1]

3. This general permit cannot be revised, except to transfer the permit. [62-604.600(6)(b)2]

4. This general permit will expire five years from the date of issuance. If the project has been started and not completed by that time, a new permit must be obtained before the expiration date in order to continue work on the project. [62-4.030]

5. Upon completion of construction of the collection/transmission system project, and before placing the facilities into operation for any purpose other than testing for leaks or testing equipment operation, the permittee shall obtain clearance from the Department. This clearance may be obtained expeditiously using the Department’s

Business Portal at http://www.fldepportal.com/go/ (via “Submit” then “Registration/Notification” and “Submit

Notifications to FDEP”. The submission is for “Division of Water Resource Management Domestic/Industrial

Wastewater” and the submittal type is “Request for Approval to Place a Domestic Wastewater

Collection/Transmission System into Operation”).

For further clarification contact:

William Gillett 407-897-4131

3319 Maguire Blvd, Suite 232

Orlando, Florida 32803-3767

6. New or modified collection/transmission facilities can be placed into operation 3 days after Form 62-

604.300(3)(b), (adopted and incorporated by reference in paragraph 62-604.300(3)(b), F.A.C., effective October

4, 2021, http://www.flrules.org/Gateway/reference.asp?No=Ref-13560), is submitted and received by the

Department or delegated local program, provided no substantial deviations are noted on Form 62-604.300(3)(b) and the Department or delegated local program does not notify the permittee of public health or environmental concerns regarding placing the facilities into operation.

When substantial deviations are noted on Form 62-604.300(3)(b), (adopted and incorporated by reference in paragraph 62-604.300(3)(b), F.A.C., effective October 4, 2021), http://www.flrules.org/Gateway/reference.asp?No=Ref-13560), new or modified collection/transmission facilities can be placed into operation 10 days after Form 62-604.300(3)(b) is submitted unless the Department or delegated local program notifies the permittee of public health or environmental concerns regarding placing the facilities into operation.

[62-604.700(3) and (4)]

7. Abnormal events shall be reported to the Department’s Central District Office in accordance with Rule 62-

604.550, F.A.C. For unauthorized spills of wastewater in excess of 1000 gallons per incident, or where information indicates that public health or the environment may be endangered, oral reports shall be provided to the STATE WATCH OFFICE TOLL FREE NUMBER (800)320-0519 as soon as practical, but no later than 24 hours from the time the permittee or other designee becomes aware of the circumstances. Unauthorized releases or spills less than 1000 gallons per incident are to be reported orally to the Department’s Central District Office within 24 hours from the time the permittee, or other designee becomes aware of the circumstances. [62-604.550] http://www.dep.state.fl.us/legal/Rules/shared/62-4/62-4.pdf http://www.fldepportal.com/go/ http://www.flrules.org/Gateway/reference.asp?No=Ref-13560 http://www.flrules.org/Gateway/reference.asp?No=Ref-13560