This solicitation seeks proposals for an upgrade to the nurse call system at the Alvin C. York VA Medical Center campuses in Murfreesboro and Nashville, Tennessee. The project involves general construction and electrical work including labor, materials, equipment, and supervision to upgrade the nurse call system wiring and equipment in accordance with provided specifications and drawings. Proposals are due by July 19, 2021 for consideration, with the contractor expected to complete the work expeditiously once awarded. The solicitation was issued by the Department of Veterans Affairs Veterans Health Administration VISN 9 for Project 626A4-20-104.
View the file
Other files
Show all 29
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
UPGRADE NURSE CALL SYSTEM
TVHS- NASHVILLE CAMPUS
1310 24TH AVE S,
NASHVILLE, TENNESSEE 37212
VA PROJECT #: 626A4-20-104
VA PROJECT NUMBER
Building Number
Drawing Number
Project Title
Date Checked Drawn
Drawing Title
Approved:
VA FORM 08-6231
A
B C
D E
21 4 5 6 7
321 4 5 6 7
A B
C E
Dwg. of
LocationLocation
Office of
Construction and Facilities
Management
PROJECT MANAGER:
ACG Project Number
Revisions: Date
CONSULTANTS:
JULY 19, 2021
LG
KK
626A4-20-104
TVHS- NASHVILLE CAMPUS
1310 24TH AVE S, NASHVILLE, TENNESSEE 37212
20-171
FULLY SPRINKLERED
Headquarters:
Apogee Consulting Group, P.A.
1151 Kildaire Farm Road, Suite 120
Cary, North Carolina 27511 www.acg-pa.com 919-858-7420
© COPYRIGHT Apogee Consulting Group, P.A.
Nash:1
Engineers Architects U.S. Department of Veterans Affairs
UPGRADE NURSE CALL SYSTEM
NASHVILLE/MURFREESBORO
CAMPUS
TVHS- ALVIN C. YORK CAMPUS
3400 LEBANON PIKE, MURFREESBORO, TENNESSEE 37129
Murf:1,2,3,4,5,7,8,9,11
17,106,116,117,120
100% CONSTRUCTION DOCUMENTS
G-001
COVER SHEET
1 5
PROJECT SITE MAP
NASHVILLE/MURFREESBORO CAMPUS
TVHS- ALVIN C. YORK CAMPUS
3400 LEBANON PIKE,
MURFREESBORO, TENNESSEE 37129
VAMC NASHVILLE, TENNESSEE
PROJECT LOCATION MAP
PROJECT
SITE
PROJECT SITE MAP
VAMC MURFREESBORO, TENNESSEE
PROJECT LOCATION MAP
PROJECT SITE
VAMC NASHVILLE, TENNESSEE
VAMC MURFREESBORO, TENNESSEE
NORTH
NORTH
NORTH
NORTH
DRAWING LIST
11811
KO
RLA K . KUDJ IKU
CHARLOTTE , NORTH CAROL
I N
ANOR T H C A R O L I N
A
RE
G I
STERED ARCH ITECT
DocuSign Envelope ID: 902C8DA2-A23F-4D0E-8CC1-1FDD1FE07EFF
7/19/2021
G-002
CAMPUS KEY PLAN AND NOTES
2 5
LGKK
VAMC MURFREESBORO, TENNESSEECAMPUS KEY PLAN
VAMC NASHVILLE, TENNESSEECAMPUS KEY PLAN
EXISTING BUILDING - PART OF SCOPE
BUILDING ENTRANCE
NORTH
NORTH
BID ALTERNATES
REFERENCE SECTION 01 00 00 OF THE SPECIFICATIONS FOR THE SCHEDULE OF BID
ALTERNATES TO BE INCLUDED WITH THE BID PACKAGE. SEE TECHNOLOGY SHEETS FOR
ADDITIONAL INFORMATION ON BID ALTERNATES.
BASE BID ITEM, GENERAL CONSTRUCTION: WORK INCLUDES GENERAL CONSTRUCTION,
ELECTRICAL WORK; INCLUDES ALL LABOR, MATERIAL, EQUIPMENT AND SUPERVISION TO
PERFORM THE REQUIRED ELECTRICAL AND LOW VOLTAGE WORK TO UPGRADE THE
NURSE CALL SYSTEM.
BID ITEM 1: INCLUDES ALL WORK IN BASE BID, BUT EXCLUDE ALL WORK SHOWN ON
SHEETS 17TD111 AND 17TN111.
BID ITEM 2: SAME AS BID ITEM 1 BUT EXCLUDE ALL WORK IN BUILDING 106.
BID ITEM 3: SAME AS BID ITEM 2 BUT EXCLUDE ALL WORK ASSOCIATED WITH ROOMS
LABELED "EXAM" WITHIN THE DEFINED LIMITS ON SHEETS 117TN111.
BIDDER SHALL PROVIDE A SEPARATE BID PRICE FOR THIS WORK. IF THE BID DEDUCT
ALTERNATE IS NOT ACCEPTED, THE AREA WILL BE RENOVATED PER DRAWINGS AND
SPECIFICATIONS.
VA PROJECT NUMBER
Building Number
Drawing Number
Project Title
Date Checked Drawn
Drawing Title
Approved:
VA FORM 08-6231
A
B C
D E
21 4 5 6 7
321 4 5 6 7
A B
C E
Dwg. of
LocationLocation
Office of
Construction and Facilities
Management
PROJECT MANAGER:
ACG Project Number
Revisions: Date
CONSULTANTS:
JULY 19, 2021
626A4-20-104
TVHS- NASHVILLE CAMPUS
1310 24TH AVE S, NASHVILLE, TENNESSEE 37212
20-171
FULLY SPRINKLERED
Headquarters:
Apogee Consulting Group, P.A.
1151 Kildaire Farm Road, Suite 120
Cary, North Carolina 27511 www.acg-pa.com 919-858-7420
© COPYRIGHT Apogee Consulting Group, P.A.
Nash:1
Engineers Architects U.S. Department of Veterans Affairs
UPGRADE NURSE CALL SYSTEM
NASHVILLE/MURFREESBORO
CAMPUS
TVHS- ALVIN C. YORK CAMPUS
3400 LEBANON PIKE, MURFREESBORO, TENNESSEE 37129
Murf:1,2,3,4,5,7,8,9,11
17,106,116,117,120
100% CONSTRUCTION DOCUMENTS
1. INDICATIONS OF PROJECT LIMITS OR LINES OF DEMARCATION ARE SHOWN FOR GENERAL SCOPE DEFINITION AND REFLECT THE UNDERSTANDING OF THE DESIGNER AS TO THE LIMITATIONS OF THE WORK AREA IN AN OCCUPIED AREA. ACTUAL CONTRACT LIMITS ARE TO BE DETERMINED BY
AGREEMENT BETWEEN THE COR AND CONTRACTOR BEFORE THE START OF THE WORK.
2. DRAWINGS ARE PREPARED USING DIMENSIONS AND PRODUCT DRAWINGS FOR SPECIFIC PRODUCTS. DETAILS FOR SPECIFIC PRODUCTS MAY CHANGE BEFORE THEY ARE ACTUALLY INCORPORATED INTO THE WORK, AND PRODUCTS BY OTHER MANUFACTURERS ARE ALSO ACCEPTABLE. THEREFORE, ACTUAL INSTALLATION DETAILS AND DIMENSIONS MAY DIFFER FROM THOSE SHOWN. CONTRACTOR SHALL VERIFY INSTALLATION REQUIREMENTS FOR ALL PRODUCTS TO BE INCORPORATED IN THE WORK (INCLUDING THICKNESS FOR RECESSED OR SEMI-RECESSED PRODUCTS) AND IS
RESPONSIBLE FOR ACCOMMODATING AND COORDINATING CHANGES TO OTHER MATERIALS OR PRODUCTS THAT ARE NECESSARY BECAUSE OF THESE DIFFERENCES.
3. THE DRAWINGS AND SPECIFICATIONS ARE SEPARATED INTO DISCIPLINES FOR CONVENIENCE. THE SEPARATIONS ARE USED ONLY FOR THE PURPOSES OF CONVENIENCE AND REFERENCE AND IN NO WAY DO THEY DEFINE OR LIMIT THE SCOPE OR INTENT OF ANY PART OF THE DRAWINGS AND
SPECIFICATIONS AS A WHOLE. THE FACT THAT THE DRAWINGS ARE SEPARATED IN NO WAY SUGGESTS THAT THE WORK IS NOT TO BE CONSTRUCTED AS A COMPLETE, INTEGRATED AND UNIFIED WHOLE.
4. THE DRAWINGS AND SPECIFICATIONS, INCLUDING DRAWINGS PREPARED BY SPECIFIC ENGINEERING DISCIPLINES ARE COMPLEMENTARY; ITEMS SHOWN IN ANY ONE LOCATION IN THE DRAWINGS SHALL BE CONSIDERED TO BE REQUIREMENTS OF THE CONTRACT FOR CONSTRUCTION. IN THE EVENT
OF AN INCONSISTENCY BETWEEN THE DRAWINGS AND SPECIFICATIONS, OR WITHIN EITHER DOCUMENT, THE CONTRACTOR SHALL SEEK CLARIFICATION OR INTERPRETATION FROM THE OWNER PRIOR TO BIDDING. WHERE INCONSISTENCIES ARE NOT CLARIFIED PRIOR TO BIDDING, AND WHERE THE
ACTUAL SOLUTION OR INTENT CANNOT BE REASONABLY INFERRED, THE CONTRACTOR SHALL PROVIDE THE BETTER QUALITY OR GREATER QUANTITY OF WORK.
5. THE CONTRACTOR SHALL NOTIFY THE OWNER IMMEDIATELY SHOULD DISCREPANCIES BE FOUND IN THE DRAWINGS AND SPECIFICATIONS.
6. THE CONTRACTOR IS RESPONSIBLE FOR CHECKING ALL FIELD CONDITIONS AND DIMENSIONS AS THEY RELATE TO THIS PROJECT, FOR EACH PHASE. SHOULD DISCREPANCIES EXIST BETWEEN THE WORK INDICATED AND ACTUAL FIELD CONDITIONS, NOTIFY THE OWNER PRIOR TO PROCEEDING WITH
THE WORK.
7. DO NOT SCALE THE DRAWINGS. DRAWING SCALES AS INDICATED ARE FOR REFERENCE ONLY AND ARE NOT INTENDED TO ACCURATELY DEPICT ACTUAL OR DESIGNATED CONDITIONS. WRITTEN DIMENSIONS SHALL GOVERN.
8. PROVIDE SEALANT AT ALL INTERSECTIONS BETWEEN DIFFERENT MATERIALS.
9. COORDINATE WORK OF ALL TRADES PRIOR TO STARTING CONSTRUCTION.
10. REFER TO ALL OTHER TRADE DRAWINGS AND SPECIFICATIONS FOR ADDITIONAL INFORMATION ON THIS PROJECT.
11. PROVIDE BLOCKING AT PARTITIONS AS REQUIRED FOR MOUNTING OF WALL-MOUNTED ITEMS: PROVIDE SUPPLEMENTAL FRAMING AT WALL OPENINGS INCLUDING KING STUDS, JACK STUDS, AND CRIPPLE STUDS, AS REQUIRED FOR COMPLETION OF THE WORK.
12. DIMENSIONS SHOWN ARE TO FACE OF STUD FRAMING, FACE OF CONCRETE/MASONRY WALLS, OR FINISHED FACE OF EXISTING WALL SURFACE.
13. ALL WOOD IN CONTACT WITH CONCRETE SHALL BE PRESSURE TREATED.
1. KEY NOTES AND DRAWINGS ARE INTENDED TO GRAPHICALLY REPRESENT GENERAL WORK AND DO NOT PORTRAY FULL SCOPE OF THE PROJECT. SEE SPECIFICATIONS FOR DETAILED REQUIREMENTS.
2. REMOVE EXISTING CONSTRUCTION AS DESIGNATED HEREIN AND CLEAR AREA OF DEBRIS PRIOR TO PROCEEDING WITH NEW CONSTRUCTION.
3. EXISTING EQUIPMENT REMOVED SHALL BE PROPERLY DISPOSED OF, OFF PROJECT GROUNDS. COORDINATE WITH OWNER.
4. AT AREAS INDICATED TO BE PATCHED AND REPAIRED, FOR ADDITION AND RENOVATION PROJECTS: THE CONSTRUCTION AND ASSEMBLY OF THE PATCH OR REPAIR SHALL MATCH THE ASSEMBLY AND INTEGRITY OF THE ADJACENT EXISTING
CONSTRUCTION, FOR FIRE RATING, MATERIALS, FINISH, THICKNESS, AND QUALITY.
5. COORDINATE WORKING HOURS ALLOWED FOR DEMOLITION AND WASTE REMOVAL WITH OWNER.
6. NOTIFY OWNER OF ANY DEMOLITION REQUIRED AND NOT INDICATED FOR INSTALLATION OF ELECTRICAL OR DATA ITEMS. AFTER SUCH DEMOLITION AND INSTALLATION, PATCH OR REPLACE MATERIALS AND FINISHES TO MATCH EXISTING.
7. CONTRACTOR SHALL PROTECT AREA ADJACENT TO THE DEMOTION AND NEW CONSTRUCTION WORK TO PREVENT DAMAGES, (IF DAMAGED REPAIR, RE-PATCH, SAND SMOOTH AND REFINISH TO MATCH EXISTING.) REPAIR OR REPLACE ITEMS DAMAGED
DURING CONSTRUCTION ACTIVITIES AT NO ADDITIONAL COST.
8. THE INFORMATION CONTAINED IN THESE DEMOLITION DOCUMENTS DEFINES GENERAL SCOPE ONLY AND DOES NOT RELIEVE THE CONTRACTOR OF THE RESPONSIBILITY OF PROVIDING ALL DEMOLITION REQUIRED FOR THE COMPLETION OF THE
PROJECT.
9. DO NOT ENCROACH ON ADJACENT OCCUPIED AREAS NOT IDENTIFIED WITHIN THE SCOPE OF WORK.
10. REFER TO THE ELECTRICAL DRAWINGS FOR FURTHER INFORMATION REGARDING DEMOLITION OF ELECTRICAL SYSTEMS.
11. BEFORE THE START OF WORK, IDENTIFY ANY REQUIRED DEMOLITION BEYOND THE IDENTIFIED PROJECT SCOPE WHETHER ABOVE, BELOW, OR OUTSIDE THE PROJECT AREA. NOTIFY AND COORDINATE WITH THE OWNER, PROVIDE DEMOLITION OF THESE
AREAS AND PATCH THE SAME AS A PART OF THE SCOPE OF THE PROJECT.
12. ALL ITEMS TO BE TEMPORARILY REMOVED TO ACCOMMODATE INSTALLATION OF NEW WORK BY OTHER TRADES (INCLUDING, BUT NOT LIMITED TO ACOUSTICAL TILE AND CEILING MOUNTED DEVICES) SHALL BE CAREFULLY REMOVED AND REINSTALLED TO
IT'S ORIGINAL AND OPERATIONAL STATE, FOLLOWING THE COMPLETION OF THE WORK. CONTRACTOR SHALL REPAIR OR REPLACE DAMAGED ITEMS AND EXISTING AREAS DURING CONSTRUCTION ACTIVITIES TO MATCH EXISTING CONDITIONS AT NO
ADDITIONAL COST.
13. ALL DEMOLITION WORK SHALL BE PERFORMED WITH DUE CARE AND DILIGENCE IN ORDER TO PREVENT ARBITRARY DAMAGE OR INTERRUPTION OF SERVICE OR CONCEALED UTILITIES INTENDED TO REMAIN IN SERVICE. DISCOVERY OF UTILITIES OR
CONDITIONS LOCATED DIFFERING FROM THOSE INDICATED OR THAT ARE NOT IDENTIFIED, SHALL BE REPORTED TO THE OWNER.
14. AFTER REMOVAL OF EXISTING SOLID CONCRETE MASONRY WALL, FILL FLOOR VOIDS UP TO FINISH CONCRETE LEVEL AND PERFORM FLOOR LEVELING FOR ENTIRE AREA OF RENOVATION.
15. VERIFY ALL EXISTING CONDITIONS PRIOR TO BEGINNING WORK. NOTIFY OWNER AND ARCHITECT OF ANY CONFLICTS PRIOR TO PROCEEDING WITH DEMOLITION.
16. ALL ITEMS BEING SALVAGED OR REMOVED SHALL REMAIN THE PROPERTY OF THE OWNER UNTIL CONFIRMATION HAS BEEN MADE AS TO WHETHER THE OWNER WILL RETAIN SUCH ITEMS. ALL ITEMS NOT BEING SALVAGED BY THE VA TO BE REMOVED AND
DISPOSED OF BY THE CONTRACTOR IN APPROVED MANNER.
17. CONTRACTOR SHALL NOTIFY OWNER OF ANY AREA REQUIRING DEMOLITION OTHER THAN SHOWN IN THESE DRAWINGS DUE TO UNFORSEEN CONDITIONS, TO ACCOMMODATE INSTALLATION OF ALL OTHER TRADES (INCLUDING ROOF PENETRATIONS).
AFTER SUCH DEMOLITION AND INSTALLATION, PATCH OR REPLACE MATERIALS AND FINISHES TO MATCH EXISTING.
18. COORDINATE WITH OWNER FOR CONSTRUCTION ACCESS ROUTE AND LOCATIONS OF DUMPSTER AREA. COORDINATE WITH OWNER FOR SCHEDULE OF USE OF ACCESS ROUTE FOR WASTE REMOVAL AND CONTRACTOR USE OF FREIGHT ELEVATOR (AS
REQUIRED).
DEMOLITION NOTESGENERAL NOTES LEGEND
INTERIM LIFE SAFETY MEASURES IN EFFECT FOR THE
UPGRADE NURSE CALL SYSTEM
THIS EXIT IS CLOSED AND LEADS TO A
CONSTRUCTION AREA
PLEASE USE ALTERNATE EXITS AS MARKED
1'-5"
ICRA, ILSM, FIRE WATCH AND
MISC. FORMS
PAPER
CADDY
ILSM TEMPORARY BARRIER TAG
PROJECT:
PRIME CONTRACTOR:
SUB CONTRACTOR:
EMERGENCY CONTACT NO.:
BARRIER INSTALLATION DATE:
BARRIER EXPIRATION DATE:
FIRE EXTINGUISHER ON
PORTABLE FLOOR
BRACKET (ILSM MAY
REQUIRE MORE THAN
ONE).
PROVIDE STICKY
MATS (CHANGED END
OF SHIFT OR MORE IF
NECESSARY TO
MAINTAIN
CLEANLINESS).
HEPA NEGATIVE
AIR UNIT
SUPPLY DUCTS
EITHER KEEP
RUNNING OR COVER
WHEN RUNNING TO
KEEP DUST OUT
COVER ALL RETURNS
AT THE
GRATE/DIFFUSERS
F L E
X
D
U C
T
SUSPENDED PLASTIC
ZIPPER WALL
CURTAIN BARRIER
POST ICRA, ILSM, FIRE
INSPECTION SHEETS
VISIBLE TO PUBLIC
FIRE PULL
STATION WITH
AUDIO / VISUAL
DUCT TO OUTSIDE
OF BUILDING
G-102
4/5
G-102
G-102
HARD WALLS AND
DOORS BARRIER
HEPA
NEGATIVE AIR
UNIT
FINISHED FLOORING TO BE KEPT
CLEAN. FLOORS NOT BEING REPLACED
MUST BE PROTECTED. COVER WITH
ROSIN PAPER / FIRE RATED PLYWOOD.
FIRE RATED PLYWOOD,
TEMPORARY. SALVAGE
PROTECT AND STORE
EXISTING WINDOW TO
BE RE-INSTALLED
AFTER CONSTRUCTION
IS COMPLETE.
V I F
V
I F
V.I.F.
V I F
E X
I S
T I N
G
W
A L L
V I F
E X
I S
T I N
G
W
A L L
INFECTION CONTROL RISK MITIGATION RECOMMENDATIONS MATRIX
OF PRECAUTIONS FOR CONSTRUCTION AND RENOVATION
Class III
Patient Risk Group Table
Infection Control Matrix - Class of Precautions: Construction
Project by Patient Risk
TYPE A
Construction Project Type
Major demolition and construction projects
Includes, but is not limited to:
- activities which require consecutive work shifts
- requires heavy demolition or removal of a complete ceiling system
- new construction
Work that generates a moderate to high level of dust or requires demolition or removal of any fixed building components or assemblies
Includes, but is not limited to:
- sanding of walls for painting or wall covering
- removal of floor coverings, ceiling tiles and casework
- new wall construction
- minor duct work or electrical work above ceilings
- major cabling activities
- any activity which cannot be completed within a single work shift
Small scale, short duration activities which create minimal dust
Includes, but is not limited to:
- installation of telephone and computer cabling
- access to chase spaces
- cutting of walls or ceiling where dust migration can be controlled
Inspection and Non-Invasive Activities
Includes, but is not limited to:
- removal of ceiling tiles for visual inspection limited to 1 tile to 50 square feet
- painting (but not sanding), wall covering
- electrical trim work, minor plumbing, and activities which do not generate dust or require cutting of walls or access to ceilings other than for visual inspection
Type of Construction / Project Activity Table
Group 2
Medium Risk
Group 1
Low Risk
- Therapy Areas
- Respiratory Therapy
- Outpatient Clinics
- CBOC's
- Mental Health Units
- VACANT AREA ADJACENT TO
OCCUPIED AREA
- Office areas (non-clinical)
- Hallways
- FES/EMS areas
I
Patient Risk Group
TYPE
D
TYPE
C
TYPE
B
TYPE
A
Group 4
Highest Risk
Group 3
High Risk
- Pharmacy
- Radiology/ CT Scanner
- Urgent Care
- Laboratories
- CLCs
- SPD
- AMCU
- Respiratory Isolation Rooms
III
TYPE DTYPE CTYPE B
o r control procedures are necessary.
C L A
S S
I V
C L A
S S
I I
During Construction Project
C L A
S S
I
C L A
S S
I I I
1. Remove barrier materials carefully to minimize spreading of dirt and debris associated with construction.
2. Contain construction waste before transport in tightly covered containers.
3. Cover transport receptacles or carts. Tape covering
4. Vacuum work area with HEPA filtered vacuums.
5. Wet mop area with disinfectant after barriers are removed.
6. Remove or isolate HVAC system in areas where work was being performed.
1. Remove barrier materials carefully to minimize spreading of dirt and debris associated with construction.
2. Contain construction waste before transport in tightly covered containers.
3. Cover transport receptacles or carts. Tape covering.
4. Vacuum work with HEPA-filtered vacuums.
5. Wet mop with disinfectant.
6. Remove isolation of HVAC system in areas where work is being performed.
1. Wipe surfaces to remove dust
Upon Completion of Project
1. Wipe work surfaces with disinfectant.
2. Contain construction waste before transport in tightly covered containers.
3. Wet mop and/or vacuum work area with HEPA filtered vacuum before leaving work areas.
4. Remove isolation of HVAC system in areas where work is being performed.
1. Includes all activities required by Class II
2. Obtain Infection Control Permit from Hospital Safety Officer or Facilities
Management Maintenance and Engineering department before construction begins.
3. Remove or isolate HVAC system in area where work is being done to prevent contamination of duct system.
4. Complete all critical barriers before construction begins or implement control cube method.
5. Maintain negative air pressure within work site utilizing HEPA-equipped air filtration units.
6. Contain construction waste before transport in tightly covered containers.
7. Cover transport receptacles or carts. Tape covers.
8. Wet mop and/or vacuum with HEPA filtered vacuum before leaving work areas.
9. Remove isolation of HVAC system in areas where work is being performed.
1. Execute work by methods to minimize raising dust from construction operations.
1. Includes all activities required by Class I
2. Provide active means to prevent airborne dust from dispersing into atmosphere.
3. Water mist work surfaces to control dust while cutting.
4. Seal unused doors with duct tape.
5. Block off and seal air vents.
6. Replace adhesive walk-off mats at entrance and exit of work area.
Replace used mats in accordance with manufacturer's recommendations.
7. Remove or isolate HVAC system in area where work is being done to prevent contamination of duct system.
1. Includes all activities required by Class III.
2. Obtain Infection Control Permit from Hospital Safety Officer or Facilities
Management Maintenance and Engineering department before construction begins.
3. Isolate HVAC system in areas where work is being done to prevent contamination of duct system.
4. Complete all critical barriers or implement control cube method before construction begins.
5. Maintain negative air pressure within work site utilizing HEPA equipped air filtration units.
6. Seal holes, pipes, conduits, and punctures appropriately.
7. Construct anteroom and require all personnel to pass through this room so they can be vacuumed sing a HEPA vacuum cleaner before leaving work site or they can wear cloth or paper coveralls that re removed each time they leave the work site.
8. All personnel entering work site are required to wear shoe covers.
Shoe covers must be changed each ime the worker exits the work area.
9. Place adhesive walk-off mats at entrance to work area within anteroom.
10. Replace per manufacturer's recommendations. Do not remove work area barriers until completed project is inspected each by the Hospital Department Safety Officer, Facilities Management Maintenance and Engineering and thoroughly cleaned by the Hospital Environmental Services Department or their contracted Environmental Service Company. Contain construction waste before transport in tightly covered containers.
11. Cover transport receptacles or carts. Tape covering
12. Vacuum work area with HEPA filtered vacuums.
13. Wet mop with disinfectant after barriers are removed.
14. Remove isolation of HVAC system in areas where work is being performed.
Class IV
Note: Infection Control approval will be required when the Construction Activity and Risk Level indicate that
It is the Contractor's Responsibility to provide the following Infection Control
Precautions depending upon the Area Class Designation
II
I
LOW Risk Group 1
HIGH Risk Group 3
HIGHEST Risk Group 4
MEDIUM Risk Group 2
IV
IV
IV
III/IV
III/IV
III/IV
III/IV
III
III
III
I
A P
P R
O X
A
F
F
SUSPENDED
PLASTIC ZIPPER
WALL CURTAIN
BARRIER
POST ICRA,
ILSM, FIRE
INSPECTION
SHEETS VISIBLE
TO PUBLIC
G-102
A P
P R
O X
A
F
F
DOOR IN HARD
ICRA BARRIER
POST ICRA,
ILSM, FIRE
INSPECTION
SHEETS VISIBLE
TO PUBLIC
G-102
A
M
G-100
TYPICAL ICRA DETAILS
Scale: No Scale
ILSM SIGNAGE
Scale: No Scale
ILSM BARRIER TAG
Scale: 1/2" = 1'-0"
TYPICAL CONSTRUCTION PLAN LAYOUT
Scale: 1/2" = 1'-0"
TYPICAL ICRA CROSS SECTION
Scale: 1/2" = 1'-0"
TYPICAL ICRA ROOM ELEVATION (CLASS IV)
1.
2.
3.
4.
TAPE ALL SERVICES TO PROTECT AGAINST
CONTAMINATION.
THE CONTRACTOR SHALL NOT HAUL DEBRIS
THROUGH PATIENT-CARE AREAS WITHOUT PRIOR
APPROVAL OF THE COR AND THE MEDICAL CENTER.
USING A HEPA VACUUM, CLEAN INSIDE THE BARRIER
AND VACUUM CEILING TILE PRIOR TO REPLACEMENT.
ANY CEILING ACCESS PANELS OPENED FOR
INVESTIGATION BEYOND SEALED AREAS SHALL BE
SEALED IMMEDIATELY WHEN UNATTENDED.
AT COMPLETION, REMOVE CONSTRUCTION
BARRIERS AND CEILING PROTECTION CAREFULLY,
OUTSIDE OF NORMAL WORK HOURS. VACUUM AND
CLEAN ALL SURFACES FREE OF DUST AFTER THE
REMOVAL.
NOTE:
TAG SHALL BE PLACED ON ALL ILSM
TEMPORARY BARRIERS. FINAL LOCATION BY G.C.
CONTRACTOR TO VERIFY AND COORDINATE FINAL
AND APPROVED ICRA MEASURES WITH THE VA
NASHVILLE/MURFREESBORO ICRA PERSONNEL,
PRIOR TO THE COMMENCEMENT OF CONSTRUCTION
ACTIVITY.
5.
Scale: 1/2" = 1'-0"
TYPICAL ICRA ROOM ELEVATION (CLASS II)
JULY 19, 2021
LG
KK
626A4-20-104
TVHS- NASHVILLE CAMPUS
1310 24TH AVE S, NASHVILLE, TENNESSEE 37212
20-171
FULLY SPRINKLERED
VA PROJECT NUMBER
Building Number
Drawing Number
Project Title
Date Checked Drawn
Drawing Title
Approved:
VA FORM 08-6231
A
B C
D E
21 4 5 6 7
SHEET NOTES:
321 4 5 6 7
A B
C E
Dwg. of
LocationLocation
Office of
Construction and Facilities
Management
PROJECT MANAGER:
ACG Project Number
Revisions: Date
CONSULTANTS:
Headquarters:
Apogee Consulting Group, P.A.
1151 Kildaire Farm Road, Suite 120
Cary, North Carolina 27511 www.acg-pa.com 919-858-7420
© COPYRIGHT Apogee Consulting Group, P.A.
Nash:1
Engineers Architects U.S. Department of Veterans Affairs
UPGRADE NURSE CALL SYSTEM
NASHVILLE/MURFREESBORO
CAMPUS
TVHS- ALVIN C. YORK CAMPUS
3400 LEBANON PIKE, MURFREESBORO, TENNESSEE 37129
Murf:1,2,3,4,5,7,8,9,11
17,106,116,117,120
100% CONSTRUCTION DOCUMENTS
11811
KO
RLA K . KUDJ IKU
CHARLOTTE , NORTH CAROL
I N
ANOR T H C A R O L I N
A
RE
G I
STERED ARCH ITECT
11811
KO
RLA K . KUDJ IKU
CHARLOTTE , NORTH CAROL
I N
ANOR T H C A R O L I N
A
RE
G I
MECH
CONGRE BATH
ELEC.
6'-0"
CLEAR
MIN.
4 5 6
ONE BED ROOM
RESTROOM
WITH
SHOWER
366A
C L
E A
R
M I N
4 5 6
RESTROOM
WITH SHOWER
327A
326329
TWO BED ROOM
TWO BED ROOM
4 5 6
TOILET
409A
LINEN
DATA
MENTAL
ON CALL
MENTAL
ON CALL
CLEAN
C L E
A R
M I N
4 5 6
TOILET
ELECTRICAL
2-BED
RM
TOILET
110A
TOILET
109A
CORRIDOR
COMM
TOILET
ELECTRICAL
4 5 6
CORRIDOR
HAC
TREATMENT
6'-0"
CLEAR
MIN.
4 5 6
CORRIDOR
NURSE
STATION
ELEVATOR
LOBBY
WARD
CLERK
125B
CHARTING
125A
CORRIDOR
NOURISHMENT
KITCHEN
5'-0"
CLEAR
MIN
C
L
E
A
R
M
I
N
ALCOVE
CORRIDOR
TWO
BEDRM
TOILET
237A
ONE
BEDRM
6'-0"
CLEAR
6'-0"
CLEAR
TWO
BEDRM
TOILET
236A
C L E
A R
M I N
STAFF
TOILET
CORRIDOR
TOILET
247B
STORAGE
STORAGE
247A
QUIET
248A
ANTE
4 5 6
4 5 6
CLOSET
103B
CORRIDOR
FEMALE TOILET
109BED RM
BED RM
C L
E A
R
M I N
OFFICE
CLOSET
121A
NURSING RM
113A
4 5 6
Bedroom #14
Bath #15 Bath #14
Bath #13
Clo 4
C L
E A
R
4 5 6
TOILET
C134A
2- BED RM
C134
6'-0"
CLEAR
4 5 6
CORRIDOR
C013
LINEN
C132
ELECTRICAL
C116
TOILET
C117A
CONGREGATE
BATH
C117
HAC
C115
TOILET
C114A
C L E
A R
4 5 6
LINEN
112I
STAFF
TOILET
112C
PACU
CONTROL
112L
ISOLATION
112G
MED
112K
PATIENT
NUTRITION
112D
STORAGE
112A
OFFICE
112E
ANTE
112F
STATION
STATION
STATION
STATION
STATION
STATION
4 5 6
CUBICLE-10
105L
NURSE MGR
ELEC
HAC
CORRIDOR
LOUNGE
TLT
103A
CLEAN UTILITY
MECH
103E
ON CALL
RECEPTION
WAITING
d e s k v v m a t v
120M
120N
C L E
A R
M I N
4 5 6
HAC
TELE
SURGERY
MINOR
7A
7B
A
M
G-102
TYPICAL ICRA PLANS -
MURFREESBORO CAMPUS
5 5
Scale: 1/8" = 1'-0"
TYPICAL CONGREGATE BATH
(CLASS IV)
Scale: 1/8" = 1'-0"
TYPICAL ONE AND TWO BEDRM/
TOILET (CLASS IV)
Scale: 1/8" = 1'-0"
TYPICAL BED RM/ FEMALE
TOILET (CLASS IV)
Scale: 1/8" = 1'-0"
TYPICAL OFFICE
(CLASS II)
Scale: 1/8" = 1'-0"
TYPICAL BEDROOM/ BATH
(CLASS IV)
Scale: 1/8" = 1'-0"
TYPICAL 2 - BED RM/ TOILET
(CLASS IV)
Scale: 1/8" = 1'-0"
TYPICAL CONGREGATE BATH
(CLASS IV)
Scale: 1/8" = 1'-0"
TYPICAL ONE BEDROOM/
REST RM/ SHOWER (CLASS IV)
Scale: 1/8" = 1'-0"
TYPICAL TWO BED ROOM/ RESTROOM
WITH SHOWER (CLASS IV)
Scale: 1/8" = 1'-0"
TYPICAL MENTAL ON CALL/
TOILET (CLASS IV)
Scale: 1/8" = 1'-0"
TYPICAL RECEPTION
(CLASS II)
Scale: 1/8" = 1'-0"
TYPICAL TELE
ROOM (CLASS IV)
Scale: 1/8" = 1'-0"
TYPICAL 2-BED/ TOILET
(CLASS IV)
Scale: 1/8" = 1'-0"
TYPICAL COMM ROOM
(CLASS II)
Scale: 1/8" = 1'-0"
TYPICAL TREATMENT ROOM
(CLASS IV)
Scale: 1/8" = 1'-0"
TYPICAL NURSE STATION
(CLASS IV)
Scale: 1/8" = 1'-0"
TYPICAL BEDRM/ TOILET
(CLASS IV)
Scale: 1/8" = 1'-0"
TYPICAL TOILET/ ANTE/
STORAGE (CLASS IV)
Scale: 1/8" = 1'-0"
TYPICAL PACU
(CLASS IV)
Scale: 1/8" = 1'-0"
TYPICAL CUBICLE
(CLASS IV)
Scale: 1/8" = 1'-0"
TYPICAL ELEC ROOM
(CLASS II)
Scale: 1/8" = 1'-0"
TYPICAL LOUNGE
(CLASS II)
1. PROVIDE TEMPORARY PLASTIC BARRIER
PARTITION TO THE UNDERSIDE OF
CEILING WITH ZIPPER ENTRY. PARTITION
SHALL BE INSPECTED BY VA ICRA STAFF
PRIOR TO START OF CONSTRUCTION IN
SPACE. MAINTAIN NEGATIVE PRESSURE
VENTILATION IN THE CONSTRUCTION
SPACE.
2. PROVIDE TWO STICKY MATS AT EACH
CONSTRUCTION ACCESS POINT IN ALL
PHASES.
3. WORK TO BE PERFORMED AT THE
MASTER AND SLAVE CONTROL PANEL
LOCATIONS SHALL BE PERFORMED AT
ONE LOCATION AT A TIME.
4. USE A PORTABLE DUST EXTRACTOR
AND AIR SCRUBBER WITH HEPA
FILTRATION SYSTEM.
5. CONTRACTOR SHALL COVER ALL
FURNITURE WITHIN ROOM WITH
PLASTIC, PRIOR TO COMMENCING
WORK IN A SPACE AND REMOVE PRIOR
TO POST-CONSTRUCTION TERMINAL
CLEANING.
6. THE AIR WITHIN THE CONSTRUCTION
AREA SHALL BE NEGATIVE WITH
RESPECT TO SURROUNDING AREAS AND
WITH NO DISRUPTION OF AIR SYSTEMS
OF ADJACENT AREAS. USE OF THE
NEGATIVE AIR PRESSURE SYSTEM
WITHIN THE ENCLOSURE TO REMOVE
DUST SHALL PASS AIR THROUGH AN
INDUSTRIAL GRADE, PORTABLE HEPA
FILTER CAPABLE OF FILTRATION RATES
OF 300-800 CUBIC FEET PER MINUTE
(FT3/MIN), OR EXHAUST AIR DIRECTLY
TO THE OUTSIDE IF APPROVED BY
VAMC. IF EXHAUST INTO A ROOM, A
PRE-FILTER AND HEPA FILTER SHALL BE
USED BEFORE EXHAUST.
7. INSTALL HARD DUCT WITH NON-FLANGE
HANGER, OR SOFT DUCT WITH
SUPPORTING STRAPS AS REQUIRED
HUNG FROM CEILING ABOVE. BOTTOM
OF DUCT SHALL BE A MINIMUM OF 7'-2''
ABOVE FINISH FLOOR. DUCT SHALL BE
ROUTED THROUGH EXISTING
MECHANICAL EQUIPMENT ROOM, OR
TEMPORARILY ROUTED THROUGH
CORRIDOR OR COR APPROVED PATH TO
EXTERIOR WINDOW. CONTRACTOR TO
TEMPORARILY REMOVE AND REINSTALL
WINDOW AFTER CONSTRUCTION
COMPLETION.
7A. CONTRACTOR TO DETERMINE NUMBER
OF EXHAUST FANS REQUIRED TO
MAINTAIN NEGATIVE PRESSURE LEVEL
INSIDE CONSTRUCTION AREA.
7B. TURN UP EXHAUST ON EXTERIOR SIDE,
CONTRACTOR SHALL VERIFY LOCATION
OF AIR INTAKES AT THE PROPER
DISTANCE FROM EXHAUST. VERIFY
LOCAL JURISDICTION CODE AND VA
REQUIREMENTS FOR DISTANCE PRIOR
STARTING WORK.
1. REMOVE ALL TRASH DAILY FROM THE WORK AREA.
2. THESE DRAWINGS ARE BASED ON FIELD SURVEY
AND EXISTING PLANS. VERIFY ALL FIELD
CONDITIONS.
3. COORDINATE WITH VA COR FOR OFF-HOURS
SCHEDULE AND TEMPORARY REROUTING ACCESS
FOR HOSPITAL STAFF AND VISITORS, PRIOR TO
ERECTING TEMPORARY BARRIERS.
4. CONSULT WITH VA SAFETY DEPARTMENT TO
MAINTAIN MINIMUM CLEARANCE IN CORRIDORS AND
HALLWAYS.
5. EXISTING WINDOWS THAT NEED TO BE
TEMPORARILY REMOVED TO ACCOMMODATE
DISCHARGED AIR EXHAUST DUCT, SHALL BE
RE-INSTALLED AFTER CONSTRUCTION.
6. CONTRACTOR TO VERIFY AND COORDINATE FINAL
AND APPROVED ICRA MEASURES WITH THE VA
NASHVILLE/MURFREESBORO ICRA PERSONNEL,
PRIOR TO THE COMMENCEMENT OF
CONSTRUCTION ACTIVITY.
7. ROOM TYPES SHOWN ON THIS SHEET ARE TYPICAL
FOR THE MURFREESBORO CAMPUS.
VA PROJECT NUMBER
Building Number
Drawing Number
Project Title
Date Checked Drawn
Drawing Title
Approved:
VA FORM 08-6231
A
B C
D E
21 4 5 6 7
SHEET NOTES:
SHEET KEY NOTES:
321 4 5 6 7
A B
C E
Dwg. of
LocationLocation
Office of
Construction and Facilities
Management
PROJECT MANAGER:
ACG Project Number
Revisions: Date
CONSULTANTS:
JULY 19, 2021
LG
KK
626A4-20-104
TVHS- NASHVILLE CAMPUS
1310 24TH AVE S, NASHVILLE, TENNESSEE 37212
20-171
FULLY SPRINKLERED
Headquarters:
Apogee Consulting Group, P.A.
1151 Kildaire Farm Road, Suite 120
Cary, North Carolina 27511 www.acg-pa.com 919-858-7420
© COPYRIGHT Apogee Consulting Group, P.A.
Nash:1
X
Engineers Architects U.S. Department of Veterans Affairs
UPGRADE NURSE CALL SYSTEM
NASHVILLE/MURFREESBORO
CAMPUS
TVHS- ALVIN C. YORK CAMPUS
3400 LEBANON PIKE, MURFREESBORO, TENNESSEE 37129
Murf:1,2,3,4,5,7,8,9,11
17,106,116,117,120
100% CONSTRUCTION DOCUMENTS
WALL RATINGS
1 HR FIRE WALL
1 HR FIRE SMOKE WALL
2 HOUR FIRE SMOKE WALL
2 HOUR FIRE WALL
SMOKE WALL
NON RATED SMOKE PARTITION
CORRIDOR WALL IN NON SPRINKLERED
AREA
HAZARDOUS
11811
KO
RLA K . KUDJ IKU
CHARLOTTE , NORTH CAROL
I N
ANOR T H C A R O L I N
A
RE
G I
ADO AUTOMATIC DOOR OPERATOR
AFF ABOVE FINISH FLOOR
CCTV CLOSED CIRCUIT TELEVISION
COAX COAXIAL CABLE
COMM COMMUNICATION
COR CONTRACTING OFFICER
REPRESENTATIVE
DC DOOR CONTACT SWITCH
DN DOWN
DO DOOR OPERATOR
DVR DIGITAL VIDEO RECORDER
EEB EMERGENCY EXIT BUTTON
EL ELECTRICAL STRIKE
FA FIRE ALARM
FAP FIRE ALARM PANEL
FAAP FIRE ALARM ANNUNCIATOR PANEL
FO FIBER OPTIC
IT INTERCOMMUNICATION ROOM
MATV MASTER ANTENNA TELEVISION
MM MULTI MODE FIBER
NAC NETWORK APPLIANCE CIRCUIT PANEL
NS NO SCALE
NTS NOT TO SCALE
NVR NETWORK VIDEO RECORDER
TECHNOLOGY ABBREVIATIONS LIST
OC ON CENTER
OIT OFFICE OF INFORMATION TECHNOLOGY
PACS PHYSICAL ACCESS CONTROL SYSTEM
PAMN PUBLIC ADDRESS AND MASS NOTIFICATION SYSTEM
PB PUSH BUTTON
PDU RACK POWER DISTRIBUTION UNITS
POE POWER OVER ETHERNET
PR PAIR
RX REQUEST TO EXIT
SEP SERVICE ENTRANCE PROTECTION
SLC SIGNALING LINE CIRCUIT
TEL TELEPHONE
TGB TELECOMM GROUND BUS BAR
TM TELEMONITORING
TMGB TELECOMM MAIN GROUND BUS BAR
TP TWISTED PAIR
TR TELECOMM ROOM
TTB TELEPHONE TERMINAL BOARD
TV TELEVISION
WM WIRE MANAGEMENT
WAP WIRELESS ACCESS POINT
UL UNDERWRITERS LABORATORY
UPS UNINTERRUPTIBLE POWER SUPPLY
UTP UNSHIELDED TWISTED PAIR
N NEW DEVICES
NCA NETWORK CONTROL ANNUNCIATOR
DVC DIGITAL VOICE COMMAND
SS STAINLESS STEEL
E EXISTING DEVICES
BOD BASIS OF DESIGN
CLG CEILING
EG EQUIPMENT GROUND
NCE NURSE CALL EQUIPMENT
SM SINGLE MODE FIBER
CATV CABLE TELEVISION
UNO UNLESS NOTED OTHERWISE
AWG AMERICAN WIRE GUAGE
GND GROUND
TECHNOLOGY SYMBOL LEGEND
SYMBOL HEIGHT DESCRIPTION
NURSE CALL PATIENT BED INTERFACE RECEPTACLE (37 PIN)
ENHANCED NURSE CALL, STAND ALONE, CODE BLUE
STATION WITH CLEAR BUTTON COVER
NURSE CALL EMERGENCY STATION WITH PULL CORD WITH AUDIO IN
RESTROOM (+40"), NO AUDIO IN SHOWER (V - VANDAL RESISTANCE, PB - PUSH BUTTON
INSTEAD OF CALL CORD, HS - HIGH SECURITY STEEL COVER PLATE)
NURSE CALL DUTY STATION
NURSE CALL MASTER STATION/CONSOLE
NURSE CALL DOME LIGHT
(Z - ZONE LIGHT, V - VANDAL RESISTANCE)
NURSE CALL EQUIPMENT CABINETNCE
18"
HEADWALL
/40"
40",72"
18"
60"
CEILING
6' TO
TOP
NURSE CALL PATIENT STATION WITH CALL CORD INCLUDES:
- CODE BLUE
- STAFF ASSIST
- AUDIO
- CLEAR BUTTON COVER
(2 - DUAL PATIENT STATION, HS - VANDAL RESISTANT HIGH SECURITY STEEL COVER
PLATE)
HEADWALL
ABOVE
DOOR NURSE CALL DOME LIGHT
M
N
N
C
E
B
P
D
A NURSE CALL AUXILIARIESHEADWALL
/40"
R
PB
NURSE CALL PATIENT STATION
(PB - PUSH BUTTON, M - MICROPHONE, K -KEYED, HS - HIGH SECURITY STEEL
COVER PLATE)
N M
42"
Z
B2 P
BUTTON STATION WITH CLEAR BUTTON COVER
NUMBER OF BUTTONS (1 - SINGLE BUTTON, 2 - DOUBLE BUTTON)
BUTTON PROGRAMMING (B - CODE BLUE, P - PUSH FOR HELP, S - STAFF ASSIST)
ALL HEIGHTS ARE TO CENTER OF DEVICE UNLESS NOTED OTHERWISE.
ANY HEIGHTS INDICATED IN PLANS SHALL SUPERCEDE THOSE LISTED HERE.
SEE DRAWINGS FOR MORE INFORMATION.
NOTE: NOT ALL SYMBOLS ARE USED.
FOUR POST OIT EQUIPMENT RACK
OIT EQUIPMENT CABINET
HEADWALL
FLOOR
FLOOR
S
TWO POST OIT EQUIPMENT RACKFLOOR
NURSE CALL PATIENT STATION WITH PILLOW SPEAKER (GET WELL) INCLUDES:
- CODE BLUE
- STAFF ASSIST
- AUDIO
- CLEAR PLASTIC COVER
(2 - DUAL PATIENT STATION, HS - VANDAL RESISTANT HIGH SECURITY STEEL COVER
PLATE)
T
40" NURSE CALL STAFF TERMINAL
TV OUTLET WALL MOUNTED. COMBINATION ANTENNA AND WIRED REMOTE
RECEPTACLE WITH 1/4", 1-GANG, FDA LISTED, 3-CONDUCTOR PHONE JACK WITH
STAINLESS STEEL FACEPLATE.
84"/96"
CEILING
60"
TV OUTLET WALL MOUNTED. COMBINATION ANTENNA AND WIRED REMOTE
RECEPTACLE WITH 1/4", 1-GANG, FDA LISTED, 3-CONDUCTOR PHONE JACK WITH
STAINLESS STEEL FACEPLATE.
A
TECHNOLOGY SYMBOL LINE TYPE EXPLANATIONS
SYMBOLS THAT ARE GRAY/HALF-TONE IN APPEARANCE ARE DEVICES THAT ARE EXISTING TO REMAIN.
THESE LINES MATCH THE TONE OF THE BUILDING'S LINES. THESE SYMBOLS CAN APPEAR ON SHEETS WITH EITHER DEMOLITION OR NEW WORK PLANS. THEY ARE TYPICALLY ACCOMPANIED WITH A SHEET
NOTE OR KEY NOTE.
A SYMBOLS THAT ARE DARK AND DASHED IN APPEARANCE ARE DEVICES THAT ARE EXISTING TO BE
DEMOLISHED. THESE SYMBOLS SHOULD ONLY APPEAR ON DEMOLITION SHEETS UNLESS NOTED
OTHERWISE.
A SYMBOLS THAT ARE DARK IN APPEARANCE AND ARE NOT DASHED ARE NEW DEVICES TO BE
INSTALLED. THESE SYMBOLS SHOULD ONLY APPEAR ON SHEETS WITH NEW WORK PLANS UNLESS
NOTED OTHERWISE.
TYPICAL
SYMBOL DESCRIPTION
ELECTRICAL GENERAL NOTES
1. ALL ELECTRICAL DEVICES, FIXTURES, EQUIPMENT AND FEEDERS SHALL BE INSTALLED IN
ACCORDANCE WITH THE PROJECT SPECIFICATIONS, THE MANUFACTURER'S RECOMMENDED
PROCEDURES, ALL APPLICABLE LOCAL AND STATE CODES, AMERICANS WITH DISABILITIES ACT
AND WITH THE LATEST EDITION OF THE NATIONAL ELECTRICAL CODE AND VA STANDARDS.
2. PROVIDE ADDITIONAL SUPPORT FOR DEVICES, FIXTURES, EQUIPMENT AND FEEDERS WHERE THE
BUILDING CONSTRUCTION IS NOT SUITABLE FOR DIRECT MOUNTING.
3. FIRESTOP, DRAFTSTOP, SMOKESTOP AND/OR PROTECT THE ANNULAR SPACE AROUND ALL
PENETRATIONS THROUGH WALLS, PARTITIONS, FLOORS, CEILING, AND ROOFS IN ACCORDANCE
WITH THE REQUIREMENTS OF THE NATIONAL ELECTRICAL CODE, UL LISTING REQUIREMENT AND
THE APPLICABLE BUILDING CODES.
4. VERIFY CEILING SYSTEMS AND PROVIDE MOUNTING ACCESSORIES, TRIMS AND ALL REQUIRED
MOUNTING HARDWARE TO SUIT THE PARTICULAR INSTALLATION.
5. PROTECT EXISTING UNDERGROUND AND BUILDING INTERIOR UTILITIES DURING CONSTRUCTION.
6. BRANCH CIRCUIT CONDUCTORS SHALL BE 12 AWG COPPER MINIMUM.
7. COORDINATE ANY AND ALL WORK WITH ALL OTHER TRADES PRIOR TO INSTALLATION SO AS TO
AVOID CONFLICT DURING CONSTRUCTION.
8. ALL PANELS SHALL HAVE TYPED, COMPLETED DIRECTORIES INDICATING EQUIPMENT SERVED AND ROOM NUMBER (AS INDICATED ON FINAL BUILDING ROOM SIGNAGE) OF EQUIPMENT LOCATION, OR
SPARE, OR SPACE.
9. MANUFACTURER'S NAME AND MODEL NUMBER ARE GIVEN FOR DESCRIPTIVE PURPOSES, TO
INDICATE A QUALITY STANDARD, AND ARE NOT INTENDED TO LIMIT PRODUCTS TO A PARTICULAR
MANUFACTURER. PRODUCTS DEEMED EQUAL AND APPROVED BY THE DESIGNER WILL BE
ACCEPTED. ALL PRODUCTS MUST COMPLY WITH "BUY AMERICAN ACT".
10. ALL FEEDERS AND CIRCUITRY SHALL BE TORQUED PER THE PANEL, BREAKER, AND/OR
PARTICULAR EQUIPMENT MANUFACTURER'S SPECIFICATIONS.
11. CONDUCTORS TO SWITCHES, RECEPTACLES, AND ALL OTHER DEVICES SHALL BE TERMINATED ON
THE DEVICE'S SCREW TERMINALS.
12. MOUNTING HEIGHTS INDICATED ARE TO CENTER OF DEVICE, OUTLET, FIXTURE, OR EQUIPMENT
UNLESS NOTED OTHERWISE.
13. ALL WIRE TERMINATIONS SHALL BE RATED FOR 75 DEGREES C.
14. ALL CONDUCTORS SHALL HAVE THHN/THWN INSULATION, UNLESS OTHERWISE NOTED.
15. ALL CONDUIT SHALL BE RGS OR EMT UNLESS OTHERWISE NOTED. FMC CONDUIT SHALL BE USED
ON VIBRATING EQUIPMENT (MAXIMUM LENGTH OF 6 FEET). PVC SHALL BE USED FOR
UNDERGROUND CONDUIT OR WHERE CONCRETE-ENCASED. WHERE VIBRATING EQUIPMENT IS
LOCATED OUTSIDE, LFMC CONDUIT SHALL BE USED (MAXIMUM SIX FEET) FOR FINAL CONNECTIONS.
16. ALL ELECTRICAL MATERIALS, DEVICES, APPLIANCES AND EQUIPMENT SHALL BE LABEL LISTED BY
AN APPROVED THIRD PARTY TESTING AGENCY.
17. FOR ALL LED FIXTURES, THE FIXTURE MUST BE CAPABLE OF SELF-RESETTING TO THE
SWITCHED/CONTROLLED STATE DURING ANY FLUCTUATION IN POWER SUPPLY WHERE AUTOMATIC
PROTECTIVE MEASURES DISABLE THE LED LAMPS. PROVIDE A LETTER OR STATEMENT FROM THE
MANUFACTURER, OR OTHER ACCEPTABLE PROOF, THAT ALL LED FIXTURES, WITH OR WITHOUT
BROWNOUT PROTECTION, WILL RETURN TO THE SWITCHED/CONTROLLED STATE AUTOMATICALLY.
PROVIDE STATEMENT WITH THE FIXTURE SUBMITTALS.
18. IN CASE OF CONFLICTS OR DISCREPANCIES WITHIN OR AMONG THE CONTRACT DRAWINGS, THE
BETTER QUALITY, MORE STRINGENT REQUIREMENTS OR GREATER QUANTITY OF WORK , AS
DETERMINED BY THE GOVERNMENT, SHALL BE PROVIDED.
19. COMPRESSION COUPLINGS SHALL BE USED. NO SET SCREW FITTINGS ARE ALLOWED.
20. MINIMUM CONDUIT SIZE TO BE USED IS 3/4".
120V DUPLEX RECEPTACLE
RECEPTACLE MODIFIERS:
AC: 3" ABOVE COUNTERTOP/BACKSPLASH
GFI: GROUND FAULT CURRENT INTERRUPTER
WP: WEATHERPROOF ENCLOSURE
DED: DEDICATED CIRCUIT
120V DUPLEX RECEPTACLE EMERGENCY OUTLET
AND COVER PLATE SHALL BE RED IN COLOR
120V QUADRUPLEX RECEPTACLE
120V QUADRUPLEX RECEPTACLE EMERGENCY
OUTLET AND COVER PLATE SHALL BE RED IN COLOR
JUNCTION BOX, WALL MOUNTED, PURPOSE AS NOTED
DISCONNECT SWITCH NON-FUSED
DISCONNECT SWITCH FUSED
SINGLE POLE WALL SWITCH: 48" AFF STANDARD UNO
SYMBOL HEIGHT DESCRIPTION
18"
18"
18"
18"
AS
NOTED
72" TOP
72" TOP
SWITCH MODIFIERS:
M: MOTOR-RATED
48"
ALL HEIGHTS ARE TO CENTER OF DEVICE UNLESS NOTED OTHERWISE.
TOP: HEIGHT TO TOP OF DEVICE
ANY HEIGHTS INDICATED IN PLANS SHALL SUPERCEDE THOSE LISTED HERE.
SPECIAL RECEPTACLE
EQUIPMENT CONNECTIONAS
NOTED
E
208V DUPLEX RECEPTACLE18"
18"
120V DUPLEX RECEPTACLE FLOOR BOX
120V DUPLEX RECEPTACLE EMERGENCY FLOOR BOX
OUTLET AND COVER PLATE SHALL BE RED IN COLOR
120V QUADUPLEX RECEPTACLE FLOOR BOX
120V QUADUPLEX RECEPTACLE EMERGENCY
FLOOR BOX OUTLET AND COVER PLATE SHALL BE
RED IN COLOR
CLNG
J
J
J
JUNCTION BOX, CEILING MOUNTED, PURPOSE AS
NOTED
JUNCTION BOX, FLOOR MOUNTED, PURPOSE AS
NOTED
PANELBOARDS: PANELBOARD DOORS MAY BE SHOWN TO
INDICATE OPENING SIDE OF RECESSED PANELBOARDS.
SEE PANELBOARD IDENTIFICATION FOR DESIGNATION
CODES.
HOME RUN TO BRANCH CIRCUIT PANEL: THE PANEL
DESIGNATION AND CIRCUIT DESIGNATION ARE SHOWN
ADJACENT TO THE HOME RUN ARROW. CIRCUIT
BREAKER SIZES (AMPS/NUMBER OF POLES) ARE SHOWN
IN THE PANEL SCHEDULE WITH THE CORRESPONDING
PANEL AND CIRCUIT DESIGNATION.
EXAMPLE: HOME RUN TO PANELBOARD 'LPN';
CIRCUITS 1, 3, 5.
SYMBOL NOTATIONS: UPPER CASE LETTERS ADJACENT
TO SYMBOLS INDICATE A UNIT TYPE. SEE APPROPRIATE
SCHEDULE OR SPECIFICATIONS.
'LPN'-1,3,5
ELECTRICAL SYMBOL LEGEND
VA PROJECT NUMBER
Building Number
Drawing Number
Project Title
Date Checked Drawn
Drawing Title
Approved:
VA FORM 08-6231
A
B C
D E
21 4 5 6 7
321 4 5 6 7
Dwg. of
LocationLocation
Office of Construction and Facilities Management
PROJECT MANAGER: ACG Project Number
Revisions: Date
CONSULTANTS:
JULY 19, 2021 ADRJVE
626A4-20-10420-171
100% CONSTRUCTION DOCUMENTS
FULLY SPRINKLERED
Headquarters:
Apogee Consulting Group, P.A.
1151 Kildaire Farm Road, Suite 120 Cary, North Carolina 27511 www.acg-pa.com 919-858-7420 © COPYRIGHT Apogee Consulting Group, P.A. 107Engineers Architects
U.S. Department of Veterans Affairs
TVHS- NASHVILLE CAMPUS
1310 24TH AVE S,NASHVILLE, TENNESSEE 37212
TVHS- ALVIN C. YORK CAMPUS
3400 LEBANON PIKE, MURFREESBORO, TENNESSEE 37129
UPGRADE NURSE CALL SYSTEM
NASHVILLE/MURFREESBORO
CAMPUS
T-001
TECHNOLOGY SYMBOLS, NOTES AND
ABBREVIATIONS
TECHNOLOGY GENERAL NOTES
1. ALL COMMUNICATIONS DEVICES AND EQUIPMENT SHALL BE INSTALLED IN ACCORDANCE
WITH THE PROJECT SPECIFICATIONS, THE MANUFACTURER'S RECOMMENDED
PROCEDURES, ALL APPLICABLE LOCAL AND STATE CODES, AMERICANS WITH DISABILITIES
ACT AND WITH THE LATEST EDITION OF THE NATIONAL ELECTRICAL CODE, BICSI
STANDARDS, VA TELECOMMUNICATIONS AND SPECIAL TELECOMMUNICATION SYSTEMS
DESIGN MANUAL.
2. PROVIDE ADDITIONAL SUPPORT FOR DEVICES AND EQUIPMENT WHERE THE BUILDING
CONSTRUCTION IS NOT SUITABLE FOR DIRECT MOUNTING.
3. FIRESTOP, DRAFTSTOP, SMOKESTOP AND/OR PROTECT THE ANNULAR SPACE AROUND
ALL PENETRATIONS THROUGH WALLS, PARTITIONS, FLOORS, CEILINGS, AND ROOF IN
ACCORDANCE WITH THE REQUIREMENTS OF THE NATIONAL ELECTRICAL CODE, UL LISTING
REQUIREMENT AND THE APPLICABLE BUILDING CODES.
4. PROVIDE DRAWINGS SHOWING ALL PENETRATIONS. ALL CABLING SHALL COMPLY WITH
THE LATEST EDITION OF TELECOMMUNICATIONS DISTRIBUTION METHOD MANUAL AND
ANSI/TIA/EIA PUBLICATIONS.
5. COMPLY WITH THE LATEST ANSI/TIA/EIA 607 - STANDARD FOR
TELECOMMUNICATION BONDING COMMERCIAL BUILDING.
6. COMPLY WITH THE LATEST ANSI/TIA/EIA 568 - 2006 STANDARD FOR INSTALLATION
COMMERCIAL BUILDING TELECOMMUNICATIONS CABLING.
7 COMPLY WITH THE LATEST ANSI/TIA/EIA 569 - COMMERCIAL BUILDING STANDARD FOR
TELECOMMUNICATIONS PATHWAYS AND SPACES.
8. COMPLY WITH THE LATEST NFPA 70 NATIONAL ELECTRICAL CODE.
9. COMPLY WITH THE LATEST NFPA 99 HEALTHCARE FACILITIES CODE.
10. COMPLY WITH THE LATEST NFPA 101 LIFE SAFETY CODE.
11. COMPLY WITH THE LATEST OIT DESIGN GUIDE.
12. COORDINATE ANY AND ALL WORK WITH ALL OTHER TRADES PRIOR TO INSTALLATION SO
AS TO AVOID CONFLICT DURING CONSTRUCTION.
13.
14.
MOUNTING HEIGHTS INDICATED ARE TO CENTER OF DEVICE, BOXES, OUTLET, OR
EQUIPMENT UNLESS NOTED OTHERWISE.
15.
ALL CONDUITS SHALL BE RGS OR EMT UNLESS OTHERWISE NOTED.
16.
ALL MATERIALS, DEVICES, APPLIANCES AND EQUIPMENT SHALL BE LABEL LISTED BY AN
APPROVED THIRD PARTY TESTING AGENCY.
17.
ANY DISCREPANCY BETWEEN PLANS AND SPECIFICATIONS SHALL BE BROUGHT TO THE
ATTENTION OF THE VA COR, ARCHITECT, AND ENGINEER OF RECORD FOR CLARIFICATION.
THE MORE STRINGENT OF THE THEM SHALL TAKE PRECEDENCE.
18.
19.
ALL COPPER OUTLETS/CONNECTORS SHALL BE TIA/EIA CAT 6A.
20.
ALL WORK AREA OUTLETS SHALL BE 8 PIN, CAT 6A KEYSTONE JACK WIRED PER T568B AS
DIRECTED BY THE VA COR.
21.
LABELING SHALL BE ACCORDING TO LATEST ANSI/TIA 606A&B EDITION AS WELL AS THE
STANDARDS SET FORTH BY VA HOSPITAL OIT.
INSTALL NURSE CALL SYSTEM PER VA TELECOMMUNICATIONS AND SPECIAL
TELECOMMUNICATIONS SYSTEMS DESIGN MANUAL.
PROGRAM ALL NURSE CALL SYSTEM PER VA REQUIREMENT FOR EACH AREA.
A. CONTRACTOR SHALL COORDINATE PATIENT ROOM(S) WORK WITH THE
NURSE MANAGER AND COR.
B. ROOM(S) WILL BE TURNED OVER TO THE CONTRACTOR FOR WORK AND
WILL BE AT THE DIRECTION OF THE NURSE MANAGER AND COR.
C. THE NURSE CALL WORK SHALL BE DONE ON ONE OR TWO PATIENT
ROOM(S) AT A TIME.
D. AFTER THE FIRST PATIENT ROOM(S) ARE COMMISSIONED ON THE NEW
NURSE CALL SYSTEM, THE CONTRACTOR CAN MOVE TO THE NEXT SET
OF PATIENT ROOM(S).
E. WORK SHALL BE LIMITED TO ONE OF THE WINGS AT A TIME.
F. PRIOR TO CONDUCTING WORK WITHIN SPECIFIC WINGS THE
CONTRACTOR SHALL DO THE FOLLOWING:
F.A. INSTALL NURSE CALL EQUIPMENT CABINETS.
F.B. INSTALL NURSE CALL CONSOLES.
F.C. CONNECT NURSE CALL EQUIPMENT CABINETS TO THE VA IT
NETWORK.
F.D. INSTALL ALL CABLING AND WIRING IN EXISTING OR NEW RACEWAY.
F.E. COMMISSION NEW MASTER CONSOLE AND REMOTE CONSOLES AND
TRAIN STAFF ON FLOOR IN OPERATION OF THE NEW SYSTEM.
F.F. REPLACE ALL NURSE CALL DEVICES WITH NEW DEVICES IN EACH
PATIENT ROOM(S) AND COMMISSION THESE DEVICES.
F.G. REPEAT PROCESS ON WING UNTIL COMPLETE.
F.H. REPEAT PROCESS FOR OTHER WINGS, UNTIL ALL WORK IS
COMPLETE.
F.I. PERFORM FINAL TEST OF THE COMPLETED SYSTEM INCLUDING ALL
NURSE CALL STATIONS, DEVICES, WIRING, TV INTERFACE, AND
LIGHTING INTERFACE. PROVIDE A SPREAD SHEET FOR EACH TASK
ON AN EXCEL SPREAD SHEET.
F.J. ONCE ALL ROOMS FOR ALL FLOORS ARE COMPLETE, THEN REMOVE
THE EXISTING NURSE CALL EQUIPMENT CABINET, MASTER
CONSOLE AND TURN OVER ALL EXISTING NURSE CALL EQUIPMENT
AND DEVICES TO THE VA/COR.
PHASING NOTES
22. ALL NURSE CALL CABLING SHALL BE IN MINIMUM 3/4" CONDUIT.
24. BASIS OF DESIGN IS FACILITY STANDARD:
· DASHBOARDS AND REPORTS
· CENSUS BOARDS
· ENTERPRISE CONFIGURATION
· PATIENT MANAGEMENT INTEGRATION - STAFF ASSIGNMENT AND SHARING
INTEGRATION
· PHONE INTEGRATION
· EVENT INTEGRATION
· STAFF DASHBOARDS AND REPORTS
· STAFF LOCATION AND DURESS INTEGRATION
· CLINICAL MOBILE STAFF APP CAPABLE
DEDUCT ALTERNATE NO. 1: INCLUDES ALL WORK IN BASE BID, BUT EXCLUDE ALL WORK SHOWN
ON SHEETS 17TD111 AND 17TN111.
DEDUCT ALTERNATE NO. 2: SAME AS DEDUCT ALTERNATE NO. 1 BUT EXCLUDE ALL WORK IN
BUILDING 106.
DEDUCT ALTERNATE NO. 3: SAME AS DEDUCT ALTERNATE NO. 2 BUT EXCLUDE ALL WORK
ASSOCIATED WITH ROOMS LABELED "EXAM" WITHIN THE DEFINED
LIMITS ON SHEETS 117TN111.
DEDUCT ALTERNATE #
23. CONTRACTOR SHALL REMOVE ALL OLD NURSE CALL WIRING, DEVICES, DOME
LIGHTS, NURSE CALL EQUIPMENT PANELS, CODE BLUE PANELS, CODE BLUE
ANNUNCIATOR IN OPERATOR'S OFFICE, NURSE CALL PANIC BUTTONS, CODE BLUE
BUTTONS, BATHROOM PULL STATIONS, SERVERS AND CABLING TO SERVERS,
UNUSED CONDUITS ABOVE CEILINGS, AND ANY OTHER COMPONENTS OF THE
EXISTING SYSTEMS THAT ARE BEING REPLACED UNLESS OTHERWISE NOTED OR
INDICATED ON THE DRAWINGS. COORDINATE WITH COR PRIOR TO ANY REMOVAL.
DocuSign Envelope ID: BA659FA3-E303-449B-A1FA-811899152E7D
AREAWAY
STAIR
Ra mp
U p
HISTO LAB
P&H STORAGE
(11'x24')
HAZZARD WASTE
(8'x12')
NO 9
CRAWL SPACE
WAITING SPACE
CB-14A
STRETCHER
ALCOVE
CB-24A
TOILET
E-18B
OTHER
F-7C
TELEPHONE CLOSET
F-2A
HONEYWELL RM
D-72
TOILET
LINEN
D-23
DRESS
D-53A
DRESS
D-54A
TOILET
D-53B
TOILET
D-54B
TOILET
D-51B
TOILET
D-52B
CHASE
C-04A
BD
ELECTRICAL
CLOSET
D-30
TELE CLOSET
C-07E
BC ELEC
CLOSET
C-07D
ELECTRICAL
CLOSET
C-07C
CLOSET
MALE
TOILET
C-08D
FEMALE
TOILET
C-08B
FEMALE
STAFF
TOILET
G-51
FEMALE
STAFF
TOILET
G-55
CLOSET
G-46
CLOSET
G-08A
ELECTRICAL
CLOSET
A-22A
ELECTRICAL
CLOSET
BB
FROZEN
SECTION
G-18 B-A118
PEST CONTROL
WORK RM
E-18A
PETT SCAN
D-40
CORRIDOR
CB-23
OFFICE
F-11A
ELEVATOR LOBBY
CB-F1
CORRIDOR
CB-4
SWITCH GEAR
E-11
BSLE LAB
D-12D
CORRIDOR
CB-12
AREAWAY
CORRIDOR
CB-15
CORRIDOR
CB-13
BOILER RM
E-25F
CORRIDOR
CB-9C
CORRIDOR
CB-3
SCRUB UP
ALCOVE
CB-3C
CLEAN CORE
CB-3
CLEAN CORE
CB-3
FAN RM - 4
B-B105
MECH RM
AHU-26
FAN RM 11
C-07I
CLEAN
ALCOVE
C-07
MED
PREP
C-07A
C-07J
C-07K
C-07L
CLINICAL
NURSE
LEADER
C-07M
STORAGE
ALCOVE
SPD
C-07N
C-07O
C-07P
STORAGE
ALCOVE
SHOWER /
TOILET
C-07Q
C-07R
C-07S
C-07T
C-07U13
C-07V
EMERGENCY
GENERATOR
B-G124B
FAN RM 5
B-G124
ELECTRICAL
B-G124A
MECH EQUIP
F-10
CORRIDOR
CB-14
RECEIVING
AND
SHIPPING
DOCK
CORRIDOR
CB-18
STORAGE
E-23
STORAGE
E-23A
RECEIVING & ISSUE AREA
EQUIP STORAGE FORMS
STORAGE
E-22
CORRIDOR
CB-17
STORAGE
E-09A
STAFF
TOILET
E-08
STORAGE
D-68C
E-10
E-10A
MAIL RM
E-14
ELEVATOR
EQUIP
E-13
CORRIDOR
CB-16
CORRIDOR
CB-16B
CORRIDOR
D-26
CORRIDOR
CB-20
CORRIDOR
CB-19
STORAGE
D-13
FILTER STORAGE
F-6A
STORAGE
F-5
OFFICE
F-4
DUCT SHAFT
OFFICE
F-3
ELECTRICAL
CLOSET
F-2
JANITOR
CLOSET
F-1
VACANT
HOUSE
KEEPING
F-6
OFFICE
F-6B
IRM
F-6A
STORAGE
F-9C
TOILET
D-16
BIOMED SHOP
D-15
CONTROL RM
F-11B
F-11
COMPRESSOR RM
F-12
CLOSET
F-12A
MECH EQUIP
CRAWL SPACE
F-8
TRANSFORMER RM
F-14
ELECTRICAL
F-13
SHOP
F-9
PIT
OFFICE
F-9A CB-F4
STORAGE
F-9B
STORAGE
D-14
CORRIDOR
CB-24
CORRIDOR
CB-24
CORRIDOR
CB-11
CYTO LAB
D-05
CORRIDOR
CB-10
CORRIDOR
CB-9D
CORRIDOR
CB-9
CORRIDOR
CB-16E
CORRIDOR
CB-16C
CORRIDOR
CB-16A
MECH
E-5
BIOMED ENG
REPAIRING &
DEVELOPMENT
E-01
CONTROL RM
D-18MRI
D-17
ELECTRICAL SHOP STORAGE
D-68A
ELECTRONICS
D-68B
KEY SHOP
D-69
MULTI PURPOSE
E-09E
OFFICE
E-11A
VESTIBULE
E-09
TOILET
E-12
ELEVATOR
P-9
EQUIP RM
E-19
OFFICE
E-22A
MED GAS
E-21
MED GAS
E-20
PEST
CONTROL
OFFICE
E-18ELECTRICAL
E-17
OFFICE
E-14A
SIGNAL
E-15
SIGNAL
E-16
SVC RM
E-26
GROUNDS EQUIP
E-25
CLOSET
E-25A
BOILER OPERATOR
E-25E
A/C OPERATIONS
SHOP
E-25B
FIRE EXT
FLAM
STORAGE
E-24
E-25C
GROUNDS
& TRANS
E-25D
CORRIDOR
CB-19
CORRIDOR
CB-22
PACU
G-56
CORRIDOR
CB-9A
CORRIDOR
CB-1
ELEVATOR LOBBY
CB-1A
CORRIDOR
CB-24
CORRIDOR
CB-21
EQUIP STORAGE & TESTING
B-01
DISPATCH AREA
B-01A
DECONTAMINATION RM
B-02
PREPARATION, ASSEMBLY
& STERILIZATION
B-02B
STERIS RM
B-01B
OFFICE
B-02A
EQUIP
B-01C
VESTIBULE
CB-19A
EMERGENCY
GENERATOR RM
E-25G
EMERGENCY
GENERATOR RM
E-25H
CORRIDOR
CB-7
ELECTRICAL
CLOSET
A-16
CORRIDOR
CB-8
SCRUB
CB-3B
CORRIDOR
CB-6A
STORAGE
CB-5
CORRIDOR
CB-6
FLOW CYTOMETRY
A-04
OFFICE
A-04A
OFFICE
A-04B
CORRIDOR
CB-6
EMBALMING
A-03
CHEMISTRY
A-17
BLOOD BANK
A-14
TOILET
C-02
SIGNAL
CLOSET
C-01
WAITING
C-03
ELECTRICAL
CLOSET
A-15
BA2
COMM
CLOSET
A-17A
OFFICE
A-14A
CENTRAL STORAGE
A-17G
FEMALE
TOILET
A-06
ELEVATOR
EQUIP
A-05
ELEVATOR
S-1
AUTOPSY
A-02
A-01BA-01D
A-01C
CHEM SUPER
LEAD TECH
A-17F
LEAD TECH
A-17E
LEAD TECH
A-17D
OFFICE
A-07
HAC
A-08
PATH CHIEF
A-09
HEMA SUPER
A-17C
FEMALE
TOILET
A-10
FEMALE
TOILET
A-11
MULTI PURPOSE
A-17B
MALE
TOILET
A-12
MALE
TOILET
A-13
OFFICE
D-06A
ELEVATOR
FS-1
ELEVATOR
FS-2
MRI
D-19
FILM PROCESSING LAB
D-24
CORRIDOR
CB-12
RADIOGRAPHIC
FLUOROSCOPIC
D-54
MULTI PURPOSE
D-73A
ELECTRICAL ENG
D-70 OFFICE
D-71
STAFF
D-65B
STAFF
D-65A
WAITING
D-02
MALE TOILET
D-49
RADIOGRAPHIC
FLUOROSCOPIC
RM
D-51
RADIOGRAPHIC
FLUOROSCOPIC
D-52
RADIOGRAPHIC
FLUOROSCOPIC
D-53
COMPUTER
RM
D-57CONTROL
D-24A
MICRO LAB
D-12
T C LAB
D-12E
GEN WASH
D-09
ELECTRICAL
CLOSET
A-26
READING RM
D-04
CUTTING RM
D-05A
SAW RM
MULTI PURPOSE
D-05C
SCREENIING
D-06
FEMALE TOILET
D-07
MALE TOILET
D-08
BLK STORAGE
D-05D
MICRO OFFICE
D-05E
WORK RM
D-12C
ANTE RM
D-12B
OFFICE
D-12A
BD2
D-11
BD1
D-10
ELECTRICAL
CLOSET
D-29
STORAGE
D-28E
SCRUB/WORK
AREA
D-24B
DARK RM
CONTROL
D-51C
CONTROL
D-52C
DARK RM
D-22A
MAMMOGRAPHY
D-22
READING RM
D-21
VESTIBULE
D-20
HC TOILET
D-20A
HC TOILET
D-20B
LOUNGE/LOCKERS
D-58
CONTROL
D-53C
CONTROL
D-54C
HAC
D-55
STORAGE
D-56
CHEST RM
D-62
TOILET
D-63
TOILET
D-64
CONTROL RM
D-61
AUTOMATED
RADIOGRAPHIC
D-60
PROCEDURE
ROOM
D-59
ELECTRIC SHOP
D-68
SWITCHBOARD RM
D-67
D-66
OFFICE
E-09B
OFFICE
E-09C
OFFICE
E-09D OFFICE
E-09F
OFFICE
E-09G
OFFICE
E-09H
BUSINESS
RM
E-09I
OFFICE
E-09J
C-07H
A/C SHOP
E-27
MAINT
FOREMAN
E-07
OFFICE
E-08
OFFICE
E-08A
A/C
FOREMAN
E-06
PAINT
SHOP
E-05
CARPENTER
SHOP
E-04
MACH
SHOP
E-03 ELECTRICAL
CLOSET
BE
E-26A
PLUMBING SHOP
E-02
OFFICE
E-01C
BIOMEDICAL
ENGG
STORAGE
E-01B
RECEIVING &
CLEANING
E-01A
ELECTRICAL RM
B-01F
BLDG MGT
LOCKERS
B-03
ELEVATOR
P-3
ELEVATOR
P-4
ELEVATOR
P-5
BLDG MGT
TOILET
B-03A
VESTIBULE
CONSULT/
MEDITATION
C-03A
SOILED
C-07G
SOILED
UTILITY
G-56A
RECOVERY
STORAGE
G-56B
OFF LINE
MONITORING
G-47
ALCOVE
G-49
TELE
G-49C
ELECRICAL
CLOSET
SIGNAL
G-49B
CLEAN
LINEN
G-56D
SIGNAL
G-49A
RECOVERY
CLEAN
UTILITY
G-56E
RECOVERY
NURSE
STATION
RECOVERY
ISOLATION
BEDROOM
G-54
G-53
ANTE RM
G-56C
RECOVERY
ISOLATION
BEDROOM
G-52
PACU
G-50
BATH
G-48A
ON CALL
G-48
HAC
G-43
OFFICE
C-09
FEMALE LOCKER
C-08A
MALE LOCKER
C-08C
STAFF
MULTIPURPOSE
C-08
NURSE
MANAGER
C-07W
HAC
C-06
CLOSET
C-07B
C-07F
CLEAN EQUIP /
SUPPLY
C-05
ELECTRICAL
CLOSET
C-04
GAS STORAGE NURSE
MGR
OFFICE
B-01Q
MALE
LOCKERS
B-01O
MALE
TOILET
B-01P
FEMALE
TOILET
B-01N
FEMALE
LOCKERS
B-01M
HAC
B-01L
SPD CHIEF
& ASSIST
B-01K
LOGISTICS
SUPV
B-01J
SPD ADMIN
B-01I
LOGISTICS ITEM
MGRS
B-01H
BREAKOUT AREA
B-01G
LOGISTICS ITEM
MGRS
B-06
ENGG TOILET
B-04A
ENGG
LOCKERS
B-04
HAC
B-05
OFFICE
D-73
OFFICE
D-74
STORAGE
D-74A
OFFICE
D-73D
OFFICE
D-73C
CLERICAL OFFICE
D-73B
STAFF
D-65C
STAFF
D-65D
STAFF
D-65E
RESIDENT/
INTERN
D-65F
CONFERENCE/ CLASS RM
D-65G
ADP
D-01
SIG
CLOSET
D-02G
CHIEF TECH
D-50
SVC CHIEF
D-65
SEC
D-65I
RECEPTION & SEC
D-65H
ELEVATOR
S-2
ELEVATOR
S-1
FEMALE TOILET
D-48
TECH
D-03A
HOT LAB
D-40D
TREAT
D-40E
TREAT
D-40F
TOILET
D-40C
CTRL RM
D-40B
MULTI
VIEWING
D-41
MULTI
VIEWING
CB-12D
D-42
STORAGE
CB-12C
D-43
MULTI
VIEWING
D-44
MULTI
VIEWING
D-45
OFFICE
D-46
ADP
COORD
D-47
ELECTRICAL
CLOSET
D-02F
OFFICE
D-02E
OFFICE
D-02D
GANTRY
D-40A
OFFICE
D-02C
OFFICE
D-02B
OFFICE
D-02A
ADP COMPUTER RM
D-03
FEC
ELEVATOR
P-8
OFFICE
A-19D
LAB SEC
A-19
TISSUE TYP
A-20
FLOW CYTO
A-20A
ANCILLARY LISTING
A-21
RADIATION SAFETY
& EQUIP RM
A-25P
EXIST TELEPHONE EQUIP RM
ULTRASOUND 2
A-25K
VIEWING/
CONFERENCE
A-25J
SEC
A-25H
CHIEF
A-25I
TELE
EQUIP
EXPANS
A-22
HOT LAB
A-25O
BIOCHEMISTRY LAB
A-25N
ULTRASOUND 3
A-25L
ULTRASOUND 4
A-25M
ELECTRICAL
CLOSET
A-25R
BA2
EXAM
EQUIP STORAGE
A-25S
OFFICE
A-19E
OFFICE
A-19F
MULTI-PURPOSE
A-19A
OFFICE
A-18
OFFICE
A-19B
OFFICE
A-19C
ELECTRICAL
CLOSET
A-27
COMPUTER RM
A-25U
NUCLEAR IMAGING
A-25T
HAC
A-25W
ULTRASOUND 1
A-0V
WAITING RM
A-25X
RCPT &
FILES
A-25
TOILET
A-25A
STAFF
TOILET
A-25B
OFFICE
HOUSE
STAFF
A-25C
STAFF
LOUNGE
A-25D
EXIST
FIRE
ALARM
PANELS
A-23
STAFF
NON-PHYSICIAN
OFFICE
A-25E
STAFF
PHYSICIAN
OFFICE
A-25F
STUDY
CUBICLES
A-25G
VEST
B-01R
ANEST
WORK RM
B-07
ANEST EQUIP
STOR
SCRUB-UP
ALCOVE
G-33
EXT RAD
CONTROL
G-32
NEUROSURGERY O R 9
G-36
SUB STERILE
G-37
PUMP
TECHS
PREP RM
G-36A
CARDIAC OR 8
G-38
CORRIDOR
CB-2C
CORRIDOR
CB-2B
CORRIDOR
CB-2
CHIEF
G-08
OFFICE
G-11
FEMALE SHOWER
G-23B
DICTATING
G-23A
MALE LOCKERS
G-24BMALE TOILET
& SHOWER
G-24A
CLEAN
CORE
SUPPORT
G-34
VESTIBULE
HAC
B-02F
TOILET
B-02D
TOILET
B-02E
ELEVATOR
P-6
ELEVATOR
P-7 FEMALE TOILET
G-23C
FEMALE
LOCKERS
G-23D
VESTIBULE
STAFF LOUNGE
G-23
PHYSICIAN
LOUNGE
G-24
ORTHOPEDIC OR 7
G-39
OFFICE
G-28
SCRUB UP
ALCOVE
G-29
SCRUB-UP
ALCOVE
G-30
OFFICE
G-31
EQUIP
G-28A
SUB
STERILE
G-42
PLASTER &
SPLINTS
G-41
EQUIP
STORAGE
G-40
OPERATING RM
GENERAL
G-27
SUB STERILE
G-26A
OPERATING RM
GENERAL
G-26
GENERAL
OPERATING RM
G-25SUB
STERILE
G-21A
OPERATING RM
GENERAL
G-21
OPERATING RM
GENERAL
G-19
SCRUB
SUB
STERILE
G-19A
REC & OR
HEAD NURSES
G-01
ELECTRICAL
CLOSET
G-22
PHONE/SGNL RM
G-20A
G-20B
G-20C
EQUIPMENT
G-20
HOLDING
G-17
OFFICE
G-02A
ANESTHESIOLOGY
SERVICE
G-02
OFFICE
G-02E
OFFICE
G-02D
OFFICE
G-02C
OFFICE
G-02B
CONTROL
G-03
OFFICE
G-15
ON CALL
G-16
OFFICE
G-04
STAFF
TOILET
G-15A
STAFF
TOILET
G-15B
OFFICE
G-07
SEC
G-13
CONFERENCE RM
G-14
HAC
G-12
ELEVATOR
LOBBY
CB-10A
ELEVATOR
LOBBY
CB-16D
NUCLEAR
CARDIOLOGY
A-25Q
HAZ.
HAZ.
45 & 30 KVA
MENS
RESTROOM
WOMENS
RESTROOM
45 KVA
HOUSE KEEPING
STORAGE
75 KVA
EQUIP
F-7A PEN
D-19A
RECOVERY
BED RM
RECOVERY
BED RM
RECOVERY
BED RM
RECOVERY
BED RM
RECOVERY
BED RM
RECOVERY
BED RM
RECOVERY
BED RM
RECOVERY
BED RM
RECOVERY
BED RM
RECOVERY
BED RM
STRETCHER
ALCOVE
WC
ALCOVE
STRETCHER
ALCOVE
WC
ALCOVE
STERILE STORAGE
30KVA
112.5 KVA
MULTI-PURPOSE
B-G127S
TLT
B-B101G
ALCOVE
B-G127V
CL
EA
N
SU
PP
LY
B\ -G
7R
PV CV LAB #1
B-B101I
EPS CV LAB #2
B-G127J
CONTROL #1
B-B101J
CV LAB #3
B-B101O
CONTROL #2
B-B101Q
CORRIDOR
B-G127F
VIEW
B-G127O
CV EQUIP #2
B-B101N
SOILED UTIL
B-B101E
PREP/HOLDING
B-G127T
H.A.C B-B101H
CRASH CART
ALCOVE
B-B101R
TLT
1-G127W
CV EQUIP #3
B-B101P
ALCOVE
B-G127W
ALCOVE
B-G127X
CHANGE
B-G127Y
COR.
B-G127Z
CLEAN LINEN
B-G127AA
ALCOVE
B-G127BB
CV
E
QU
IP
#2 B-
B1
N
G-44G-35
G-09H
G-09G
OFFICE
G-04
REFRIGERATOR
STORAGE
OFFICE
ELECTRICAL
CLOSET
G-22
STAIR
F-1
STAIR
NO. 2
STAIR
NO. 1
STAIR
NO. 10
STAIR
NO. 8
STAIR
NO. 7
STAIR
NO. 6
STAIR
NO. 4
MULTIPURPOSE
CB-15
WAITING
OFFICE
D-27G
HOLDING
D-27D
CHANGING
TOILET
D-27E
CT-9
D-27C
CT-…