SEDS Checkpoint Ad-Hoc Deployment Services SOW.docx

DOCX document 52 KB Posted

Attached to
Screening Equipment Deployment Services (SEDS) - Checkpoint (CP)
Solicitation number
TSA25-04-0431
Issued by

About this file

The provided document is a Statement of Work (SOW) for Ad-Hoc Deployment Services related to the unscheduled and unplanned deployment of Checkpoint Screening Equipment. The task order has a base period of one year with four option years, and covers the shipping, rigging, installation, relocation, and decommissioning of checkpoint screening equipment at airports, TSA labs, and other government sites within the United States and potentially internationally. The SOW outlines general and specific requirements for checkpoint deployment services, program management, and deliverables such as monthly status reports, site implementation plans, and decommission checklists. The pricing schedule is provided, with CLINs for program management and various ad-hoc deployment services. The SOW is part of a larger Screening Equipment Deployment Services (SEDS) - Checkpoint (CP) contract opportunity being planned by the Transportation Security Administration.

View the file

Other files

File Type Posted
Checkpoint Pricing Worksheetxlsx.xlsx XLSX spreadsheet
Checkpoint CPSS Task Order SOW.docx DOCX document
SEDS Checkpoint Program Management Task Order SOW.docx DOCX document
SEDS Checkpoint Follow-On RFI final.docx DOCX document
SEDS Checkpoint Deployment Efforts_SOW.docx DOCX document
SEDS CP IDIQ SOW.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Transportation Security Administration Checkpoint - Screening Equipment Deployment Services Ad-Hoc Deployment Services Task Order SOW

Acquisition Program Management office, Deployment and Logistics Division 2-18-2021

Table of Contents

1.Task Order Title: Ad-Hoc Deployment Services2
2.Task Order Information2
2.1.Period of Performance2
2.2.Travel2
2.3.Government Furnished Property (GFP)2
3.Scope2
3.1.Checkpoint Deployment Services – General Requirements2
3.2.Checkpoint Deployment Services – Specific Requirements2
4.Program Management Requirements2
5.Deliverables3
6.Price/Cost Schedule4
7.Contracting Officer’s Representative (COR)5

Task Order Title: Ad-Hoc Deployment Services Task Order Information Period of Performance This task order will have a base period of one (1) year, with four (4) options years.

Travel The Requirements of this Task Order are to perform all of the Travel Tasks as outlined in Section 5.0 of the IDIQ SOW.

Government Furnished Property (GFP) The Requirements of this Task Order are to perform all of the Government Property tasks as outlined in Section 2.6 of the IDIQ SOW.

Scope This Task Order is for Ad-Hoc deployment services related to the unscheduled and unplanned deployment of Checkpoint Screening Equipment. This effort covers the tasks associated with the shipping, rigging, installation, relocation, and decommissioning of Checkpoint screening equipment and peripherals at geographically dispersed airports, TSA labs, other Government sites, and other locations within the United States and potentially International locations requested by TSA.

Checkpoint Deployment Services – General Requirements The Requirements of this Task Order are to perform all of the Checkpoint Deployment Tasks as outlined in Section 3.0 of the IDIQ SOW.

1.1. Checkpoint Deployment Services – Specific Requirements

The Requirements of this Task Order are to perform all of the Checkpoint Deployment Tasks as outlined in Section 4.0 of the IDIQ SOW.

Program Management Requirements The Requirements of this Task Order are to perform all of the Program Management Tasks as outlined in Section 2.0 of the IDIQ SOW.

Deliverables

Title of Deliverable
CDRL Number or n/a if an informal deliverable
Due Date
IDIQ SOW Reference Section
Monthly Status Report
A003
Monthly
2.4.2
Meeting Agenda
n/a
Two (2) Business Days prior to meeting.
2.4.3
Meeting Minutes
n/a
Two (2) Business Days after conclusion of meeting.
2.4.3
DD1149
n/a
Five (5) business days prior to any

equipment movement, with an exception for “Urgent” requests.

2.6

Government Furnished Property Weekly Status Report
A006
Weekly, Monday before Noon EST
2.6
Site Implementation Plan (SIP)
B001
Ten (10) Days after approval of Concept Designs
4.2
Site Survey Report
B002
3-5 Days after completion of a site visit
4.2
Concept Drawings
B003
Ten (10) days after completion of site visit
4.2
Issue for Construction Design
B004
Ten (10) days after approval of concept drawings
4.2
As-built Design
B005
PDF and CAD via email within thirty (30) days of project completion. Quarterly on CD
4.2
Daily Site Report
n/a
Daily, for active site work
4.5
Decommission Checklists
D001
Five (5) Business Days after Decommission
4.5

Price/Cost Schedule

CLIN
Description
Units
Unit Price
Total Price
00001A
Program Management
00002A
Ad-Hoc Unplanned Deployment Services
00003A
Ad-Hoc Unplanned Deployment Services (ITF)
00004A
Ad-Hoc Unplanned Deployment Services (CPSS)
10001A
Program Management
10002A
Ad-Hoc Unplanned Deployment Services
10003A
Ad-Hoc Unplanned Deployment Services (ITF)
10004A
Ad-Hoc Unplanned Deployment Services (CPSS)
20001A
Program Management
20002A
Ad-Hoc Unplanned Deployment Services
20003A
Ad-Hoc Unplanned Deployment Services (ITF)
20004A
Ad-Hoc Unplanned Deployment Services (CPSS)
30001A
Program Management
30002A
Ad-Hoc Deployment Services
30003A
Ad-Hoc Unplanned Deployment Services (ITF)
30004A
Ad-Hoc Unplanned Deployment Services (CPSS)
40001A
Program Management
40002A
Ad-Hoc Unplanned Deployment Services
40003A
Ad-Hoc Unplanned Deployment Services (ITF)
40004A
Ad-Hoc Unplanned Deployment Services (CPSS)

Total Price

Contracting Officer’s Representative (COR)

TSA COR

Name: TBD Phone Number: TBD Email: TBD

Alternate COR Name: TBD Phone Number: TBD Email: TBD

File details come from the government source that posted it. Updated .