TOC.pdf

PDF 74 KB Posted

Attached to
Contract Hazardous Materials Abatement of Cottage #5 in Boulder, Montana
Solicitation number
DEQ-IFB2025-425001
Issued by
Big Horn County, Montana

About this file

This document contains the contract documents for the Montana State Training School Cottage #5 Project in Boulder, Montana. The project involves hazardous materials abatement services, including lead-based paint removal, asbestos removal, and PCB ballast disposal at Cottage #5. The contract documents include the invitation to bid, instructions to bidders, bid form, agreement form, general conditions, supplementary conditions, and technical specifications. The project is scheduled for completion in July 2024, and the contract documents provide information on the required permits, submittals, measurements and payments, and contract closeout procedures.

The contract documents also include various forms, such as the notice of award, notice to proceed, certificates of substantial and final completion, and affidavits related to contractor releases and lien waivers. The attachments include a Phase II Environmental Site Assessment report, a vinyl floor tile lab report, and a location diagram for the 2-inch walls. Pricing terms, set-asides, and funding sources are not explicitly stated in the provided documents.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Montana Department of Environmental Quality

CONTRACT DOCUMENTS FOR THE

Montana State Training School Cottage #5 PROJECT

Boulder Cottage #5 Project July 2024 i

TECHNICAL SPECIFICATIONS

DIVISION 0 – BIDDING AND CONTRACT REQUIREMENTS SECTION

INVITATION TO BID 00100

INSTRUCTION TO BIDDERS 00200

BID FORM 00300

AGREEMENT FORM 00500

GENERAL CONDITIONS FOR PUBLIC WORKS PROJECTS 00700

SUPPLEMENTARY CONDITIONS 00810

MONTANA PREVAILING WAGE RATES FOR BUILDING PROJECTS 2024

DIVISION 1 – GENERAL SPECIFICATIONS

SUMMARY OF WORK 01010

WORK COORDINATION 01043

PERMITS 01060

SUBMITTALS 01070

MEASUREMENTS & PAYMENTS 01150

CONTRACT CLOSEOUT 01700

DIVISION 2 – SITE WORK SPECIFICATIONS

MOBILIZATION 02000

LEAD BASED PAINT REMOVAL 02065

ASBESTOS REMOVAL 02067

PCB BALLAST DISPOSAL 02069

LEAD BASED PAINT ENCAPSULATION 02080

Montana Department of Environmental Quality

CONTRACT DOCUMENTS FOR THE

Montana State Training School Cottage #5 PROJECT

Boulder Cottage #5 Project July 2024 ii

FORMS

NOTICE OF AWARD C-510

NOTICE TO PROCEED C-550

CERTIFICATE OF SUBSTANTIAL COMPLETION C-625a

CERTIFICATE OF FINAL COMPLETION C-625b

WORK CHANGE DIRECTIVE C-940

CHANGE ORDER C-941

FIELD ORDER C-942

AFFIDAVIT ON BEHALF OF THE CONTRACTOR

AFFIDAVIT OF RELEASE OF LEANS

FINAL WAIVER OF LIEN

ASBESTOS PROJECT PERMIT

ASBESTOS WASTE SHIPMENT RECORD

ATTACHMENTS

Attachment A - Phase II ESA Report

Attachment B - Vinyl Floor Tile Lab Report

Attachment C - Location of 2-inch walls

File details come from the government source that posted it. Updated .