Complete Division 2.pdf
PDF 4 MB Posted
- Solicitation number
- DEQ-IFB2025-425001
- Issued by
- Big Horn County, Montana
About this file
This document is a set of specifications for a state and local government contract to provide hazardous materials abatement services at Cottage #5 in Boulder, Montana. The scope of work includes the removal of asbestos-containing materials, lead-based paint, and PCB-containing light ballasts. The contractor must be trained, licensed, and experienced in the proper handling, containment, and disposal of these hazardous materials in accordance with all applicable federal, state, and local regulations. Key requirements include TCLP sampling, worker safety protocols, decontamination procedures, and proper containerization and disposal of all waste materials. The project is scheduled for July 2024, and the contractor will be responsible for all labor, materials, equipment, and incidentals necessary to fully complete the abatement work.
The specifications outline pricing and payment terms, which will be identified in Section 01150. There are no indications of any set-asides or incumbent contractors. Funding requirements and sources are not explicitly stated, but the state and local government agencies involved will be responsible for overseeing and administering the contract.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SERVICE
QUALITY
INTEGRITY
Division 2
Site Work
SERVICE
QUALITY
INTEGRITY
This page left blank intentionally.
Section 02000 Mobilization - Asbestos
Boulder Cottage #5 Project 02000 - 1 of 2 July 2024
PART 1 - GENERAL
1.01 SUMMARY
A. Payment will be made for mobilization & demobilization to cover the costs of preparatory work and operations, including but not limited to those necessary for the movement of personnel, equipment, supplies, materials, and incidentals to the project site; for the establishment of all offices, buildings and other facilities necessary for the Work on the project; for Contractor overhead relating to the project; and for all other work and operations which must be performed or cost(s) incurred including project closeout, final cleanup, moving off of project site upon completion of Work, any costs associated with winter shutdown, costs relating to fees, permits, licenses, insurance, contract bonds and taxes which the Contractor is to obtain or pay, to perform work, and all submittals required that are not paid for under other items.
B. The Contractor shall to the best effort follow an idle-reduction policy as referenced by ASTM Standard E-2893 whenever possible.
C. The Contractor shall to the best effort use heavy equipment with advanced emissions controls operated on ultra-low sulfur diesel as referenced by ASTM Standard E-2893 whenever possible.
D. The Contractor shall minimize the number of mobilizations to the project site.
1. Contractors can enter on Odyssey Lane to access the North Side of Cottage 5 and they can enter through Venture Way to access the South Side.
E. The Contractor shall use best management practices (BMPs) for erosion control and groundwater infiltration measures, as necessary. It is not anticipated that the disturbance will be great enough to require a stormwater pollution prevention plan, but it does not preclude the Contractor from BMPs.
PART 2 - PRODUCTS (NOT USED)
PART 3 - EXECUTION (NOT USED)
PART 4 - MEASUREMENT AND PAYMENT (NOT USED)
4.01 METHOD OF MEASUREMENT
A. Measurement and payment shall be as identified in Section 01150.
END OF SECTION 02000
Section 02000 Mobilization - Asbestos
Boulder Cottage #5 Project 02000 - 2 of 2 July 2024
Section 02065 Lead Based Paint Removal
Boulder Cottage #5 Project 02065- 1 of 8 July 2024
1.01 DESCRIPTION OF WORK
A. Toxicity Characteristic Leaching Procedure (TCLP) Tests will be taken as required for the disposal of building material components removed from the building.
B. All lead-based paint removal must be accomplished in a manner which prevents damage to adjacent surfaces and at all times protects the health and safety of workers, the environment, and the general public. All efforts must be taken to eliminate the potential for dust releases and water runoff during all removal operations.
C. All lead-based paint removal must be performed by trained employees.
D. All removed lead containing materials and the resulting debris require wrapping, bagging, or some other type of proper containerization. All resulting containers of removed materials and/or debris shall be carefully handled.
E. The Contractor must ensure that leaded components, debris, or lead-contaminated materials are not burned or disturbed, so they result in lead exposure to workers, residents, children, the environment, or observers.
F. If components to be removed contain gross areas of loose or peeling paint, these areas shall be wet scraped, or HEPA vacuumed prior to removal. The paint chips shall be contained either in the HEPA vacuum or in a separate 6-mil polyethylene bag.
G. Components which are removed shall be wrapped with 2 layers of 6-mil polyethylene and stored for disposal. All disposals shall be in accordance with the more stringent of all applicable local, state and/or Federal regulations.
1.02 QUALITY ASSURANCE
A. Use adequate numbers of skilled workmen who are thoroughly trained, licensed, and experienced in the necessary skills and crafts and who are completely familiar with the specified requirements and the methods needed for proper performance of the work of this Section.
B. Cited Standards are incorporated herein by reference and govern the work:
1. U.S. Department of Housing and Urban Development (HUD), Guidelines for the Evaluation and Control of Lead-Based Paint Hazards in Housing, Chapter 13 Abatement by Encapsulation, 2nd edition, July 2012
2. Residential Lead-Based Paint Hazard Reduction Act of 1992 (Title X of the Housing and Community Development Act of 1992 (US Public Law 102-550), Section 1017, 42 U.S.C. 4852c)
Boulder Cottage #5 Project 02065- 2 of 8 July 2024
3. Lead Standard: 29 CFR 1910.1025 and 29 CFR 1926.62, U.S. Occupational Safety and Health Administration (OSHA) (1993)
4. ASTM E1908-16 Standard Guide for Sample Selection of Debris Waste from a Building Renovation or Lead Abatement Project for Toxicity Characteristic Leaching Procedure (TCLP) Testing for Leachable Lead (Pb), 2016
PART 2 - PRODUCTS
2.01 MATERIALS
A. TCLP Sampling
1. Provide all materials necessary to complete TCLP sampling, as specified in ASTM Standard E 1908-16.
B. LBP Abatement
1. Polyethylene sheeting - 6-mil thick for covering non-removable items, floors, walls, ceilings, for construction barriers and wrapping objects too large to place into waste disposal bags. Opaque polyethylene shall be used for barriers on public side of enclosures. Nylon, polyester, or fiberglass reinforced polyethylene sheeting shall be used where additional strength is required. Fire retardant polyethylene shall be used where the potential for fire exists.
2. Disposal containers - non-porous, sealable drums for disposal of items which could tear bags.
3. Signs and labels - Illuminated notification signs, visible from all angles of approach to all dwelling units, which comply with OSHA regulations and read "Warning - Lead Work Area - Poison - No Smoking or Eating." Letters shall be in bold lettering that is at least two inches tall. Construction/regulated area caution and warning signs and barrier tape shall also be provided. When at all possible, tape shall be installed 20 feet outside and around soil abatement or dust abatement area. Sign shall indicate "Authorized Personnel Only" without reference to lead abatement or dust lead remediation.
4. Fencing - Temporary security fencing may be required to prevent unauthorized entry into soil lead abatement work areas.
C. LBP Disposal
1. The disposal of the waste from LBP removal must be per Federal, State and local regulations and meet the requirements of the landfill selected for disposal.
2.02 EQUIPMENT
A. TCLP Sampling
Boulder Cottage #5 Project 02065- 3 of 8 July 2024
1. Provide all equipment necessary to complete TCLP sampling, as specified in ASTM Standard E 1908-16.
B. LBP Abatement
1. Provide all necessary equipment for lead-based paint removal and disposal, as well as equipment necessary for site cleanup. Equipment shall include but not be limited to carts, sanders, approved saws and vacuums, water sprayers, landers and scaffolding, lighting, and other abatement equipment.
PART 3 - EXECUTION
3.01 TCLP SAMPLING
A. Follow procedures outlined in ASTM Standard E 1908-16 for TCLP Sampling.
B. Take a minimum of three (3) samples for analysis.
C. Take composite samples of structure following ACM removal.
1. Identify components to be removed.
2. Take sub-samples of each component using a power drill or by removing portions of the component.
3. Mix sub-samples together in proportion to their percent by weight in the total quantity of debris being removed.
4. The resulting weight of the sample must equal or exceed a 100-gram minimum sample weight.
D. Package samples according to ASTM E 1908-16 and send to an approved laboratory for analysis. The Contractor will be responsible for all packaging, shipping, and lab fees.
3.02 ABATEMENT REQUIREMENTS
A. The work area and items to be removed shall first be HEPA vacuumed. All visible, loose debris or dust shall be vacuumed or wet wiped clean.
B. The work area and items to be removed shall be wet misted with a water sprayer or similar device to reduce dust or particles in the air. Whenever dust can be seen in the air as a result of the removal work, spray wet mist the area again to reduce the levels of dust or particles in the air.
C. Conduct all removal work in a slow, careful, deliberate manner to minimize the creation of any dust or debris and to prevent damage to any adjacent surfaces that are to remain. Use all tools in the correct manner appropriate for their design.
Boulder Cottage #5 Project 02065- 4 of 8 July 2024
D. After the lead-based paint components have been removed, HEPA vacuum the area behind the removed component to pick up any loose debris or dust.
E. All removed items which have nails or other sharp fasteners shall have the fasteners removed and/or bent over completely so they will not puncture the bags they are placed in or the plastic they are covered with.
F. Removed items must be cut into small lengths to facilitate carrying and disposal. No removed item shall be longer than 8 feet in length. All cutting shall be completed with hand saws or power saws that are equipped with a shrouded head that is attached to a HEPA vacuum or filtration system.
G. All removed components shall be placed in 6-mil disposal bags or wrapped in 6-mil plastic with all seams securely sealed.
H. All debris, waste, cleaning materials, hardware or other removed items associated with the lead- based painted substrates/components item which is being removed shall be disposed of in separate disposal bags and shall not be included with disposal of the substrate item.
3.03 ABATEMENT COMPONENTS
A. Abatement components may include all or a portion of the following:
1. Windows shall have lead-based paint removed from the window components while protecting the window components from damage to maintain the historical nature of the building.
2. Prior to ceiling and wall removal, all trim (chair rail, baseboard, ceiling molding, etc.) present on the wall shall be removed and safely stored on-site for future reinstallation in the building. All utility lines shall be completely deenergized, capped or turned off, using proper lockout/tagout procedures, at the main service entrance for the area prior to wall substrate removal. The actual wall removal process will employ the use of a cold chisel, reciprocating saw, "sawzall", or sledgehammer (or other appropriate devices). The Contractor shall remove as large a portion of material as possible at a time that can be easily managed, wrapped, and carried. Caution must be exercised to prevent damage to all adjacent surfaces or existing utilities or services which will remain. Wall material and debris shall be containerized at a size that is easily handled and carried.
Unless otherwise noted, all wall materials shall be removed. All studs, blocking and other wall structure shall remain intact, in sound condition (no member cut, moved or otherwise damaged). Wall lead-based painted substrate which is removed shall be frequently cleaned to prevent abatement personnel from standing and working in debris. Large debris shall constantly be removed; other debris shall be shoveled, or HEPA vacuumed as necessary to keep floor area clear.
3.04 LEAD-BASED PAINT COMPONENT DISPOSAL
A. All materials, whether hazardous or non-hazardous, shall be handled, secured, and disposed of in accordance with all laws and the provisions of this Section and any and
Boulder Cottage #5 Project 02065- 5 of 8 July 2024 all other applicable federal, state, county or local regulations and guidelines. It shall be the sole responsibility of the Contractor to assure complete compliance with the more stringent of all laws and regulations relating to any and all hazardous and nonhazardous waste storage, handling, security, and disposal. Until hazardous waste characterization analytical results are available, all waste materials (including water) shall be handled, stored, and secured as hazardous wastes, and stored separately from all other wastes. All wastes shall be separated and segregated into appropriate waste streams.
B. Prior to the start of work, the Contractor must coordinate disposal with an approved disposal facility.
C. During or after the actual abatement, the Contractor shall not: leave debris in the yard or in near-by property; place debris into an unsecured container; incinerate debris; dump debris at any unauthorized location; place debris in any unauthorized dumpster; transport any waste or debris in non-licensed or permitted vehicles; or introduce lead contaminated (non-filtered) water onto soils, into storm sewers (shall not be poured down yard inlet or street drain) or sanitary sewers (shall not be flushed down toilet or any other household, residential or commercial type drain system).
D. The Contractor shall make all efforts to minimize the amount of hazardous waste produced (through accepted practices of waste separation/segregation, etc.).
Additionally, the Contractor shall seek to identify and use a transport, storage, and disposal (TSD) facility that will incinerate, recycle, or reclaim all wastes rather than having wastes sent to a landfill for whole disposal. All wastewater, clean water, and wash water shall be so labeled. All wastewater shall be labeled "filtered" (using 3-micron filter) or "non-filtered". All non-filtered wastewater containers shall be labeled "hazardous waste" and with a date the Contractor began to collect contaminated water in that container. All filtered water must be hazardous waste characterization tested to confirm that it is or is not hazardous and disposed of accordingly.
E. Testing on lead-based painted abatement items or abatement waste materials shall be completed by the Contractor. Testing shall be performed as soon as representative samples are generated. Representative samples for each waste stream will be taken and analyzed to comply with applicable federal, state, county or local regulations and guidelines.
F. Hazardous waste characterization tests will be paid for by the Contractor if the Contractor has unnecessarily separated waste materials and/or debris, so as to create additional waste streams, or if the Contractor has consolidated waste streams and failed to appropriately and properly segregate and separate waste streams from one another.
G. A representative number of samples of the following materials will be tested to determine whether or not they are hazardous:
1. Wastewater - filtered and non-filtered, including all wash water;
2. Dust from HEPA filters;
Boulder Cottage #5 Project 02065- 6 of 8 July 2024
3. All lead-based painted component/substrate items;
4. Plastic sheets, duct tape, or tape used to cover floors or other services during the lead-based paint abatement;
5. Solvents and caustics used during the abatement process (if any);
6. Rags, sponges, mops, scrapers, HEPA vacuum filters, and other materials used for abatement, and clean-up; and,
7. Any other items contaminated with lead-based paint or items produced as a result of lead-based paint abatement activity.
8. Storage, Inspection and Record Keeping Requirements. Any item found to be hazardous, by way of testing, shall be kept in a secured area and lockable container, that is inaccessible to all persons other than abatement personnel. All hazardous waste shall be labeled "Lead-Based Paint Abatement Hazardous Waste" and the date that the Contractor began to collect waste in that container. All hazardous and non-hazardous waste shall be kept in separate containers. All hazardous waste shall be stored, handled, transported, and disposed of in a manner to meet the more stringent of all federal, state, and local requirements.
The Contractor shall, on at least a weekly basis, inspect all waste containers to ensure that the containers and the container integrity are sound and continue to be appropriate for the wastes stored in the containers. The Contractor shall keep a journal which records the results of all container inspections conducted and includes the dates and times of the inspection, as well as the name of the individual(s) conducting the inspections.
3.05 CONFIRMATION SAMPLING
A. Once all known areas of LBP designated for removal have been removed from the buildings, a confirmation survey will be performed by the Contractor using an XRF field instrument calibrated for the standard detection limits for LBP surveys. Suitable sample locations should have adequate, non-faded, and unchipped paint. The confirmation survey will use field screening using the XRF field instrument to determine if any remaining paint is LBP. Remaining LBP components shall be encapsulated per Specification 02080.
B. If LBP is found during confirmation screening, the sample nomenclature for XRF will be numbered in sequential order as determined by the XRF unit. The results of the XRF survey will be recorded on field sheets or the logbook. Locations, if found, will be noted on floor plans for future locating and removal or encapsulation prior to the building renovation. If conditions warrant nomenclature modification, the change will be documented in the logbook.
Boulder Cottage #5 Project 02065- 7 of 8 July 2024
PART 4 - METHOD OF MEASUREMENT AND BASIS OF PAYMENT
4.01 METHOD OF MEASUREMENT AND PAYMENT
END OF SECTION 02065
Boulder Cottage #5 Project 02065- 8 of 8 July 2024
Section 02067 - Asbestos
Boulder Cottage #5 Project 02067 - 1 of 8 July 2024
A. The work specified herein shall be the removal of asbestos-containing material by a Contractor knowledgeable, qualified, and certified in the removal, treatment, handling, and disposal of asbestos-containing material, and the subsequent cleaning of the affected environment, who comply with Federal and State Regulations which mandate work practices, and who are capable of performing the work of this contract.
B. The asbestos removal Contractor shall supply all labor, materials, equipment, services, insurance, and incidentals which are necessary or required to perform the work in accordance with applicable governmental regulations and these specifications.
1.02 REGULATIONS
A. Comply with applicable Federal, State, and local regulations.
1. Title 29, Code of Federal Regulations, Section 1910.1001. and Section 1926.1101.
Occupational Safety and Health Administration (OSHA), US Department of Labor.
2. Title 40, Code of Federal Regulations, Part 61, Subparts A and B, National Emission Standards for Hazardous Air Pollutants. US Environmental Protection Agency (EPA).
3. Statute 75-2-501 et seq., MCA, Asbestos Control
4. ARM 17.74.301-405, Asbestos Control
5. All State, County, and City codes and ordinances as applicable.
1.03 SUBMITTALS, NOTICES, AND PERMITS
A. Post caution signs in and around the work area to comply with OSHA Regulation 29 CFR 1910.1001(g)(1).
B. Manufacturer's certification that vacuums, negative air pressure equipment, and other local exhaust ventilation equipment conform to ANSI 29.2-79.
C. An Asbestos Project Permit Application must be submitted to the Montana Department of Environmental Quality, Asbestos Control Program a minimum of ten (10) business days prior to the start of the asbestos removal project.
D. A copy of the asbestos inspection report must be onsite during the asbestos project or demolition.
1.04 PERSONNEL PROTECTION
Boulder Cottage #5 Project 02067 - 2 of 8 July 2024
A. Prior to the commencement of work, the workers shall be instructed, and shall be knowledgeable, in emergency evacuation and evacuation procedures to be followed in the event of compressor failure shall be included in worker training prior to commencement of work.
B. All respiratory protection shall be provided to workers in conjunction with a respiratory protection program which shall meet the requirements of 29 CFR 1910.134(b)(1-11).
This program shall be posted at the work site.
C. Provide workers with personally issued and marked respiratory equipment approved by The National Institute for Occupational Safety and Health (NIOSH).
D. Respiratory protection shall be worn by all persons potentially exposed to asbestos from the initiation of the asbestos demolition project until all areas have been given clearance. Clearance shall be obtained by visual inspection and air monitoring.
E. Provide authorized visitors with suitable respirators and respiratory training whenever they are required to enter the work area to a maximum of 4 per day.
F. Provide workers with sufficient sets of protective full body clothing. Such clothing shall consist of full body coveralls and headgear. Provide eye protection and hard hats as required by applicable safety regulations. Disposable type protection clothing, headgear, and footwear may be provided.
G. Provide authorized visitors with suitable protective clothing, headgear, eye protection, and footwear whenever they are required to enter the work area, to a minimum of 4 sets per shift.
H. Implement asbestos worker protection procedures that meet all Federal, State, County, and local regulations, and guidelines for worker safety.
1.05 EQUIPMENT REMOVAL
A. Clean surfaces of contaminated containers and equipment thoroughly by wet sponging or wiping before moving such items into the Equipment Decontamination Enclosure System Washroom for final cleaning and removal to uncontaminated areas. Ensure that personnel do not leave the Work Area through the Equipment Decontamination Enclosure.
1.06 QUALITY ASSURANCE
A. Use adequate numbers of skilled workmen who are thoroughly trained, licensed, and experienced in the necessary skills and crafts and who are completely familiar with the specified requirements and the methods needed for proper performance of the work of this Section.
PART 2 - PRODUCTS
2.01 MATERIALS
Boulder Cottage #5 Project 02067 - 3 of 8 July 2024
A. Deliver all materials in the original packages, containers, or bundles bearing the name of the manufacturer and the brand name.
B. Store all materials subject to damage off the ground away from wet or damp surfaces, and under cover sufficient to prevent damage or contamination.
C. Damaged or deteriorating materials shall not be used and shall be removed from the premises and properly disposed of.
D. Plastic (polyethylene) sheet, of 4 mil thickness or greater as specified, in sized to minimize the frequency of joints.
E. Tape - capable of sealing joints of adjacent sheets of plastic sheets and for attachment of plastic sheet to finished or unfinished surfaces of dissimilar materials and capable of adhering under both dry and wet conditions, including use of amended water.
F. Surfactant (wetting agent) - shall consist of 50 percent polyoxyethylene ether and 50 percent of polyoxyethylene polyglycol ester, or equivalent, and shall be mixed with water to provide a concentration of one once surfactant to 5 gallons of water or as directed by manufacturer.
G. Impermeable containers - suitable to receive and retain any asbestos-containing or contaminated materials until disposal at an acceptable disposal site. (The containers shall be labeled in accordance with OSHA Regulation 29 CFR 1910.1200(f)). Containers must be both air and watertight.
H. Warning labels and signs- as required by OSHA Regulation 29 CFR 1926.1101(k)(7)(iii).
I. Spray or trowel applied fire resistant materials- ULI labeled and listed, asbestos-free (mineral/fiber) (cementitious) material to provide the degree of fire protection required by the applicable building code.
J. Spray or trowel-applied thermal or acoustical insulation material used for patching or replacement must provide performance characteristics equivalent to or better than original material.
2.02 EQUIPMENT
A. Provide suitable tools for asbestos.
1. Negative air pressure equipment- High efficiency particulate absolute (HEPA) filtration systems shall be equipped with filtration equipment in compliance with ANSI 29.2-79, local exhaust ventilation. No air movement system or air filtering equipment shall discharge unfiltered air outside the Work Area.
PART 3 - EXECUTION
3.01 STRUCTURAL ASSESSMENT
Boulder Cottage #5 Project 02067 - 4 of 8 July 2024
A. If it is determined that wall studs must be removed as a part of the ACM removal Work, the Contractor shall hire a licensed Professional Engineer, qualified by the State of Montana to perform Structural Engineering, to investigate the structure to determine if ACM materials can be removed without posing a risk to the integrity of the structure.
3.02 PREPARATION
A. Shut down electric power. Provide temporary power and lighting and ensure safe installation of temporary power sources and equipment per applicable electrical code requirements.
B. Shut down and isolate heating, cooling, and ventilating air systems to prevent contamination and fiber dispersal to other areas of the structure. During the work, vents within the Work Area shall be sealed with tape and plastic sheeting.
C. Pre-clean movable objects within the proposed work areas using HEPA vacuum equipment and/or wet cleaning methods as appropriate and remove such objects from work areas to a temporary location. Where scheduled to be removed, carpeting shall be disposed of as contaminated material.
D. Pre-clean fixed objects within the proposed work areas, using HEPA vacuum equipment and/or wet cleaning methods as appropriate, and enclose within minimum 4 mil plastic sheeting sealed with tape.
E. Clean the proposed work areas using HEPA vacuum equipment or wet cleaning methods as appropriate. Do not use methods that raise dust, such as dry sweeping or vacuuming with equipment not equipped with HEPA filters.
F. Seal off all openings, including but not limited to windows, corridors, doorways, skylights, ducts, grills, diffusers, and any other penetrations of the work areas, with plastic sheeting (minimum of 4 mils thick) sealed with tape. Doorways and corridors which will not be used for passage during work must be sealed with barriers as described in 3.02D.
G. Cover floor and wall surfaces with plastic sheeting sealed with tape. Use a minimum of two layers of 6 mil plastic on floors and two layers of 4 mil plastic on walls. Cover floors first so that plastic extends at least 12 inches up on walls, then cover walls with plastic sheeting to the floor level, thus overlapping the floor material by a minimum of 12 inches.
H. Provide airlocks at entrances to and exits from the work areas.
I. Remove and clean ceiling-mounted objects, such as lights and other items not previously sealed off, that interfere with asbestos abatement. Use handheld water spraying or HEPA vacuum equipment during fixture removal to reduce fiber dispersal. See paragraph for work by other trades.
J. Maintain emergency and fire exits from the work areas, or establish alternative exits satisfactory to fire officials.
Boulder Cottage #5 Project 02067 - 5 of 8 July 2024
K. After preparation of work areas and decontamination enclosure systems, remove ceiling (panels and tiles) within the work areas progressively and carefully, (clean using HEPA vacuum equipment and damp sponge and wrap clean (panels and tiles) in 4 mil minimum thickness plastic and store in building as directed by building owner and dispose of as contaminated waste, L. After preparation of work areas and decontamination enclosure systems, remove plaster ceilings, including lath, furring channel system (grid), wire ties, clips, screws, and other accessory items and dispose of as contaminated waste. Spray ceiling debris and the immediate work area with amended water to reduce dust as the work progresses.
M. In all cases, access between contaminated and uncontaminated rooms or areas shall be through an airlock as described in Section 3.02.H. In all cases, access between any two rooms within the decontamination enclosure systems shall be through a curtained doorway.
N. Construct a workers’ decontamination enclosure system contiguous to the work area consisting of three totally enclosed chambers to conform with standard drawings bound herein as follows.
O. Provide sufficient facilities for worker safety, equipment, and decontamination.
P. Ensure that barriers and plastic linings are effectively sealed and taped. Repair damaged barriers and remedy defects immediately upon discovery.
Q. Visually inspect enclosures at the beginning of each work period.
R. Use smoke methods to test effectiveness of barriers when directed by Engineer.
S. Asbestos abatement work shall not commence until:
1. Arrangements have been made for disposal of waste at an acceptable site.
2. Work Areas and decontaminated enclosure systems and parts of the building required to remain in use are effectively segregated.
3. Tools, equipment, and material waste receptors are on hand.
4. Arrangements have been made for building security.
5. All other preparatory steps have been taken and applicable notices posted and permits obtained.
6. All worker training has been completed and documentation is on site.
T. The work area and items to be removed shall be wet misted with a water sprayer or similar device to reduce dust or particles in the air. Whenever dust can be seen in the air as a result of the removal work, spray wet mist the area again to reduce the levels of dust or particles in the air.
Boulder Cottage #5 Project 02067 - 6 of 8 July 2024
U. Conduct all removal work in a slow, careful, deliberate manner to minimize the creation of any dust or debris and to prevent damage to any adjacent surfaces that are to remain.
Use all tools in the correct manner appropriate for their design.
V. After the lead-based paint substrates/components have been removed, HEPA vacuum the area behind the removed substrate/component to pick up any loose debris or dust.
W. All removed items which have nails or other sharp fasteners shall have the fasteners removed and/or bent over completely so they will not puncture the bags they are placed in or the plastic they are covered with.
X. Removed items must be cut into small lengths to facilitate carrying and disposal. No removed item shall be longer than 8 feet in length. All cutting shall be completed with hand saws or power saws that are equipped with a shrouded head that is attached to a HEPA vacuum or filtration system.
Y. All removed substrates/components shall be placed in 6-mil disposal bags or wrapped in 6-mil plastic with all seams securely sealed.
Z. All debris, waste, cleaning materials, hardware or other removed items associated with the lead- based painted substrates/components item which is being removed shall be disposed of in separate disposal bags and shall not be included with disposal of the substrate item.
3.03 ASBESTOS REMOVAL
A. Spray asbestos material with amended water, using spray equipment capable of providing a "mist" application to reduce the release of fibers. Saturate the material sufficiently to wet it to the substrate without causing excess dripping. Spray the asbestos material repeatedly during the work process to maintain wet conditions and to minimize potential asbestos fiber dispersion.
B. In order to maintain indoor asbestos concentrations at a minimum, the saturated asbestos must be removed in manageable sections. Material shall not be allowed to dry out. Material drop shall not exceed 15 feet.
C. Seal filled containers. Place caution labels on containers in accordance with OSHA Regulation 29 CFR1926.1101(k)(7) if not already preprinted on containers. Clean external surfaces of containers thoroughly by wet sponging in the designated area. Move containers to the washroom, wet clean each container thoroughly, and move to holding area pending removal to uncontaminated areas. Ensure that containers are removed from the holding area by workers who have entered from uncontaminated areas dressed in clean coveralls. Ensure that workers do not enter from uncontaminated areas into the washroom or the work area; ensure that contaminated workers do not exit the work area through the Equipment Decontamination Enclosure System.
D. After completion of stripping work, all surfaces from which asbestos has been removed shall be wet brushed and sponged or cleaned by an equivalent method to remove all visible material. During this work, the surfaces being cleaned shall be kept wet.
Boulder Cottage #5 Project 02067 - 7 of 8 July 2024
E. After substrate is dry and is visibly free of asbestos materials and before plastic sheeting is removed, the plastic sheeting and substrate shall be sprayed with one (1) coat of approved encapsulate sealer following manufacturer's recommendations for applications.
F. If at any time during the removal, air sampling or visual inspections indicate contamination of areas outside the work area, immediate steps shall be taken by the contractor to decontaminate these areas. Unprotected individuals shall be prohibited from entering contaminated areas until air sampling and visual inspections verify decontamination has been completed.
3.04 CLEANUP
A. After cleaning the work area, wait at least 24 hours to allow for the settlement of dust, and again wet clean and/or clean with HEPA vacuum equipment all surfaces in the work area. After completion of the second cleaning operation, perform a complete visual inspection of the work area to ensure that the work area is free of contamination.
B. Sealed drums and all equipment used in the work area shall be included in the cleanup and shall be removed from work areas via the Equipment Decontamination Enclosure at an appropriate time in the cleaning sequence.
C. If the Inspector finds visible accumulations of dust in the work area, the contractor shall repeat the wet cleaning until the work area is in compliance, at the contractor's expense.
3.05 DISPOSAL OF ACM
A. Prior to the start of Work, the Contractor must coordinate disposal with an approved disposal facility.
B. The Contractor shall obtain and complete the Asbestos Waste Shipment Record as required by the Montana Department of Environmental Quality (MTDEQ).
C. As the work progresses and to prevent exceeding available storage capacity on site, remove sealed and labeled containers of asbestos waste and dispose of such containers at an authorized disposal site in accordance with the requirements of the MTDEQ.
Submit documentation regarding ACM waste disposal, including copies of the Waste Disposal Record and bill-of-ladings to the Engineer.
D. Sealed plastic bags must be placed in the appropriate transport container unless the bags have been broken or damaged. Damaged bags must remain in the sealed drum.
Workers handling waste materials shall wear appropriate protective clothing and respirators.
E. All wastewater shall be filtered and disposed of in a manner acceptable with the MTDEQ.
3.06 AIR MONITORING AND ANALYSIS
Boulder Cottage #5 Project 02067 - 8 of 8 July 2024
A. Documentation of air sampling must include as a minimum: Calculations of minimum sample volume to achieve necessary detection limits; sampling times; sampling locations (with appropriate diagrams); evidence of periodic inspection of sampling equipment; documentation of pre and post calibration of equipment; detailed description of work conditions; description of worker protective devices; and a description of any atypical environmental conditions.
B. Documentation of sample analysis must include as a minimum: Sample identification;
total sample duration; sample flow rate; total air volume; total fibers counted (with work sheets); total fields counted; blank filter analysis; reticle field area; and fiber concentration in fibers per cubic centimeter. Analytical results must include calculation of detection limits as given in Appendix G of Environmental Protection Agency Publications EPA 560/55-83-002, March 1983, Guidance for Controlling Friable Asbestos- Containing Materials in Buildings:
1. DL = (10 fibers/100 fields/V) (FA/MFA) (1 liter/1000 cm3) Where: DL= detection limit in fibers/cubic centimeter
2. V = Volume of air sampled in liters
3. FA = effective collecting area of the filter in square millimeters (typically 385 mm2 for 25 mm filters)
4. MFA = microscopic field area in square millimeters (typically 0.00785 mm2)
C. A final visual inspection and final clearance will be performed by the Owner’s Representative.
D. Air sampling analysis must be performed by individuals trained in the National Institute for Occupational Safety and Health (NIOSH) 582 course on Asbestos Air Sampling and Analysis. Sample analysis shall be conducted by a non-biased laboratory proficient participant in the NIOSH Proficiency Analytical Testing Program (PAT) for Asbestos. An individual is a proficient participant in NIOSH PAT program if the individual is directly involved in submission of samples to NIOSH or is included in the quality control program for a proficient laboratory.
PART 4 - METHOD OF MEASUREMENT AND BASIS OF PAYMENT
Section 02068 PCB Ballast Disposal
Boulder Cottage #5 Project 02068 - 1 of 6 July 2024
A. All PCB containing light ballast shall be removed in a manner which prevents damage to adjacent surfaces and at all times protects the health and safety of workers, the environment and the general public. All efforts must be taken to eliminate that potential for PCB releases during the removal operations.
B. All removed PCB containing materials require wrapping, bagging or some other type of proper containerization. All resulting containers of removed materials and/or ballasts shall be carefully handled.
C. Proper handling and disposal of PCB containing ballasts with care in appropriate facilities.
D. Any light ballasts that do not have the term “No PCB’s” clearly printed on the original label must be assumed to contain PCB’s and be treated as such. Any light ballasts with the term “No PCB’s” clearly printed on the original label may be disposed of as municipal solid waste.
E. Any light ballasts not containing the term “No PCB’s” clearly printed on the original label must be disposed of in accordance with applicable regulatory and permit requirements and 40 CFR 761.
1.02 QUALITY ASSURANCE
A. Use adequate numbers of skilled workmen who are thoroughly trained, licensed, and experienced in the necessary skills and crafts and who are completely familiar with the specified requirements and the methods needed for proper performance of the work of this Section.
PART 2 - PRODUCTS
2.01 MATERIALS
A. PCB Light Ballast Removal
1. Provide all materials necessary to complete PCB containing light ballasts removal, in accordance with applicable regulations and guidelines.
B. PCB Ballast Disposal
1. Disposal containers – Non-porous, sealable drums for disposal of items which could tear bags.
Boulder Cottage #5 Project 02068 - 2 of 6 July 2024
2. Labels – Permanent ink shall be used to label containers containing PCB light ballasts. Labels shall contain, at a minimum, the date the material was collected, the initials or name of the person who collected the material, the site and location of the collection, and the material contained.
2.02 EQUIPMENT
A. PCB Ballast Removal
1. Provide all equipment necessary to complete PCB Ballast Removal, as specified in these specifications.
B. PCB Ballast Disposal
1. Provide all necessary equipment for PCB Ballast Disposal, as well as equipment necessary for site cleanup. Equipment shall include but not be limited to ladders and scaffolding, lighting, buckets or containers, sealable bags, and other abatement equipment.
PART 3 - EXECUTION
3.01 PCB BALLAST REMOVAL REQUIREMENTS
A. All work must be completed in accordance with regulatory requirements and 40 CFR 761.
B. Arrangements must be made for proper disposal of PCB containing ballasts prior to removing the materials.
C. Power sources should be deenergized prior to removing the materials.
D. Any containers intended for use for transportation or containment of PCB containing ballasts shall be inspected by the Contractor for damage or leaks prior to use.
E. Any leaks or spills must be properly cleaned and remediated, and notification must be provided to the Engineer.
F. Materials shall be stored in DOT Specification containers in conformance with DOT and 40 CFR 761 regulations and suitable for the ballasts being transported and disposed.
G. Any containers containing PCB containing ballasts shall be labelled accordingly with the date the item was placed in the container and the item stored in the container and the site and location the item was obtained.
3.02 PCB BALLAST DISPOSAL REQUIREMENTS
A. Any PCB ballasts shall be disposed of with proper documentation and notification provided to the Engineer.
Boulder Cottage #5 Project 02068 - 3 of 6 July 2024
B. PCB containing ballasts shall be disposed of with proper containment and in an approved facility that is capable of disposing of the waste in accordance with all applicable regulations.
C. Comply with disposal requirements and transportation requirements outlined in applicable regulations and 40 CFR 761.
D. The disposal facility, name, address, and EPA identification number and the Engineer notified of the facility to be used for disposal.
E. Provide a certificate of disposal as identified in 40 CFR 761, Subpart 3 to the Engineer.
3.03 PCB BALLAST HANDLING AND TRANSPORTATION
A. All materials, whether hazardous or non-hazardous, shall be handled, secured, and disposed of in accordance with all laws and the provisions of this Section and any and all other applicable federal, state, county or local regulations and guidelines. It shall be the sole responsibility of the Contractor to assure complete compliance with the more stringent of all laws and regulations relating to any and all hazardous and nonhazardous waste storage, handling, security, and disposal. Until hazardous waste characterization analytical results are available, all waste materials (including water) shall be handled, stored, and secured as hazardous wastes, and stored separately from all other wastes. All wastes shall be separated and segregated into appropriate waste streams.
B. Prior to the start of work, the Contractor must coordinate disposal with an approved disposal facility.
C. During or after the actual abatement, the Contractor shall not: leave debris in the yard or in near-by property; place debris into an unsecured container; incinerate debris; dump debris at any unauthorized location; place debris in any unauthorized dumpster; transport any waste or debris in non-licensed or permitted vehicles; or introduce PCB contaminated (non-filtered) water onto soils, into storm sewers (shall not be poured down yard inlet or street drain) or sanitary sewers (shall not be flushed down toilet or any other household, residential or commercial type drain system).
D. The Contractor shall make all efforts to minimize the amount of hazardous waste produced (through accepted practices of waste separation/segregation, etc.).
Additionally, the Contractor shall seek to identify and use a transport, storage, and disposal (TSD) facility that will incinerate, recycle, or reclaim all wastes, rather than having wastes sent to a landfill for whole disposal.
E. Prior to the start of Work, the Contractor shall complete an EPA Abatement Notification.
F. Hazardous waste characterization tests will be paid for by the Contractor if the Contractor has unnecessarily separated waste materials and/or debris, so as to create additional waste streams, or if the Contractor has consolidated waste streams and
Boulder Cottage #5 Project 02068 - 4 of 6 July 2024 failed to appropriately and properly segregate and separate waste streams from one another.
G. Storage, Inspection and Record Keeping Requirements. Any item found to be hazardous, by way of testing, shall be kept in a secured area and lockable container, that is inaccessible to all persons other than abatement personnel. All hazardous waste shall be labeled "PCB Abatement Waste" and the date that the Contractor began to collect waste in that container. All hazardous and non-hazardous waste shall be kept in separate containers. All hazardous waste shall be stored, handled, transported, and disposed of in a manner to meet the more stringent of all federal, state, and local requirements. The Contractor shall, on at least a weekly basis, inspect all waste containers to ensure that the containers and the container integrity are sound and continue to be appropriate for the wastes stored in the containers. The Contractor shall keep a journal which records the results of all container inspections conducted and includes the dates and times of the inspection, as well as the name of the individual(s) conducting the inspections.
PART 4 - METHOD OF MEASUREMENT AND BASIS OF PAYMENT
4.01 METHOD OF MEASUREMENT
END OF SECTION 02068
Boulder Cottage #5 Project 01010 - 5 of 6 July 2024
Boulder Cottage #5 Project 01010 - 6 of 6 July 2024
Section 02080 Lead-Based Paint Encapsulation
Boulder Cottage #5 Project 02080- 1 of 4 July 2024
A. All LBP encapsulations must be performed by trained employees.
B. The Contractor must ensure that leaded components, debris, or lead-contaminated materials are not disturbed so they result in lead exposure to workers, residents, children, the environment, or observers.
1.02 QUALITY ASSURANCE
A. Use adequate numbers of skilled workmen who are thoroughly trained, licensed, and experienced in the necessary skills and crafts and who are completely familiar with the specified requirements and the methods needed for proper performance of the work of this Section.
B. Cited Standards are incorporated herein by reference and govern the work:
1. ASTM E 1795-17 Standard Specification for Non-Reinforced Liquid Coating Encapsulation Products for Leaded Paint in Buildings, 2017
2. ASTM E 1796-03(2016) Standard Guide for Selection and Use of Liquid Coating Encapsulation Products for Leaded Paint in Buildings, 2016
3. ASTM E1797-12(2017) Standard Specification for Reinforced Liquid Coating Encapsulation Products for Leaded Paint in Buildings, 2017
4. U.S. Department of Housing and Urban Development (HUD), Guidelines for the Evaluation and Control of Lead-Based Paint Hazards in Housing, Chapter 13 Abatement by Encapsulation, 2nd edition, July 2012
5. Residential Lead-Based Paint Hazard Reduction Act of 1992 (Title X of the Housing and Community Development Act of 1992 (US Public Law 102-550), Section 1017, 42 U.S.C. 4852c)
6. Lead Standard: 29 CFR 1910.1025 and 29 CFR 1926.62, U.S. Occupational Safety and Health Administration (OSHA) (1993)
1.03 SUBMITTALS
A. Submit one (1) electronic copy of product literature including technical data and label. Product literature shall include the Approved Encapsulant product, and the same documentation for all supplementary system components.
B. Submit one (1) electronic copy of performance testing reports from an independent testing laboratory demonstrating satisfactory compliance with all requirements of the ASTM E 1795 protocol, and the dry film thickness at which compliance was achieved.
Boulder Cottage #5 Project 02080- 2 of 4 July 2024
C. Submit one (1) electronic copy of a 20-year performance warranty, and any product installation and any application guide relevant to qualifying application for manufacturer’s warranty. The warranty shall cover performance in accord with intent and purpose of encapsulation and definition of abatement of lead-based paint.
Encapsulant warranties, which are limited to claims concerning manufacturer defects, are not acceptable.
D. Submit one (1) electronic copy of an applicator’s proposed guarantee of workmanship for a period of one year from the date of substantial completion.
E. Submit one (1) electronic copy of documentation available from encapsulant manufacturer indicating that the encapsulant composition has been independently reviewed by a certified toxicologist, that the encapsulant has been determined to be non-toxic, and that the encapsulant has been formulated with an EPA accepted and FDA approved, bitter tasting anti-ingestion agent.
1.04 STORAGE OF MATERIALS
A. Storage temperature shall be between 40 F (4.5 C) and 90 F (32 C), or such other ambient temperature conditions as may be specifically recommended by product manufacturer.
B. Encapsulants shall not be permitted to freeze on site, and delivery of encapsulant should be refused if freezing during transit is probable.
C. Avoid storage directly in hot sun exposures.
D. Keep containers tightly closed when not in use.
PART 2 - PRODUCTS
2.01 MATERIALS
A. LBP Encapsulation
1. Polyethylene sheeting - 6-mil thick for covering non-removable items, floors, walls, ceilings, and for construction barriers. Opaque polyethylene shall be used for barriers on public side of enclosures. Nylon, polyester, or fiberglass reinforced polyethylene sheeting shall be used where additional strength is required. Fire retardant polyethylene shall be used where the potential for fire exists.
2. Signs and labels - Illuminated notification signs, visible from all angles of approach to all dwelling units, which comply with OSHA regulations and read "Warning - Lead Work Area - Poison - No Smoking or Eating." Letters shall be in bold lettering that is at least two inches tall. Construction/regulated area caution and warning signs and barrier tape shall also be provided. When at all possible, tape shall be installed 20 feet outside and around soil abatement or dust abatement area. Sign shall indicate "Authorized Personnel Only" without reference to lead abatement or dust lead remediation.
Boulder Cottage #5 Project 02080- 3 of 4 July 2024
2.02 EQUIPMENT
A. LBP Encapsulation
1. Provide all necessary equipment for LBP encapsulation.
PART 3 - EXECUTION
3.01 ENCAPSULATION REQUIREMENTS
A. The work area and items to be encapsulated shall have surfaces prepared first. Follow manufacturer’s recommendations to remove all loose paint, dirt, grease, mildew, mold, and remnants of cleaning products. All visible, loose debris or dust shall be vacuumed or wet wiped clean.
B. Notify Engineer immediately upon determination that surfaces scheduled to receive encapsulant are unacceptable for proper adhesion or subsequent performance.
C. Patch or repair any defects in the surface prior to applying the encapsulant paint.
D. Conduct at least one 6”x6” patch test on each type of building component,…