Complete Division 0.pdf
PDF 4 MB Posted
- Solicitation number
- DEQ-IFB2025-425001
- Issued by
- Big Horn County, Montana
About this file
This document is the Complete Division 0 Bidding and Contract Documents for the Montana Training School Cottage #5 Project located in Boulder, Montana. The project consists of the removal and disposal of all asbestos-containing material (ACM), lead-based paint (LBP), and polychlorinated biphenyl (PCB)-containing light ballasts from Cottage #5, which was previously used as a women's dormitory. The hazardous materials must be properly addressed to allow for the reuse and redevelopment of the property. Qualified contractors are invited to submit bids, which will only be accepted electronically through the QuestCDN website until a specified date. A pre-bid walkthrough is scheduled, and addenda may be issued to clarify or change the bidding documents.
The contract will be awarded to the lowest responsive and responsible bidder. Bidders must demonstrate experience and competence to perform the work, and will be evaluated on criteria such as maintaining a permanent place of business, having adequate equipment and financial status, and relevant technical experience. The contract will require performance and payment bonds, and the contractor must comply with Montana's prevailing wage law and other state requirements.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SERVICE
QUALITY
INTEGRITY
Division 0
Bidding and Contract Documents
SERVICE
QUALITY
INTEGRITY
This page left blank intentionally.
Boulder Cottage #5 July 2024 00100 - 1 of 2
SECTION 00100
INVITATION FOR BIDS
MONTANA TRAINING SCHOOL COTTAGE #5 PROJECT, BOULDER, MT
WWC Engineering (WWC) will receive bids for work associated with the Montana State Training School Cottage #5 Project. The Project consists of removal and disposal of all asbestos-containing material (ACM), removal and disposal of LBP, and removal of PCB-containing light ballasts at Cottage #5 located in Boulder, MT on the Montana State Training School Campus. The building, dating back to its construction in 1923, initially served as the women’s dormitory for the Montana State School for Feeble-Minded Individuals. It continued to operate in this capacity until the 1970s or 1980s when it was left vacant. The hazardous building materials must be properly addressed to allow reuse and redevelopment of the Project.
Bidders will be required to satisfy the OWNER Grantee as to their experience and competence to construct the work as described in the Instruction for Bidders section of the Contract Documents. Qualified contractors are invited to submit bids on this Project.
Complete digital project bidding documents must be downloaded from www.questcdn.com by inputting the project eBidDoc #9238161 into the QuestCDN project search page for a fee of $60.00. Bidders may contact Kyna Christensen at kchristensen@wwcengineering.com for questions related to the Project.
Bids will ONLY be received and accepted via the online electronic bid service through QuestCDN.com until {DATE}, at which time bids will be tabulated by QuestCDN and available on their website. To access the electronic bid worksheet, go to www.questcdn.com and type in the eBidDoc number #9238161 in the project search; download the project documents and click the online bidding button at the top of the advertisement. Prospective bidders must be on the plan holders list through Quest CDN for bids to be accepted. Bids shall be completed according to the Instructions for Bidders. Contractors submitting an electronic bid will be charged an additional $60 at the time of bid submission. Please contact Quest CDN Customer Support at 952-233-1632 or info@questcdn.com for assistance in free membership registration, downloading and working with digital information.
Selection of the successful Bidder will be in accordance with Montana Code Annotated.
Contractors must be prepared to meet all federal requirements for work funded by an EPA Brownfields Grant. Contractors and subcontractors that are Minority, Women, Disadvantaged, Small Businesses and/or Small Businesses in rural areas are strongly encouraged to submit a bid. No bid will be withdrawn within thirty days (30 days) after receipt of bids. Snowy Mountain Development Corporation reserves the right to reject any and all bids and to waive any irregularities therein.
Boulder Cottage #5 July 2024 00100 - 2 of 2
Boulder Cottage #5 July 2024
00200 - 1 of 10
SECTION 00200
INSTRUCTIONS TO BIDDERS
DEFINED TERMS
Terms used in these Instructions to Bidders will have the meanings indicated in the General Conditions and the Supplementary Conditions. Additional terms used in these Instructions to Bidders have the meanings indicated below which are applicable to both the singular and plural thereof:
“Bidder” - The individual or entity who submits a Bid directly to Engineer
“Issuing Office” - The office from which the Bidding Documents are to be issued and where the bidding procedures are to be administered.
“Successful Bidder” - The lowest responsible Bidder submitting a responsive Bid to whom Owner (on the basis of Owner evaluations as hereinafter provided) makes an award.
COPIES OF BIDDING DOCUMENTS
Complete sets of the Bidding Documents in the number and for the deposit sum, if any, stated in the Invitation to Bid may be obtained from the Issuing Office. The deposit will not be refunded.
Complete sets of Bidding Documents must be used in preparing Bids; neither Owner nor Engineer assumes any responsibility for errors or misinterpretations resulting from the use of incomplete sets of Bidding Documents.
Owner and Engineer in making copies of Bidding Documents available on the above terms do so only for the purpose of obtaining Bids on the Work and do not confer a license or grant for any other use.
QUALIFICATION OF BIDDERS
To demonstrate Bidder’s qualifications to perform the Work, within five (5) days of OWNER’s request, Bidder shall submit written evidence, such as financial data, previous experience in performing comparable work, and present commitments.
In determining the lowest responsible bid, the following elements will be considered:
whether the Bidder involved (a) maintains a permanent place of business; (b) has adequate plant and equipment to do the work properly and expeditiously; (c) has a suitable financial status to meet obligations incident to the work; and (d) has appropriate technical experience.
Each Bidder may be required to show that former work performed by him has been handled in such a manner that there are not just or proper claims pending against such work. No Bidder will be acceptable if he is engaged on any other work which impairs his ability to finance his contract. The Bidder shall demonstrate his ability by meeting all requirements herein stipulated, if asked for them.
Pursuant to 75-2-511, MCA, Bidder is required to be accredited by the Montana Department of Environmental Quality, Asbestos Control Program to participate in an asbestos-related occupation.
00200 - 2 of 10
Bidder is advised to carefully review those portions of the Bid Form requiring Bidder’s representations and certifications.
EXAMINATION OF BIDDING DOCUMENTS, OTHER RELATED DATA AND
SITE
Subsurface and Physical Conditions
There are no special provisions for this project.
Copies of reports and drawings referenced in paragraph 5.03.A will be made available by Engineer to any Bidder on request. Those reports and drawings are not part of the Contract Documents, but the “technical data” contained therein upon which Bidder is entitled to rely as provided in paragraph 5.03 of the General Conditions has been identified and established in paragraph 5.03 of the Supplementary Conditions. Bidder is responsible for any interpretation or conclusion Bidder draws from any “technical data” or any other data, interpretations, opinions, or information contained in such reports or shown or indicated in such drawings.
Underground Facilities
Information and data with respect to existing Underground Facilities at or contiguous to the Site is not available for this project.
Hazardous Environmental Condition
The Drawings identify those areas relating to a Hazardous Environmental Condition identified at the Site, if any, that Engineer has used in preparing the Bidding Documents.
Provisions concerning responsibilities for the adequacy of data furnished to prospective Bidders with respect to subsurface conditions, Underground Facilities and other physical conditions, and possible changes in the Bidding Documents due to differing or unanticipated conditions appear in paragraphs 5.03, 5.04, and 5.05 of the General Conditions. Provisions concerning responsibilities for the adequacy of data furnished to prospective Bidders with respect to a Hazardous Environmental Condition at the Site, if any, and possible changes in the Contract Documents due to any Hazardous Environmental Condition uncovered or revealed at the Site which was not shown or indicated in the Drawings or Specifications or identified in the Contract Documents to be within the scope of the Work appear in paragraph 5.06 of the General Conditions.
Upon request, Owner will provide Bidder access to the site to conduct such examinations, investigations, explorations, tests, and studies as Bidder deems necessary for submission of a Bid. Bidder shall fill and compact all holes and clean up and restore the Site to its former condition upon completion of such explorations, investigations, tests, and studies. Bidder shall comply with all applicable Laws and Regulations relative to excavation and utility locates.
Paragraph 7.12.E of the General Conditions indicates that if an Owner safety program exists, it will be noted in the Special Provisions.
It is the responsibility of each Bidder before submitting a Bid to:
Examine and carefully study the Bidding Documents including any Addenda and the other related data identified in the Bidding Documents.
00200 - 3 of 10
Visit the site and become familiar with and satisfy Bidder as to the general, local, and Site conditions that may affect cost, progress, and performance of the Work;
including but not limited to those general and local conditions affecting transportation, disposal, handling and storage facilities, availability of labor, water, power, roads, climactic conditions and seasons, physical conditions at the work Sites and project area as a whole, job site topography and ground conditions, equipment and facilities needed preliminary to and during work prosecution.
Become familiar with and satisfy Bidder as to all Federal, State, and Local Laws and Regulations that may affect cost, progress, or performance of the Work.
Obtain and carefully study (or assume responsibility for doing so) all additional or supplementary examinations, investigations, explorations, tests, studies, and data concerning conditions (surface, subsurface, and Underground Facilities) at or contiguous to the Site which may affect cost, progress, or performance of the Work or which relate to any aspect of the means, methods, techniques, sequences and procedures of construction expressly required by the Bidding Documents, and safety precautions and programs incident thereto;
Agree at the time of submitting its bid that no further examinations, investigations, exploration, tests, studies, or data are necessary for the determination of its Bid for performance of the Work at the price bid and within the times and in accordance with the other terms and conditions of the Bidding Documents.
Become aware of the general nature of the work to be performed by Owner and others at the Site that relates to the Work as indicated in the Bidding Documents.
Correlate the information known to Bidder, information and observations obtained from visits to the Site, reports and drawings identified in the Bidding Documents, and all additional examinations, investigations, explorations, tests, studies, and data with the Bidding Documents.
Promptly give Engineer written notice of all conflicts, errors, ambiguities, or discrepancies that Bidder discovers in the Bidding Documents and confirm that the written resolution thereof by Engineer is acceptable to the Bidders; and
Determine that the Bidding Documents are generally sufficient to indicate and convey understanding of all terms and conditions for the performance of the Work.
The submission of a Bid will constitute an incontrovertible representation by Bidder that Bidder has complied with every requirement of this Article 4, that without exception the Bid is premised upon performing and furnishing the Work required by the Bidding Documents and applying any specific means, methods, techniques, sequences or procedures of construction that may be shown or indicated or expressly required by the Bidding Documents, that Bidder has given Engineer written notice of all conflicts, errors, ambiguities, and discrepancies that Bidder has discovered in Bidding Documents and the written resolutions thereof by Engineer are generally sufficient to indicate and convey understanding of all terms and conditions for performing and furnishing the Work.
PRE-BID CONFERENCE
A Prebid Walkthrough is scheduled for August 19, 2024 at 9:00 am (Venture Way, Boulder, MT). This walkthrough is optional but recommended, PPE will be required to
00200 - 4 of 10 be onsite. Contact Kyna Christensen at kchristensen@wwcengineering.com for additional information about walkthrough.
SITE AND OTHER AREAS
The Site is identified in the Bidding Documents. All additional lands and access thereto required for temporary construction facilities, construction equipment, or storage of materials and equipment to be incorporated in the Work are to be obtained and paid for by Contractor. Easement for permanent structures or permanent changes in existing facilities are to be obtained and paid for by Owner unless otherwise provided in the Bidding Documents.
INTERPRETATIONS AND ADDENDA
All questions about the meaning or intent of the Bidding Documents are to be submitted to Engineer in writing. Interpretations or clarifications considered necessary by Engineer in response to such questions will be issued by Addenda mailed or delivered to all parties recorded by Engineer as having received the Bidding Documents. Questions received less than ten (10) days prior to the date for opening of Bids may not be answered. Only questions answered by formal written Addenda will be binding. Oral and other interpretations or clarifications will be without legal effect.
Addenda may be issued to clarify, correct, or change the Bidding Documents as deemed advisable by Owner or Engineer.
Any addenda issued during the time of bidding or forming a part of the Contract Documents loaned to the Bidder for the preparation of his proposal, shall be covered in the Bid and shall be made a part of the Agreement. Receipt of each addendum shall be acknowledged in the Bid. Any Bid in which all issued addenda are not acknowledged will be considered incomplete and will not be read.
BID SECURITY
A Bid Bond will be required for this project. A Bid must be accompanied by Bid security made payable to Owner in an amount of [10] percent of Bidder’s maximum Bid price (determined by adding the base bid and all alternates) and in the form of a Bid bond issued by a surety meeting the requirements of Paragraph 6.01 of the General Conditions. Such Bid bond will be issued in the form included in the Bidding Documents.
The Bid security of the apparent Successful Bidder will be retained until Owner awards the contract to such Bidder, and such Bidder has executed the Contract, furnished the required Contract security, and met the other conditions of the Notice of Award, whereupon the Bid security will be released. If the Successful Bidder fails to execute and deliver the Contract and furnish the required Contract security within 15 days after the Notice of Award, Owner may consider Bidder to be in default, annul the Notice of Award, and the Bid security of that Bidder will be forfeited, in whole in the case of a penal sum bid bond, and to the extent of Owner’s damages in the case of a damages-form bond. Such forfeiture will be Owner’s exclusive remedy if Bidder defaults.
The Bid security of other Bidders that Owner believes to have a reasonable chance of receiving the award may be retained by Owner until the earlier of 7 days after the
00200 - 5 of 10
Effective Date of the Contract or 61 days after the Bid opening, whereupon Bid security furnished by such Bidders will be released.
Bid security of other Bidders that Owner believes do not have a reasonable chance of receiving the award will be released within 7 days after the Bid opening.
CONTRACT TIMES
The number of days within which, or the dates by which, the Work is to be (a) Substantially Completed and (b) also completed and ready for final payment are set forth in the Agreement.
LIQUIDATED DAMAGES
Provisions for liquidated damages, if any, are set forth in the Agreement.
SUBSTITUTE AND “OR-EQUAL” ITEMS
The Contract, if awarded, will be on the basis of materials and equipment specified or described in the Bidding Documents without consideration of possible substitute or “or- equal” items. Whenever it is indicated in the Bidding Documents that a substitute or “or equal” item of material or equipment may be furnished or used by Contractor if acceptable to Engineer, application for such acceptance will not be considered by Engineer until after the Effective Date of the Agreement. The procedure for submission of any such application by Contractor and consideration by Engineer is set forth in Paragraphs 7.04 and 7.05 of the General Conditions and may be supplemented in the General Requirements or Special Provisions.
SUBCONTRACTORS, SUPPLIERS AND OTHERS
If the apparent Successful Bidder declines to make any such substitution, the Owner may determine such Bidder to be non-responsive and reject the Bid. Declining to make requested substitution will not constitute grounds for forfeiture of the Bid Security of any Bidder. Any Subcontractor, Supplier, individual or entity so listed and against which Owner and Engineer make no written objection prior to the giving of the Notice of Award will be deemed acceptable to Owner and Engineer subject to revocation of such acceptance after the Effective Date of the Agreement as provided in Paragraph
7.06 of the General Conditions.
Contractor shall not be required to employ any Subcontractor, Supplier, individual, or entity against whom Contractor has reasonable objection.
PREPARATION OF BID
The Bid Form is included with the Bidding Documents; additional copies may be obtained from the Engineer. Bids shall be strictly in accordance with the prescribed form. Any modifications thereof or deviations therefrom may be considered as sufficient cause for rejection. Bids carrying riders or qualifications to the Bid being submitted may be rejected as irregular.
All blanks on the Bid Form shall be completed by printing in ink or by typewriter and the Bid signed. A Bid price shall be indicated for each Bid item listed therein, or the words “No Bid”, “No Change”, or “Not Applicable” entered.
00200 - 6 of 10
Bids by a corporation must be executed in the corporate name by the president or a vice-president or other corporate officer who is authorized to bind the corporation, and the corporate seal shall be affixed and attested by the secretary or an assistant secretary. The corporate address and state of incorporation must be shown below the signature. The Bid of a corporation, which is signed by a person other than a corporate officer, must be accompanied by evidence of authority to sign.
A bid by a partnership shall be executed in the partnership name and signed by a partner, whose title must appear under the signature and the official address of the partnership must be shown below the signature.
A Bid by a limited liability company shall be executed in the name of the firm by a member and accompanied by evidence of authority to sign. The State of formation of the firm and the official address of the firm must be shown below the signature.
A Bid by an individual shall show the Bidder’s name and official address.
A Bid by a Joint Venture shall be executed by each Joint Venturer in the manner indicated on the Bid form. The official address of the Joint Venture must be shown below the signature.
The Bid shall contain an acknowledgment of receipt of all Addenda (the numbers of which must be filled in on the Bid Form). Bids in which all issued addenda are not acknowledged will be considered incomplete and will not be read.
The address and telephone number for communications regarding the Bid must be shown.
Current Montana Contractor’s registration number, if any, must be shown.
BASIS OF BID; EVALUATION OF BIDS
Bids
Bidders shall submit a Bid on a unit price and/or lump sum basis for each item of Work listed in the Bid schedule as provided in the Bid form. The Bid will not be considered unless the Bid Form contains prices for all unit price and/or lump sum items, and alternates, as shown on the Bid Form. Bids and totals shall be shown legibly in their proper locations. The total amount of the Bid shall be legibly written and numerically presented in the proper places and the Bid Form shall be manually signed.
The total of all estimated prices will be determined as the sum of the products of the estimated quantity of each item and the unit price bid for the item. The final quantities and Contract Price will be determined in accordance with paragraph 13.03 of the General Conditions.
Discrepancies between the multiplication of units of Work and unit price will be resolved in favor of the unit prices. Discrepancies between the indicated sum of any column of figures and the correct sum thereof will be resolved in favor of the correct sum. Discrepancies between words and figures will be resolved in favor of the words.
00200 - 7 of 10
SUBMITTAL OF BID
Each prospective Bidder is to execute one copy of the Bidding Documents Signature Pages and upload them to the QuestCDN website when they submit their bid. The Bid form is to be filled out online and submitted.
A Bid shall be submitted no later than the date and time prescribed and at the place indicated in the Invitation to Bid. Bids will only be accepted through the QuestCDN website (www.questcdn.com). No Bids will be accepted via mail.
ANY BID WILL BE REJECTED IF:
Alternative Bids will not be considered unless called for.
Bids by telephone, telegraph, fax or other telecommunication systems will not be considered.
MODIFICATION AND WITHDRAWAL OF BIDS
Requests for modification or withdrawal must be written and must be signed in the same manner and by the same person(s) who signed the Bid.
If, within twenty-four hours after Bids are opened any Bidder files a duly signed written notice with Owner and promptly thereafter demonstrates to the reasonable satisfaction of Owner that there was a material and substantial mistake in the preparation of its Bid, that Bidder may withdraw its Bid. Thereafter, if the Work is rebid or negotiated, that Bidder will be disqualified from further bidding on the Work.
OPENING OF BIDS
Bids will be opened at the time set for opening in the Invitation to Bid and, unless obviously non-responsive. An abstract of the amounts of the base Bids and major alternates (if any) will be made available to Bidders after the opening of Bids.
BIDS TO REMAIN SUBJECT TO ACCEPTANCE
All bids will remain subject to acceptance for sixty (60) days after the day of the Bid opening, but Owner may, in its sole discretion, release any Bid and return the Bid security prior to the end of this period.
AWARD OF CONTRACT
Owner reserves the right to reject any and all Bids, including without limitation, nonconforming, non-responsive, unbalanced or conditional Bids. Owner further reserves the right to reject the Bid of any Bidder whom it finds, after reasonable inquiry and evaluation, to be non-responsible. Owner also reserves the right to waive all informalities not involving price, time, or changes in the Work and to negotiate contract terms with the Successful Bidder. Owner reserves the right to reject the Bid of any Bidder if Owner believes it would not be in the best interest of the Project to make an award to that Bidder whether because Bid is not responsive, or the Bidder is unqualified or of doubtful financial ability or fails to meet any other pertinent standard or criteria established by Owner.
More than one Bid for the same Work from an individual or entity under the same or different names will not be considered. Reasonable grounds for believing that any Bidder has an interest in more than one Bid for the Work may be cause for
00200 - 8 of 10 disqualification of the Bidder and the rejection of all Bids in which that Bidder has an interest.
In evaluating Bids, Owner and Engineer will consider whether or not the Bids comply with the prescribed requirements, and such alternates, unit prices and other data, as may be requested in the Bid Form or prior to the Notice of Award.
In evaluating Bidders, Owner will consider the qualifications of Bidders and may consider the qualifications and experience of Subcontractors, Suppliers, and other individuals or entities proposed for those portions of the Work for which the identity of Subcontractors, Suppliers, and other individuals or entities must be submitted.
Owner may conduct such investigations as Owner deems necessary to establish the responsibility, qualifications and financial ability of Bidders, proposed Subcontractors, Suppliers, individuals, or entities to perform the Work in accordance with the Contract Documents.
If the Contract is to be awarded, Owner will award the Contract to the responsible bidder whose Bid, conforming with all material terms and conditions of the Bidding Documents, is lowest price, in the best interest of the Project, and other factors considered, The Owner reserves the right to accept or reject the Bids, or portions of Bids if denoted in the Bid as separate schedules, and to award more than one Bid or schedule for the same Bid if any of the aforementioned combination of Bids or schedules will be in the best interest of the Owner. The Owner reserves the right to cancel the award of any Agreement at any time before the complete execution of said Agreement by all parties without any liability against the Owner.
BONDS AND INSURNACE
Article 6 of the General Conditions, as may be modified by the Supplementary Conditions, sets forth Owner’s requirements as to performance and payment bonds, other required bonds (if any), and insurance. When the Successful Bidder delivers the executed Agreement to Owner, it must be accompanied by required bonds and insurance documentation.
SIGNING OF AGREEMENT
When Owner gives a Notice of Award to the Successful Bidder, it shall be accompanied by the required number of unsigned counterparts of the Agreement with the other Contract Documents which are identified in the Agreement as attached thereto. Within fifteen (15) days thereafter, Successful Bidder shall sign and deliver one (1) counterparts of the Agreement and attached documents to Owner. Within five
(5) days thereafter Owner shall deliver one fully signed counterpart to Successful Bidder.
STATE LAWS AND REGULATIONS
All applicable laws, ordinances and the rules and regulations of authorities having jurisdiction over construction of the project shall apply to the Contract throughout.
State laws and ordinances which the Contractor must comply with, include but are not limited to, those involving workmen’s compensation insurance, contractor registration, employment preference to Montana contractors and Montana residents, Montana Prevailing Wages, and gross receipts tax
00200 - 9 of 10
Contractors shall be registered to bid this project. Registration shall be per Montana Code Annotated 39-9-201. All Subcontractors whose portion of the work is over $2,500 will be required to submit proof of registration with the Department of Labor and Industry (DOLI).
00200 - 10 of 10
Boulder Cottage #5 July 2024 00300 - 1 of 8
SECTION 00300
BID FORM
MT State Training School Cottage #5
Boulder, MONTANA
THIS BID SUBMITTED TO: WWC ENGINEERING
1.01 The undersigned Bidder proposes and agrees if this Bid is accepted, to enter into an
Agreement with Owner in the form included in the Bidding Documents, to perform and furnish all Work as specified or indicated in the Bidding Documents for the prices and within the times indicated in this Bid and in accordance with the other terms and conditions of the Bidding Documents.
1.02 The undersigned Bidder proposes and agrees if this Bid is accepted, to enter into an Agreement with Owner in the form included in the Bidding Documents, to perform and furnish all Work as specified or indicated in the Bidding Documents for the prices and within the times indicated in this Bid and in accordance with the other terms and conditions of the Bidding Documents.
1.03 In submitting this Bid, Bidder represents, as set forth in the Agreement, that:
A. Bidder has examined and carefully studied the Bidding Documents, other related data identified in the Bidding Documents, and the following Addenda, receipt of all which is hereby acknowledged:
Addendum No. Addendum Date
B. Bidder has visited the Site and become familiar with and is satisfied as to the general, local, and Site conditions that may affect cost, progress, and performance of the Work
C. Bidder is familiar with and is satisfied as to all federal, state, and local Laws and Regulations that may affect cost, progress, and performance of the Work.
D. Bidder has carefully studied all (1) reports of explorations and tests of subsurface conditions at or contiguous to the Site and all drawings of physical conditions in or relating to existing surface or subsurface structures at or contiguous to the Site (except Underground Facilities) which have been identified in the Special Provisions as provided in paragraph 5.03 of the General Conditions, and (2) reports and drawings of a Hazard Environmental Condition, if any, which has been identified in the Special Provisions as provided in paragraph 5.06 of the General Conditions.
E. Bidder has obtained and carefully studied (or assumes responsibility for having done so) all additional or supplementary examinations, investigations, explorations, tests, studies and data concerning conditions (surface, subsurface and Underground Facilities) at or contiguous to the Site which may affect cost, Boulder Cottage #5 July 2024 00300 - 2 of 8 progress, or performance of the Work or which relate to any aspect of the means, methods, techniques, sequences, and procedures of construction expressly required by the Bidding Documents to be employed by Bidder, and safety precautions and programs incident thereto.
F. Bidder does not consider that any further examinations, investigations, explorations, tests, studies or data are necessary for the determination of this Bid for performance of the Work at the price(s) bid and within the times and in accordance with the other terms and conditions of the Bidding Documents.
G. Bidder is aware of the general nature of the Work to be performed by Owner and others at the Site that relates to the Work as indicated in the Bidding Documents.
H. Bidder has correlated the information known to Bidder, information and observations obtained from visits to the Site, reports and drawings identified in the Bidding Documents, and all additional examinations, investigations, explorations, tests, studies and data with the Bidding Documents.
I. Bidder has given Engineer written notice of all conflicts, errors, ambiguities, or discrepancies that Bidder has discovered in the Bidding Documents, and the written resolution thereof by Engineer is acceptable to Bidder.
J. The Bidding Documents are generally sufficient to indicate and convey understanding of all terms and conditions for the performance of the Work for which this Bid is submitted.
1.04 Bidder further represents that this Bid is genuine and not made in the interest of or on behalf of any undisclosed individual or entity and is not submitted in conformity with any agreement or rules of any group, association, organization or corporation; Bidder has not directly or indirectly induced or solicited any other Bidder to submit a false or sham Bid; Bidder has not solicited or induced any person, firm or corporation to refrain from bidding; and Bidder has not sought by collusion to obtain for itself any advantage over any other Bidder or over Owner.
1.05 The Bidder certifies that no official of the Owner, Engineer, or any member of such official’s immediate family, has direct or indirect interest in the pecuniary profits or Contracts of the Bidder.
1.06 The Bid Form shall be completed online at www.questcdn.com eBid #9238161. The Bidder will complete the Work in accordance with the Contract Documents for the following price(s):
Item.
No. Description Unit1
Estimated Quantity2
100 Taxes, Bonding, and Insurance LS 1
101 Mobilization/Demobilization LS 1
102 Removal and disposal of all ACM -- Light Insulation Backing on first and second floors
EA 19
103 Removal and disposal of all ACM - vinyl flooring material (including mastic) on first and second floors SF 1,130
Boulder Cottage #5 July 2024 00300 - 3 of 8
Additional Alternative Items
Item No.
Description Unit Estimated Quantity
112 Replace broken windowpanes (ACM, LPB) EA 1
113 Replace/Repair Damage Exterior Door (ACM, LBP) EA 1
Notes:
1. EA = Each, LS = lump sum, LF = linear foot, SF = square foot,
2. Quantities listed are estimates for bidding purposes only; actual quantities may vary from those shown on this Bid Schedule.
3. Bid prices shall include all applicable taxes and fees. Project is located in Jefferson
County.
A. Unit Prices have been computed in accordance with paragraph 13.03.B. of the
General Conditions.
B. Bidder acknowledges that estimated quantities are not guaranteed and are solely for the purpose of comparison of Bids, and final payment for all Unit Price Bid items will be based on actual quantities provided, determined as provided in the Contract Documents.
C. The undersigned agrees that the unit prices shall govern in checking the Bid, and should discrepancy exist in the Total Estimated Price and Total Amount of Unit
Item.
No. Description Unit1
Estimated Quantity2
104 Removal and disposal of all ACM – Vertical Pipe insulation on first floor EA 4
105 Removal and disposal of all ACM - Plaster in first floor hallway
SF 50
106 Removal and disposal of all ACM - Soil & ACM Pipe and Pipe Debris SF 5,180
107 Supply & Laying RCR Liner SF 5,180
108 Removal, disposal, and/or Encapsulation of Lead-based paint on the First-Floor walls and ceiling surfacing
SF 11,060
109 Removal and Disposal of Second Floor LBP ceiling surfacing
SF 3,670
110 Removal, disposal and/or encapsulation of Lead- Based Paint on the Second-Floor walls & door frame surfacing
SF 11,550
111 Removal and Disposal of all encountered PCB containing Light Ballasts throughout the Building
EA 15
Boulder Cottage #5 July 2024 00300 - 4 of 8
Prices Bid as listed above after extensions are checked and corrections made, if any, the Total Amount of Unit Prices Bid as corrected shall be used in awarding this Contract.
D. The Owner reserves the right to reject any or all bids.
1.07 Bidder agrees that the Work will be substantially completed and ready for final payment in accordance with 15.06 of the General Conditions on or before the dates or within the number of calendar days indicated in the Agreement.
1.08 Bidder accepts the provisions of the Agreement as to liquidated damages in the event of failure to complete the Work within the times specified above, which shall be stated in the Agreement.
1.09 The terms used in this Bid with the initial capital letters have the meanings indicated in the Instructions to Bidders, General Conditions, and the Supplementary Conditions.
1.10 Bidder understands that partial bids will not be considered. Successful bidder shall provide cost estimates for Bid Schedules I, II, III, IV, and V.
Boulder Cottage #5 July 2024 00300 - 5 of 8
SIGNATURE PAGES
Please complete the signature pages, sign them, and upload them with your bid at www.questcdn.com, eBid#9238161.
SUBMITTED on , .
(Date) Montana Contractor's Registration # (if any) .
Employer’s Tax ID No. ____________________________________________
If BIDDER is:
An Individual:
(Name typed or printed)
By:
Doing Business as:
(Individual’s Signature
Business Address:
Phone No.: FAX No.:
A Partnership:
(Partnership Name)
(Signature)
(Name, typed or printed)
Boulder Cottage #5 July 2024 00300 - 6 of 8
A Corporation:
(Corporation Name)
State of Incorporation:
Type (General Business, Professional, Service, Limited Liability):
(Signature of person authorized to sign)
Title:
Attest:
(Signature)
Date of Qualification To Do Business Is:
(Corporate Seal) A Joint Venture: Each Joint Venture Must Sign
Joint Venturer Name:
(Name)
(Signature of Joint Venture Partner)
Name:
(Name, printed or typed)
Title:
Boulder Cottage #5 July 2024 00300 - 7 of 8
Joint Venturer Name:
(Name)
(Signature of Joint Venture Partner)
Name:
(Name, printed or typed)
Title:
Address of Joint Venture for Receipt of Official Communication:
Address:
(Each Joint Venture must sign. The manner of signing for each individual, partnership and corporation that is a party to the joint venture should be in the manner indicated above.)
Boulder Cottage #5 July 2024 00300 - 8 of 8
Boulder Cottage #5 Project August 2024 00810 - 1 of 8
SECTION 00810
SUPPLEMENTARY CONDITIONS
These Supplementary Conditions to the General Conditions amend or supplement the Standard General Conditions of the Construction Contract (No. C-700, 2013 Edition) and other provisions of the Contract Documents as indicated below. All provisions that are not so amended or supplemented remain in full force and effect.
SC - 2.03 BEFORE STARTING CONSTRUCTION
Add a new paragraph immediately after paragraph 2.03.A.3 of the General Conditions which is to read as follows:
2.03.A.4 Contractor shall submit a preliminary list of construction equipment with hourly rates, owned or rented by the Contractor and all Subcontractors that will be used in the performance of the work. The equipment list will include information necessary to confirm the hourly rates per Paragraph 13.01.B.5.c of the General Conditions and these Supplementary Conditions including: make, model, and year of manufacture as well as the horsepower, capacity or weight, and accessories.
SC - 2.05 INITIAL ACCEPTANCE OF SCHEDULES
Delete the first paragraph of 2.05.A of the General Conditions in its entirety and insert the following in its place:
Prior to the first application for payment all schedules and documents identified in paragraph 2.03.A shall be finalized and acceptable to the Engineer and Owner. No progress payment shall be made to Contractor until acceptable schedules are submitted to Engineer and Owner as provided below. Acceptance of these schedules and documents by either Engineer or Owner will neither impose on Engineer or Owner responsibility for the sequencing, scheduling or progress of the Work and will not interfere with or relieve Contractor from Contractor’s full responsibility, therefore.
Add the following after Paragraph 2.05.A.3:
Contractor’s Schedule of Construction Equipment will be acceptable to Engineer as to form and substance if it provides the necessary information to reference the equipment and establish the hourly rates in accordance with paragraph 13.01.B.5.c.
SC - 4.01 NOTICE TO PROCEED
Delete the first sentence of Paragraph 4.01.A of the General Conditions and insert the following in its place:
Following the execution of the Agreement by the Owner and the Contractor, written Notice to Proceed with the work shall be given by the Owner to the Contractor. The Contract Time will commence to run on the day indicated in the Notice to Proceed.
SC-4.04 PROGRESS SCHEDULE
Delete Paragraph 4.04.A.1 of the General Conditions in its entirety and replace with the following:
Boulder Cottage #5 Project August 2024 00810 - 2 of 8
1. Contractor shall submit to Engineer with each application for payment an updated progress schedule reflecting the amount of work completed and adjustments to future work. Such adjustments will be acceptable to Engineer as providing an orderly progression of the work to completion within any specified milestones and the Contract Time. No progress payment will be made to Contractor until the updated schedules are submitted to and acceptable to Engineer and Owner. Review and acceptance of progress schedules by the Engineer will neither impose on Engineer responsibility for the sequencing, scheduling or progress of the work, nor interfere with or relieve Contractor from Contractor’s full responsibility, therefore.
SC - 5.01 AVAILABILITY OF LANDS
Add to Paragraph 5.01.C of the General Conditions the following:
If it is necessary or desirable that the Contractor use land outside of the Owner’s easement or right-of-way, the Contractor shall obtain consent from the property owner and tenant of the land. The Contractor shall not enter for materials delivery or occupy for any other purpose with men, tools, equipment, construction materials, or with materials excavated from the site, any private property outside the designated construction easement boundaries or right-of-way without written permission from the property owner and tenant.
SC - 5.03 SUBSURFACE AND PHYSICAL CONDITIONS
Add to Paragraph 5.03.A.4. of the General Conditions the following:
The following reports and drawings are available related to the existing surface structure at the site:
Phase II Environmental Site Assessment for South Campus Montana State Training School Cottage #5 Venture Way, Boulder, Jefferson County, Montana December 2018.
Letter Report, Limited Asbestos Survey, Montana State Training School South Campus Cottage #5, Boulder, Montana, Northern Industrial Hygiene, November 29, 2023
Map of 2-inch Walls, Highlighted, areas where plaster and clay tile are present and must be preserved.
SC – 5.04 - DIFFERING SUBSURFACE OR PHYSICAL CONDITIONS
Add the following to the end of Paragraphs 5.04.A.
Contractor to notify Owner and Engineer in writing about differing subsurface or physical conditions within 15 days of discovery and before disturbing the subsurface as stated above.
No claim for an adjustment in the contract price or contract times (or Milestones) will be valid for differing subsurface or physical conditions if procedures of this paragraph
5.04 are not followed.
Boulder Cottage #5 Project August 2024 00810 - 3 of 8
SC - 5.05 - UNDERGROUND FACILITIES
Add the following new paragraph immediately after Paragraph 5.05.A.2.
3. At least two but not more than ten business days before beginning any excavation, the Contractor shall according to MCA 69-4-501, notify all owners of underground facilities and coordinate the work with the owners of such underground facilities. The information shown or indicated in the Contract Documents with respect to existing underground facilities is based on information and data obtained from the owners of the facilities without field exploration, and as such, Owner and Engineer are not responsible for the accuracy or completeness of such information or data.
SC- 6.02 INSURANCE – GENERAL PROVISIONS
Delete Paragraph 6.02.B of the General Conditions in its entirety and replace with the following:
B. Without limiting any of the other obligations or liabilities of the Contractor, Contractor shall secure and maintain such insurance from an insurance company (or companies) authorized to write insurance in the State of Montana, with minimum “A.M. Best Rating” of A-, VI, as will protect the Contractor, the vicarious acts of subcontractors, the Owner and the Engineer and their agents and employees from claims for bodily injury, or property damage which may arise from operations and completed operations under this Agreement. Contractor shall not commence work under this Agreement until such insurance has been obtained and certificates of insurance, with binders, or certified copies of the insurance policy shall have been filed with the Owner and the Engineer.
Add the following new paragraph immediately after 6.02.J:
K. All insurance coverage shall remain in effect throughout the life of the Agreement, except that the Contractor shall maintain the Commercial General Liability Policy including product and completed operations coverage for a period of at least one year following the substantial completion date for property damage resulting from occurrences during the agreement period.
SC- 6.03.I.3 CANCELATION NOTICE
Amend paragraph 6.03.I.3 of the General Conditions by striking out the words “10 days” and replacing them with the words “45 days” and as so amended paragraph 6.03.I.3 remains in effect.
Add the following immediately at the end of 6.05.C.
Contractor shall be responsible for any deductible or self-insured retention.
SC-7.02 WORKING HOURS
Add the following to Paragraph 7.02.B:
Boulder Cottage #5 Project August 2024 00810 - 4 of 8
Regular working hours are defined as 8:00 AM. to 5:00 P.M. Emergency work may be done without prior permission.
SC- 7.12 SAFETY AND PROTECTION
Add new paragraphs to the end of paragraph 7.12.E of the General Conditions as follows:
G. It is expressly understood by the parties to this Agreement that the Contractor is solely responsible for initiating, maintaining, and supervising safety precautions and programs in connection with the work. The right of the Owner and Engineer to observe or otherwise review the work and operations shall not relieve the Contractor from any of his covenants and obligations hereunder.
Contractor shall incorporate all safety requirements into his construction progress and work schedules including preconstruction and scheduled monthly safety meetings, posted safety rules, tailgate meetings, and site inspections by safety and other inspectors employed by the Contractor.
H. The Contractor shall be responsible for and shall take necessary precautions and provide all material and equipment to protect, shore, brace, support and maintain all underground pipes, conduits, drains, sewers, water mains, gas mains, cables, etc., and other underground construction uncovered in the proximity, or otherwise affected by the construction work performed by him.
All pavement, surfacing, driveways, curbs, walks, buildings, grass areas, trees, utility poles or guy wires damaged by the Contractor’s operations in the performance of this work shall be repaired and/or replaced to the satisfaction of the Owner, Engineer, and effected property owner at the Contractor’s expense. The Contractor shall also be responsible for all damage to streets, roads, highways, shoulders, ditches, embankments, culverts, bridges, or other public or private property or facility, regardless of location or character, which may be caused by moving, hauling, or otherwise transporting equipment, materials, or men to and from the work or any part of site thereof; whether by him or his subcontractors. The Contractor shall make satisfactory and acceptable arrangements with owner of, or the agency or authority having jurisdiction over, the damaged property or facility concerning its repair or replacement, or payment of costs incurred in connection with said damage.
I. The Contractor shall conduct his work so as to interfere as little as possible with public travel, whether vehicular or pedestrian. Whenever it is necessary to cross, obstruct, or close roads, driveways, and walks, whether public or private, the Contractor shall obtain approval from the governing party and shall, at his own expense, provide and maintain suitable and safe bridges, detours, and other temporary expedients for the accommodation of public and private drives before interfering with them. The provisions for temporary expedients will not be required when the Contractor has obtained permission from the owner and tenant of the private property, or from the authority having jurisdiction over public property involved, to obstruct traffic at the designated point.
Boulder Cottage #5 Project August 2024 00810 - 5 of 8
J. Safety provisions must be entirely adequate and meet with City or State and
Federal regulations to protect the public on these streets and roads.
SC- 7.18 INDEMNIFICATION
Add a new paragraph immediately after paragraph 7.18.A. of the General Conditions which is to read as follows:
While Owner and Engineer may have the right under this Contract to observe or otherwise review the work, progress and operations of the Contractor, it is expressly understood and agreed that such observation shall not relieve the Contractor from any of its covenants and obligations hereunder.
SC- 13.01 COST OF THE WORK
Delete paragraph 13.01.B.5.c of the General Conditions in its entirety and insert the following in its place:
13.01.B.5.c The rental of all construction equipment and machinery and parts thereof whether rented from Contractor or rented from others. The cost shall be calculated as follows and will include the costs of transportation, loading, unloading, assembly, dismantling and removal thereof for equipment involved only in the changed portion of the work covered under the cost of the work method. Transportation, loading and assembly costs will not be included for equipment already on the site which is being used for other portions of the work. The cost of any such equipment, machinery, or parts shall cease when the use thereof is no longer necessary for the work. Hourly equipment and machinery rates shall be calculated from the Rental Rate Blue Book for Construction Equipment, and the Equipment List submitted according to SC 2.03 and SC 2.05, and as follows:
1. For working equipment, the hourly rate shall be the monthly rental rate divided by 176 hours per month plus the hourly operating cost.
2. For equipment on standby, the hourly rate shall be 50% of the monthly rental rate divided by 176 hours per month, and the hourly operating cost shall not be applied.
3. For specialized equipment rented for a short duration used for change order work or additional work not part of the scope of work bid, the equipment rental rates will be negotiated prior to the work being performed.
SC- 13.03 UNIT PRICE WORK
Delete paragraph 13.03.E.1 and 2 of the General Conditions in its entirety and insert the following in its place:
1. The quantity of a particular item of Unit Price Work performed by Contractor differs by more than 25% from the estimated quantity of such item indicated in the
Boulder Cottage #5 Project August 2024 00810 - 6 of 8
Agreement, and
2. The total cost of the particular individual item of Unit Price Work amounts to 10% or more of the Contract Price which is the total sum of all schedules (if any), and
SC- 15.01.B APPLICATIONS FOR PAYMENTS
Add the following language at the end of paragraph 15.01.B.1 of the General Conditions:
Payments for materials in storage shall be based only upon the actual cost of the materials and equipment to Contractor and shall not include any overhead or profit.
Bill of Sale, invoice or other document warranting clear title for materials in storage will be waived for the material in storage included in the first progress payment application. However, proof of payment and clear title must be submitted with Application No. 2 for all material included in Application No. 1.
This is the start of the file's text. The full file is on GovTribe.