This document is a utility billing record showing water and sewer consumption and charges for the Thurgood Marshall Federal Judiciary Building in Washington, D.C. for the 2025 calendar year.

The facility consumed a total of 5,443.40 hundred cubic feet (CCFs) of water throughout 2025, incurring total charges of $135,193.69. Monthly consumption varied significantly, with peak usage occurring in August 2025 (699.83 CCFs, $16,008.76) and the lowest usage in December 2025 (318.36 CCFs, $8,847.80). Summer months (July through October) showed notably higher consumption levels, ranging from 556.97 to 699.83 CCFs, while winter and spring months generally remained below 400 CCFs. Monthly charges ranged from a minimum of $8,173.34 in January to a maximum of $16,008.76 in August, with most months averaging approximately $9,500 to $10,000.

View the file

Other files

File Type Posted
TMFJB ESPC PPQ.docx DOCX document
TMFJB ESPC NOO RFI Responses.pdf PDF
NOO_TMFJB_050126.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Month Year Billed CCFs Charges January 2025 305.08 $8,173.34 February 2025 354.99 $9,166.54 March 2025 388.55 $9,721.89 April 2025 385.10 $9,858.13 May 2025 433.41 $10,707.00 June 2025 391.52 $9,873.40 July 2025 556.97 $13,165.84 August 2025 699.83 $16,008.76 September 2025 616.47 $14,426.82 October 2025 627.30 $15,391.16 November 2025 365.82 $9,853.01 December 2025 318.36 $8,847.80

Total 5,443.40 $135,193.69

Water/Sewer Total

Thurgood Marshall Federal Judiciary Building 2025 DC Water Billed Consumption and Cost