Seismic Retrofit of Public Works Building at City Yards
Solicitation number
2023-IFB-AIA-842
Issued by
Los Angeles County, California

About this file

This document is a comprehensive Project Manual for the Seismic Retrofit and ADA Upgrade of the Pasadena Public Works Building, prepared by IDS Group, Inc. for the City of Pasadena. The project involves a voluntary seismic retrofit of a concrete tilt-up panel building with wood diaphragms, located at 233 W. Mountain St., Pasadena, California. The scope includes selective demolition and replacement of ceilings and roofing, ADA upgrades to the 1st and 2nd floors such as replacing non-compliant millwork in the breakroom and kitchen, updating drinking fountains, re-striping accessible parking stalls, and upgrading the path of travel from parking to the building. The project will be constructed under a single prime contract, with work primarily scheduled during non-business hours from 6:00 PM to 5:30 AM, Monday through Friday.

The project is funded through federal sources, specifically the Federal Emergency Management Agency (FEMA) Hazard Mitigation Grant Program (HMGP) and American Rescue Plan Act (ARPA) funds. The contractor will be required to comply with specific reporting procedures outlined by the granting agencies and coordinate activities with the City's Representative to minimize disruption to ongoing operations. The project manual includes detailed technical specifications across multiple divisions, covering everything from general requirements and existing conditions to specific installation procedures for structural, architectural, and mechanical components. Contractors will need to provide comprehensive documentation, including construction checklists, test reports, and compliance with various quality assurance and safety standards throughout the project's execution.

View the file

Other files

Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PROJECT MANUAL

BIDDING AND CONTRACTING REQUIREMENTS

PASADENA PUBLIC WORKS

BUILDING SEISMIC RETROFIT

IDS Project #: 22X051.00

PLANCHECK RESUBMITTAL

DATE: January 16, 2023

PASADENA PUBLIC WORKS BUILDING TABLE OF CONTENTS

SEISMIC RETROFIT AND ADA UPGRADE 000110 - 1

SPECIFICATIONS

TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

011000 Summary of the Work

012300 Alternates

012500 Substitution Procedures

012600 Contract Modification Procedures

012900 Payment Procedures

013100 Project Management and Coordination

013233 Photographic Documentation

013300 Submittal Procedures

013553 Security Procedures

014000 Quality Requirements

015000 Temporary Facilities and Controls

016000 Product Requirements

017300 Execution

017419 Construction Waste Management and Disposal

017700 Closeout Procedures

017823 Operation and Maintenance Data

017839 Project Record Documents

017900 Demonstration and Training

019113 General Commissioning Requirements

DIVISION 02 – EXISTING CONDITIONS

024119 Selective Demolition

DIVISION 05 – METALS

051200 Structural Steel Framing

PASADENA PUBLIC WORKS BUILDING TABLE OF CONTENTS

SEISMIC RETROFIT AND ADA UPGRADE 000110 - 2

DIVISION 06 – WOOD, PLASTICS, AND COMPOSITES

061000 Rough Carpentry

DIVISION 07 – THERMAL AND MOISTURE PROTECTION

070150.19 Preparation for Re-roofing

076200 Sheet Metal Flashing and Trim

079200 Joint Sealants

DIVISION 09 - FINISHES

092216 Non-Structural Metal Framing

092900 Gypsum Board

095113 Acoustical Ceiling Panels

099123 Interior Painting

DIVISION 22 – PLUMBING

224100 Residential Plumbing Fixtures

224713 Drinking Fountains

DIVISION 32 – EXTERIOR IMPROVEMENTS

321216 Asphalt Paving 321723 Pavement Markings

321726 Tactile Warning Surfacing

END OF TABLE OF CONTENTS

PASADENA PUBLIC WORKS BUILDING SUMMARY

SEISMIC RETROFIT AND ADA UPGRADE 011000 - 1

SECTION 011000 - SUMMARY

PART 1 - GENERAL

1.1 PROJECT INFORMATION

A. Project Identification: Pasadena Public Works Building Seismic Retrofit

1. Project Location: 233 W. Mountain St. Pasadena, CA 91103

B. Owner: City of Pasadena

1. Owner's Representative: Tiffiny Chen

C. Architect: John Silber, IDS Group, Inc.: 1 Peters Canyon Road, Suite 130, Irvine, CA 92606

1.2 WORK COVERED BY CONTRACT DOCUMENTS

A. The Work of Project is defined by the Contract Documents and consists of the following:

1. The work of this contract shall consist of a voluntary seismic retrofit of a concrete tilt up panel building with wood diaphragms per the structural plans and ADA upgrade

Scope of Work for the Seismic Retrofit will include;

-Selective demolition and replacement of ceilings & roofing

Scope of Work for the ADA upgrade will include;

1st Floor;

-Remove and replace the non-compliant millwork in the breakroom #133

-Replace the existing non complaint drinking fountain

-Re-stripe the accessible parking stalls and

-Upgrade the path of travel from the accessible parking to the building

2nd Floor;

- Remove and replace the non-compliant millwork in the kitchen #216

-Replace the existing non-complaint drinking fountain

B. Type of Contract.

1. Project will be constructed under a single prime contract.

1.3 ACCESS TO SITE

A. General: Contractor shall have use of specified work areas within Project site as indicated on plans for construction operations during construction period. Contractor's use of Project site is

SEISMIC RETROFIT AND ADA UPGRADE 011000 - 2

limited by Owner's right to maintain business operations, perform work and/or to retain other contractors on portions of Project.

B. Use of Site: Limit use of Project site to work in areas indicated. Do not disturb portions of

Project site beyond areas in which the Work is indicated.

1. Limits: Confine construction operations as shown on the drawings.

2. Staging areas: Construction materials may only be stored in staging areas specified on the drawings. All interior spaces not designated as staging areas must be cleaned of all dust and debris at the end of each work day prior to arrival of building occupants.

3. Driveways, Walkways and Entrances: Keep driveways and entrances serving premises clear and available to Owner, Owner's employees, and emergency vehicles at all times.

Do not use these areas for parking or storage of materials.

a. Schedule deliveries to minimize use of driveways and entrances by construction operations.

b. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.

C. Condition of Existing Building: Maintain portions of existing building affected by construction operations in a weathertight condition throughout construction period. Repair damage caused by construction operations.

1.4 COORDINATION WITH OCCUPANTS

A. Partial Owner Occupancy: Owner will occupy the premises during entire construction period.

Cooperate with Owner during construction operations to minimize conflicts and facilitate

Owner usage including areas of construction used by owner. Perform the Work so as not to interfere with Owner's operations. Maintain existing exits unless otherwise indicated.

1. Maintain access to existing walkways, corridors, and other adjacent occupied or used facilities. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from Owner and authorities having jurisdiction.

2. Provide not less than 72 hours' notice to Owner of activities that will affect Owner's operations.

B. Owner Limited Occupancy of Completed Areas of Construction: Owner reserves the right to occupy and to place and install equipment in completed portions of the Work, prior to

Substantial Completion of the Work, provided such occupancy does not interfere with completion of the Work. Such placement of equipment and limited occupancy shall not constitute acceptance of the total Work.

1. Architect will prepare a Certificate of Substantial Completion for each specific portion of the Work to be occupied prior to Owner acceptance of the completed Work.

2. Obtain a Certificate of Occupancy from authorities having jurisdiction before limited

Owner occupancy.

3. Before limited Owner occupancy, mechanical and electrical systems shall be fully operational, and required tests and inspections shall be successfully completed. On occupancy, Owner will operate and maintain mechanical and electrical systems serving occupied portions of Work.

SEISMIC RETROFIT AND ADA UPGRADE 011000 - 3

4. On occupancy, Owner will assume responsibility for maintenance and custodial service for occupied portions of Work.

1.5 WORK RESTRICTIONS

A. Work Restrictions, General: Comply with restrictions on construction operations.

1. Comply with limitations on use of public streets and with other requirements of authorities having jurisdiction.

2. Staging areas for all work shall be limited as specified on the drawings.

B. On-Site Work Hours: Limit work in the building to between hours of 6:00PM and 5:30AM, Monday through Friday, unless otherwise approved by the owner. Work schedule shall follow a

5 day work week starting either Sundays at 6:00PM or Mondays at 6:00PM.

1. Work for the day must be completed and all areas cleaned of dust and debris and vacated before 5:30AM for occupants to maintain regular business hours.

C. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Owner or others unless permitted under the following conditions and then only after providing temporary utility services according to requirements indicated:

1. Notify Owner not less than two days in advance of proposed utility interruptions.

2. Obtain Owner's written permission before proceeding with utility interruptions.

D. Noise, Vibration, and Odors: Coordinate operations that may result in high levels of noise and vibration, odors, or other disruption to Owner occupancy with Owner.

1. Notify Owner not less than two days in advance of proposed utility interruptions.

2. Obtain Owner's written permission before proceeding with utility interruptions.

E. Nonsmoking Building: Smoking is not permitted within the building or within 25 feet (8 m) of entrances, operable windows, or outdoor-air intakes.

F. Controlled Substances: Use of tobacco products and other controlled substances on Project site is not permitted.

1.6 SPECIFICATION AND DRAWING CONVENTIONS

A. Specification Content: The Specifications use certain conventions for the style of language and the intended meaning of certain terms, words, and phrases when used in particular situations.

These conventions are as follows:

1. Imperative mood and streamlined language are generally used in the Specifications. The words "shall," "shall be," or "shall comply with," depending on the context, are implied where a colon (:) is used within a sentence or phrase.

2. Specification requirements are to be performed by Contractor unless specifically stated otherwise.

SEISMIC RETROFIT AND ADA UPGRADE 011000 - 4

B. Division 01 General Requirements: Requirements of Sections in Division 01 apply to the Work of all Sections in the Specifications.

C. Drawing Coordination: Requirements for materials and products identified on Drawings are described in detail in the Specifications. One or more of the following are used on Drawings to identify materials and products:

1. Terminology: Materials and products are identified by the typical generic terms used in the individual Specifications Sections.

2. Abbreviations: Materials and products are identified by abbreviations scheduled on

Drawings.

3. Keynoting: Materials and products are identified by reference keynotes referencing

Specification Section numbers found in this Project Manual.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION (Not Used)

END OF SECTION 011000

PASADENA PUBLIC WORKS BUILDING ALTERNATES

SEISMIC RETROFIT AND ADA UPGRADE 012300 - 1

SECTION 012300 - ALTERNATES

PART 1 - GENERAL

1.1 SUMMARY

A. Section includes administrative and procedural requirements for alternates.

1.2 DEFINITIONS

A. Alternate: An amount proposed by bidders and stated on the Bid Form for certain work defined in the bidding requirements that may be added to or deducted from the base bid amount if

Owner decides to accept a corresponding change either in the amount of construction to be completed or in the products, materials, equipment, systems, or installation methods described in the Contract Documents.

1. Alternates described in this Section are part of the Work only if enumerated in the

Agreement.

2. The cost or credit for each alternate is the net addition to or deduction from the Contract

Sum to incorporate alternate into the Work. No other adjustments are made to the

Contract Sum.

1.3 PROCEDURES

A. Coordination: Revise or adjust affected adjacent work as necessary to completely integrate work of the alternate into Project.

1. Include as part of each alternate, miscellaneous devices, accessory objects, and similar items incidental to or required for a complete installation whether or not indicated as part of alternate.

B. Notification: Immediately following award of the Contract, notify each party involved, in writing, of the status of each alternate. Indicate if alternates have been accepted, rejected, or deferred for later consideration. Include a complete description of negotiated revisions to alternates.

C. Execute accepted alternates under the same conditions as other work of the Contract.

D. Schedule: A schedule of alternates is included at the end of this Section. Specification Sections referenced in schedule contain requirements for materials necessary to achieve the work described under each alternate.

PASADENA PUBLIC WORKS BUILDING ALTERNATES

SEISMIC RETROFIT AND ADA UPGRADE 012300 - 2

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION

3.1 SCHEDULE OF ALTERNATES

A. Any alternates, if approved, will be issued by Addendum.

END OF SECTION 012300

PASADENA PUBLIC WORKS BUILDING SUBSTITUTION PROCEDURES

SEISMIC RETROFIT AND ADA UPGRADE 01 2500-1

SECTION 01 25 00 - SUBSTITUTION PROCEDURES

PART 1 - GENERAL

1.1 SUMMARY

A. Section includes administrative and procedural requirements for substitutions.

B. Related Requirements:

1. Section 016000 "Product Requirements" for requirements for submitting comparable product submittals for products by listed manufacturers.

1.2 DEFINITIONS

A. Substitutions: Changes in products, materials, equipment, and methods of construction from those required by the Contract Documents and proposed by Contractor.

1.3 ACTION SUBMITTALS

A. Substitution Requests: Submit three copies of each request for consideration. Identify product or fabrication or installation method to be replaced. Include Specification Section number and title and Drawing numbers and titles.

1. Substitution Request Form: Use CSI Form 13.1A or approved equal.

2. Documentation: Show compliance with requirements for substitutions and the following, as applicable:

a. Statement indicating why specified product or fabrication, or installation cannot be provided, if applicable.

b. Coordination information, including a list of changes or revisions needed to other parts of the Work and to construction performed by Owner and separate contractors, that will be necessary to accommodate proposed substitution.

c. Detailed comparison of significant qualities of proposed substitution with those of the Work specified. Include annotated copy of applicable Specification Section.

Significant qualities may include attributes such as performance, weight, size, durability, visual effect, sustainable design characteristics, warranties, and specific features and requirements indicated. Indicate deviations, if any, from the Work specified.

d. Product Data, including drawings and descriptions of products and fabrication and installation procedures.

e. Samples, where applicable or requested.

f. Certificates and qualification data, where applicable or requested.

g. List of similar installations for completed projects with project names and addresses and names and addresses of architects and owners.

SEISMIC RETROFIT AND ADA UPGRADE 01 2500-2

h. Material test reports from a qualified testing agency indicating and interpreting test results for compliance with requirements indicated.

i. Research reports evidencing compliance with building code in effect for Project, from ICC-ES.

j. Detailed comparison of Contractor's construction schedule using proposed substitution with products specified for the Work, including effect on the overall

Contract Time. If specified product or method of construction cannot be provided within the Contract Time, include letter from manufacturer, on manufacturer's letterhead, stating date of receipt of purchase order, lack of availability, or delays in delivery.

k. Cost information, including a proposal of change, if any, in the Contract Sum.

l. Contractor's certification that proposed substitution complies with requirements in the Contract Documents except as indicated in substitution request, is compatible with related materials, and is appropriate for applications indicated.

m. Contractor's waiver of rights to additional payment or time that may subsequently become necessary because of failure of proposed substitution to produce indicated results.

3. Architect's Action: If necessary, Architect will request additional information or documentation for evaluation within seven days of receipt of a request for substitution.

Architect will notify Contractor of acceptance or rejection of proposed substitution within

15 days of receipt of request, or seven days of receipt of additional information or documentation, whichever is later.

a. Forms of Acceptance: Change Order, Construction Change Directive, or

Architect's Supplemental Instructions for minor changes in the Work.

b. Use product specified if Architect does not issue a decision on use of a proposed substitution within time allocated.

1.4 QUALITY ASSURANCE

A. Compatibility of Substitutions: Investigate and document compatibility of proposed substitution with related products and materials. Engage a qualified testing agency to perform compatibility tests recommended by manufacturers.

PART 2 - PRODUCTS

2.1 SUBSTITUTIONS

A. Substitutions for Cause: Submit requests for substitution immediately on discovery of need for change, but not later than 15 days prior to time required for preparation and review of related submittals.

1. Conditions: Architect will consider Contractor's request for substitution when the following conditions are satisfied:

SEISMIC RETROFIT AND ADA UPGRADE 01 2500-3

a. Requested substitution is consistent with the Contract Documents and will produce indicated results.

b. Requested substitution provides sustainable design characteristics that specified product provided.

c. Requested substitution will not adversely affect Contractor's construction schedule.

d. Requested substitution has received necessary approvals of authorities having jurisdiction.

e. Requested substitution is compatible with other portions of the Work.

f. Requested substitution has been coordinated with other portions of the Work.

g. Requested substitution provides specified warranty.

h. If requested substitution involves more than one contractor, requested substitution has been coordinated with other portions of the Work, is uniform and consistent, is compatible with other products, and is acceptable to all contractors involved.

B. Substitutions for Convenience: Not allowed.

END OF SECTION 01 2500

SEISMIC RETROFIT AND ADA UPGRADE 01 2500-4

THIS PAGE INTENTIONALLY LEFT BLANK

PASADENA PUBLIC WORKS BUILDING CONTRACT MODIFICATION PROCEDURES

SEISMIC RETROFIT AND ADA UPGRADE 01 2600-1

SECTION 01 26 00 - CONTRACT MODIFICATION PROCEDURES

PART 1 - GENERAL

1.1 SUMMARY

A. Section includes administrative and procedural requirements for handling and processing

Contract modifications.

1.2 MINOR CHANGES IN THE WORK

A. Architect will issue supplemental instructions authorizing minor changes in the Work, not involving adjustment to the Contract Sum or the Contract Time, on AIA Document G710, "Architect's Supplemental Instructions."

1.3 PROPOSAL REQUESTS

A. Owner-Initiated Proposal Requests: Architect will issue a detailed description of proposed changes in the Work that may require adjustment to the Contract Sum or the Contract Time. If necessary, the description will include supplemental or revised Drawings and Specifications.

1. Work Change Proposal Requests issued by Architect are not instructions either to stop work in progress or to execute the proposed change.

2. Within time specified in Proposal Request or 20 calendar days, when not otherwise specified, after receipt of Proposal Request, submit a quotation estimating cost adjustments to the Contract Sum and the Contract Time necessary to execute the change.

a. Include a list of quantities of products required or eliminated and unit costs, with total amount of purchases and credits to be made. If requested, furnish survey data to substantiate quantities.

b. Indicate applicable taxes, delivery charges, equipment rental, and amounts of trade discounts.

c. Include costs of labor and supervision directly attributable to the change.

d. Include an updated Contractor's construction schedule that indicates the effect of the change, including, but not limited to, changes in activity duration, start and finish times, and activity relationship. Use available total float before requesting an extension of the Contract Time.

e. Quotation Form: Use CSI Form 13.6D, "Proposal Worksheet Summary," and

Form 13.6C, "Proposal Worksheet Detail."

B. Contractor-Initiated Work Change Proposals: If latent or changed conditions require modifications to the Contract, Contractor may initiate a claim by submitting a request for a change to Architect.

SEISMIC RETROFIT AND ADA UPGRADE 01 2600-2

1. Include a statement outlining reasons for the change and the effect of the change on the

Work. Provide a complete description of the proposed change. Indicate the effect of the proposed change on the Contract Sum and the Contract Time.

2. Include a list of quantities of products required or eliminated and unit costs, with total amount of purchases and credits to be made. If requested, furnish survey data to substantiate quantities.

3. Indicate applicable taxes, delivery charges, equipment rental, and amounts of trade discounts.

4. Include costs of labor and supervision directly attributable to the change.

5. Include an updated Contractor's construction schedule that indicates the effect of the change, including, but not limited to, changes in activity duration, start and finish times, and activity relationship. Use available total float before requesting an extension of the

Contract Time.

6. Comply with requirements in Section 012500 "Substitution Procedures" if the proposed change requires substitution of one product or system for product or system specified.

7. Work Change Proposal Request Form: Use CSI Form 13.6A, "Change Order Request

(Proposal)," with attachments CSI Form 13.6D, "Proposal Worksheet Summary," and

Form 13.6C, "Proposal Worksheet Detail."

1.4 CHANGE ORDER PROCEDURES

A. On Owner's approval of a Work Changes Proposal Request, Architect will issue a Change Order for signatures of Owner and Contractor on AIA Document G701 or equal.

1.5 CONSTRUCTION CHANGE DIRECTIVE

A. Construction Change Directive: Architect may issue a Construction Change Directive on

AIA Document G714 Construction Change Directive instructs Contractor to proceed with a change in the Work, for subsequent inclusion in a Change Order.

1. Construction Change Directive contains a complete description of change in the Work. It also designates method to be followed to determine change in the Contract Sum or the

Contract Time.

B. Documentation: Maintain detailed records on a time and material basis of work required by the

Construction Change Directive.

1. After completion of change, submit an itemized account and supporting data necessary to substantiate cost and time adjustments to the Contract.

PART 2 - PRODUCTS (Not Used)

END OF SECTION 01 2600

SEISMIC RETROFIT AND ADA UPGRADE 01 2600-3

PASADENA PUBLIC WORKS BUILDING PAYMENT PROCEDURES

SEISMIC RETROFIT AND ADA UPGRADE 01 2900-1

SECTION 01 29 00 - PAYMENT PROCEDURES

PART 1 - GENERAL

1.1 SUMMARY

A. Section includes administrative and procedural requirements necessary to prepare and process

Applications for Payment.

B. Related Requirements:

1. Section 012600 "Contract Modification Procedures" for administrative procedures for handling changes to the Contract.

1.2 SCHEDULE OF VALUES

A. Coordination: Coordinate preparation of the schedule of values with preparation of Contractor's construction schedule.

1. Coordinate line items in the schedule of values with other required administrative forms and schedules, including the following:

a. Application for Payment forms with continuation sheets.

b. Submittal schedule.

c. Items required to be indicated as separate activities in Contractor's construction schedule.

2. Submit the schedule of values to Architect at earliest possible date but no later than seven days before the date scheduled for submittal of initial Applications for Payment.

B. Format and Content: Use Project Manual table of contents as a guide to establish line items for the schedule of values. Provide at least one line item for each Specification Section.

1. Identification: Include the following Project identification on the schedule of values:

a. Project name and location.

b. Name of Architect.

c. Architect's project number.

d. Contractor's name and address.

e. Date of submittal.

2. Arrange schedule of values consistent with format of AIA Document G703.

3. Provide a breakdown of the Contract Sum in enough detail to facilitate continued evaluation of Applications for Payment and progress reports. Coordinate with Project

Manual table of contents. Provide multiple line items for principal subcontract amounts in excess of five percent of the Contract Sum.

4. Round amounts to nearest whole dollar; total shall equal the Contract Sum.

SEISMIC RETROFIT AND ADA UPGRADE 01 2900-2

5. Provide a separate line item in the schedule of values for each part of the Work where

Applications for Payment may include materials or equipment purchased or fabricated and stored, but not yet installed.

6. Provide separate line items in the schedule of values for initial cost of materials, for each subsequent stage of completion, and for total installed value of that part of the Work.

7. Each item in the schedule of values and Applications for Payment shall be complete.

Include total cost and proportionate share of general overhead and profit for each item.

a. Temporary facilities and other major cost items that are not direct cost of actual work-in-place may be shown either as separate line items in the schedule of values or distributed as general overhead expense, at Contractor's option.

8. Schedule Updating: Update and resubmit the schedule of values before the next

Applications for Payment when Change Orders or Construction Change Directives result in a change in the Contract Sum.

1.3 APPLICATIONS FOR PAYMENT

A. Each Application for Payment shall be consistent with previous applications and payments as certified by Architect and paid for by Owner.

1. Initial Application for Payment, Application for Payment at time of Substantial

Completion, and final Application for Payment involve additional requirements.

B. Payment Application Times: The date for each progress payment is indicated in the Agreement between Owner and Contractor. The period of construction work covered by each Application for Payment is the period indicated in the Agreement.

C. Application for Payment Forms: Use AIA Document G702 and AIA Document G703 as form for Applications for Payment.

D. Application for Payment Forms: Use forms acceptable to Owner and Architect for Applications for Payment. Sample copies are included in Project Manual.

E. Application Preparation: Complete every entry on form. Notarize and execute by a person authorized to sign legal documents on behalf of Contractor. Architect return incomplete applications without action.

1. Entries shall match data on the schedule of values and Contractor's construction schedule.

Use updated schedules if revisions were made.

2. Include amounts of Change Orders and Construction Change Directives issued before last day of construction period covered by application.

F. Transmittal: Submit three signed and notarized original copies of each Application for Payment to Architect by a method ensuring receipt within 24 hours. One copy shall include waivers of lien and similar attachments if required.

1. Transmit each copy with a transmittal form listing attachments and recording appropriate information about application.

SEISMIC RETROFIT AND ADA UPGRADE 01 2900-3

G. Waivers of Mechanic's Lien: With each Application for Payment, submit waivers of mechanic's lien from entities lawfully entitled to file a mechanic's lien arising out of the Contract and related to the Work covered by the payment.

1. Submit partial waivers on each item for amount requested in previous application, after deduction for retainage, on each item.

2. When an application shows completion of an item, submit conditional final or full waivers.

3. Owner reserves the right to designate which entities involved in the Work must submit waivers.

4. Waiver Forms: Submit executed waivers of lien on forms acceptable to Owner.

H. Application for Payment: Every application for payment should include the following:

1. Certified Payroll (submitted directly to labor compliance in electronic format as specified by City including hard copy)

2. Updated and current Project Record Drawings (as built)

3. Monthly Construction Schedule (updated, submitted and approved)

4. Approved Schedule of Values

5. List of Subcontractors (Payments Summary)

I. Initial Application for Payment: Administrative actions and submittals that must precede or coincide with submittal of first Application for Payment include the following:

1. List of subcontractors.

2. Schedule of values.

3. Contractor's construction schedule (preliminary if not final).

J. Application for Payment at Substantial Completion: After Architect issues the Certificate of

Substantial Completion, submit an Application for Payment showing 100 percent completion for portion of the Work claimed as substantially complete.

1. Include documentation supporting claim that the Work is substantially complete and a statement showing an accounting of changes to the Contract Sum.

2. This application shall reflect Certificates of Partial Substantial Completion issued previously for Owner occupancy of designated portions of the Work.

K. Final Payment Application: After completing Project closeout requirements, submit final

Application for Payment with releases and supporting documentation not previously submitted and accepted, including, but not limited, to the following:

1. Evidence of completion of Project closeout requirements.

2. Insurance certificates for products and completed operations where required and proof that taxes, fees, and similar obligations were paid.

3. Updated final statement, accounting for final changes to the Contract Sum.

4. AIA Document G706-1994, "Contractor's Affidavit of Payment of Debts and Claims."

SEISMIC RETROFIT AND ADA UPGRADE 01 2900-4

5. AIA Document G706A-1994, "Contractor's Affidavit of Release of Liens."

PART 2 - PRODUCTS (Not Used)

END OF SECTION 01 2900

SEISMIC RETROFIT AND ADA UPGRADE 01 2900-5

PASADENA PUBLIC WORKS BUILDING PROJECT MANAGEMENT AND COORDINATION

SEISMIC RETROFIT AND ADA UPGRADE 01 3100-1

SECTION 01 31 00 - PROJECT MANAGEMENT AND COORDINATION

PART 1 - GENERAL

1.1 SUMMARY

A. Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following:

1. Coordination drawings.

2. Requests for Information (RFIs).

3. Project meetings.

4. Web-based project management software - Procore

B. Related Requirements:

1. Section 017300 "Execution" for procedures for coordinating general installation and field-engineering services, including establishment of benchmarks and control points.

1.2 DEFINITIONS

A. RFI: Request from Contractor seeking information required by or clarifications of the Contract

Documents.

1.3 INFORMATIONAL SUBMITTALS

A. Subcontract List: Prepare a written summary identifying individuals or firms proposed for each portion of the Work, including those who are to furnish products or equipment fabricated to a special design.Use CSI Form 1.5A. Include the following information in tabular form:

1. Name, address, and telephone number of entity performing subcontract or supplying products.

2. Number and title of related Specification Section(s) covered by subcontract.

3. Drawing number and detail references, as appropriate, covered by subcontract.

1.4 GENERAL COORDINATION PROCEDURES

A. Coordination: Coordinate construction operations included in different Sections of the

Specifications to ensure efficient and orderly installation of each part of the Work. Coordinate construction operations, included in different Sections, that depend on each other for proper installation, connection, and operation.

1. Schedule construction operations in sequence required to obtain the best results where installation of one part of the Work depends on installation of other components, before or after its own installation.

2. Coordinate installation of different components to ensure maximum performance and accessibility for required maintenance, service, and repair.

SEISMIC RETROFIT AND ADA UPGRADE 01 3100-2

3. Make adequate provisions to accommodate items scheduled for later installation.

B. Prepare memoranda for distribution to each party involved, outlining special procedures required for coordination. Include such items as required notices, reports, and list of attendees at meetings.

1. Prepare similar memoranda for Owner and separate contractors if coordination of their

Work is required.

C. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities and scheduled activities of other contractors to avoid conflicts and to ensure orderly progress of the work. Such administrative activities include, but are not limited to the following:

1. Preparation of Contractor’s construction Schedule

2. Preparation of the schedule of Values

3. Installation and removal of temporary facilities and control

4. Delivery and processing of submittals

5. Progress Meetings

6. Pre installation conferences

7. Project closeout activities

8. Startup and adjustment of systems

1.5 REQUESTS FOR INFORMATION (RFIs)

A. General: Immediately on discovery of the need for additional information or interpretation of the Contract Documents, Contractor shall prepare and submit an RFI in the form specified.

1. Architect will return RFIs submitted to Architect by other entities controlled by

Contractor with no response.

2. Coordinate and submit RFIs in a prompt manner so as to avoid delays in Contractor's work or work of subcontractors.

B. Content of the RFI: Include a detailed, legible description of item needing information or interpretation and the following:

1. Project name.

2. Project number.

3. Date.

4. Name of Contractor.

5. Name of Architect.

6. RFI number, numbered sequentially.

7. RFI subject.

8. Specification Section number and title and related paragraphs, as appropriate.

SEISMIC RETROFIT AND ADA UPGRADE 01 3100-3

9. Drawing number and detail references, as appropriate.

10. Field dimensions and conditions, as appropriate.

11. Contractor's suggested resolution. If Contractor's solution(s) impacts the Contract Time or the Contract Sum, Contractor shall state impact in the RFI.

12. Contractor's signature.

13. Attachments: Include sketches, descriptions, measurements, photos, Product Data, Shop

Drawings, coordination drawings, and other information necessary to fully describe items needing interpretation.

C. RFI Forms: AIA Document G716 or approved equal.

D. Architect's Action: Architect will review each RFI, determine action required, and respond.

Allow seven working days for Architect's response for each RFI. RFIs received by Architect after 1:00 p.m. will be considered as received the following working day.

1. The following RFIs will be returned without action:

a. Requests for approval of submittals.

b. Requests for approval of substitutions.

c. Requests for coordination information already indicated in the Contract

Documents.

d. Requests for adjustments in the Contract Time or the Contract Sum.

e. Requests for interpretation of Architect's actions on submittals.

f. Incomplete RFIs or inaccurately prepared RFIs.

2. Architect's action may include a request for additional information, in which case

Architect's time for response will date from time of receipt of additional information.

3. Owner/Architect’s response to RFI is a clarification or interpretation of the intent of the

Contract Documents and does not authorize changes in the Contract Sum, Milestones and/or Contract Time.

4. Architect's action on RFIs that may result in a change to the Contract Time, or the

Contract Sum may be eligible for Contractor to submit Change Proposal according to

Section 012600 "Contract Modification Procedures."

a. If Contractor believes the RFI response warrants change in the Contract Time or the Contract Sum, notify Architect and Construction Manager in writing within five (5) days of receipt of the RFI response per section 7.6 of the General

Conditions.

b. Contactor’s failure to initiate a Change Order Request (“COR”) within such period shall be deemed waiver of the right of adjustment of the Contract Sum or Contract

Time for the alleged change.

E. RFI Log: Prepare, maintain, and submit a tabular log of RFIs organized by the RFI number.

Submit log weekly. Software log with not less than the following:

1. Project name.

2. Name and address of Contractor.

3. Name and address of Architect.

4. RFI number including RFIs that were dropped and not submitted.

SEISMIC RETROFIT AND ADA UPGRADE 01 3100-4

5. RFI description.

6. Date the RFI was submitted.

7. Date Architect's response was received.

F. On receipt of Architect's, update the RFI log and immediately distribute the RFI response to affected parties. Review response and notify Architect within seven days if Contractor disagrees with response.

1. Identification of related Minor Change in the Work, Construction Change Directive, and

Proposal Request, as appropriate.

2. Identification of related Field Order, Work Change Directive, and Proposal Request, as appropriate.

1.6 PROJECT MEETINGS

A. General: Schedule and conduct and conferences at Project site unless otherwise indicated.

1. Attendees: Inform participants and others involved, and individuals whose presence is required, of date and time of each meeting. Notify Owner and Architect of scheduled meeting dates and times.

2. Agenda: Prepare the meeting agenda. Distribute the agenda to all invited attendees.

3. Minutes: Entity responsible for conducting meeting will record significant discussions and agreements achieved. Distribute the meeting minutes to everyone concerned, including Owner and Architect, within three days of the meeting.

B. Preconstruction Conference: Architect will schedule and conduct preconstruction conference before starting construction, at a time convenient to Owner and Architect, but no later than 15 days after execution of the Agreement.

1. Attendees: Authorized representatives of Owner[, Owner's Commissioning Authority,]

[, Construction Manager,] Architect, and their consultants; Contractor and its superintendent; major subcontractors; suppliers; and other concerned parties shall attend the conference. Participants at the conference shall be familiar with Project and authorized to conclude matters relating to the Work.

2. Agenda: Discuss items of significance that could affect progress, including the following:

a. Tentative construction schedule.

b. Phasing.

c. Critical work sequencing and long-lead items.

d. Designation of key personnel and their duties.

e. Procedures for processing field decisions and Change Orders.

f. Procedures for RFIs.

g. Procedures for testing and inspecting.

h. Procedures for processing Applications for Payment.

i. Distribution of the Contract Documents.

j. Submittal procedures.

k. Preparation of record documents.

l. Use of the premises[ and existing building].

m. Work restrictions.

SEISMIC RETROFIT AND ADA UPGRADE 01 3100-5

n. Working hours.

o. Owner's occupancy requirements.

p. Responsibility for temporary facilities and controls.

q. Procedures for moisture and mold control. (As applicable)

r. Procedures for disruptions and shutdowns.

s. Construction waste management.

t. Parking availability.

u. Office, work, and storage areas.

v. Equipment deliveries and priorities.

w. First aid.

x. Security.

y. Progress cleaning.

3. Minutes: Entity responsible for conducting meeting will record and distribute meeting minutes.

C. Preinstallation Conferences: Conduct a preinstallation conference at Project site before each construction activity that requires coordination with other construction.

1. Attendees: Installer and representatives of manufacturers and fabricators involved in or affected by the installation and its coordination or integration with other materials and installations that have preceded or will follow, shall attend the meeting. Advise Architect of scheduled meeting dates.

2. Agenda: Review progress of other construction activities and preparations for the particular activity under consideration, including requirements for the following:

a. Contract Documents.

b. Options.

c. Related RFIs.

d. Related Change Orders.

e. Purchases.

f. Deliveries.

g. Submittals.

h. Possible conflicts.

i. Compatibility problems.

j. Time schedules.

k. Weather limitations.

l. Manufacturer's written instructions.

m. Warranty requirements.

n. Compatibility of materials.

o. Acceptability of substrates.

p. Temporary facilities and controls.

q. Space and access limitations.

r. Regulations of authorities having jurisdiction.

s. Testing and inspecting requirements.

t. Installation procedures.

u. Coordination with other work.

v. Required performance results.

w. Protection of adjacent work.

x. Protection of construction and personnel.

SEISMIC RETROFIT AND ADA UPGRADE 01 3100-6

3. Record significant conference discussions, agreements, and disagreements, including required corrective measures and actions.

4. Reporting: Distribute minutes of the meeting to each party present and to other parties requiring information.

5. Do not proceed with installation if the conference cannot be successfully concluded.

Initiate whatever actions are necessary to resolve impediments to performance of the

Work and reconvene the conference at earliest feasible date.

D. Progress Meetings: Conduct progress meetings at weekly intervals unless noted otherwise by

Owner.

1. Attendees: In addition to representatives of Owner and Architect, each contractor, subcontractor, supplier, and other entity concerned with current progress or involved in planning, coordination, or performance of future activities shall be represented at these meetings. All participants at the meeting shall be familiar with Project and authorized to conclude matters relating to the Work.

2. Agenda: Review and correct or approve minutes of previous progress meeting. Review other items of significance that could affect progress. Include topics for discussion as appropriate to status of Project.

a. Contractor's Construction Schedule: Review progress since the last meeting.

Determine whether each activity is on time, ahead of schedule, or behind schedule, in relation to Contractor's construction schedule. Determine how construction behind schedule will be expedited; secure commitments from parties involved to do so. Discuss whether schedule revisions are required to ensure that current and subsequent activities will be completed within the Contract Time.

1) Review schedule for next period.

b. Review present and future needs of each entity present, including the following:

1) Interface requirements.

2) Sequence of operations.

3) Status of submittals.

4) Deliveries.

5) Off-site fabrication.

6) Access.

7) Site utilization.

8) Temporary facilities and controls.

9) Progress cleaning.

10) Quality and work standards.

11) Status of correction of deficient items.

12) Field observations.

13) Status of RFIs.

14) Status of proposal requests.

15) Pending changes.

16) Status of Change Orders.

17) Pending claims and disputes.

18) Documentation of information for payment requests.

SEISMIC RETROFIT AND ADA UPGRADE 01 3100-7

3. Three weeks look ahead schedules: Contractor shall provide an updated three-week look ahead schedule to every progress meeting to review upcoming work.

4. Minutes: Entity responsible for conducting the meeting will record and distribute the meeting minutes to each party present and to parties requiring information.

a. Schedule Updating: Revise Contractor's construction schedule after each progress meeting where revisions to the schedule have been made or recognized. Issue revised schedule concurrently with the report of each meeting.

1.7 Web-Based Project Management Software: The City uses Procore as it’s web-based project management software for hosting and managing project communication and documentation until Final Completion. Contractor must be familiar with the software and actively use throughout the project. All submittals, RFIs, potential change orders, and emails regarding the aforementioned must be submitted through Procore by the Contractor for the purposes of logging, tracking, and notification of the project documentation.

PART 2 - PRODUCTS (Not Used)

END OF SECTION 013100

PART 1 - GENERAL

1.1 Related Documents

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.

1.2 Summary

A. Section includes administrative and procedural requirements for the following:

1. Preconstruction photographs.

2. Periodic construction photographs.

3. Final completion construction photographs.

B. Related Requirements:

1. N/A

1.3 Informational Submittals

A. Key Plan: Submit key plan of Project site and building with notation of vantage points marked for location and direction of each photograph. Indicate same information as corresponding photographic documentation.

B. Digital Photographs: Submit image files within three days of taking photographs.

1. Submit Photos on CD-ROM or thumb-drive. Include copy of key plan indicating each photograph’s location and direction.

2. Identification: Provide the following information with each image description in file metadata tag:

a. Name of Project.

b. Name and contact information for photographer.

c. Name of Owner/Architect.

d. Name of Contractor.

e. Date photograph was taken.

f. Description of location, vantage point, and direction.

g. Unique sequential identifier keyed to accompanying key plan.

1.4 Formats and Media

SECTION 01 32 33 - PHOTOGRAPHIC DOCUMENTATION

PASADENA PUBLIC WORKS BUILDING

SEISMIC RETROFIT AND ADA UPGRADE

PHOTOGRAPHIC DOCUMENTATION

01 32 33 - 1

A. Digital Photographs: Provide color images in JPG format, produced by a digital camera with minimum sensor size of 12 megapixels, and at an image resolution of not less than 3200 by 2400 pixels. Use flash in low light levels or backlit conditions.

B. Digital Images: Submit digital media as originally recorded in the digital camera, without alterations, manipulation, editing, or modification using image-editing software.

C. Metadata: Record accurate date and time and GPS location data from camera.

D. File Names: Name media files with date and sequential numbering suffix.

1.5 CONSTRUCTION PHOTOGRAPHS

A. General: Take photographs using the maximum range of depth of field, and that are in focus.

1. Maintain key plan with each set of construction photographs that identifies each photographic location.

B. Preconstruction Photographs: Before commencement of excavation take photographs of Project site and surrounding properties, including existing items to remain during construction, from different vantage points, as directed by Owner’s Representative.

1. Flag construction limits before taking construction photographs.

2. Take 20 photographs to show existing conditions adjacent to property before starting the Work.

3. Take 20 photographs of existing buildings either on or adjoining property to accurately record physical conditions at start of construction.

4. Take additional photographs as required to record settlement or cracking of adjacent structures, pavements, and improvements.

C. Periodic Construction Photographs: Take 20 photographs monthly. Select vantage points to show status of construction and progress since last photographs were taken.

D. Final Completion Construction Photographs: Take 20 photographs after date of Substantial Completion for submission as project record documents. Owner’s Representative will inform photographer of desired vantage points.

1. Three days' notice will be given, where feasible.

2. In emergency situations, take additional photographs within 24 hours of request.

PASADENA PUBLIC WORKS BUILDING

SEISMIC RETROFIT AND ADA UPGRADE

01 32 33 - 2

3. Circumstances that could require additional photographs include, but are not limited to, the following:

a. Special events planned at Project site.

b. Immediate follow-up when on-site events result in construction damage or losses.

c. Photographs to be taken at fabrication locations away from Project site. These photographs are not subject to unit prices or unit-cost allowances.

d. Substantial Completion of a major phase or component of the Work.

e. Extra record photographs at time of final acceptance.

f. Owner's request for special publicity photographs.

PART 2 - PRODUCTS (NOT USED)

PART 3 - EXECUTION (NOT USED)

END OF SECTION

PASADENA PUBLIC WORKS BUILDING

SEISMIC RETROFIT AND ADA UPGRADE

01 32 33 - 3

PASADENA PUBLIC WORKS BUILDING SUBMITTAL PROCEDURES

SEISMIC RETROFIT AND ADA UPGRADE 013300 - 1

SECTION 013300 - SUBMITTAL PROCEDURES

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary

Conditions and other Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section includes requirements for the submittal schedule and administrative and procedural requirements for submitting Shop Drawings, Product Data, Samples and other submittals.

B. Related Requirements:

1. Section 017823 "Operation and Maintenance Data" for submitting operation and maintenance manuals.

2. Section 017839 "Project Record Documents" for submitting record Drawings, record

Specifications, and record Product Data.

3. Section 017900 "Demonstration and Training" for submitting Training program and documents.

1.3 DEFINITIONS

A. Action Submittals: Written and graphic information and physical samples that require Design

Professional and Construction Manager’s response. Action submittals are submittals indicated in individual Specification Sections as "action submittals."

B. Informational Submittals: Written and graphic information and physical samples that do not require Design Professional and Construction Manager’s response action. Submittals can be rejected for not complying with requirements. Informational submittals are those submittals indicated in individual Specification Sections as "informational submittals."

C. File Transfer Protocol (FTP): Communications protocol that enables transfer of files to and from another computer over a network serving as the basis for standard Internet protocols. An

FTP site is part of file network accessible by internal and external users.

D. Portable Document Format (PDF): An open standard file format licensed by Adobe Systems used for representing documents in a device-independent and display resolution-independent fixed-layout document format.

1.4 ACTION SUBMITTALS

A. Submittal Schedule: Submit a schedule of submittals, arranged in chronological order by dates required by construction schedule. Include time required for review, ordering, manufacturing, fabrication, and delivery when establishing dates. Include additional time required for making corrections or revisions to submittals noted by Design Professional and Construction Manager and additional time for handling and reviewing submittals required by those corrections.

1. Coordinate submittal schedule with list of subcontracts, the schedule of values, and

Contractor's construction schedule.

2. Initial Submittal: Submit…