This solicitation is for an indefinite delivery indefinite quantity job order contract to provide real property sustainment, restoration and modernization minor construction services at Military Ocean Terminal Concord in California. The contract has an estimated value between $25-100 million and will be set aside for small businesses only under NAICS code 236220. Task orders will range from $2,000 to $2 million for multi-trade construction projects including site work, demolition, mechanical system replacements, infrastructure preservation, renovation and finishes replacement. The solicitation number is W91238-23-B-0021 and bids must be hand delivered by 25 July 2023. The contract will be a single award to the responsible bidder providing the best value to the government.
View the file
Other files
Show all 34
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
MOTCO Job Order Contract (SATOC) 2487
SECTION TABLE OF CONTENTS
DIVISION 11 - EQUIPMENT
SECTION 11 11 37
ELECTRIC VEHICLE SUPPLY EQUIPMENT
PART 1 GENERAL
1.1 REFERENCES
1.2 DEFINITIONS
1.2.1 ELECTRIC VEHICLE SUPPLY EQUIPMENT
1.2.2 Certified Installers
1.3 RELATED REQUIREMENTS
1.4 SUBMITTALS
1.5 MAINTENANCE MATERIAL SUBMITTALS
1.5.1 Operation and Maintenance Manuals
1.5.2 Spare Parts
1.6 QUALITY CONTROL
1.6.1 Regulatory Requirements
1.6.2 Standard Products
1.6.2.1 Qualifications
1.6.2.2 Material and Equipment Manufacturing Date
1.6.2.3 EVSE Installers
1.7 WARRANTY
PART 2 PRODUCTS
2.1 PRODUCT COORDINATION
2.2 ELECTRIC VEHICLE SUPPLY EQUIPMENT
2.2.1 System Description
2.2.2 Level 1 EVSE
2.2.2.1 Level 1 Wall Mounted EVSE
2.2.2.2 Level 1 Pedestal Mounted EVSE
2.2.3 Level 2 EVSE
2.2.3.1 Level 2 Wall Mounted EVSE
2.2.3.2 Level 2 Pedestal Mounted EVSE
2.2.4 DC Fast Charger EVSE
2.2.4.1 DC Fast Charger Wall Mounted EVSE
2.2.4.2 DC Fast Charger Pedestal Mounted EVSE
2.2.5 Cords
2.3 CONNECTOR HOLSTER DOCK
2.4 PEDESTAL CONSTRUCTION
2.5 ACCESSORIES
2.6 CAST-IN-PLACE CONCRETE
2.7 MANUFACTURER'S NAMEPLATES
2.8 PAVEMENT MARKINGS
2.9 ELECTRIC VEHICLE SUPPLY EQUIPMENT (EVSE) SIGNAGE
2.10 WHEEL STOPS AND BOLLARDS
PART 3 EXECUTION
3.1 INSTALLATION
SECTION 11 11 37 Page 1
3.2 GROUNDING
3.2.1 Grounding Electrodes
3.3 FIELD APPLIED PAINTING
3.4 FIELD FABRICATED NAMEPLATE MOUNTING
3.5 FOUNDATION FOR EQUIPMENT AND ASSEMBLIES
3.5.1 Exterior Location
3.6 OPERATION AND MAINTENANCE
3.6.1 Operation and Maintenance Training
3.7 RECORD DOCUMENTATION
3.8 FIELD QUALITY CONTROL
3.8.1 Testing of Electric Vehicle Supply Equipment
3.8.2 Performance of Acceptance Checks and Tests
3.8.2.1 EVSE
-- End of Section Table of Contents --
SECTION 11 11 37 Page 2
SECTION 11 11 37
ELECTRIC VEHICLE SUPPLY EQUIPMENT
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
ASTM INTERNATIONAL (ASTM)
ASTM C260/C260M (2010a; R 2016) Standard Specification for Air-Entraining Admixtures for Concrete
INSTITUTE OF ELECTRICAL AND ELECTRONICS ENGINEERS (IEEE)
IEEE C2 (2017; Errata 1-2 2017; INT 1 2017) National Electrical Safety Code
NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)
NFPA 70 (2020; ERTA 20-1 2020; ERTA 20-2 2020;
ERTA 20-3 2020; TIA 20-1; TIA 20-2; TIA
20-3; TIA 20-4; TIA 20-5; TIA 20-6; TIA
20-7; TIA 20-8; TIA 20-9; TIA 20-10; TIA
20-11; TIA 20-12; TIA 20-13; TIA 20-14;
TIA 20-15; TIA 20-16; ERTA 20-4 2022)
National Electrical Code
UNDERWRITERS LABORATORIES (UL)
UL 62 (2018) UL Standard for Safety Flexible Cords and Cables
UL 2202 (2012; Reprint Feb 2018) UL Standard for Safety Electric Vehicle (EV) Charging System Equipment
UL 2231-1 (2012; Reprint Aug 2016) UL Standard for Safety Personnel Protection Systems for Electric Vehicle (EV) Supply Circuits:
General Requirements
UL 2231-2 (2012; Reprint Aug 2016) UL Standard for Safety Personnel Protection Systems for Electrical Vehicle (EV) Supply Circuits:
Particular Requirements for Protection Devices for Use in Charging Systems
UL 2251 (2017) UL Standard for Safety Plugs, Receptacles and Couplers for Electric Vehicles
SECTION 11 11 37 Page 3
UL 2594 (2016) UL Standard for Safety Electric Vehicle Supply Equipment
1.2 DEFINITIONS
1.2.1 ELECTRIC VEHICLE SUPPLY EQUIPMENT
Electric Vehicle Supply Equipment (EVSE), also referred to as "charging stations," encompasses the conductors, including the ungrounded, grounded, and equipment grounding conductors and the electric vehicle connectors, attachment plugs, and all other fittings, devices, power outlets, or apparatus installed specifically for the purpose of delivering energy from the premises wiring to the electric vehicle (EV). There are three types of EVSE:
a. Level 1 - Refers to a freestanding or wall mounted charging device that delivers a 110/120V charge, replenishing an EV battery at a rate of 4 to 6 miles of range per hour of charging time. Charging an EV at Level 1 typically takes between 7 and 20 hours depending on the size of the vehicle's battery.
b. Level 2 - Refers to a freestanding or wall mounted charging device capable of being networked that delivers a 208/240V charge, replenishing an EV battery at a rate of 10 to 20 miles of range per hour of charging time. Charging an EV at Level 1 typically takes between 2 and 5 hours depending on the size of the vehicle's battery.
c. Direct Current (DC) Fast Charging, a freestanding or wall mounted device capable of being networked that is designed to charge vehicles more quickly than Level 1 or Level 2 with an electrical output ranging between 40 kW - 120 kW delivering a charge of up to 480V. DC Fast Charging can typically replenish an EV battery at a rate of 50 to 90 miles of range per 30 minutes of charging time.
1.2.2 Certified Installers
Installers must be certified by EVSE manufacturer or a recognized certified training agency.
1.3 RELATED REQUIREMENTS
Materials not considered to be Electric Vehicle Supply Equipment or accessories are specified in Section 26 20 00 INTERIOR DISTRIBUTION SYSTEM, Section 33 71 02 UNDERGROUND ELECTRICAL DISTRIBUTION, Section 32 17 23 PAVEMENT MARKINGS and Section 26 08 00 APPARATUS INSPECTION AND TESTING applies to this section with the additions and modifications specified herein.
1.4 SUBMITTALS
Government approval is required for submittals with a "G" or "S" classification. Submittals not having a "G" or "S" classification are for Contractor Quality Control approval. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
In addition, submit in accordance with paragraph COORDINATED SUBMITTAL REVIEWS herein.
SD-02 Shop Drawings
SECTION 11 11 37 Page 4
Cords; G
Level 1 Wall Mounted EVSE; G
Level 1 Pedestal Mounted EVSE; G
Level 2 Wall Mounted EVSE; G
Level 2 Pedestal Mounted EVSE; G
DC Fast Charger Wall Mounted EVSE; G
DC Fast Charger Pedestal Mounted EVSE; G
SD-03 Product Data
Cords; G
Level 1 Wall Mounted EVSE; G
Level 1 Pedestal Mounted EVSE; G
Level 2 Wall Mounted EVSE; G
Level 2 Pedestal Mounted EVSE; G
DC Fast Charger Wall Mounted EVSE; G
DC Fast Charger Pedestal Mounted EVSE; G
SD-07 Certificates
Qualifications; G
Certified Installers; G
SD-08 Manufacturer's Instructions
Cords; G
Level 1 Wall Mounted EVSE; G
Level 1 Pedestal Mounted EVSE; G
Level 2 Wall Mounted EVSE; G
Level 2 Pedestal Mounted EVSE; G
DC Fast Charger Wall Mounted EVSE; G
DC Fast Charger Pedestal Mounted EVSE; G
SD-09 Manufacturer's Field Reports
Testing of Electric Vehicle Supply Equipment; G
SD-10 Operation and Maintenance Data
SECTION 11 11 37 Page 5
Electric Vehicle Supply Equipment, Data Package 3
SD-11 Closeout Submittals
OMSI Warranty; G
Record Documentation
1.5 MAINTENANCE MATERIAL SUBMITTALS
Provide a list of manufacturer recommended maintenance items required for EVSE Operation.
1.5.1 Operation and Maintenance Manuals
Submit in accordance with Section 01 78 23 OPERATION AND MAINTENANCE DATA. Submit two manuals and electronic file at least 2 weeks prior to field training.
1.5.2 Spare Parts
Provide one spare cord and connector assembly for every three stations installed.
1.6 QUALITY CONTROL
1.6.1 Regulatory Requirements
In each of the publications referred to herein, consider the advisory provisions to be mandatory, as though the word, "shall" or "must" had been substituted for "should" wherever it appears. Interpret references in these publications to the "authority having jurisdiction," or words of similar meaning, to mean the Contracting Officer. Provide equipment, materials, installation, and workmanship in accordance with the mandatory and advisory provisions of NFPA 70 unless more stringent requirements are specified or indicated.
1.6.2 Standard Products
Provide materials and equipment that are products of manufacturers regularly engaged in the production of such products which are of equal material, design and workmanship and:
a. Have been in satisfactory commercial or industrial use for 2 years prior to bid opening including applications of equipment and materials under comparable circumstances and of similar size.
b. Have been on sale on the commercial market through advertisements, manufacturers' catalogs, or brochures during the 2-year period.
c. Where two or more items of the same class of equipment are required, provide products of a single manufacturer; however, the component parts of the item need not be the products of the same manufacturer unless stated in this section.
1.6.2.1 Qualifications
Products having less than a 2-year field service record will be acceptable if a certified record of satisfactory field operation for not less than
SECTION 11 11 37 Page 6
6000 hours, exclusive of the manufacturers' factory or laboratory tests, is furnished.
1.6.2.2 Material and Equipment Manufacturing Date
Provide products manufactured within 2 years prior to date of delivery to site. As a minimum, meet requirements of UL, where UL standards are established for those items, and requirements of NFPA 70 for all materials, equipment, and devices.
1.6.2.3 EVSE Installers
Submit documentation certifying that pertinent personnel are qualified for EVSE installation. The documentation must include installation experience on two projects of comparable size and scope of work.
1.7 WARRANTY
Provide equipment items supported by service organizations that are convenient to the equipment installation in order to render satisfactory service to the equipment within 24 hours of notification during the warranty period of the contract.
Provide warranty for Materials and Workmanship of EVSE: Two years.
PART 2 PRODUCTS
2.1 PRODUCT COORDINATION
Provide products and materials not considered to be ELECTRIC VEHICLE SUPPLY EQUIPMENT and related accessories for power requirements as specified in Section 26 20 00 INTERIOR DISTRIBUTION SYSTEM, and Section
33 71 02 UNDERGROUND ELECTRICAL DISTRIBUTION.
2.2 ELECTRIC VEHICLE SUPPLY EQUIPMENT
2.2.1 System Description
Electric Vehicle Supply Equipment capable of charging multiple vehicles at Level 1 Level 2 Direct Current (DC) Fast Charging.
2.2.2 Level 1 EVSE
2.2.2.1 Level 1 Wall Mounted EVSE
UL 2202 , UL 2251 , UL 2231-1 , UL 2231-2 , UL 2594 . Type 1, SAE J1772 connector, 120 volt, input 15 amps, output 12 amps, 2 kW .
2.2.2.2 Level 1 Pedestal Mounted EVSE
UL 2202 , UL 2251 , UL 2231-1 , UL 2231-2 , UL 2594 . Type 1, SAE J1772 connector, 120 volt, input 15 amps, output 12 amps, 2 kW .
2.2.3 Level 2 EVSE
2.2.3.1 Level 2 Wall Mounted EVSE
UL 2202 , UL 2251 , UL 2231-1 , UL 2231-2 , UL 2594 . Type 2, SAE J1772 connector, 208 volt, input 30 amps, output 30 amps, 7.2 kW .
SECTION 11 11 37 Page 7
2.2.3.2 Level 2 Pedestal Mounted EVSE
UL 2202 , UL 2251 , UL 2231-1 , UL 2231-2 , UL 2594 . Type 2, SAE J1772 connector, 208 volt, input 30 amps, output 30 amps, 7.2 kW .
2.2.4 DC Fast Charger EVSE
2.2.4.1 DC Fast Charger Wall Mounted EVSE
UL 2202 , UL 2251 , UL 2231-1 , UL 2231-2 , UL 2594 . CHAdeMO and CCS Combination connectors, 480 volt, input 32 amps, output 62 amps, 24 kW .
2.2.4.2 DC Fast Charger Pedestal Mounted EVSE
UL 2202 , UL 2251 , UL 2231-1 , UL 2231-2 , UL 2594 . CHAdeMO and CCS Combination connectors, 480 volt, input 32 amps, output 62 amps, 24 kW .
2.2.5 Cords
UL 62 .
a. 14 feet , minimum, UL rated charging cords with integral retractable cord management mechanism or separate cord management.
2.3 CONNECTOR HOLSTER DOCK
Provide connector holster dock to store charger plugs when not in use.
Holster construction consist of high strength injection molded plastic with temperature ratings of minus 30 deg C to 50 deg C. Provide holster to match EV plug.
2.4 PEDESTAL CONSTRUCTION
Provide corrosion resistant construction for outdoor use and continuous exposure to a marine environment. Pedestal shall be NEMA 4x NEMA 3 Construction.
2.5 ACCESSORIES
a. Back-lit touch button interface keypad with audio feedback. LCD must display READY TO CHARGE, CHARGING, CHARGE COMPLETE, PAUSE-WAITING TO
CHARGE AND FAULT.
b. Daylight readable 64x480 active matrix LCD with auto brightness control.
c. Activation of EVSE upon identification utilizing magnetic swipe, RFID or barcode cards.
e. Real-time energy measurement controls.
f. Fifteen minute energy measurement interval recording.
g. Time-of-day pricing capability.
h. Nuisance tripping avoidance and auto-re-closure features.
i. Cold Load Pickup (Randomized auto restart following power outage).
SECTION 11 11 37 Page 8
j. Provide minimum four keycards/barcodes/RFID keys for each charger to activate the charger and its data network.
k. EVSE must include automatic web-based tracking / metering and control connection via a cell phone service provider compatible with Electric Vehicle Management system.
The web-based application shall generate per vehicle kW usage and charging times based on user input intervals.
EVSE Electronic Data Interface shall capture and be capable of push and pull file transfer of the parameters listed below. Web-based control capability shall enable remote charger station administration and access control by the Government. Data must be User ID and Password protected.
(1) Kilowatt (kW) data report must be compatible Microsoft Excel (Version 2007 or higher).
(2) Must have option to limit usage to designated users with bar code/key card type system (locked or open access).
(3) Manufacture control of EVSE is not allowed without prior written Government approval.
2.6 CAST-IN-PLACE CONCRETE
Shall be composed of fine aggregate, coarse aggregate, portland cement, and water so proportioned and mixed as to produce a plastic, workable mixture. Fine aggregate shall be of hard, dense, durable, clean, and uncoated sand. The coarse aggregate shall be reasonably well graded from 3/16 inch to one inch. The fine and coarse aggregates shall be free from injurious amounts of dirt, vegetable matter, soft fragments or other deleterious substances. Water shall be fresh, clean, and free from salts, alkali, organic matter, and other impurities. Concrete associated with electrical work for other than encasement of underground ducts shall be 4000 psi minimum 28-day compressive strength unless specified otherwise.
Slump shall not exceed 4 inches. Retempering of concrete will not be permitted. Exposed, unformed concrete surfaces shall be given a smooth, wood float finish. Concrete shall be cured for a period of not less than 7 days, and concrete made with high early strength portland cement shall be repaired by patching honeycombed or otherwise defective areas with cement mortar as directed by the Contracting Officer. Air entrain concrete exposed to weather using an air-entraining admixture conforming to ASTM C260/C260M. Air content shall be between 4 and 6 percent.
2.7 MANUFACTURER'S NAMEPLATES
Each item of equipment shall have a nameplate bearing, as a minimum, the manufacturer's name, address, model number, and serial number securely affixed in a conspicuous place; the nameplate of the distributing agent will not be acceptable. Include additional information as applicable to fully identify the equipment. Nameplates shall be made of noncorrosive metal.
SECTION 11 11 37 Page 9
2.8 PAVEMENT MARKINGS
Provide pavement markings for the vehicle charging parking spots to indicate the restrictions for electrical vehicle parking.
2.9 ELECTRIC VEHICLE SUPPLY EQUIPMENT (EVSE) SIGNAGE
Provide signage Electric Vehicle Supply Equipment per MUTCD and Base standards.
2.10 WHEEL STOPS AND BOLLARDS
Provide wheel stops or bollards in Electrical Vehicle parking spaces to provide protection for Electric Vehicle Supply Equipment.
PART 3 EXECUTION
3.1 INSTALLATION
Electrical installations shall conform to IEEE C2 , NFPA 70 , and to the requirements specified herein.
a. The EVSE installer must be certified by the manufacturer or a recognized training facility to perform the installation.
b. Provide chargers per manufacturer instructions and recommendations.
EVSE must be programmed and configured by a certified installer.
3.2 GROUNDING
NFPA 70 and IEEE C2 , except provide grounding systems with a resistance to solid earth ground not exceeding 25 ohms.
3.2.1 Grounding Electrodes
Provide driven ground rods as specified in Section 33 71 02 UNDERGROUND ELECTRICAL DISTRIBUTION. Connect ground conductors to the upper end of ground rods by exothermic weld or compression connector. Provide compression connectors at equipment end of ground conductors.
3.3 FIELD APPLIED PAINTING
Where field applied painting of enclosures is required to correct damage to the manufacturer's factory applied coatings, provide manufacturer's recommended coatings and apply in accordance with manufacturer's instructions.
3.4 FIELD FABRICATED NAMEPLATE MOUNTING
Provide number, location, and letter designation of nameplates as indicated. Fasten nameplates to the device with a minimum of two sheet-metal screws or two rivets.
3.5 FOUNDATION FOR EQUIPMENT AND ASSEMBLIES
3.5.1 Exterior Location
Mount on concrete slab, unless otherwise indicated. The slab shall be at least 8 inches thick, reinforced with a 6 by 6 - W2.9 by W2.9 mesh placed
SECTION 11 11 37 Page 10 uniformly 4 inches from the top of the slab. Slab shall be placed on a 6 inch thick, well-compacted gravel base. Top of concrete slab shall be approximately 4 inches above the finished grade. Edges above grade shall have 1/2 inch chamfer. The slab shall be of adequate size to project at least 8 inches beyond the equipment. Provide conduit turnups and cable entrance space required by the equipment to be mounted. Seal voids around conduit openings in slab with water- and oil-resistant caulking or sealant. Seals shall be of sufficient strength and durability to protect all energized live parts of the equipment from rodents, insects, or other foreign matter. Cut off and bush conduits 3 inches above slab surface.
3.6 OPERATION AND MAINTENANCE
3.6.1 Operation and Maintenance Training
Conduct a training course for the members of the operating staff as designated by the Contracting Officer. Make the training period consist of a total of 4, hours for Level 1 or level 2 and 8, hours for DC Fast Charge of normal working time and start it after all work specified herein is functionally completed and the Performance Tests have been approved.
Conduct field instruction that covers all of the items contained in the Operation and Maintenance Manuals as well as demonstrations of routine maintenance operations. Submit the proposed On-site Training Materials and schedule concurrently with the Operation and Maintenance Manuals and at least 30 days prior to conducting the training course.
3.7 RECORD DOCUMENTATION
Provide drawings indicating construction provided for this project.
Provide electronic files and hard copies on 11 inch by 17 inch paper.
3.8 FIELD QUALITY CONTROL
3.8.1 Testing of Electric Vehicle Supply Equipment
Provide testing of Electric Vehicle Supply Equipment with test equipment per current standards and manufacturers recommendations. Provide data submittal indicating time of charge and kW level used.
3.8.2 Performance of Acceptance Checks and Tests
Perform in accordance with the manufacturer's recommendations and include the following visual and mechanical inspections and electrical tests.
Submit reports, including acceptance criteria.
3.8.2.1 EVSE
a. Visual and mechanical inspection.
(1) Compare equipment nameplate data with specifications and approved shop drawings.
(2) Inspect physical and mechanical condition. Check for damage.
(3) Inspect anchorage, alignment, and grounding.
(4) Perform specific inspections and mechanical tests as recommended by manufacturer.
SECTION 11 11 37 Page 11
b. Electrical Tests
(1) Perform resistance measurements through all bolted connections with low-resistance ohmmeter.
(2) Verify voltage levels.
(3) Check ground fault circuit interrupt.
(4) Check pilot signal detection and verification.
(5) Verify current limit.
(6) Verify operation of alarms.
(7) Verify EVSE Electronic Data Interface.
Values of test shall be within limits of manufacturer's recommendations.
-- End of Section --
SECTION 11 11 37 Page 12
SECTION TABLE OF CONTENTS
DIVISION 11 - EQUIPMENT
SECTION 11 47 00
ICE MACHINES
PART 1 GENERAL
1.1 REFERENCES
1.2 SUMMARY
1.3 SUBMITTALS
1.4 ADMINISTRATIVE REQUIREMENTS
1.4.1 Pre-Installation Meeting
1.4.1.1 Shop Drawings
1.4.1.2 Product Data
1.4.2 LIST OF EQUIPMENT
PART 2 PRODUCTS
2.1 MATERIALS
2.2 CONSTRUCTION OF FABRICATED EQUIPMENT
2.3 FACTORY TESTS AND CERTIFICATIONS
2.4 AUTOMATIC CLEANING SYSTEM
PART 3 EXECUTION
3.1 EXAMINATION
3.2 INSTALLATION
3.3 MANUFACTURER'S WARRANTY
3.4 CONTRACTOR'S WARRANTY FOR INSTALLATION
-- End of Section Table of Contents --
SECTION 11 47 00 Page 1
SECTION 11 47 00
ICE MACHINES
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
NSF INTERNATIONAL (NSF)
NSF/ANSI 12 (2018) Automatic Ice Making Equipment
NSF/ANSI 14 (2021) Plastics Piping System Components and Related Materials
NSF/ANSI 169 (2019)Special Purpose Food Equipment and Devices
U.S. DEPARTMENT OF ENERGY (DOE)
Energy Star (1992; R 2006) Energy Star Energy Efficiency Labeling System (FEMP)
U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)
29 CFR 1910-SUBPART D Walking - Working Surfaces
29 CFR 1910.144 Safety Color Code for Marking Physical Hazards
29 CFR 1910.145 Specifications for Accident Prevention Signs and Tags
29 CFR 1910.306 Specific Purpose Equipment and Installations
1.2 SUMMARY
The work includes furnishing and installing and modifying existing ice making equipment, including dispensing, production, storage , and autocleaning equipment and related work. Include coordination of delivery through existing finished opening and vertical handling limitations within the building.
a. Provide rough-in and connect utilities to equipment in accordance with requirements specified in other sections of this specification and in conformance with the physical dimensions, capacities, manufacturer's instructions, and other requirements of the equipment furnished.
b. Equipment specified must also conform to the applicable requirements of the following reference standards: NSF/ANSI 12 , NSF/ANSI 14 , NSF/ANSI 169 , and Energy Star for powered equipment.
SECTION 11 47 00 Page 2
c. Refer to Section 11 05 40 COMMON WORK RESULTS FOR FOOD SERVICE EQUIPMENT for general requirements. Refer to Section 11 06 40.13 FOODSERVICE EQUIPMENT SCHEDULE for Food Service Equipment Schedule.
1.3 SUBMITTALS
Government approval is required for submittals with a "G" or "S" classification. Submittals not having a "G" or "S" classification are for information only. When used, a code following the "G" classification identifies the office that will review the submittal for the Government.
Submit the following in accordance with Section 01 33 00 SUBMITTAL
PROCEDURES:
SD-01 Preconstruction Submittals
Contractor's Field Verification Data; G
SD-02 Shop Drawings
Detail Drawings; G
Custom Fabricated Equipment; G
Installation Instructions and Diagrams; G
SD-03 Product Data
Ice Making Equipment
Ice Machine Autocleaning Equipment
Energy Star label for ice machine; S
SD-05 Design Data
Manufacturer's Applicable Literature; G
SD-06 Test Reports
Manufacturer's Test Data; G
Field Test Reports; G
SD-07 Certificates
NSF Certification
UL Certification
SD-08 Manufacturer's Instructions
Manufacturer's Instructions; G
SD-10 Operation and Maintenance Data
Ice Making equipment, Data Package 2; G
Submit in accordance with Section 01 78 23 OPERATION AND
SECTION 11 47 00 Page 3
MAINTENANCE DATA.
SD-11 Closeout Submittals
Manufacturer's Warranty
Contractor's Warranty for Installation
1.4 ADMINISTRATIVE REQUIREMENTS
1.4.1 Pre-Installation Meeting
Thirty days prior to the commencement of work, notify the Contracting Officer that the following items are prepared and ready for review:
1.4.1.1 Shop Drawings
Detail drawings, as specified, including insulation and utility requirements, product data, installation instructions and diagrams.
Submit custom fabricated equipment drawings after approval of ice machine equipment drawings. Drawings must be 1/4 inch scale minimum.
1.4.1.2 Product Data
Submit the product data for the following equipment, as well as the associated manufacturer's data:
a. ice making equipment
b. ice machine autocleaning equipment
c. Manufacturer's applicable literature
d. Manufacturer's Test Data
e. Energy Star Labeled
f. Manufacturer's Instructions for shipping, handling, storage, installation, and start-up.
1.4.2 LIST OF EQUIPMENT
Submit detailed Food Service Equipment List. Include submittal of NSF Certification, Energy Star Labeled and UL Certification for ice making equipment and autocleaning equipment.
PART 2 PRODUCTS
2.1 MATERIALS
Provide ice making equipment conforming to OSHA standards 29 CFR 1910.144 , 29 CFR 1910.145 , 29 CFR 1910.306 , Energy Star , and related NSF and UL standards. Floor areas adjacent to ice making equipment point of operation must conform to 29 CFR 1910-SUBPART D . Ice making equipment materials must conform to the requirements of Section 11 05 40 COMMON WORK
RESULTS FOR FOOD SERVICE EQUIPMENT.
SECTION 11 47 00 Page 4
Provide ice machine that is Energy Star labeled. Provide data identifying Energy Star label for ice machine.
2.2 CONSTRUCTION OF FABRICATED EQUIPMENT
Construction and finish of fabricated equipment must conform to the requirements of Section 11 05 40 COMMON WORK RESULTS FOR FOOD SERVICE
EQUIPMENT.
2.3 FACTORY TESTS AND CERTIFICATIONS
Submit 3 copies of all Manufacturer's Test Data and certifications, including NSF Certification; UL Certification, and Energy Star Labeled data to the Contracting Officer prior to the commencement of any installation work.
2.4 AUTOMATIC CLEANING SYSTEM
Provide ice making equipment with internal automatic cleaning system with cleaning and sanitizing capability. Provide 115/60/1 , 0.3 total amps, with 15 amp maximum fuse electrical system. Include one month supply of cleaning and sanitizing fluid plus initial start-up and testing supply.
PART 3 EXECUTION
3.1 EXAMINATION
Do not install items that show visual evidence of biological growth.
After becoming familiar with all details of the work, verify all existing dimensions, contract drawings, product data and all related conditions prior to commencing rough-in work. Advise the Contracting Officer of any discrepancies prior to ordering equipment. Submit Contractor's Field Verification Data prior to the pre-installation meeting.
3.2 INSTALLATION
Refer to Section 11 05 40 COMMON WORK RESULTS FOR FOOD SERVICE EQUIPMENT for detailed installation procedures, operation and maintenance manual requirements, training and project closeout procedures. Include all ice making and autocleaning equipment Field Test Reports. Coordinate ice machine equipment installation with water filter system as specified in section 11 46 00.
3.3 MANUFACTURER'S WARRANTY
Submit all manufacturers' signed warranties to Contracting Officer prior to final commissioning and acceptance.
3.4 CONTRACTOR'S WARRANTY FOR INSTALLATION
Submit contractor's warranty for installation to the Contracting Officer prior to final commissioning and acceptance.
-- End of Section --