Fort Gordon BASOPS Technical Exhibit H-002 - Privatized Utilities Provider Demarcation Points Electrical Lines of Demarcation
| Point of Demarcation |
| Applicable Scenario |
| Diagram |
Point of demarcation is the first point of disconnect at or in the facility.
Pad mounted transformer located outside of structure with underground service to structure and no meter exists.
| Down current side of the meter. |
| Residential service (less than 200 amps and 240V One-Phase) and Three-Phase self-contained meter installations. Electric meter exists within five feet of the exterior of the building on an underground secondary line. |
| Point of demarcation is the first point of disconnect at or in a facility. |
| Three-Phase CT metered service. |
| Secondary terminal of the transformer inside of the structure. |
| Transformer located inside the structure and an isolation device is in place with or without meter. |
Note: Utility owner must be granted 24-hour access to transformer room.
| Secondary terminal of the transformer inside of the structure. |
| Transformer located inside the structure with no isolation device in place. |
Note: Utility owner must be granted 24-hour access to transformer room.
Wastewater Lines of Demarcation
| Point of Demarcation |
| Applicable Scenario |
| Diagram |
| The point of demarcation is five feet away from the exterior of the structure or to a point beyond the cleanout, whichever is closest to the building. |
| All scenarios. |
| The point of demarcation is where the effluent pipe exits the oil/water separator. |
| All scenarios where an oil/water separator discharges to the waste water system. |
| Point of Demarcation |
| Applicable Scenario |
| Point of Demarcation Description/ Diagram |
| 17th Street Landfill (Main Post) - The point of demarcation is where the leachate line crosses the property boundary of the landfill. |
| All scenarios. |
| The point of demarcation is the Prison side of the closest manhole. |
| All scenarios. |
Natural Gas Lines of Demarcation
| Point of Demarcation |
| Applicable Scenario |
| Diagram |
Point of demarcation is the downstream side of the natural gas meter.
Natural Gas service to the building is metered.
| The point of demarcation is the downstream side of the pressure regulator. |
| Natural gas service to the building is regulated but not metered. |
| The point of demarcation is the downstream side of the closest apparatus to the exterior of the facility. |
| More than one apparatus is connected to the service line feeding the facility. |
| The point of demarcation is where the piping penetrates the building envelope. |
| No meter or regulator exists at the facility. |
Water Lines of Demarcation
| Point of Demarcation |
| Applicable Scenario |
| Diagram |
The point of demarcation is on the side of the post indicator valve.
Structures with fire suppression lines supplied by the water distribution system
Unique Points of Demarcation Water Distribution System – Fort Gordon
| Point of Demarcation |
| Applicable Scenario |
| Diagram |
The point of demarcation is the downstream side of the valve pit.
Augusta Richmond County 18” distribution line.
The point of demarcation is the downstream side of the valve pit.
Columbia County Distribution to Fort Gordon Recreation Area (Pointes West Army Resort / Clarke Hill Recreation Area).
The point of demarcation is the downstream side of the meter.
Augusta State Medical Prison (Fort Gordon Gate 3).
The point of demarcation is the downstream side of the valve box.
National Science Center.
AUD’s Purple Pipe Irrigation System – Fort Gordon
*Note: This irrigation system is not BASOPS Contractor responsibility
Replica Pool Solar Water Heating System Line of Demarcation – Fort Gordon
| Point of Demarcation |
| Applicable Scenario |
| Diagram |
The points of demarcation for this system are the valves on the pipes that tap off of the return piping from the filters.
The Replica Pool includes a solar water heating system that will not be part of this contract.
Solar Heater Solar Heater Valve Pool Return Line
Point of Demarcation image5.emf image6.emf image7.emf image8.emf image9.emf image10.emf image11.emf image12.emf image13.emf image14.emf image15.emf image16.emf image17.emf image18.emf image19.JPG image20.png image21.png image22.png image23.png image24.png image25.png image1.emf image2.emf image3.emf image4.emf