TE_6 ISR Report Example.pdf
PDF 96 KB Posted
- Attached to
- Operations and Maintenance Service Order Center Federal contract opportunity
- Solicitation number
- W91247-21-R-9003
About this file
This document contains federal contract opportunity and performance documentation for facilities maintenance services. The federal contract opportunity is solicitation number W91247-21-R-9003 for operations and maintenance service order center support. The services required include call center support and work order management in GFEBS and ARMA systems for over 55 million square feet of facilities, 1,500 miles of roads, and three airfields. The call center currently receives 300-400 calls daily and support includes work order creation, reporting, analysis and data management. The contract location is building 251 at Fort Bragg, NC and supports the Department of the Army Materiel Command Mission and Installation Contracting Command. The performance documentation provides metrics for emergency, urgent and routine maintenance completion rates and preventative maintenance spending versus plans.
View the file
Other files for this federal contract opportunity
Show all 31
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FY 2015 ISR Services ACTIVE Documentation As of 14-Jul-16
FY 2015 ISR Services – All documentation can be downloaded from http://isr.hqda.pentagon.mil
Evaluator Signature:______________________________________________________________________________________________________________________Date__________________________________________________
Service: 411. Facilities Maintenance- Training & Ops (ACTIVE Intellicode 411-AC-01-02-A) FY 2014 Intellicode #: 411-IM-01-02 Service Definition: Provide maintenance and repair of all installation facilities. Includes all Standing Operating Orders (SOO), Individual Job Orders (IJO) or Project Work Orders (PWO), Demand Maintenance Work Orders (DMO), and Preventive Maintenance Orders (PMO) work performed inside or within five feet of a facility. Excludes facility infrastructure (utility service components, roads, grounds) and environmental protection services.
Measure Description: Percentage of validated emergency demand work orders completed IAW established completion times.
Major Service Area Service Function ACTIVE Primary Service Category 1 (Weight 100%) Infrastructure Support Infrastructure Support Sustainment Projects or Orders
Measure Type Frequency Measure Toploaded Formula Shared Quarterly ([a]/[b])*100 Cost Customer Satisfaction Readiness Information Only
Green Standard Amber Standard Red Standard Black Standard 100% down to 95% Less than 94% down to75% Less than 74% down to 50% Less than 50%
Data Element Description YTD Metho d
Element Toploade d
Q1 Q2 Q3 Q4 Annual a = Number of validated emergency demand work orders completed IAW established emergency completion times (24 hours). Sum 1,232 1,362 1,126 918 b = Total number of validated emergency demand work orders. Sum 1,402 1,663 1,316 1312 c = d = e = f = g = h = i =
Data Source/Notes: SSP A, Work Order Records in GFEBS.
NOTE: Intent is to capture 'completion time' instead of 'response time'. Measure 'completion time' as the time between opening and closing time within GFEBS or other work management system.
a. This is the count of the validated Emergency orders completed within standard during thE 4th quarter (July 1, 2015 thru September 30, 2015) of FY15
b. This is the count of the validated Emergency orders completed during the 4th quarter (July 1, 2015 thru September 30, 2015) of FY15
Note: Complete is a CNF status in GFEBS Data Information: Data was pulled for all OMD 411- Facilities Maintenance (Vertical)
1. It includes all Standing Operating Orders (SOO), Individual Job Orders (IJO) or Project Work Orders (PWO), Demand Maintenance Work Orders (DMO), and Preventive Maintenance Orders (PMO) work performed inside or within five feet of a facility.
2. It excludes facility infrastructure (utility service components, roads, grounds) and environmental protection services.
3. It excludes all orders in a status of CANC. Excluding a CANC status is due to most orders in a CANC status are never responded to by a technician and are CANC in GFEBS as a result of being a duplicate request or a request that does not belong to OMD/DPW but to a privatized utility company.
TE 6 ISR Report Example http://isr.hqda.pentagon.mil/
Evaluator Signature:______________________________________________________________________________________________________________________Date__________________________________________________
Service: 411. Facilities Maintenance- Training & Ops (ACTIVE Intellicode 411-AC-01-03-A) FY 2014 Intellicode #: 411-IM-01-03
Service Definition: Provide maintenance and repair of all installation facilities. Includes all Standing Operating Orders (SOO), Individual Job Orders (IJO) or Project Work Orders (PWO), Demand Maintenance Work Orders (DMO), and Preventive Maintenance Orders (PMO) work performed inside or within five feet of a facility. Excludes facility infrastructure (utility service components, roads, grounds) and environmental protection services.
Measure Description: Percentage of validated urgent demand work orders completed IAW established completion times.
Major Service Area Service Function ACTIVE Primary Service Category 1 (Weight 100%) Infrastructure Support Infrastructure Support Sustainment Projects or Orders
Measure Type Frequency Measure Toploaded Formula Shared Quarterly ([a]/[b])*100 Cost Customer Satisfaction Readiness Information Only
Green Standard Amber Standard Red Standard Black Standard
100% down to 95% Less than 94% down to75% Less than 74% down to 50% Less than 50%
Data Element Description YTD Metho d
Element Toploade d
Q1 Q2 Q3 Q4 Annual a = Number of validated urgent demand work orders completed IAW established urgent completion times (7 calendar days). Sum 3,622 3,546 3,993 2,577 b = Total number of validated urgent demand work orders. Sum 6,881 8,033 7,877 7,227 c = d = e = f = g = h = i =
Data Source/Notes: SSP A, Work Order Records in GFEBS.
NOTE: Intent is to capture 'completion time' instead of 'response time'. Measure 'completion time' as the time between opening and closing time within GFEBS or other work management system.
a. This is the count of the validated Urgent orders completed within standard during the during the 4th quarter (July 1, 2015 thru September 30, 2015) of FY15
b. This is the count of the validated Urgent orders completed during the 4th quarter (July 1, 2015 thru September 30, 2015) of FY15
Note: Complete is a CNF status in GFEBS Data Information: Data was pulled for all OMD 411- Facilities Maintenance (Vertical).
1. It includes all Standing Operating Orders (SOO), Individual Job Orders (IJO) or Project Work Orders (PWO), Demand Maintenance Work Orders (DMO), and Preventive Maintenance Orders (PMO) work performed inside or within five feet of a facility.
2. It excludes facility infrastructure (utility service components, roads, grounds) and environmental protection services.
3. It excludes all orders in a status of CANC. Excluding a CANC status is due to most orders in a CANC status are never responded to by a technician and are CANC in GFEBS as a result of being a duplicate request or a request that does not belong to OMD/DPW but to a privatized utility company.
Data Note: The continued issue with Completing Pri 2 orders within standard is the ever increasing backlog due to lack of Manpower as well as takings (like windows and doors contract, Roofing issues, Boiler repairs) that sit with insufficient funding to contract out the tasking and insufficient Manpower to complet the job for months or years at a time.
Evaluator Signature:______________________________________________________________________________________________________________________Date__________________________________________________
Service: 411. Facilities Maintenance- Training & Ops (ACTIVE Intellicode 411-AC-01-04-A) FY 2014 Intellicode #: 411-IM-01-04
Service Definition: Provide maintenance and repair of all installation facilities. Includes all Standing Operating Orders (SOO), Individual Job Orders (IJO) or Project Work Orders (PWO), Demand Maintenance Work Orders (DMO), and Preventive Maintenance Orders (PMO) work performed inside or within five feet of a facility. Excludes facility infrastructure (utility service components, roads, grounds)
Measure Description: Percentage of validated routine demand work orders completed IAW established completion times.
Major Service Area Service Function ACTIVE Primary Service Category 1 (Weight 100%) Infrastructure Support Infrastructure Support Sustainment Projects or Orders
Shared Quarterly ([a]/[b])*100 Cost Customer Satisfaction Readiness Information Only
100% down to 95% Less than 94% down to75% Less than 74% down to 50% Less than 50%
Metho d
Element Toploade d
Q1 Q2 Q3 Q4 Annual a = Number of validated routine demand work orders completed IAW established routine completion times (30 calendar days). Sum 4,819 4,471 5,412 2,559 b = Total number of validated routine demand work orders. Sum 7,283 7,284 8,412 3,413 c = d = e = f = g =
Data Source/Notes: SSP A, Work Order Records in GFEBS.
NOTE: Intent is to capture 'completion time' instead of 'response time'. Measure 'completion time' as the time between opening and closing time within GFEBS or other work management system.
a. This is the count of the validated Routine orders completed within standard during the 4th quarter (July 1, 2015 thru September 30, 2015) of FY15
b. This is the count of the validated Routine orders completed during the 4th quarter (July 1, 2015 thru September 30, 2015) of FY15
Note: Complete is a CNF status in GFEBS Data Information: Data was pulled for all OMD 411- Facilities Maintenance (Vertical)
1. It includes all Standing Operating Orders (SOO), Individual Job Orders (IJO) or Project Work Orders (PWO), Demand Maintenance Work Orders (DMO), and Preventive Maintenance Orders (PMO) work performed inside or within five feet of a facility.
2. It excludes facility infrastructure (utility service components, roads, grounds) and environmental protection services.
3. It excludes all orders in a status of CANC. Excluding a CANC status is due to most orders in a CANC status are never responded to by a technician and are CANC in GFEBS as a result of being a duplicate request or a request that does not belong to OMD/DPW but to a privatized utility company.
Evaluator Signature:______________________________________________________________________________________________________________________Date__________________________________________________
Service: 411. Facilities Maintenance- Training & Ops (ACTIVE Intellicode 411-AC-02-05-A) FY 2014 Intellicode #: 411-IM-02-05-A
Service Definition: Provide maintenance and repair of all installation facilities. Includes all Standing Operating Orders (SOO), Individual Job Orders (IJO) or Project Work Orders (PWO), Demand Maintenance Work Orders (DMO), and Preventive Maintenance Orders (PMO) work performed inside or within five feet of a facility. Excludes facility infrastructure (utility service components, roads, grounds)
Measure Description: Percentage of emergency, urgent, and routine DMOs completed within standard and total dollar amount of preventive maintenance executed compared to planned PM.
Major Service Area Service Function ACTIVE Primary Service Category 2 (Weight 0%) Infrastructure Support Infrastructure Support Demand and Preventive Maintenance Orders
CLS Quarterly ((([a]/[b])*100) *.7) + ((([c]/[d])*100)*.3)
Cost Customer Satisfaction Readiness Information Only Y
100% down to 95% Less than 95% down to 75% Less than 75% down to 50% Less than 50%
Method
Element Toploaded
Q1 Q2 Q3 Q4 Annual a = Number of emergency, urgent, and routine DMOs completed within standard. Sum 9,673 9,379 10,531 5,363 b = Total Number of DMO issued. Sum 15,556 16,980 17,605 11,893 c = Total dollar amount of preventive maintenance executed. Sum $177,534 $514,447 $699,807.54 256,713.93 d = Total dollar amount of preventive maintenance required and planned. Sum $306,216 $382,347 $624,630.90 e = f = g =
Data Source/Notes: SSP A; Work Order Records in GFEBS
a. This is the count of the validated Emergency,Urgent, & Routine orders completed within standard during the 4th quarter (July 1, 2015 thru September 30, 2015) of FY15
b. This is the count of the validated Emergency,Urgent, & Routine orders completed during the 4th quarter (July 1, 2015 thru September 30, 2015) of FY15
c. Of the orders created in FY15 (Oct 1, 2014 thru Sept 30, 2015) this is the amount of money spent on Preventative Maintenance during the 4th quarter (July 1, 2015 thru September 30, 2015) of
FY15.
d. This is the average amount of money required and planned to complete all Preventative Maintenance orders that we created during during the 4th quarter (July 1, 2015 thru September 30, 2015) of FY15.
Note: Complete is a CNF status in GFEBS Data Information: Data was pulled for all OMD 411- Facilities Maintenance (Vertical)
1. It includes all Standing Operating Orders (SOO), Individual Job Orders (IJO) or Project Work Orders (PWO), Demand Maintenance Work Orders (DMO), and Preventive Maintenance Orders (PMO) work performed inside or within five feet of a facility.
2. It excludes facility infrastructure (utility service components, roads, grounds) and environmental protection services.
3. It excludes all orders in a status of CANC. Excluding a CANC status is due to most orders in a CANC status are never responded to by a technician and are CANC in GFEBS as a result of being a duplicate request or a request that does not belong to OMD/DPW but to a privatized utility company.
Data Note: The additional cost for PM’s this quarter comes from the Changeover season from Heat to AC and all the Preventative Maintence cost associated with that tasking.