This is a Special Conditions document for HVAC Testing, Adjusting, and Balancing (TAB) services issued by the Kentucky Community and Technical College System (KCTCS) Gateway Community and Technical College for mechanical and controls upgrades at their Florence, Kentucky campus (RFB-50-24, Account No: 470CAEWNC2400). The project encompasses six buildings totaling approximately 315,795 square feet across three campuses: the Boone Campus Center of Advanced Manufacturing Building (108,000 SF), the Boone Campus Bank of Kentucky/BB&T Classroom and Training Building (34,779 SF), the Edgewood Campus Nursing and Allied Health Building (54,140 SF), the Edgewood Campus Student Services Building (35,270 SF), the Urban Campus Technology, Innovation, and Enterprise Building (54,315 SF), and the Urban Campus Transportation Technologies Building (33,291 SF). The TAB Agency must furnish all labor, materials, tools, and instruments to perform comprehensive testing, adjusting, and balancing services on HVAC systems including hot water and chilled water equipment, air handling units, rooftop units, variable air volume boxes, furnaces, condensing units, and wall-mounted split systems. The General Contractor's substantial completion date is January 18, 2025, with final completion by February 17, 2025; the TAB contractor must achieve final completion by January 18, 2025. The TAB Agency is responsible for attending project progress meetings, completing checkout and start-up plans, participating in equipment start-up and owner training, providing preliminary TAB reports, and posting daily reports weekly in the eComm system.
Pricing for TAB services is structured on unit rates, including calibration of devices and ductwork pressure testing (priced per hour) and additional trips to the job site (priced per trip); all unit prices must include labor, materials, supplies, overhead, and profit for the agency and any subcontractors. The TAB Agency may invoice for partial payments up to 90 percent of the contract amount upon acceptance of completed work by the A/E Project Design Engineer, with the remaining 10 percent contingent on final acceptance. Invoices and change orders should be submitted to Kristi.Sharp@ky.gov, and reports must be posted in eComm under the "6.12 Invoice for TAB Services" workflow for engineer review and acceptance before payment is processed. The project directory identifies CMTA, Inc. as the engineer, Schrudde & Zimmerman, Inc. as the general contractor, and EMCOR Services/Automated Logic as the DDC Controls contractor, with the Owner Project Manager being Greg Schenck of the Kentucky Division of Engineering and Contract Administration.
View the file
Other files
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
HVAC TESTING, ADJUSTING & BALANCING SERVICES
KCTCS – Mechanical and Controls Upgrades, Gateway CTC 500 Technology Way Florence, Kentucky 41042 Account No: 470CAEWNC2400
SPECIAL CONDITIONS 01000 A - 1
DIVISION 1 – GENERAL REQUIREMENTS
SECTION 01000 A - SPECIAL CONDITIONS for TAB Work
Re: KCTCS – Mechanical and Controls Upgrades, Gateway CTC
500 Technology Way Florence, Kentucky 41042 Account #: 470CAEWNC2400 Request for Bid No: RFB-50-24
Index:
1. Project Information / Scope
2. Related Documents and Information
3. TAB – Additional Services
4. List of Unit prices
5. Coordination and Participation
6. Substantial and Final Completion Dates
7. Payment
8. Project Directory
1. PROJECT INFORMATION / SCOPE:
A. This project includes (6) buildings operated by KCTCS Gateway CTC as summarized below:
a. Boone Campus – Center of Advanced Manufacturing Building: 108,000 SF 3-story building with traditional classrooms, lab classrooms with fume hoods, and large vocational labs. HVAC equipment includes of (1) HW/CHW VAV AHU with HW reheat VAVs, (2) heat recovery VAV AHUs serving the Welding Shop, (1) single zone RTU, (2) WSHPs, (2) condensing natural gas boilers, (2) water cooled heat recovery chillers, (1) traditional water-cooled chiller, and (1) cool-ing tower.
b. Boone Campus – Bank of Kentucky/BB&T Classroom and Training Building: 34,779 SF 2-story building with traditional classrooms and large vocational labs. HVAC equipment includes of (1) HW/CHW VAV AHU with HW reheat VAVs, (2) non-condensing natural gas boilers, (1) air-cooled chiller, and (4) single zone DX/NG RTUs.
c. Edgewood Campus – Nursing and Allied Health Building: 54,140 SF 3-story building with tradi-tional classrooms and some labs with fume hoods. HVAC equipment includes of (2) HW/CHW VAV AHUs with HW reheat VAVs, (4) condensing natural gas boilers, and (1) air-cooled chiller.
d. Edgewood Campus – Student Services Building: 35,270 SF 3-story building with administrative offices and traditional classrooms. HVAC equipment includes of (1) CHW/Electric Heat VAV AHU with Electric Reheat VAVs and (1) air-cooled chiller.
e. Urban Campus – Technology, Innovation, and Enterprise Building: 54,315 SF 4-story building with traditional classrooms. HVAC equipment includes (2) DX/NG VAV RTUs with energy wheel and Electric Reheat VAVs, (1) single zone DX/NG RTU, and (1) Energy Recovery Ventilation unit serving welding lab with fume hoods.
f. Urban Campus – Transportation Technologies Building: 33,291 SF 1-story building with tradi-tional classrooms and large automotive bay work areas. HVAC equipment includes of (4) DX/NG VAV RTUs with HW reheat VAVs, (2) natural gas boilers, and (2) Make-up Air Units with natural gas heat.
B. Scope of work for the TAB (Testing Adjusting and Balancing) Agency consists of furnishing all required materials, tools, instruments, coordination, participation and labor to perform and complete the TAB services per the Project plans and specifications for the above referenced Building Project.
500 Technology Way
SPECIAL CONDITIONS 01000 A - 2
a) The HVAC systems for the building consists of Hot Water equipment, Chilled Water equipment, AHUs, RTUs, VAVs, Furnaces, Condensing Units, Wall Hung Split Systems, and exhaust fans, etc.
b) Controls for the project consist of control systems for the HVAC systems in the building. The HVAC control system will interface into the KCTCS system.
C. These Special Conditions apply to all Divisions of the Specifications for the above project. Refer to the specifications for specific information.
2. RELATED DOCUMENTS AND INFORMATION:
A. Project Documents (plans and specifications) and related information for this project is available on
DECA’s eCommunications web site hosted by Lynn Imaging.
B. After award of the TAB Contract, the successful bidder will receive a “Link” for access to the web site for the above referenced Project.
C. It is the Responsibility of the TAB Agency to review all Project Documents and coordinate their work with the GC (General Contractor), and the Commissioning Agency for the Project.
3. TAB PRESSURE TESTING:
A. The TAB Agency shall include in their Bid the following.
a) Additional Services:
1. Supplemental Services:
i. Attend Project Progress Meetings as needed
2. Un-anticipated Services:
i. Work not anticipated in the Base Bid Documents. This may include repeated testing due to the equipment not being ready for/or passing the initial tests; ad-ditional services requested by the Owner or Engineer.
B. Posting Daily Reports in eComm:
a) The TAB Agency shall document their time spent in Daily Reports Log.
b) TAB Agency shall post their Daily Reports Weekly under workflow “7.2 AE/ Owner Observation
Reports” in eComm (eCommunications) for this Project.
c) The TAB Agency shall indicate in their Project Log which items are repeats of work, not ready, failed, etc, as this time will be back-charged by Change Order from the GC’s Contract.
d) There are no allowances in this project.
500 Technology Way
SPECIAL CONDITIONS 01000 A - 3
4. LIST OF UNIT PRICES:
A. Unit Prices shall include furnishing all labor, materials, supplies, services and all items of cost, and overhead and profit for the Agency and any Subcontractor involved. Unit Prices shall be used uniformly without modification for either additions or deductions.
Description of Work Quantity Unit Price
Calibration of devices, Ductwork and Casing Pressure Testing 1Hour $ /Hour
Additional Trips to Job Site 1Trip $ /Trip
5. Coordination and Participation:
C. Coordination with GC and the HVAC Contractor:
a) The TAB Agency is responsible for certain aspects for this project including, but not limited to the following:
i. Completion of Checkout and Start-up Plans
ii. Participation in equipment start-up
iii. Providing draft/pencil copies of preliminary TAB reports as systems complete TAB pro-cedures
iv. Participation in Owner Training
v. Participation in TAB Verification.
6. SUBSTANTIAL AND FINAL COMPLETION DATES:
A. Project Completion dates for the GC (General Contractor):
• Substantial Completion date is January 18, 2025
• Final Completion date is February 17, 2025
B. Project completion date for the TAB Contractor:
• Final Completion is January 18, 2025
C. The TAB Agency is responsible for coordinating their work with the project schedule through the Gen-eral Contractor and the Commissioning Agency.
7. PAYMENT:
A. The TAB Agency may submit invoicing for partial payments up to 90% of the contract amount pending the acceptance of the completed work by the A/E Project Design Engineer.
B. The TAB Agency may submit invoicing for remaining 10% of their contract contingent upon final ac-ceptance of the completed work.
500 Technology Way
SPECIAL CONDITIONS 01000 A - 4
A. Invoicing and change orders should be emailed to Kristi.Sharp@ky.gov. Reports should be loaded in Ecommunications.
a) To post a Report go to your Dashboard in eComm; find this Project by RFB #; pick “Item Logs” (from the blue bar); pick “6.12 Invoice for TAB Services” from the dropdown menu; post your report, and then pick “save and submit to next step”.
b) The TAB Report will then go to the Engineer for either: review and comments; revert back a step; and/or for acceptance.
c) The TAB Agency will receive payment, after acceptance of the TAB Report by those in the eComm Workflow.
8. PROJECT DIRECTORY:
Agency:
KCTCS – Gateway Community and Technical College Mike Blevins Phone: 502 607-1356 mike.blevins@kctcs.edu
Engineer:
CMTA, Inc.
Braydi McPherson-Hathaway Prospect, KY 40059 Phone 614-315-4070 bhathaway@cmta.com
General Contractor (GC):
Schrudde & Zimmerman, Inc.
Sherry Seger Phone 859-331-3160 ss@schrudde-zimmerman.com
DDC Controls Contractor:
EMCOR Services/Automated Logic Brian Sheeley Phone 859-266-5300 bsheely@emcor.net
Owner Project Manager(s):
Greg Schenck Division of Engineering and Contract Administration Bush Building 403 Wapping Street Frankfort, KY 40601 Mobile: 502-234-0519 Greg.schenck@ky.gov mailto:charles.c.ammonsjr.nfg@mail.mil mailto:ss@schrudde-zimmerman.com mailto:bsheely@emcor.net mailto:Greg.schenck@ky.gov
File details come from the government source that posted it. Updated .