This is an Addendum to an Indefinite Quantity Contract (IQC) issued by the Maryland Department of General Services (DGS) for pistol range modifications and repairs under solicitation TA-000-232-002A (DGS-23-306-IQC). The addendum modifies the terms and conditions of the original IQC agreement to clarify contractor responsibilities and performance requirements for facility modifications and maintenance work at state-operated pistol ranges. The contract encompasses repair, modification, and improvement services to existing range infrastructure, with work to be performed on an as-needed basis under individual task orders issued throughout the contract term.

The addendum establishes pricing structure parameters, payment terms, and performance standards for contractor submissions under the IQC framework. The document specifies that all work must comply with applicable Maryland regulations, building codes, and safety standards for firearms facilities. Contractors must maintain current licenses and certifications required for the type of work performed. The addendum clarifies scope limitations, insurance requirements, and procedures for task order issuance and completion. Any modifications to the original contract terms outlined in the base solicitation are superseded by provisions in this addendum, ensuring that all subsequent task orders and contractor performance align with the updated requirements.

View the file

Other files

Show all 19

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Addendum No. 2

March 9, 2026

STATE OF MARYLAND

DEPARTMENT OF GENERAL SERVICES

Atif Chaudhry, Secretary

Project No.: TA-000-232-002A IQC Pistol Range Modifications & Repairs

This Addendum will clarify, add to, delete from, correct and/or change the bid documents for the project referenced above to the extent indicated. This Addendum is hereby made a part of the bid documents on which the contract will be based. By submitting a bid for this solicitation you acknowledge receipt of this addendum. All questions must be in writing and addressed to the Procurement Officer, Natasha Ramsundar at natasha.ramsundar@maryland.gov.

This Addendum includes:

• Responses to RFIs

• Sheet/Drawing (E-7) – Reference Only

End of Addendum #2

Issued by:

State of Maryland

Office of State Procurement 301 W. Preston Street, Room 1204

Baltimore, MD 21201 Natasha Ramsundar

Natasha Ramsundar Procurement Officer

TA-000-232-002A IQC - Pistol Range Modifications & Repairs Response to RFIs

1. Will you be able to provide another site visit? We have subcontractor interest in seeing the site.

Any site visits requiring access (other than the pre-bid meeting) shall be coordinated in advance by calling the Rangemaster - Firearms Training Facility, Mr. Jamie Green at 410- 552-6300 or jamiel.green@maryland.gov.

2. On the electrical riser diagram, can you please confirm what is existing to remain and what is to be replaced?

Energy efficient 4' LED exterior fixtures to replace the 2 bulb CFL lighting. Energy efficient exterior flood fixtures to replace 100-watt metal halide fixtures. Items not described in this specification, but required for a safe, complete installation in accordance with all codes, laws, regulations, and generally accepted building industry practices are considered to be included and provided by the Contractor as part of this project with no additional cost to owner.

3. Is the lighting control system existing to remain or is it to be replaced?

Sheet E-7 provided with this addendum. lighting control system to be upgraded as required to function with new LED lighting fixtures. Any modifications are included in this scope of work, as applicable.

4. Are there any hazardous materials on site that we should be aware of?

Hazardous materials have not been identified on this project. Work will be completed on open air range.

5. It appears that the scope of work on the first two sheets of drawings S101 and S201 are clearly defined. The rest of the drawings, it is not clear what is existing vs. new work.

How do we determine what is new work?

Drawings provided for reference only. Scope of work identified in the project manual.

See III-3. Bid Summary.

6. Are the lighting plans showing replacement of all light fixtures one-for-one and nothing else?

Fixtures to be replaced identified on sheet E-1. Energy efficient 4' LED exterior fixtures to replace the 2 bulb CFL lighting. Energy efficient exterior flood fixtures to replace 100-watt metal halide fixtures. One for one replacement with all necessary materials to complete the replacement are included in the scope of work.

7. How will you go about replacing only 5ft of gutter? That will create several splice points that will eventually leak.

Length of gutter replacement to be determined by DGS. Unit price bid is based on five

(5) ft sections.

8. How are the 2x4 wood backing to be connected to the structure?

Replace in-kind with new fasteners, approved for wet locations.

9. To what extent are existing trench drains to be cleaned? Does that include the drain lines to the storm sewer? If so, how far?

Trench drains to be cleaned within the footprint of the range. Contractor to prevent debris from traveling down stormdrain pipe with a plug/filter while cleaning.

10. Note J calls for structural steel to be coated. Does this pertain to all exposed roof trusses, or is there other structural steel you are referring to? What about the steel inside of the enclosed room or any other steel?

Note J refers to steel used in the structural repairs identified on sheets S101 and S201.

This note does not apply to all existing structural steel.

mailto:jamiel.green@maryland.gov

11. CMU coating is shown at the existing CMU walls. Are all walls to be coated on all surfaces?

Apply Masonry Elastomeric Waterproof Coating to all CMU walls excluding the storage area internal walls, after repairs are completed.

12. Can you please confirm if MBE Form "D-3A CERTIFED MBE SUBCONTRACTOR PARTICIPATION CERTIFICATION" should be submitted with the bid, or if that form is to be submitted after notice of intent to award?

The D-3A Certified MBE Subcontractor Participation certification form is not required to be submitted with the Bid but will be requested at a later date from the qualifying bidder.

13. Please clarify the Section III-2, Repairs in the Project Manual. The project manual states to make repairs to the joist end connections based on S101, and details; A,B, and C on S201. It also states to use S201 for the storage room gaps. The drawings provided do not have these pages and it is not clear which details are to be used.

Sheets S101 and S201 provided in the Reference Drawings attachment.

14. Please provide specification or basis of design for the Metal safe protective sealant for trusses and steel baffle plates.

See Project Manual attachment five (5) LR Metal Roofs Application Guide 2025.

15. Please provide specification for the 3” metal insulation plate listed in Unit Price #1.

Insulation plate specification shall be provided by Tectum Panel Manufacturer installation instructions. Fastener placement locations same as existing. 3-inch plates to provide long-term corrosion resistance and prevent damage to Tectum Panels.

16. Please clarify demo of existing panels is to be included in Unit Price #1.

Unit Price one (1) includes all work associated with the replacement of the Tectum Panel, to include demolition of the existing panel to be replaced. DGS will identify the panels to be replaced after award and prior to construction.

Andalora Text Box

NOT FOR CONSTRUCTION - FOR REFERENCE ONLY