T02 Specifications Addendum 1 01 25 2022.pdf

PDF 67 KB Posted

Attached to
USMS Vehicle Barrier and Gate Replacement , Tallahassee Courthouse Amendment 0002
Solicitation number
47PE0722R0009
Issued by

About this file

This document provides specifications and phasing plans for the replacement of vehicle barriers and gates at the U.S. Courthouse Annex and U.S. Bankruptcy Courthouse in Tallahassee, Florida. The project will replace four existing active vehicle barriers with new M30 systems, refurbish and replace existing vehicular sliding gates to meet UL 325 standards, install new high-speed sliding gate operators, a new pre-engineered UL752 level 3 ballistic rated guard booth, a new pedestrian swing gate, fixed bollards, card reader and camera infrastructure, and complete miscellaneous site work including concrete, paving, and landscaping. The specifications require the contractor to provide a temporary guard booth during the first phase, allow staging in designated areas, and complete work during daytime hours according to the outlined phasing plan over a period of approximately ten months with individual gates and barriers taken offline in scheduled phases to maintain security and access.

View the file

Other files

Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Specifications - Addendum 1

1/25/2022

U.S. Marshals Gate Replacement, Tallahassee

1. Provide a temporary Guard Booth at Gate 17M-2 during the first phase of construction. The booth will require HVAC, electrical, and lighting. The temporary booth will not require a ballistic rating. Exact type, size, and location to be coordinated with USMS.

2. A specific crash rating is not required during construction. However, as noted on G002, each vehicle barrier is a primary security access point into the site, which must be secured at all times during construction.

3. Park heavy equipment and vehicles in approved areas when construction is not taking place.

4. Work to occur during normal business hours from 7am – 6pm. Noisy work may need to be completed after hours once coordinated in advance with USMS & GSA. In addition, the City of Tallahassee has a noise ordinance in effect from 10pm - 7am.

5. Staging will be allowed in the small area North of Gate 17A-1 and the larger grass area South of 17A. If additional lay down area is needed, the GC shall coordinate with USMS & GSA. The contractor will be responsible for all restoration at the end of the project.

6. Phasing plan and anticipated durations:

a. Gate 17M-1 Area will be completely shut down. During this time all traffic that needs to gain access to 17M-3 will enter and exit through gate 17M-

2. (4 Months)

b. Gates 17M-2 and 17A-2 will be under construction concurrently. All traffic needing access through 17M-2 will use gate 17M-1. All traffic needing access through 17A-2 will use 17A-1. (3 Months)

c. Gate 17A-1. All traffic needing access through 17A-1 will need to use

17A-2. (3 Months)