T02 DB SOW - Claude Pepper Fed Bldg Miami_Fire Alarm Replacement 07-18-2024.pdf

PDF 682 KB Posted

Attached to
Fire Alarm System Replacement - Claude Pepper Fed Bldg, Miami - Amendment 0002 Federal contract opportunity
Solicitation number
47PE0724R0024
Issued by
General Services Administration Public Buildings Service Region 4

About this file

This document is a Design-Build (DB) Contract Statement of Work (SOW) for the Fire Alarm Replacement Project at the Claude Pepper Federal Building in Miami, Florida. The SOW provides detailed requirements for the design and construction of a new fire alarm and emergency communications system to replace the existing obsolete system.

Key details:

  • This is a 100% Small Business set-aside DB contract project with a total duration of 330 calendar days.
  • The design phase includes 35%, 65%, 95%, and 100% design submissions with defined review periods. The construction phase requires the contractor to meet substantial completion within 180 days of the notice to proceed.
  • The new fire alarm system must comply with PBS-P100, NFPA 72, IFC, and IBC standards and integrate with building systems like elevators, generators, and HVAC.
  • The contractor must perform site investigations, environmental hazards assessments, and asbestos abatement as required.
  • The contractor will utilize a secure electronic project management system provided by GSA and comply with document security requirements for sensitive building information.

View the file

Other files for this federal contract opportunity

Other files attached to Fire Alarm System Replacement - Claude Pepper Fed Bldg, Miami - Amendment 0002, newest first.
File Type Posted
T09 Pre Bid Site Visit Sign In Roster - 2nd Site Visit 47PE0724R0024 CPFB FA Replacement 2024 08 08.pdf PDF
T09 Pre Bid Site Visit Sign In Roster 47PE0724R0024 CPFB FA Replacement 2024 07 16.pdf PDF
SF 30 Solicitation Amendment 47PE0724R0024_0002 2024 08 19.pdf PDF
SF 30 Atch_Claude Pepper Fire Alarm RFI Responses Amendment 0002_2024 08 19.pdf PDF
SF 30 Atch_Claude Pepper Fire Alarm RFI Responses 08 02 2024.pdf PDF
SF 30 Solicitation Amendment 47PE0724R0024_0001 2024 08 02.pdf PDF
T02 DB SOW Atch Claude Pepper FL ACM Report 2023 07 25.pdf PDF
T10 Reps and Certs 47PE0724R0024.docx DOCX document
T05 Wage Determination_Wage Decision FL20240215 2024 07 12.pdf PDF
T02 DB SOW Atch Claude Pepper As-Builts Fire Alarm All Floors 2006.pdf PDF
T02 DB SOW Atch Claude Pepper As-Builts 5th_14th_15th FL Fire Alarm 2016.pdf PDF
T02 DB SOW Atch Misc As Built and Reqts Docs Fire Alm System Replace CPFB Fwd 2024 07 22.zip ZIP file
T10 THE AGREEMENT_RFP 47PE0724R0024-Fire Alarm Replacement-CPFB Miami 2024 07 23.pdf PDF
T10 THE SOLICITATION_RFP 47PE0724R0024-Fire Alarm Replacement-CPFB Miami 2024 07 23.pdf PDF
T10 SF 1442_ 47PE0724R0024 Fire Alarm Replacement-CPFB Miami 2024 07 23.pdf PDF
T10 RFP Instructions 47PE0724R0024 Fire Alarm System CPFB Miami 2024 07 23.pdf PDF
Show all 16

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DB Contract Statement of Work

CLAUDE PEPPER FEDERAL BUILDING

51 1st AVENUE

MIAMI, FLORIDA 33130

GSA BUILDING NUMBER: FL0061ZZ

Fire Alarm Replacement Project

Solicitation Number 47PE0724R0024

Statement of Work for

Design-Build (DB) Contract

PROJECT IDENTIFICATION

Project Name: FIRE ALARM SYSTEM REPLACEMENT

51 SW 1st AVENUE

MIAMI, FLORIDA 33130

GSA BUILDING NUMBER: FL0061ZZ

Project Number: 000029217

Region: 04

Building Name: Claude Pepper Federal Building

Building Address: 51 SW 1ST Avenue Miami, Florida 33130

Building Number: FL0061ZZ

ABT: Florida South

GSA Project Manager: Bobby Stone

DEVELOPED BY: Rex Burch, GSA Regional Fire Protection Engineer Date: 05/01/2024; Rev. 05/17/2024; Rev 06/27/2024; Rev. 07/08/2024;

Rev. 07/18/2024.

51 1st AVENUE

MIAMI, FLORIDA 33130

GSA BUILDING NUMBER: FL0061ZZ

SOW Writer(s): Rex Burch, GSA Regional Fire Protection Engineer

Estimator: Eric Ray

Date: 05/15/2024

TABLE OF CONTENTS

Table of Contents

1 PROJECT DESCRIPTION

1.1 PROJECT TYPE:

1.2 Project Goals and Objectives

1.3 Project Delivery Approach

2 GENERAL REQUIREMENTS

2.1 Contract Parties and Contract Work

2.2 Professional Ethics and Standards of Practice

2.3 Project Delivery Team Roles and Responsibilities

2.4 Owner’s Project Requirements (OPR)

2.5 Budget

2.6 Schedule

2.7 DB Contractor Team

2.8 Performance Objectives

2.8.1 Standards and Criteria Documents

2.8.2 Sustainable Design/LEED®

2.8.3 Fire Protection/Life Safety

2.8.4 Historic Preservation

2.9 Cost Management

2.9.1 Cost Estimating

2.9.2 Construction Cost Management

2.10 Project Management Responsibilities

2.10.1 Communications Plan

2.10.2 Detailed Project Schedule Development and Maintenance

2.10.3 Project Progress Meetings/Presentations

2.10.4 Meeting Agendas, Attendance, Minutes and Correspondence

51 1st AVENUE

MIAMI, FLORIDA 33130

GSA BUILDING NUMBER: FL0061ZZ

2.10.5 Design Quality Assurance

2.10.6 Electronic Project Management System

2.10.6.1 Overview

2.10.6.2 Purpose

2.10.6.3 Definition

2.10.6.4 Project Documentation

2.10.6.5 Equipment and Training

2.10.6.6 Personnel Requirements

2.10.6.7 Data Ownership

2.10.6.8 References

2.11 Electronic/Print Media

2.11.1 Computer Aided Design (CAD) Standards

2.11.2 Other Electronic Documents

2.11.3 Plans and Specifications

2.12 DB Personnel Security Requirements

2.12.1 Law Enforcement Checks and Background Investigations

2.12.2 Credentialing and Return of Credentials

2.12.3 Subcontracts

2.13 Document Security

2.13.1 Documents

2.13.2 Identification and Labeling/Marking

2.13.3 Copying from Labeled/Marked Documents

2.13.4 Redacting

2.13.5 Safeguarding and Storage

2.13.6 Dissemination

2.13.7 Destruction

2.13.8 Reporting

2.13.9 Subcontracts

2.14 Record Keeping

2.15 Construction General Requirements

3 SCOPE OF SERVICES

3.1 Pre-Design Stage

3.1.1 Pre-Design Surveys/Studies/Analyses

3.2 Design Stage

3.2.1 Design Concept Phase

3.2.2 Design Development (DD) 35% Phase

51 1st AVENUE

MIAMI, FLORIDA 33130

GSA BUILDING NUMBER: FL0061ZZ

3.2.3 Design (65% CD) Phase

3.2.4 Design (95% CD) Phase

3.2.5 Design (100% CD) Phase

3.3 Construction Stage

3.3.1 Construction Delivery Phase

3.4 Closeout Stage

3.4.1 Final Project Photographs

3.4.2 DB Contract Closeout

4 ADMINISTRATION

4.1 Submission, Review and DB Contractor Fixed Price Table

4.2 Design Stage and Construction Documents Phase Progress Reviews and Payments

4.2.1 Progress Payment Schedule

4.2.2 Monthly Progress Reports

4.2.3 Progress Review Meetings

4.2.4 Delays

4.3 Payment for Construction Delivery Phase Work

4.4 Travel

4.5 Reproduction and Delivery

5 APPENDIX A - Owner’s Project Requirements

5.1 General Requirements

5.1.1 Building Occupancy During Construction

5.1.2 Noise Management

5.1.4 Schedule Delays

5.2 Existing Conditions: Must be verified by DB Engineers

5.2.1 Existing Fire Alarm System and Access To

5.3 Asbestos Abatement

5.3.1 Responsibilities

5.4 Architectural New Work Requirements

5.5 Fire Alarm System Requirements

5.6 Electrical New Work Requirements

5.7 Final Inspection

51 1st AVENUE

MIAMI, FLORIDA 33130

GSA BUILDING NUMBER: FL0061ZZ

1 PROJECT DESCRIPTION

1.1 PROJECT TYPE:

This is a Design/Build project that includes the complete replacement of the existing antiquated and obsolete fire alarm system (Notifier NFS-3030) at the Claude Pepper U.S. Federal Building located in Miami, Florida. The project will include the complete removal of the existing fire alarm system including all component parts, devices, conduit, and wiring with the design and installation of a new fire alarm and emergency communications system which will serve the entire building.

The new automatic fire alarm system will include all fire alarm system components, conduit, wiring, and associated devices, including any modifications to appurtenant building systems and all incidental interface functions and related work for a complete and functional fire alarm and emergency communications system compliant with PBS-P100, NFPA 72, IFC, and IBC.

1.2 Project Goals and Objectives

GOALS:

To provide a safer facility for all occupants in the event of an emergency, by providing a new addressable fire alarm and emergency communications system designed to meet current fire and life safety codes, as well as properly functioning with all appurtenant building systems including, but not limited to elevators, emergency generator, fire pump, sprinkler system, stair and shaft pressurization, door release devices, smoke control and HVAC system(s). This project will also include the electric release of any electronic locking mechanisms for egress compliance with NFPA 101 life Safety Code.

OBJECTIVES:

To design/install a new fire alarm and emergency communications system which meets the 2021 edition of GSA PBS P-100, the 2022 Edition of NFPA 72, and the 2021 Edition of NFPA 101 Life Safety Code.

1.3 Project Delivery Approach

The approach to deliver this project is through design-build method where design might overlap construction. It is preferred to submit 35% design development as first phase of design, then 65% construction documents, then 95% pre-final construction documents and finally the 100% CDs.

Construction and ordering of equipment can start as early as the compliance with the 95% design review comments. Final approval of this project is subject to the acceptance of the operational performance of all components installed to a satisfactory level to GSA.

2 GENERAL REQUIREMENTS

51 1st AVENUE

MIAMI, FLORIDA 33130

GSA BUILDING NUMBER: FL0061ZZ

The requirements set forth in this section apply to all stages and phases of the project as described in the Scope of Services section below.

Provide Design/Build Services to replace the existing fire alarm system as indicated in Section 5, Owner’s Project Requirements. Contractor shall be responsible for all required equipment to provide a complete turnkey project.

Asbestos Abatement, site supervision, and the furnishing of security approved workers.

Contractor to provide all labor, materials, equipment and testing required to accomplish design and construction of all affected areas, including the preparation of code compliant (IBC, IFC, NFPA standards, and PBS-P100), Construction Documents, site investigations, site measurements, reproduction services, phasing plans, coordination. Demolition and abatement (if required), site supervision, and the furnishing of security approved workers.

2.1 Contract Parties and Contract Work

The parties to this contract are the Contractor, hereinafter referred to as the Design-Build (DB) Contractor, and the United States Government. For purposes of this contract, the office representing the Government is the General Services Administration (GSA), Region Four, Public Buildings Service, hereinafter referred to as the GSA.

The individual authorized to act on the behalf of the GSA in the administration of this contract is the GSA Contracting Officer. The GSA Contracting Officer may delegate certain of his or her authorities to others, and if so, will notify the DB Contractor in writing of the specific authorities delegated to, and limitations placed upon, named authorized representatives. The DB Contractor shall not take any direction, or act upon any information, from individuals other than those having the requisite authority as confirmed by the GSA Contracting Officer’s written notification.

This contract includes both Design Stage services and Construction Stage work, all to be performed by the DB Contractor. Design Stage services include providing Design Concept, Design Development and Construction Document services. Construction Stage work includes performing construction in conformance with the performance specification provided in Appendix B. The DB Contractor shall proceed with the Design Stage services upon receipt of the GSA notice to proceed with that portion of the work. The GSA will issue a notice to proceed with the Construction Stage work upon completion of the Design Stage services and the GSA approval of the DB Contractor final Construction Document submission.

The DB Contractor shall be the Architect or Engineer of Record for the project and shall bear all responsibilities and liabilities attendant thereto.

The specific activities, tasks, and deliverables required of the DB Contractor are further delineated in this Statement of Work.

2.2 Professional Ethics and Standards of Practice

In the conduct of all activities required for or otherwise related to the performance of the contract work, the DB Contractor shall conform to and uphold all established ethical principles and professional standards of practice governing the DB contractor segment of the construction industry, including the International Union of Architects (UIA) Accord on Recommended International

51 1st AVENUE

MIAMI, FLORIDA 33130

GSA BUILDING NUMBER: FL0061ZZ

Standards of Professionalism in Architectural Practice, the American Council of Engineering Companies (ACEC) Ethical Guidelines, and the tenets of professional ethics contained in the Design- Build Institute of America (DBIA) Design-Build Manual of Practice.

2.3 Project Delivery Team Roles and Responsibilities

In the performance of the requirements of this contract, the DB Contractor shall work in concert with other parties on the Project Delivery Team. The Project Delivery Team will include other contractors, the GSA personnel, customer agency representatives, and other stakeholders. The GSA will develop, periodically update, and maintain throughout the course of the project, a listing of the Project Delivery Team membership and respective roles and responsibilities.

The GSA may engage other parties to perform specialized duties and requirements as appropriate for the project.

2.4 Owner’s Project Requirements (OPR)

The Design Stage services and Construction Stage work under this Statement of Work must comply with the GSA owner’s project requirements (OPR) documentation provided in Appendix A.

2.5 Budget

See Solicitation documents for project magnitude.

2.6 Schedule

Provide an overall project delivery schedule addressing the schedule for all stages of design, construction, and tenant occupancy. Incorporate the 15 nationally agreed-to milestones in the schedule.] Coordinate this overall schedule with the Submission, Review and DB Contractor Fixed Price Table in the Administration section. For the Construction Stage work, the Contracting Officer should insert the required performance time in FAR clause 52.211-10, Commencement, Prosecution, and Completion of Work, and ensure that any scheduling information provided here is consistent with that performance time.

2.7 DB Contractor Team

The DB Contractor shall provide experts in disciplines listed in PBS-P100, Facilities Standards for the Public Buildings Service, and as otherwise required in this section, with credentials as indicated, as they apply to this project. The DB Contractor shall provide sufficient staff of project managers, architects, design engineers, field engineers, superintendents, inspection and testing engineers, scheduling specialists, cost engineers, clerical and accounting personnel, etc. to perform the required work.

At a minimum, the DB Contractor key team members shall consist of the following:

[Edit the list below as appropriate to the requirements of the project. Identify below any additional requirements for special experts on the DB Contractor team.]

51 1st AVENUE

MIAMI, FLORIDA 33130

GSA BUILDING NUMBER: FL0061ZZ

● Project manager

● Architectural designer

● Engineering designers - all disciplines

● Major consultants - i.e., registered fire protection engineer, lead environmental coordinator, energy conservation officer, waste management coordinator, historic preservation expert

● Construction superintendent

● Quality control superintendent

● Project engineer

● Construction supervisors

● Tenant representative

● Safety program coordinator

The DB Contractor shall utilize the personnel named in its offer to perform the services required under this contract. In the event that any of the personnel named in the DB Contractor accepted proposal (incorporated into this contract by reference) become unavailable, the DB Contractor shall promptly submit a complete written resume for a proposed substitution, any other information necessary for the GSA to approve or disapprove, and a detailed explanation of the circumstances necessitating the proposed substitution.

In addition to the key team members identified above, the DB Contractor shall provide administrative, clerical, and technical personnel as necessary to perform the services required under this contract.

During the performance of the services required under this contract, the DB contractor shall obtain the GSA written consent before making any substitution for subcontractors and outside associates or consultants specifically identified and agreed to during negotiations.

See FAR 52.236-5, Material and Workmanship, regarding removal of any employee deemed incompetent, careless, or otherwise objectionable.

See also FAR 52.244-4 regarding subcontractors and outside associates and consultants.

2.8 Performance Objectives

2.8.1 Standards and Criteria Documents

2.8.1.1 Applicability

All services must be conducted in accordance with the documents listed below. The applicable version of each document shall be the version current at the time of award of this contract. In the event of a conflict between the requirements stated in these documents and requirements provided elsewhere in this Statement of Work, the requirements in the Statement of Work will prevail.

2.8.1.2 Document List

2.8.1.2.1 US. General Services Administration (GSA)

● PBS-P100, Facilities Standards for the Public Buildings Service, 2021 Edition, including all applicable standards, criteria and guides listed therein. Design Stage submissions must comply with PBS-P100 Appendix A unless otherwise indicated in this Statement of Work

51 1st AVENUE

MIAMI, FLORIDA 33130

GSA BUILDING NUMBER: FL0061ZZ

● Architectural Barriers Act Accessibility Standard (ABAAS)

● PBS Order 3490.1A “Document security for sensitive but unclassified paper and electronic building information”

● PBS P-120, Project Estimating Requirements for the Public Buildings Service, latest edition

● The GSA PBS Pricing Desk Guide, October 3rd, 2011

● PBS National Business Space Assignment Policy (NBSAP), Latest Edition

● PBS Asbestos Policy, March 27, 2008

● PBS Construction Specifications Format and Guidelines

● Secretary of the Interior’s Standards for Rehabilitation and Illustrated Guidellines for

Rehabilitating Historic Buildings (U.S. Department of the Interior, National Park Service, 1992)

● Large Project Guidelines for CPM Specification 01310

● CPM Specification for Projects exceeding $2M

● Carpet Specification Guideline for Broadloom and Modular Tile

● GSA PBS BIM Guide Series 01 through 08

● Existing facility drawings.

● GSA Fire Watch Guidelines, Dated (01/2020)

● GSA Final Fire Alarm Acceptance Testing Procedures F03.05.01.0908

● Final Fire Alarm Acceptance Testing Procedures (Appendix B)

● Final Acceptance Testing - F3.05.0908

● Analog Addressable Voice Evacuation Fire Alarm Systems (GSA Specifications

Guideline)

● Existing Asbestos Periodic Surveillance Plan

● A pdf of Existing Fire Alarm Drawings will be provided. Fire Alarm System and wall configuration accuracy is not guaranteed as these drawings are dated; therefore, due diligence is the contractor’s responsibility including but not limited to a secondary site inspection to verify all conditions prior to providing a cost proposal.

● ASTM: Compliance with the latest edition of ASTM is required and mandatory.

● Underwriters Laboratories: Compliance with the latest edition of U.S. is required and mandatory.

● OSHA: Compliance with the latest edition of OSHA is required and mandatory.

● NFPA 13 (2022 Edition)

● NFPA 20 (2022 Edition)

● NFPA 70 (2020 Edition)

● NFPA 72 (2022 Edition)

● NFPA 101, Life Safety Code (2021 Edition)

● International Building Code (2021 Edition)

● International Fire Code (2021 Edition)

● NFPA 241 Standard for Safeguarding Construction, Alteration, and Demolition

Operations (2022 Edition)

2.8.1.2.2 U.S Courts

● U.S. Courts Design Guide, (USCDG), 2007 (includes revisions through June 2008)

● U.S. Courts Design Guide – Renovation & Alteration Appendix, September 15, 2009

● U.S. Courts Courthouse Design Reference Manual: An Architect’s Desk Reference, November 2007

● Courtroom Technology Manual, August 1999

51 1st AVENUE

MIAMI, FLORIDA 33130

GSA BUILDING NUMBER: FL0061ZZ

● U.S. Courts Mail Room Construction Guidelines, April 2, 2002 (Includes 13-page excerpt of Section VI from “Mail Safety in the Federal Judiciary” study undertaken by

AOUSC.

● U.S Courts Design Guide, Amendment to Chapters 1, 2, 15, & 16; dated January 14, 2016.

2.8.1.2.3 U.S. Marshals Services (USMS)

● USMS Publication 64, USMS Office - Construction Management (Volumes I & II) Manual of Responsibilities, Requirements, and Specifications for construction of USMS Special Spaces and Support Spaces, dated August 2022.

● USMS Publication 64 – Judicial Security Systems Requirements and Specifications, Volume III, 2005

● US.M.S./ADT Security Coordination, March 2009

2.8.1.2.4 U.S. Attorney’s Office (USOA)

● U.S. Attorney’s Office Design Guide, January 7, 2014

● U.S. Attorney’s Office Master Specifications, August 17, 2010

● U.S. Attorneys’ Facilities Standards

2.8.1.2.5 Energy Performance & Sustainable Design

● GSA Region 4 LonWorks Building Automation System (BAS) Requirements, v4.0

● Technology Policy for PBS Owned Building Monitoring and Control Systems, March

31, 2011

● GSA Region 4 Advanced Metering Guideline, July 9, 2014

● GSA Region 4 Advanced Metering Deployment Procedure

● Building Technologies Technical Reference Guide, v1.1, February 5, 2014

● Telecommunications Distribution Design Guide, July 27, 2011

● HVAC Controls Requirements Document

● The GSA PBS LEED® Applications Guide

● GSA Building Commissioning Guide, April 2005 (Available at http://www.wbdg.org/ccb/GSAMAN/buildingcommissioningguide.pdf (static) and http://www.gsa.gov/commissioning (web-based))

High Performance and Sustainable Buildings Guidance, December 1, 2008 (Available at http://www.wbdg.org/pdfs/hpsb_guidance.pdf.)

2.8.1.2.6 Physical Security

● Physical Security Criteria for Federal Facilities (PSC): An Interagency Security Committee (ISC) Standard, April 12, 2010 (For Official Use Only) o PSC Addendum July 25, 2011 (For Official Use Only)

● GSA Facility Security Requirements for Explosive Devices Applicable to Facility

Security Levels III and IV (GSA Interpretation of ISC Physical Security Criteria), August 2, 2011 (Controlled Unclassified Information (CUI)

● The Design-Basis Threat (ISC Report), 6th Edition, November, 2012 (For Official Use Only (FOUO))

● GSA Alternative Path Analysis & Design Guidelines for Progressive Collapse Resistance, October 24, 2013 (Available at www.gsa.gov/portal/content/103205.)

http://www.wbdg.org/ccb/GSAMAN/buildingcommissioningguide.pdf http://www.gsa.gov/commissioning http://www.wbdg.org/pdfs/hpsb_guidance.pdf http://www.gsa.gov/portal/content/103205

51 1st AVENUE

MIAMI, FLORIDA 33130

GSA BUILDING NUMBER: FL0061ZZ

● The Site Security Design Guide, June 2007 (Available at http://www.gsa.gov/portal/content/280533)

● GSA/USMS Design Notebook for Federal Building Lobby Security

● ISC Design-Basis Threat Report, 6th Edition, November, 2012

Any conflicts or ambiguities within or among the referenced standards and criteria documents, or any deviations from requirements contained in the standards and criteria documents, must be reported to the GSA in writing, for determination as to applicability.

2.8.2 Sustainable Design/LEED®

2.8.2.1 Green Purchasing Plan

The GSA Green Purchasing Plan (GPP) requires the purchase of environmentally sustainable products and services in all new contracts (including task and delivery orders against new and existing contracts) in order to reduce GSA’s environmental footprint. This requires the supply or use of products and services that are energy efficient (Energy Star or FEMP-designated), low standby power, water efficient, biobased, environmentally preferable, non-ozone depleting, contain recycled content, or are non-toxic or less toxic alternatives. Central Office is monitoring green purchasing by conducting bi-annual audits of all new contracts/orders. See OPR Appendix for more detailed requirements.

GSA is required to buy recovered materials as designated by the U.S. Environmental Protection Agency (EPA) through the comprehensive procurement guidelines (CPG). Information can be obtained about the EPA list of designated products and accompanying recycled–content recommendations on the internet at www.epa.gov/cpg. Additional requirements for use of biobased, rapidly renewable content, and recycled content materials are as per P100 2010 page 94.

2.8.2.2 C&D Waste Management Requirements

GSA's minimum requirement is to divert 50% of C&D waste from landfills/incinerators, with a higher goal of 70% diversion. The design specifications completed by the A/E must be consistent with these goals. The A/E must include the template Construction Waste Management and Disposal specification in the design. This document is a template and must be tailored to the project. The A/E must also include the C&D Waste Management Report form as an attachment to the specification. Templates for both of these documents are attached to this document.

2.8.2.2.1 Waste Management Plan

A waste management plan shall be submitted at the completion of construction documents phase of the project or within 14 days of date established for the Construction Notice-to- Proceed. The plan includes at the minimum the following requirements:

1. Describe strategies for minimizing waste

2. During project planning, include a bulk estimate in weight (tons) or volume (cubic yards) of waste diverted and anticipated weight/volume for materials going to landfill.

3. Anticipated recycling revenue: Shall be factored into contractor bid and contractor should provide an estimate of the recycling proceeds amount.

http://www.gsa.gov/portal/content/280533 http://www.epa.gov/cpg

51 1st AVENUE

MIAMI, FLORIDA 33130

GSA BUILDING NUMBER: FL0061ZZ

4. Final rates based upon weight (tons).

5. List of diversion facilities and disposal activities to be used. (Include name, location, and phone number)

2.8.2.2.2 Waste Management Monthly Reports

Contractors are required to submit a monthly waste management report that details the amount of C&D waste by material diverted/recycled as well as the amount sent to landfill on the project. These reports shall be submitted to the GSA PM and/or COR in electronic format.

2.8.2.3 Miscellaneous Green Requirements

In addition, the contractor shall develop the design in a way that implements the following environmental objectives:

● Eliminate or reduce the generation of hazardous waste and the need for special material processing (including special handling, storage, treatment, and disposal)

● Promote the use of nonhazardous and recovered materials

● Realize life-cycle cost savings

● Promote cost-effective waste reduction when creating plans, drawings, specifications, standards, and other product descriptions authorizing material substitutions, extensions of shelf-life, and process improvements

● Promote waste reduction through the use of duplexing (two-sides copying and printing) and electronic communications companying recycled–content recommendations on the internet at www.epa.gov/cpg.

2.8.3 Fire Protection/Life Safety

Fire protection and life safety design requirements must comply with PBS-P100, Chapter 7. As provided in PBS-P100 Chapter 7, fire safety during construction must comply with the requirements in the IBC, IFC, and NFPA 241. NFPA 101 is the primary applicable standard regarding all egress requirements. NFPA 72 is the primary applicable standard regarding all fire alarm installation and NFPA 13 is the primary standard regarding all sprinkler installation. In cases where NFPA is silent on an issue, and IBC addresses the issue, the IBC requirement will apply. The DB Contractor registered fire protection engineer is required to be a full participant in the Project Delivery Team throughout the Design and Construction Stages of the project, and should be thoroughly familiar with PBS-P100.

For all projects involving fire protection engineering issues, the DB contractor shall have a Registered Fire Protection Engineer on the project team. A dialog must be established between the Design Team Fire Protection Engineer and the GSA Regional Fire Protection Engineer. The GSA Regional Fire Protection Engineer shall have the right to revise the specific requirements within PBS-P100, Chapter 7, based on a technical evaluation/analysis and the project’s specific need. The GSA Regional Fire Protection Engineer will serve as the Authority Having Jurisdiction (AHJ), and should be consulted regarding any code discrepancies or conflicts. Any such discrepancies or conflicts will be discussed with and decided by the GSA Regional Fire Protection Engineer.

http://www.epa.gov/cpg

51 1st AVENUE

MIAMI, FLORIDA 33130

GSA BUILDING NUMBER: FL0061ZZ

2.8.3.1 Environmental Hazards

The GSA asbestos policy states: "Prior to conducting any work in the vicinity of ACM an assessment shall be conducted by a competent person to determine the potential to disturb such ACM and sufficient controls designed into the project. This "pre-alteration assessment" shall be conducted for all facility projects regardless of the age of the facility and will address both accessible and inaccessible ACM. Destructive sampling shall be conducted where necessary to address inaccessible ACM."

All renovation projects must comply with the latest Public Buildings Service Asbestos Policy including the conducting of a Pre-alteration assessment. See Scope of Services section for requirements.

2.8.4 Historic Preservation

According to the ABP, the Claude Pepper Federal Building was constructed in 1964 and is eligible for Historical Registry.

2.9 Cost Management

2.9.1 Cost Estimating

The estimated cost of construction (ECC) as provided in the DB Contractor proposal, including any modifications thereto as a result of final contract negotiation, shall serve as the baseline construction budget for the project at the time of award of the DB contract. The DB Contractor shall provide the following breakdowns of the baseline construction budget before any other work begins:

· a CSI Master format 50 Division, level 4 breakdown (Summary and detailed breakdown) of the baseline construction budget, with a separate tenant improvement (TI) and security line item for each tenant agency; and

· a preliminary plan for allocation of the construction work among subcontracts and that which is to be self-performed (ensure all subcontracted work isn’t charged GC burdens), with a corresponding breakdown of the baseline construction budget. (If the construction work allocation plan and cost breakdown provided in the DB Contractor proposal are still valid, they will serve this purpose.)

Before the start of the Design Stage and Design Concept Phase, the DB Contractor, and the GSA must agree on both DB Contractor breakdowns of the baseline construction budget.

The DB Contractor cost estimates shall comply with the following requirements:

- Masterformat 50 Division, Level 4 pricing is required for all work – both self-performed work as well as all sub-contracted work.

The DB Contractor shall update the construction work allocation plan and both baseline construction budget breakdowns at the end of the Design Concept Phase, and/or after completion of the Design Development Phase and before beginning work on the construction documents.

With each such update, the DB Contractor shall provide supporting detailed cost estimates. GSA or its consultant will review the DB Contractor cost estimates to assure that:

· Line-item breakdowns are correct and consistent.

- No lump sum pricing will be accepted.

- Quantity, Labor and Material costs for each line item shall be provided.

- DB Contractor must provide a breakdown of all Per Diem expenses to include total number of employees and total number of days for all self-performed and sub-contracted

51 1st AVENUE

MIAMI, FLORIDA 33130

GSA BUILDING NUMBER: FL0061ZZ

work.

· All design elements are included.

- All design fees are broken out separately by design submission.

· Unit costs are reasonable.

· Accurate quantity takeoffs and unit cost are provided for each item.

· Level of detail is appropriate to the project phase.

· Cost escalation yearly factors are appropriately applied and notated.

· Balance of costs among building systems is acceptable.

· Balance of core/shell and TI/security costs meets latest GSA’s Pricing Desk Guide for Warm Lit Shell policy.

· Up-to-date scope modifications are reflected.

· Formats are correct (Maybe reference GSA TICS table).

The DB Contractor shall be responsible to reconcile any significant differences between the updated baseline construction budget breakdowns and the previously agreed upon breakdowns.

For the CSI Master format 50 Division, level 4 breakdowns, DB Contractor reconciliation shall include justification of any significant differences between the CSI Masterformat 50 Division, level 4 line items. For the construction work allocation breakdowns, DB Contractor reconciliation shall include justification of differences in the construction work allocation plans and/or in the amounts for self-performed work and subcontract work packages. The DB Contractor shall prepare and submit a cost estimating reconciliation report summarizing the reconciliation process and the justification for cost migration between the budget line items in both budget breakdowns. Upon approval by the GSA, the reconciled breakdowns shall serve as the updated baseline construction budget.

2.9.2 Construction Cost Management

This contract is for a fixed price for the construction services.

2.10 Project Management Responsibilities

2.10.1 Communications Plan

The DB Contractor shall assist the GSA in developing and complying with a project communications plan. This plan will be used and maintained throughout the project and modified as necessary to suit each project phase.

The DB Contractor contractual responsibility is to the GSA only and not to other contractors, tenant agencies or local community interests where the project is located. The DB Contractor shall direct all questions and requests from tenant agencies and local community interests to the GSA. Prior to contacting any parties other than the GSA regional personnel, the DB Contractor shall confirm all meetings and/or communications with the GSA.

The DB Contractor shall not release any oral, written or graphic information regarding this project to outside sources without obtaining prior consent from the GSA. All requests for information concerning the project must be referred to the GSA for response.

All presentations to non-GSA entities must be first approved by the GSA.

51 1st AVENUE

MIAMI, FLORIDA 33130

GSA BUILDING NUMBER: FL0061ZZ

2.10.2 Detailed Project Schedule Development and Maintenance

The GSA overall project schedule is provided above in the Schedule section of these General Requirements.

Before starting any other work, the DB Contractor shall develop and provide a detailed schedule in Microsoft Project® or other approved scheduling software for completion of all Design Stage activities, tasks, and submissions required herein, leading up to and including the final construction documents submission(s). The schedule shall include the 15 nationally agreed-to milestones as appropriate. After the DB Contractor receives notice to proceed with the Construction Stage work, the DB Contractor shall provide and maintain a detailed schedule in Microsoft Project® for completion of all Construction Stage activities, tasks, and submissions required herein. The DB Contractor schedules shall itemize all required submission dates and review durations, and must conform to the milestones and durations provided in the GSA overall schedule and the Submission, Review, and DB Contractor Fixed Price Table schedule provided below in the Administration section.

The DB Contractor shall provide monthly schedule updates to the GSA, showing progress on and completion of all required Design Stage services and Construction Stage work. If the schedule updates indicate that previously approved schedules may not be met, GSA will give immediate notice and request appropriate recommendations from the DB Contractor.

Refer to FAR 52.236-15 Schedules for Construction Contracts and to the Scope of Services Construction Delivery Phase section for additional schedule requirements.

2.10.3 Project Progress Meetings/Presentations

During the Design Stage, the DB Contractor shall host project progress meetings, and/or presentations, with the GSA and primary tenant group heads as required to keep all parties apprised of the design progress/status and impending activities. These meetings may coincide with meetings/presentations required below under the Scope of Services. The DB Contractor shall also host special project technical meetings as needed involving Project Delivery Team technical disciplines.

After construction begins, the DB Contractor shall conduct and a GSA representative and/or consultant will attend weekly progress meeting(s) and weekly subcontractor meeting(s). The DB Contractor shall also attend construction oversight meetings with representatives from the GSA and the Project Delivery Team on a monthly basis.

2.10.4 Meeting Agendas, Attendance, Minutes and Correspondence

The DB Contractor shall prepare and distribute an agenda for each DB Contractor hosted project meeting, in advance of the meeting date.

DB Contractor representation at all meetings shall include those individuals having knowledge of the agenda topics and authority to make decisions and commit resources.

The DB Contractor shall provide minutes of all DB Contractor hosted project meetings and presentations to all attendees identifying new and unresolved old action items and associated responsible parties. Minutes must be provided within seven calendar days after each meeting.

The DB Contractor shall reply to correspondence from the GSA, outside agencies, GSA contractors and construction subcontractors within 7 calendar days.

51 1st AVENUE

MIAMI, FLORIDA 33130

GSA BUILDING NUMBER: FL0061ZZ

2.10.5 Design Quality Assurance

The GSA requires that DB Contractor design submissions undergo two general types of design review: owner’s review and codes and standards review. The GSA staff and GSA customer agencies will conduct reviews of all DB Contractor design submissions. In addition to the GSA reviews, the following design quality assurance services will be performed during the Design Stage as further indicated under the Scope of Services below.

2.10.5.1 Owner’s Review

GSA or its contractor will perform owner’s reviews and provide thorough and detailed written review comments. The purpose is to ensure that established functional, aesthetic and spatial requirements of the project are satisfied.

GSA or its contractor will conduct owner’s reviews to assure that:

● The design is responsive to the GSA program goals, objectives and priorities.

● The renovated facility can be efficiently operated and maintained.

● The design adequately and efficiently accommodates the space program.

● Interests of local community groups and other external stakeholders are considered and accommodated to the extent possible.

2.10.5.2 Codes and Standards Review

GSA or its contractor will perform codes and standards reviews and provide thorough and detailed written review comments. The purpose is to ensure that the proposed design complies with applicable regulations, codes, and standards referenced in the standards and criteria documents listed above under performance objectives.

2.10.5.3 Constructability

Constructability of the project as designed is the sole responsibility of the DB Contractor. To ensure that the design can be constructed within schedule and budget and that the sequencing of construction is planned for optimum efficiency, the DB Contractor should assure that:

● The level of design complexity is consistent with the project’s schedule and budget constraints.

● Materials, processes, equipment and labor are appropriate and available.

● Construction work required is in conformance with standard construction practices, and equipment, products, materials, fixtures, etc. are readily available in the marketplace, to the maximum extent possible.

● Building systems are compatible and viable.

● Drawings and specifications are complete and thoroughly coordinated among disciplines.

● Defects, omissions, inconsistencies, conflicts, and ambiguities in documents are identified.

● Drawings are coordinated for multiple construction phases, if applicable.

● Site and building access, logistics, available storage and tenant occupancy requirements are accommodated.

● Existing conditions are shown correctly and adequately.

51 1st AVENUE

MIAMI, FLORIDA 33130

GSA BUILDING NUMBER: FL0061ZZ

● Construction options and unit prices are logical, thoroughly described and understandable.

● Construction details are appropriate, complete, thoroughly described and workable.

● General requirements items are thorough and properly addressed.

● Construction documents and construction phasing provide for continuous use of all building systems (including phone, data, fire alarm, security etc.) during all construction.

● Construction duration, phasing, and subcontracting plans are reasonable and logical.

2.10.5.4 Design Review Procedures

The DB Contractor will coordinate all design reviews, and prepare design review reports. For the DB Contractor final design concept submission and each subsequent submission, the DB contractor will coordinate with the reviewing parties as necessary to reconcile any conflicting comments and consolidate all reconciled design review comments into a single design review report.

● All reviewing parties are required to return comments no later than 7 calendar days prior to the end of the corresponding review period shown in the Design Stage Submission, Review, and DB Contractor Fixed Price Table in the Administration section below.

● The DB will prepare and submit the design review report with written responses within 14 calendar days after comment due date.

2.10.6 Electronic Project Management System

2.10.6.1 Overview

A secure, web-based, electronic project management (ePM) system will be provided by the GSA to accommodate the information needs of all project participants. The ePM system will be implemented at the beginning of the Design Stage and maintained continuously through completion of the Design and Construction Stages. All communications among the major parties involved in the execution of the project are to be captured and recorded in the ePM system. User licenses and training will be provided for all Government and contracted members of the Project Delivery Team who will require access to the ePM system.

2.10.6.2 Purpose

GSA will require the DB Contractor to utilize an Enterprise electronic Project Management (e-PM) system on this project. GSA’s goal is to implement this state-of-the art technology to reduce administrative and overhead costs, eliminate redundancies, and institute a collaboration tool to ensure better accountability among all project team members. This technology will provide up-to-date information, encourage disciplined methods for monitoring progress, ensure better communication regarding changes, provide improved documentation, and enable PBS executives to have real-time access to status of projects.

2.10.6.3 Definition

e-PM is defined as an internet-based information and project communication system that allows the entire project team to collaborate in a centralized and secured repository. All project-specific correspondence, workflow processes, and documentation will be stored and routed within the ePM system.

51 1st AVENUE

MIAMI, FLORIDA 33130

GSA BUILDING NUMBER: FL0061ZZ

2.10.6.4 Project Documentation

The DB Contractor is required to timely and accurately post, review, respond, and collaborate with other team members using the following features and/or workflow processes within the ePM system:

Project Team Directory – Contractor shall provide an updated directory of contact information for all companies, subcontractors and project team members who are engaged on this project.

Schedules – Contractor shall post, review, and/or respond to CPM schedule updates within the ePM system.

Meeting Minutes – Contractor shall enter meeting agendas, records and minutes in the system for all applicable meetings as designated by the GSA PM.

Project Correspondence – Contractor shall manage and maintain all incoming and outgoing correspondence and associated logs for all correspondence related to the project.

Budget and Cost Management – Contractor to provide estimates and work breakdown structure (WBS) to provide GSA with accurate budget/cost analysis.

Contract Management – Contractor to provide administration of all contract tasks related to the project.

Pay Applications Requests (Invoices) – The Contractor shall create invoices for review by GSA.

Once the invoices are agreed to by GSA then the invoices should be submitted to GSA per the instructions given by the Contracting Officer.

Progress Photos – Contractor shall upload all progress photos into the system.

Permits & Approvals – Contractor shall upload and maintain current copies of all permits and agency approvals that relate to the project.

Design Drawings/Design Packages – Contractor shall submit design drawings and design packages into the system.

Design Review Comments – Contractor shall post and/or respond to design comments related to his/her role in the project team Daily/Progress Reports – The Contractor identified in e-PM shall maintain construction progress reports, daily reports/logs, and documentation of inspections.

Inspection Reports – Maintain inspection reports on materials and/or workmanship to assure compliance with all construction requirements.

Safety/Injury Reports – Maintain reports on construction contractors' compliance with current safety regulations and standards.

Punchlists – Maintain list(s) of observed defects and omissions.

Request For Information (RFI) – The system shall manage the RFI process and all Request for Information shall be entered and responded to by the Contractor within the e-PM system.

Issue Tracking – Contractor to log and respond to issues that are related and affect other stakeholders within the project team.

Submittals – The system shall manage the submittals and the Contractor is responsible for uploading submittal documentation and using the system to track the submittal process.

Change Management – Cost Events and Change Orders will be managed by the e-PM system and the Contractor shall be responsible for reporting potential changes and logging Requests for Change Orders in the system. The Contractor shall also upload and manage all documentation supporting Requested Change Orders.

Shop Drawings – The Contractor shall submit all shop drawings in the system for review by GSA (and the CM where applicable).

As-built Drawings and Specifications – The Contractor shall use the system to record all approved specifications as well as all as-built construction documents.

GSA reserves the right to require the Contractor to upload other documentation not mentioned above that is needed to support the project.

51 1st AVENUE

MIAMI, FLORIDA 33130

GSA BUILDING NUMBER: FL0061ZZ

2.10.6.5 Equipment and Training

The e-PM system is based on the Proliance software that was developed by Meridian Systems.

Users will be provided a username and password after they have completed the HSPD-12 process. The Contractor shall log into the e-PM system to enter the Project Documentation listed in section 2.0. All correspondence should be communicated through the e-PM system.

GSA will hold several training sessions to familiarize team members with the system, and all Contractor staff are expected to attend one of these sessions or otherwise receive proper training on the system’s use. Furthermore, all Contractor team members who are actively participating on the project must have access to the proper computer equipment and software to access and utilize the e-PM system and be trained in the proper usage of said equipment and software. All workstations require a high-bandwidth Internet connection.

2.10.6.6 Personnel Requirements

The DB Contractor shall be required to have an adequate number of people who can complete the HSPD-12 background check process to have rights to log into the e-PM system.

2.10.6.7 Data Ownership

GSA shall retain ownership of all data entered into the system and shall administrate and distribute all information contained therein.

2.10.6.8 References

PBS SECURITY ORDER 3490.1A (June 1, 2009)

2.11 Electronic/Print Media

2.11.1 Computer Aided Design (CAD) Standards

Starting with the design development submission all drawing materials provided by the DB Contractor, including final as-built drawings, must conform to the GSA PBS computer aided design (CAD) standards. Go to http://www.gsa.gov/cifm for requirements.

2.11.2 Other Electronic Documents

In addition to any hardcopy submission requirements, all design submissions must also be submitted in an electronic format. All electronic media must be in a form readable by standard office automation applications.

2.11.3 Plans and Specifications

Provide 7 hardcopy sets of plans and specifications at each required design development and construction documents submission. The size of prints (e.g. full/half-size plans) will be as directed by the GSA.

51 1st AVENUE

MIAMI, FLORIDA 33130

GSA BUILDING NUMBER: FL0061ZZ

2.12 DB Personnel Security Requirements

In the performance of work required under this contract, all DB Contractor personnel must present proper identification to gain access to occupied building areas housing federal operations. DB Contractor personnel means DB Contractor employees and subcontractor employees at all tiers.

DB Contractor personnel requiring daily/weekly access to occupied building areas housing federal operations, over a period of 10 days or more, shall undergo background investigations conducted by the United States Government, and will be issued Government-wide standard secure and reliable forms of identification issued by the federal Government (i.e., federal personal identity verification (PIV) credentials) as required under Homeland Security Presidential Directive-12 (HSPD-12).

Credentialed DB Contractor personnel must wear their PIV credential cards visibly above the waist at all times while in occupied building areas housing federal operations.

All other DB Contractor personnel requiring access to occupied building areas housing federal operations will be issued visitor badges upon entry, must wear their visitor badges visibly above the waist, and must surrender their visitor badges upon exit.

All non-PIV credentialed DB Contractor personnel must be escorted at all times (including after hours) while in occupied building areas housing federal operations. The escort must be a PIV credentialed individual who has been found suitable after completion of the required background investigation.

2.12.1 Law Enforcement Checks and Background Investigations

You must complete both the fingerprinting and e-QIP process within seven (7) business days.

Fingerprinting/Enrollment Process for Background Investigation After submission of the Contractor Information Worksheet (CIW) provided by GSA, you will receive a fingerprint/enrollment scheduling instructional email from the GSA Managed Service Office’s (MSO) USAccess program via HSPD12Admin@usaccess.gsa.gov. You must complete your fingerprint process before you finish your e-QIP Invitation.

✓ Ensure that your email spam filter settings will allow you to receive the MSO email

✓ The instructions will include a list of acceptable identity documents. Bring the required forms of identity documents to your enrollment appointment

✓ Schedule an “enrollment” appointment and complete the fingerprinting/enrollment process as soon as possible

✓ If you are over 100 miles from a MSO USAccess Shared Credentialing Station, please email the GSA Project Manager to determine how to best complete your fingerprinting process.

e-QIP Invitation

After submission of the Contractor Information Worksheet (CIW) provided by GSA, you will have access to complete the Office of Personnel Management's (OPM) Electronic Questionnaire for Investigations Processing (e-QIP). The OPM has been directed to complete a background investigation for the purposes of determining your suitability. You have seven (7) business days to log in, complete the questionnaire, electronically upload the signature pages, and submit questionnaire form.

mailto:HSPD12Admin@usaccess.gsa.gov

51 1st AVENUE

MIAMI, FLORIDA 33130

GSA BUILDING NUMBER: FL0061ZZ

Note: The e-QIP must be filled out by the applicant or with the assistance of an authorized third party. United States Code provides for criminal and/or financial penalties if the information on this form is proven to be deliberately falsified [18 USC § 1001].

This is the start of the file's text. The full file is on GovTribe.