This document is a Request for Information (RFI) containing responses from the General Services Administration (GSA) regarding a solicitation for the replacement of the fire alarm system at the Claude Pepper Federal Building in Miami, Florida.

The key details are:

  • This is a Design/Build project for the complete replacement of the existing fire alarm system, including removal of all components and installation of a new code-compliant fire alarm and emergency communications system.
  • The new system must comply with PBS-P100, NFPA 72, IFC, and IBC requirements.
  • The solicitation is a 100% Small Business Set-Aside.
  • The RFI responses address questions about the existing system, required system components, demolition and installation sequencing, site access, and the availability of as-built drawings and test reports.

View the file

Other files

File Type Posted
T09 Pre Bid Site Visit Sign In Roster - 2nd Site Visit 47PE0724R0024 CPFB FA Replacement 2024 08 08.pdf PDF
SF 30 Atch_Claude Pepper Fire Alarm RFI Responses Amendment 0002_2024 08 19.pdf PDF
T09 Pre Bid Site Visit Sign In Roster 47PE0724R0024 CPFB FA Replacement 2024 07 16.pdf PDF
SF 30 Solicitation Amendment 47PE0724R0024_0002 2024 08 19.pdf PDF
SF 30 Solicitation Amendment 47PE0724R0024_0001 2024 08 02.pdf PDF
T02 DB SOW Atch Claude Pepper As-Builts Fire Alarm All Floors 2006.pdf PDF
T10 THE AGREEMENT_RFP 47PE0724R0024-Fire Alarm Replacement-CPFB Miami 2024 07 23.pdf PDF
T02 DB SOW Atch Misc As Built and Reqts Docs Fire Alm System Replace CPFB Fwd 2024 07 22.zip ZIP file
T10 Reps and Certs 47PE0724R0024.docx DOCX document
T10 SF 1442_ 47PE0724R0024 Fire Alarm Replacement-CPFB Miami 2024 07 23.pdf PDF
T10 THE SOLICITATION_RFP 47PE0724R0024-Fire Alarm Replacement-CPFB Miami 2024 07 23.pdf PDF
T05 Wage Determination_Wage Decision FL20240215 2024 07 12.pdf PDF
T02 DB SOW Atch Claude Pepper As-Builts 5th_14th_15th FL Fire Alarm 2016.pdf PDF
T02 DB SOW Atch Claude Pepper FL ACM Report 2023 07 25.pdf PDF
T10 RFP Instructions 47PE0724R0024 Fire Alarm System CPFB Miami 2024 07 23.pdf PDF
T02 DB SOW - Claude Pepper Fed Bldg Miami_Fire Alarm Replacement 07-18-2024.pdf PDF
Show all 16

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

GSA - Claude Pepper FB - Fire Alarm Replacement

CPFB Fire Alarm Sytem

47PE0724R0024, Amendment 0001 8/2/2024

RFI # RFI/Comment GSA Response

Will GSA be issuing As-Built Drawings in the near future of the existing Fire Alarm System? Also, the Fire Protection Asbuilt Drawings for reference? This information is necessary to see what may be existing to get the intent of what was originally installed to aid i the design and estimating of the replacement system.

All existing drawings are provided, but device locations and wall configurations accuracy is not guaranteed as these drawings are dated material; all contractors are encouraged to field verify anything questionable. Reminder: This is to be a100% new code compliant fire alarm system without regard to the existing fire alarm system.

Will there be a sequence of how the demolition as well the new installation procedures be issued. Or will this be decided by the General Contractor overseeing the project?

General contractor to coordinate with GSA FPE to determine sequence to maintain existing fire alarm system while cutting in new system on selected floors.

Will there be afterhours work coordinated for extremely noisy work, core drilling, x-raying, etc.? Also for any work to be carried out when the tenants cannot vacate their area during normal business hours of the day if necessary to perform daily task of work?

Yes, some work will need to be scheduled outside of normal business hours.

How many power supplies will be required per floor?

Minimum one (1). Electrical calculations to determine if additional is needed.

How many SLC Loops will be required per floor?

Provide a minimum of two (2) Class B Signaling Line Circuits (SLC) per floor.

The system must be designed and installed so that a single open, wire to wire short, or any other Class B impairment on an SLC does not affect more than 2,415 m2 (26,000 ft2) of gross floor area. The floor SLCs must be isolated from the SLC risers and network.

6 What Class of Fire Alarm System will be installed for 1.) the initiation circuit; 2.) the NAC circuit?

Class B; minimum of two distinct fire alarm audible notification appliance circuits and a minimum of two distinct visible notification appliance circuits must be provided on each floor.

Is there an existing Smoke Control System in place currently?

Stair Pressurization only.

GSA - Claude Pepper FB - Fire Alarm Replacement

8 If there is an existing Smoke Control in place, will it have to be revamped, too?

Stair pressurization is existing and will be operational by others prior to completion of the FACP Replacement Project.

If there is no Smoke Control in place, will one be required?

Stair pressurization is existing and in place and the new fire alarm system will be requirted to be connected to this system for activation.

Will there be a Area of Refuge System required under this Design- Build Contract?

Yes

11 is there a Refrigerant Monitoring System in place for this Building. Yes, display panel wall mounted in the mechanical room.

Can existing conduit installed in inaccessible location be used for the new system in order to minimize cutting, patching & painting?

Any such areas will be reviewed by the GSA FPE and if determined to be inaccessable or not feasible due to too much cutting or patching, then existing conduit can be allowed. Note, it is the intention of this project to install all new (RED) conduit except possibly in some select areas if proven to be inaccessable or not viable due to complexity of work involved to access.

14 Are existing conduits able to be reused when applicable?

Any such areas will be reviewed by the GSA FPE and if determined to be inaccessable or not feasible due to too much cutting or patching, then existing conduit can be allowed. Note, it is the intention of this project to install all new (RED) conduit except possibly in some select areas if proven to be inaccessable or not viable due to complexity of work involved to access.

Is a side by side installation expected, if so are we able to switch the devices over one floor at a time assuming fire alarm integrity is intact?

Yes, side by side and one floor at a time switchover acceptable.

16 Will you provide the annual Test and Inspection report? Yes 17 Will there be an opportunity for a second site walk through See amendment description.

18 Will you provide updated site drawings?

No, only the existing drawings that are already provided, but device locations and wall configurations accuracy is not guaranteed as these drawings are dated material; all contractors are encouraged to field verify anything questionable. Reminder: This is to be a100% new code compliant fire alarm system without regard to the existing fire alarm system.