Supplemental Information~1.pdf
PDF 2 MB Posted
- Solicitation number
- 27-494DOT-FINAD-B-54297
- Issued by
- Dekalb County, Illinois
About this file
This is a Project Manual for generator additions at the Illinois Department of Transportation (IDOT) District 3 maintenance facilities in Ladd/Sycamore, Bureau/DeKalb County, prepared by Prairie Engineers dated March 25, 2025. The manual specifies comprehensive requirements for the design, procurement, and installation of whole-site backup generators at two locations: Ladd Maintenance Headquarters in Spring Valley and Sycamore Maintenance Headquarters in Sycamore, Illinois under invitation for bid B-54297. The scope includes natural gas standby engine generators with all necessary equipment, parts, fuel systems, transfer switches, electrical integration, and site-specific infrastructure modifications as detailed in generator plans and parts lists. The project encompasses divisions covering general requirements (shop drawings, product data, operating and maintenance data, extended warranties), cast-in-place concrete work, facility natural gas piping, and electrical systems including common work results, low-voltage power conductors and cables, grounding and bonding, raceway boxes, identification systems, overcurrent protective device coordination studies, panelboards, enclosed switches, and engine generators with transfer switches. Bids are due November 5, 2026, with a non-mandatory pre-submission conference and site walk-through scheduled for October 28, 2026 at 9:00 a.m. at Ladd and 11:00 a.m. at Sycamore, requiring confirmation two business days in advance. The initial contract term is 24 months from the last dated signature, with a maximum total term not to exceed 10 years including extensions. Construction must commence between March 15 and November 15, with any work started prior to November 15 completing before that date.
Vendors must include all freight costs in unit pricing with FOB destination, freight prepaid delivery during regular workweeks between 8:00 a.m. and 2:00 p.m. Pricing terms and specific contract amounts are to be entered by the State prior to execution. The solicitation is open to all vendors registered in BidBuy with no stated set-asides, though qualified vendors may claim Illinois Business Preference or Domestic Product Preference under the Illinois Procurement Code. All work is subject to prevailing wage requirements. Vendor insurance requirements include general commercial liability of $1 million per occurrence and $2 million annual aggregate, auto liability of $1 million per occurrence, and workers' compensation insurance as required by law. Subcontractors with annual value of $100,000 or more require prior written approval and must provide Illinois Standard Certifications. Bids must remain firm for 180 days, and winning bids valued at $1,000 or more are subject to a $15 Minority Contractor Opportunity Initiative fee. The project does not receive federal funding. The manual includes detailed specifications for all materials, products, and installation procedures, requiring compliance with applicable standards including the National Electrical Code (2023), NFPA codes, ASME standards, and ASTM specifications.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Blank ipg-active-registered-vendor-disclosure-formerly-forms B~2.docx | DOCX document | |
| contract Ladd Sycamore B-54297~1.docx | DOCX document | |
| Proposed Generator Parts Lists Ladd and Sycamore.pdf | ||
| Proposed Generator Plans 1.pdf | ||
| Questions and Answers B-54297 ~1.docx | DOCX document | |
| IFB offer-to-the-state-of-illinois B-54297 .pdf | ||
| contract Ladd Sycamore B-54297~3.docx | DOCX document | |
| vendor-disclosure-formerly-forms-a-v27-1-2026~2.docx | DOCX document | |
| IFB vendor-instructions-and-requirements B-54297~2.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
00 01 10 - 1
PROJECT MANUAL
00 01 10 – Table of Contents
State of Illinois
DEPARTMENT OF TRANSPORTATION
PRAIRIE ENGINEERS,
PROJECT MANUAL FOR
PROPOSED GENERATOR ADDITIONS, LADD/SYCAMORE, BUREAU/DEKALB, ILLINOIS.
DATE: 03/25/2025
DOCUMENT TITLE PAGES
00 01-10 Table of Contents 00 01 10-1-1
SPECIFICATIONS
01 33 23 Shop Drawings, Product Data, & Samples 01 33 23-1-5 01 78 23 Operating & Maintenance Data. 01 78 23-1-1 01 78 36 Extended Warranties & Bonds 01 78 36-1-1 03 30 00 Cast-in-Place Concrete. 03 30 00-1-8 22 11 13 Facility Natural-Gas Piping 22 11 13-1-9 26 05 00 Common Work Results for Electrical Systems. 26 05 00-1-7 26 05 19 Low-Voltage Electrical Power Conductors and Cable. 26 05 19-1-5 26 05 26 Grounding and Bonding for Electrical Systems. 26 05 26-1-10 26 05 33 Raceway Boxes for Electrical Systems. 26 05 33-1-11 26 05 53 Identification for Electrical Systems. 26 05 53-1-6 26 05 73 Overcurrent Protective Device Coordination Study. 26 05 73-1-5 26 24 16 Panelboards. 26 24 16-1-7 26 28 19 Enclosed Switches. 26 28 19-1-3 26 32 13 Engine Generator and Transfer Switch. 26 32 13-1-11
DIVISION 1 – GENERAL REQUIREMENTS
01 33 23 – Shop Drawings, Product Data & Samples
01 33 23 - 1
1. GENERAL
1.1 REQUIREMENTS INCLUDE
A. Electrical Contractor make submittals to Architect/Engineer. Architect/Engineer shall maintain a master list of submittals.
1.2 GENERAL CONTRACTOR
A. Review submittals within 5 business days.
1. Verify field dimensions.
2. Verify compliance with Contract requirements.
B. Certify review.
C. Transmit reviewed submittals to Architect/Engineer.
1.3 DEFINITIONS
A. Shop drawings: Shop drawings are original drawings prepared by Contractor, subcontractor, sub-subcontractor, supplier or distributor, which illustrate some portion of the work, showing fabrication, layout, setting or erection details.
1. Prepared by qualified detailer.
2. Identify details by reference to sheet and detail numbers shown on contract drawings.
3. Maximum sheet size: (36" x 24".)
4. Submit electronic copies in PDF format.
B. Product data:
1. Manufacturer's standard schematic drawings edited to fit this project.
2. Manufacturer's catalog sheets, brochures, diagrams, schedules, performance charts, illustrations and other standard descriptive data.
a. Clearly mark each copy to identify pertinent materials, products or models.
b. Show dimensions and clearances.
c. Show wiring diagrams and controls.
C. Samples: Physical samples to illustrate materials, equipment or workmanship. Approved samples establish standards by which complete work is judged. Maintain at site as directed.
Protect until no longer needed.
1. Office samples: Of sufficient size to clearly illustrate:
a. Functional characteristics of product or material.
b. Full range of color samples.
c. After review, samples may be used on construction of project.
01 33 23 - 2
2. Field samples and mock-ups:
a. Erect at project site at location approved by Architect/ Engineer.
b. Construct each sample or mock-up complete, including work of all crafts required in finished work.
c. Remove as directed.
1.4 SCHEDULE SUBMITTAL
A. Submit schedule of all exhibits to Architect/Engineer within 10 business days after preconstruction meeting.
1. Prepare schedule in bar chart format. Include:
a. Exhibit identification.
b. Specification section and page number.
c. Date of submittal to Architect/Engineer.
d. Latest date for final approval.
e. Fabrication time.
f. Date of installation.
2. Architect/Engineer will review and comment on exhibit schedule and will advise the contractor as to which submittals require longer review durations.
3. Submit number of copies of shop drawings, product data and samples which contractor requires for distribution plus 6 copies which will be retained by Architect/Engineer.
a. Schedule may be submitted to A/E electronically.
B. Accompany submittals with transmittal letter, in duplicate, containing:
1. Date.
2. Project title and number.
3. Contractor's name and address.
4. The number of shop drawings, product data and samples submitted.
5. Notification of deviations from Contract.
6. Other pertinent data.
C. Submittals shall include:
1. Date and revision dates.
2. Project title and number.
3. Names of:
a. Architect/Engineer.
b. Architect/Engineer's consultant(s).
c. Subcontractor.
d. Sub-subcontractor.
e. Supplier.
f. Manufacturer.
g. Separate detailer when pertinent.
4. Identification of product or material.
5. Relation to adjacent structure or material.
01 33 23 - 3
6. Field dimensions clearly identified as such.
7. Specification section and page number.
8. Specified standards, such as ASTM number or ANSI.
9. A blank space, for Architect/Engineer's stamp.
10. Identification of previously approved deviation(s) from contract documents.
11. Contractor's stamp, initialed or signed, certifying to review of submittal, verification of field measurements and compliance with Contract.
12. Space for Contractor's approval stamp.
1.5 RESUBMISSION REQUIREMENTS
A. Resubmit all shop drawings, product data, and samples as requested by the contractor and/or
A/E.
1.6 RESPONSIBILITIES
A. Review shop drawings, product data and samples prior to submission to the next level of authority.
B. Verify:
1. Field dimensions.
2. Field construction criteria.
3. Catalog numbers and similar data.
C. Coordinate each submittal with requirements of:
1. The work.
2. The contract documents.
D. Contractor's responsibility for errors, omissions or deviation from contract documents in submittals is not relieved by Architect/Engineer's review of submittals.
E. Prior to submission, notify Architect/Engineer and CDB in writing of all proposed deviations in submittals from contract requirements. Substitution of materials or equipment may only be approved by change order.
F. Do not begin any work which requires submittals without Architect/Engineer's approval.
G. After Architect/Engineer's review, make response required by A/E's stamp and distribute copies. Indicate by transmittal that copy of approved data has been delivered to installer.
H. When the other contracts are assigned to the Coordinating Contractor:
1. Assigned contractors send their submittals to Coordinating Contractor.
2. Coordinating Contractor reviews and initials assigned contractors' submittals for compliance with scope, coordination and integration with the work of all other contractors.
3. Coordinating Contractor transmits his reviewed copies of assigned contractors' submittals to Architect/Engineer.
4. Coordinating Contractor retains copy of submittals after review by Architect/Engineer and distributes copies to submitting contractor and to other contractors for coordination and integration.
01 33 23 - 4
5. Coordinating Contractor: Enforce resubmission requirements.
1.7 ARCHITECT/ENGINEER'S DUTIES
A. Review submittals within 14 calendar days.
1. Review for:
a. Design concept of project.
b. Compliance with contract documents.
2. Review all requests for proposed deviations. Obtain CDB's concurrence and respond to
Contractor's request.
3. Affix stamp, date and initials or signature certifying to review of submittal, and with instructions for contractor response.
4. Return submittals to sender for response or distribution.
B. Schedule 01 33 23:
1. 03 30 00 - Cast-In-Place Concrete
a. Product Data
b. Mix Design
c. Test Reports
d. Laboratory Test Results
2. 22 11 23 - Facility Natural-Gas Piping
a. Product Data
b. Design Data
c. Certifications
3. 26 05 26 - Grounding and Bounding for Electrical Systems
a. Product Data
b. Shop Drawings
c. Test Reports
4. 26 05 53 - Identification for Electrical Systems
a. Schedule
5. 26 05 73 - Overcurrent Protective Device Coordination Study
a. Product Data
b. Certificates
c. Qualifications
d. Action Items
6. 26 24 16 - Panelboards
a. Shop Drawings
b. Product Data
01 33 23 - 5
7. 26 28 19 - Enclosed Switches
a. Product Data
b. Installation Instructions
8. 26 32 13 - Engine Generator and Transfer Switch
a. Shop Drawings
b. Product Data
c. Installation Instructions
END 01 33 23
01 78 23 – Operating & Maintenance Data
01 78 23 - 1
1.1 REQUIREMENTS INCLUDE
A. Electrical Contractor provide Operating and Maintenance Data in accordance with Article
01 78 23 of the Standard Documents for Construction and the Project Manual.
2. NUMBER OF REQUIRED SUBMITTALS
2.1 Provide one (1) bound copy and three (3) electronic copies on CD of each Operating &
Maintenance Manual.
3. REQUIRED SUBMITTALS
A. 22 11 23 - Facility Natural-Gas Piping
1. Operation Data
2. Descriptive Literature
B. 26 24 16 - Panelboards
1. Operation Data
2. Descriptive Literature
C. 26 28 19 - Enclosed Switches
1. Operation Data
2. Descriptive Literature
D. 26 32 13 – Engine Generator and Transfer Switch
1. Operation Data
2. Descriptive Literature
3. Start-up Documentation
END 01 78 23
01 78 36 – Extended Warranties & Bonds
CDB-01 78 36 JANUARY 2006 01 78 36 - 1
CDB-546-190-013
1. GENERAL
1.1 REQUIREMENTS INCLUDE
A. Electrical Contractor shall warrant the work in accordance with the Standard
Documents for Construction. In addition, the following extended Warranties and
Bonds shall be provided as specified.
2. EXTENDED WARRANTIES AND BONDS
2.1 Electrical Contractor
A. 26 32 13 - Engine Generator and Transfer Switch
1. The Contractor shall submit a two (2) year warranty for generator.
END 01 78 36
03 30 00 - 1
DIVISION 03 - CONCRETE
03 30 00 – Cast-In-Place Concrete
1. GENERAL
1.1 WORK INCLUDES
A. Base Bid:
1. Electrical Contractor provide:
a. Exterior slabs on grade, including patching of walks, parking & drives.
b. Interior concrete slab repairs.
c. Miscellaneous concrete elements, including equipment pads and equipment pits.
d. Concrete protection and curing.
e. Grouting of dowels.
f. Grouting of miscellaneous items scheduled on the drawings.
g. Vapor retarder.
h. Testing
1.3 REFERENCE STANDARDS
A. ACI 117 - Standard Specifications for Tolerances for Concrete Construction and Materials; 2010.
B. ACI 211.1 - Standard Practice for Selecting Proportions for Normal, Heavyweight, and Mass
Concrete; 1991 (Reapproved 2009).
C. ACI 301-20 - Specifications for Concrete Construction; 2020
D. ACI 302.1R - Guide for Concrete Floor and Slab Construction; 2004 (Errata 2007).
E. ACI 304R - Guide for Measuring, Mixing, Transporting, and Placing Concrete; 2000.
F. ACI 305R - Hot Weather Concreting; 2010.
G. ACI 306R - Cold Weather Concreting; 2010.
H. ACI 308R - Guide to Curing Concrete; 2001 (Reapproved 2008).
I. ACI 318 - Building Code Requirements for Structural Concrete and Commentary; 2014 (Errata
2016).
J. ASTM C1602/C1602M - Standard Specification for Mixing Water Used in the Production of
Hydraulic Cement Concrete; 2022.
K. ASTM C172/C172M - Standard Practice for Sampling Freshly Mixed Concrete; 2017.
L. ASTM C31/C31M - Standard Practice for Making and Curing Concrete Test Specimens in the Field; 2024b.
M. ASTM C33/C33M - Standard Specification for Concrete Aggregates; 2024.
N. ASTM C39/C39M - Standard Test Method for Compressive Strength of Cylindrical Concrete
Specimens; 2024.
O. ASTM C94/C94M - Standard Specification for Ready-Mixed Concrete; 2024c.
P. ASTM C109/C109M - Standard Test Method for Compressive Strength of Hydraulic Cement
Mortars (Using 2-in. or (50-mm) Cube Specimens); 2023.
03 30 00 - 2
Q. ASTM C143/C143M - Standard Test Method for Slump of Hydraulic-Cement Concrete; 2020.
R. ASTM C150/C150M - Standard Specification for Portland Cement; 2024.
S. ASTM C173/C173M - Standard Test Method for Air Content of Freshly Mixed
Concrete by the Volumetric Method; 2024a.
T. ASTM C260/C260M - Standard Specification for Air-Entraining Admixtures for
Concrete; 2010a (Reapproved 2016).
U. ASTM C309 - Standard Specification for Liquid Membrane-Forming Compounds for Curing
Concrete; 2019.
V. ASTM C330/C330M - Standard Specification for Lightweight Aggregates for Structural
Concrete; 2023.
W. ASTM C494/C494M - Standard Specification for Chemical Admixtures for Concrete; 2024.
X. ASTM C618 - Standard Specification for Coal Fly Ash and Raw or Calcined Natural Pozzolan for Use in Concrete; 2023.
Y. ASTM C1107/C1107M - Standard Specification for Packaged Dry, Hydraulic-
Cement Grout (Nonshrink); 2020.
Z. ASTM C1240 - Standard Specification for Silica Fume Used in Cementitious Mixtures; 2020.
AA. ASTM C1602/C1602M - Standard Specification for Mixing Water Used in the Production of
Hydraulic Cement Concrete; 2022.
AB. ASTM D1751 - Standard Specification for Preformed Expansion Joint Filler for Concrete
Paving and Structural Construction (Nonextruding and Resilient Bituminous Types); 2023.
AC. ASTM E1643 - Standard Practice for Selection, Design, Installation and Inspection of Water
Vapor Retarders Used in Contact with Earth or Granular Fill Under Concrete Slabs; 2024.
AD. ASTM E96/E96M - Standard Test Methods for Water Vapor Transmission of Materials; 2024.
1.4 SUBMITTALS
A. Product Data: Submit manufacturers' data on manufactured products showing compliance with specified requirements and installation instructions.
B. For curing compounds, provide data on method of removal in the event of incompatibility with floor covering adhesives.
C. Mix Design: Submit proposed concrete mix design.
D. Test Reports: Submit report for each test or series of tests specified.
E. Project Record Documents: Accurately record actual locations of embedded utilities and components that will be concealed from view upon completion of concrete work.
F. Laboratory Test Results: Concrete Work: Submit laboratory test reports for concrete materials and mix design tests. Submit written report to IDOT Representative for each proposed concrete mix at least 15 days prior to start of work. Do not begin concrete production until mixes have been reviewed and are acceptable to the Architect.
G. Test Reports: Testing laboratory shall submit to the IDOT Representative reports of test results from field sampling required in Paragraph 3.3. of this section, within six (6) days.
03 30 00 - 3
1.5 QUALITY ASSURANCE
A. Perform work of this section in accordance with ACI 301 and ACI 318.
B. Follow recommendations of ACI 305R when concreting during hot weather.
C. Follow recommendations of 1 when concreting during cold weather.
D. Contractor shall be responsible for correction of concrete work which does not conform to the specified requirements, including strength, tolerances and finishes. Correct deficient concrete as directed by the IDOT Representative.
E. Concrete Testing Service: The Contractor shall retain a recognized testing laboratory to perform materials evaluation, testing and design of concrete mixes.
F. Quality Control Testing During Construction: (By Contractor's Testing Laboratory): Concrete shall be sampled and tested for quality control during the placement of concrete, as follows:
2. Sampling Fresh Concrete: ASTM C172/C172M , except modified for slump to comply with ASTM C94/C94M.
a. Slump: ASTM C143/C143M; one test for each concrete load at point of discharge;
and one for each set of compressive strength test specimens.
b. Air Content: ASTM C231, pressure method; one for each set of compressive strength test specimens.
c. Compression Test Specimens: ASTM C31/C31M; one set of 3 standard cylinders for each compressive strength test, unless otherwise directed. Mold and store cylinders for laboratory cured test specimens except when field-cure test specimens are required.
d. Concrete Temperature: Test hourly when air temperature is 40 degrees F. and below, and when 80 degrees F. and above; and each time a set of compression test specimens are made.
e. Compressive Strength Tests: ASTM C39ASTM C39/C39M; one set for each 50
cu. yds. or fraction thereof, of each concrete class placed in any one day or for each 4,000 sq. ft. of surface area placed; 1 specimen tested at 7 days, 2 specimens tested at 28 days, unless requested otherwise by IDOT Representative.
1) A minimum of two test sets for each day’s pour.
2) Make only one set of tests from any one batch of concrete.
3. Compressive Strength Qualifications (ASTM C94/C94M and ACI 318):
a. Compressive Strength at 28 days: Per Paragraph 2.8.E.
b. Consider tests satisfactory, when average of three consecutive strength tests of laboratory cured specimens, representing each specified concrete strength is as follows:
1) Equal to or greater than specified strength.
2) Not more than 10% of strength tests have values less than the specified strength.
3) No individual, properly molded, cured cylinder shows strength less than 500 psi lower than the specified strength.
c. When the strength of field-cured cylinders is less than 85% of companion laboratory-cured cylinders, evaluate current operations and provide corrective procedures for protection and curing the in-place concrete.
G. Qualifications of Ready-Mix Plant: Be certified by the Illinois Department of Transportation
(IDOT).
1.6 PRODUCT DELIVERY, STORAGE & HANDLING
A. Ready Mix Concrete: Comply with the requirements of ASTM C94.
http://global.ihs.com/doc_detail.cfm?rid=BSD&document_name=ASTM%20C94/C94M http://global.ihs.com/doc_detail.cfm?rid=BSD&document_name=ASTM%20C94/C94M http://global.ihs.com/doc_detail.cfm?rid=BSD&document_name=ASTM%20C94/C94M http://global.ihs.com/doc_detail.cfm?rid=BSD&document_name=ASTM%20C94/C94M http://global.ihs.com/doc_detail.cfm?rid=BSD&document_name=ASTM%20C94/C94M http://global.ihs.com/doc_detail.cfm?rid=BSD&document_name=ASTM%20C94/C94M http://global.ihs.com/doc_detail.cfm?rid=BSD&document_name=ASTM%20C94/C94M http://global.ihs.com/doc_detail.cfm?rid=BSD&document_name=ASTM%20C94/C94M http://global.ihs.com/doc_detail.cfm?rid=BSD&document_name=ASTM%20C94/C94M http://global.ihs.com/doc_detail.cfm?rid=BSD&document_name=ASTM%20C94/C94M http://global.ihs.com/doc_detail.cfm?rid=BSD&document_name=ASTM%20C94/C94M http://global.ihs.com/doc_detail.cfm?rid=BSD&document_name=ASTM%20C94/C94M http://global.ihs.com/doc_detail.cfm?rid=BSD&document_name=ASTM%20C94/C94M http://global.ihs.com/doc_detail.cfm?rid=BSD&document_name=ASTM%20C94/C94M http://global.ihs.com/doc_detail.cfm?rid=BSD&document_name=ASTM%20C94/C94M http://global.ihs.com/doc_detail.cfm?rid=BSD&document_name=ASTM%20C94/C94M http://global.ihs.com/doc_detail.cfm?rid=BSD&document_name=ASTM%20C94/C94M http://global.ihs.com/doc_detail.cfm?rid=BSD&document_name=ASTM%20C94/C94M http://global.ihs.com/doc_detail.cfm?rid=BSD&document_name=ASTM%20C94/C94M http://global.ihs.com/doc_detail.cfm?rid=BSD&document_name=ASTM%20C94/C94M http://global.ihs.com/doc_detail.cfm?rid=BSD&document_name=ASTM%20C94/C94M http://global.ihs.com/doc_detail.cfm?rid=BSD&document_name=ASTM%20C94/C94M http://global.ihs.com/doc_detail.cfm?rid=BSD&document_name=ASTM%20C94/C94M http://global.ihs.com/doc_detail.cfm?rid=BSD&document_name=ASTM%20C94/C94M http://global.ihs.com/doc_detail.cfm?rid=BSD&document_name=ASTM%20C94/C94M http://global.ihs.com/doc_detail.cfm?rid=BSD&document_name=ASTM%20C94/C94M http://global.ihs.com/doc_detail.cfm?rid=BSD&document_name=ASTM%20C94/C94M http://global.ihs.com/doc_detail.cfm?rid=BSD&document_name=ASTM%20C94/C94M http://global.ihs.com/doc_detail.cfm?rid=BSD&document_name=ASTM%20C94/C94M http://global.ihs.com/doc_detail.cfm?rid=BSD&document_name=ASTM%20C94/C94M http://global.ihs.com/doc_detail.cfm?rid=BSD&document_name=ASTM%20C94/C94M http://global.ihs.com/doc_detail.cfm?rid=BSD&document_name=ASTM%20C94/C94M http://global.ihs.com/doc_detail.cfm?rid=BSD&document_name=ASTM%20C94/C94M http://global.ihs.com/doc_detail.cfm?rid=BSD&document_name=ASTM%20C94/C94M http://global.ihs.com/doc_detail.cfm?rid=BSD&document_name=ASTM%20C94/C94M http://global.ihs.com/doc_detail.cfm?rid=BSD&document_name=ASTM%20C94/C94M http://global.ihs.com/doc_detail.cfm?rid=BSD&document_name=ASTM%20C94/C94M http://global.ihs.com/doc_detail.cfm?rid=BSD&document_name=ASTM%20C94/C94M http://global.ihs.com/doc_detail.cfm?rid=BSD&document_name=ASTM%20C94/C94M http://global.ihs.com/doc_detail.cfm?rid=BSD&document_name=ASTM%20C94/C94M http://global.ihs.com/doc_detail.cfm?rid=BSD&document_name=ASTM%20C94/C94M http://global.ihs.com/doc_detail.cfm?rid=BSD&document_name=ASTM%20C94/C94M http://global.ihs.com/doc_detail.cfm?rid=BSD&document_name=ASTM%20C94/C94M http://global.ihs.com/doc_detail.cfm?rid=BSD&document_name=ASTM%20C94/C94M http://global.ihs.com/doc_detail.cfm?rid=BSD&document_name=ASTM%20C94/C94M
03 30 00 - 4
1.7 JOB CONDITIONS
A. Environmental Requirements: Protect concrete from physical damage or reduced strength due to weather extremes.
1. In cold weather comply with ACI 306R.
2. In hot weather comply with ACI 305R.
1.8 PROTECTION
A. Adjacent Work:
1. Provide protection for previously finished surfaces during placement of concrete.
2. Spilled concrete on previously finished surfaces shall be removed as soon as possible.
Surfaces damaged by spilled concrete shall be required to be restored to the original finish.
B. This Work:
1. Take into consideration the climatic conditions that will be encountered during and after the pour, and provide proper protection in accordance with ACI 305R and ACI 306R. Refer to paragraphs specifying finishing, sealing and hardener for concrete.
2. Protect concrete that is to remain exposed to view until completion of contract.
PART 2 PRODUCTS
2.1 CONCRETE MATERIALS
A. Cement: ASTM C150/C150M, Type IA - Air Entraining Portland type.
1. Acquire cement for entire project from same source.
B. Fine and Coarse Aggregates: ASTM C33/C33M.
1. Acquire aggregates for entire project from same source.
C. Lightweight Aggregate: ASTM C330/C330M.
D. Fly Ash: 1, Class C or F.
E. Calcined Pozzolan: 1, Class N.
F. Silica Fume: 1, proportioned in accordance with 2.
G. Water: ASTM C1602/C1602M; clean, potable, and not detrimental to concrete.
2.2 ADMIXTURES
A. Do not use chemicals that will result in soluble chloride ions in excess of 0.1 percent by weight of cement.
B. Air Entrainment Admixture: ASTM C260/C260M.
C. High Range Water Reducing and Retarding Admixture: ASTM C494/C494M Type G.
D. High Range Water Reducing Admixture: ASTM C494/C494M Type F.
E. Water Reducing Admixture: ASTM C494/C494M Type A.
2.3 ACCESSORY MATERIALS
A. Under slab Vapor Retarder: Multi-layer, fabric-, cord-, grid-, or aluminum-reinforced http://global.ihs.com/doc_detail.cfm?rid=BSD&document_name=ASTM%20C94/C94M http://global.ihs.com/doc_detail.cfm?rid=BSD&document_name=ASTM%20C94/C94M http://global.ihs.com/doc_detail.cfm?rid=BSD&document_name=ASTM%20C94/C94M http://global.ihs.com/doc_detail.cfm?rid=BSD&document_name=ASTM%20C94/C94M http://global.ihs.com/doc_detail.cfm?rid=BSD&document_name=ASTM%20C94/C94M http://global.ihs.com/doc_detail.cfm?rid=BSD&document_name=ASTM%20C94/C94M http://global.ihs.com/doc_detail.cfm?rid=BSD&document_name=ASTM%20C94/C94M http://global.ihs.com/doc_detail.cfm?rid=BSD&document_name=ASTM%20C94/C94M http://global.ihs.com/doc_detail.cfm?rid=BSD&document_name=ASTM%20C94/C94M http://global.ihs.com/doc_detail.cfm?rid=BSD&document_name=ASTM%20C94/C94M http://global.ihs.com/doc_detail.cfm?rid=BSD&document_name=ASTM%20C94/C94M http://global.ihs.com/doc_detail.cfm?rid=BSD&document_name=ASTM%20C94/C94M http://global.ihs.com/doc_detail.cfm?rid=BSD&document_name=ASTM%20C94/C94M http://global.ihs.com/doc_detail.cfm?rid=BSD&document_name=ASTM%20C94/C94M http://global.ihs.com/doc_detail.cfm?rid=BSD&document_name=ASTM%20C94/C94M http://global.ihs.com/doc_detail.cfm?rid=BSD&document_name=ASTM%20C94/C94M http://global.ihs.com/doc_detail.cfm?rid=BSD&document_name=ASTM%20C94/C94M http://global.ihs.com/doc_detail.cfm?rid=BSD&document_name=ASTM%20C94/C94M http://global.ihs.com/doc_detail.cfm?rid=BSD&document_name=ASTM%20C94/C94M http://global.ihs.com/doc_detail.cfm?rid=BSD&document_name=ASTM%20C94/C94M http://global.ihs.com/doc_detail.cfm?rid=BSD&document_name=ASTM%20C94/C94M http://global.ihs.com/doc_detail.cfm?rid=BSD&document_name=ASTM%20C94/C94M http://global.ihs.com/doc_detail.cfm?rid=BSD&document_name=ASTM%20C94/C94M http://global.ihs.com/doc_detail.cfm?rid=BSD&document_name=ASTM%20C94/C94M http://global.ihs.com/doc_detail.cfm?rid=BSD&document_name=ASTM%20C94/C94M http://global.ihs.com/doc_detail.cfm?rid=BSD&document_name=ASTM%20C94/C94M http://global.ihs.com/doc_detail.cfm?rid=BSD&document_name=ASTM%20C94/C94M http://global.ihs.com/doc_detail.cfm?rid=BSD&document_name=ASTM%20C94/C94M http://global.ihs.com/doc_detail.cfm?rid=BSD&document_name=ASTM%20C94/C94M http://global.ihs.com/doc_detail.cfm?rid=BSD&document_name=ASTM%20C94/C94M http://global.ihs.com/doc_detail.cfm?rid=BSD&document_name=ASTM%20C94/C94M http://global.ihs.com/doc_detail.cfm?rid=BSD&document_name=ASTM%20C94/C94M http://global.ihs.com/doc_detail.cfm?rid=BSD&document_name=ASTM%20C94/C94M http://global.ihs.com/doc_detail.cfm?rid=BSD&document_name=ASTM%20C94/C94M http://global.ihs.com/doc_detail.cfm?rid=BSD&document_name=ASTM%20C94/C94M http://global.ihs.com/doc_detail.cfm?rid=BSD&document_name=ASTM%20C94/C94M http://global.ihs.com/doc_detail.cfm?rid=BSD&document_name=ASTM%20C94/C94M http://global.ihs.com/doc_detail.cfm?rid=BSD&document_name=ASTM%20C94/C94M
03 30 00 - 5 polyethylene or equivalent, complying with ASTM E1745, Class B; stated by manufacturer as suitable for installation in contact with soil or granular fill under concrete slabs. The use of single ply polyethylene is prohibited.
1. Installation: Comply with ASTM E1643.
2. Accessory Products: Vapor retarder manufacturer's recommended tape, adhesive, mastic, prefabricated boots, etc., for sealing seams and penetrations.
3. Manufacturers:
a. Fortifiber Building Systems Group ; Moistop Ultra 10
b. Stego Industries, LLC; Stego Wrap, 10 mil Class A
c. W. R. Meadows, Inc; PERMINATOR Class A - 10 mils
B. Non-Shrink Cementitious Grout: Premixed compound consisting of non-metallic aggregate, cement, water reducing and plasticizing agents.
1. Grout: Comply with ASTM C1107/C1107M.
2. Minimum Compressive Strength at 48 Hours, ASTM C109/C109M: 2,000 pounds per square inch.
3. Products containing aluminum powder are not permitted.
2.4 BONDING AND JOINTING PRODUCTS
A. Slab Isolation Joint Filler: 1/2 inch thick, height equal to slab thickness, with removable top section that will form 1/2-inch-deep sealant pocket after removal.
1. Material: ASTM D1751, cellulose fiber.
B. Dowel Sleeves: Plastic sleeves for smooth, round dowels.
2.5 CURING MATERIALS
A. Curing Compound, Non-dissipating: Liquid, membrane-forming, clear, non-yellowing acrylic;
complying with ASTM C309.
2.6 CONCRETE MIX DESIGN
A. Proportioning Normal Weight Concrete: Comply with ACI 211.1 recommendations.
B. Concrete Strength: Establish required average strength for each type of concrete on the basis of field experience or trial mixtures, as specified in ACI 301.
1. For trial mixtures method, employ independent testing agency acceptable to IDOT
Representative for preparing and reporting proposed mix designs.
C. Admixtures: Add acceptable admixtures as recommended in ACI 211.1 and at rates recommended or required by manufacturer.
D. Cementitious Materials: Limit percentage, by weight, of cementitious materials other than
Portland Cement in concrete as follows:
1. Fly Ash: 25 percent.
2. Slag Cement: 50 percent.
3. Combined Fly Ash or pozzolan and Slag Cement: 50 percent Portland Cement http://global.ihs.com/doc_detail.cfm?rid=BSD&document_name=ASTM%20C94/C94M http://global.ihs.com/doc_detail.cfm?rid=BSD&document_name=ASTM%20C94/C94M http://global.ihs.com/doc_detail.cfm?rid=BSD&document_name=ASTM%20C94/C94M http://global.ihs.com/doc_detail.cfm?rid=BSD&document_name=ASTM%20C94/C94M http://global.ihs.com/doc_detail.cfm?rid=BSD&document_name=ASTM%20C94/C94M http://global.ihs.com/doc_detail.cfm?rid=BSD&document_name=ASTM%20E1643
03 30 00 - 6 minimum, with Fly Ash or pozzolan not exceeding 25 percent.
E. Normal Weight Concrete:
1. Compressive Strength, when tested in accordance with ASTM C39/C39M at 28 days: 4,000 pounds per square inch.
2. Total Air Content: 6 percent, determined in accordance with ASTM C173/C173M.
3. Maximum Slump: 4 inches.
4. Maximum Aggregate Size: 5/8 inch.
2.9 MIXING
A. Transit Mixers: Comply with ASTM C94/C94M.
B. Adding Water: If concrete arrives on-site with slump less than suitable for placement, do not add water that exceeds the maximum water-cement ratio or exceeds the maximum permissible slump.
PART 3 EXECUTION
3.1 EXAMINATION
A. Verify lines, levels, and dimensions before proceeding with work of this section.
3.2 PREPARATION
A. Inspection: Notify IDOT Representative and testing facility at least 24 hours prior to placement of concrete.
B. Verify that forms are clean and free of rust before applying release agent.
C. Coordinate placement of embedded items with erection of concrete formwork and placement of form accessories.
D. Interior Slabs on Grade: Install vapor retarder under interior slabs on grade. Comply with
ASTM E1643. Lap joints minimum 6 inches. Seal joints, seams and penetrations watertight with manufacturer's recommended products and follow manufacturer's written instructions.
Repair damaged vapor retarder before covering.
1. Vapor Retarder Over Granular Fill: Install compactible granular fill before placing vapor retarder as indicated on drawings. Do not use sand.
3.3 INSTALLING REINFORCEMENT AND OTHER EMBEDDED ITEMS
A. Comply with requirements of ACI 301. Clean reinforcement of loose rust and mill scale, and accurately position, support, and secure in place to achieve not less than minimum concrete coverage required for protection.
B. Install welded wire reinforcement in maximum possible lengths, and offset end laps in both directions. Splice laps with tie wire.
3.4 PLACING CONCRETE
A. Place concrete in accordance with ACI 304R.
B. Place concrete for floor slabs in accordance with ACI 302.1R.
C. Notify IDOT Representative not less than 24 hours prior to commencement of placement operations.
03 30 00 - 7
D. Maintain records of concrete placement. Record date, location, quantity, air temperature, and test samples taken.
E. Place concrete continuously without construction (cold) joints wherever possible; where construction joints are necessary, before next placement prepare joint surface by removing laitance and exposing the sand and sound surface mortar, by sandblasting or high-pressure water jetting.
F. Finish floors level and flat, unless otherwise indicated, within the tolerances specified below.
3.5 SLAB JOINTING
A. Locate joints as indicated on drawings.
B. Anchor joint fillers and devices to prevent movement during concrete placement.
C. Isolation Joints: Use preformed joint filler with removable top section for joint sealant, total height equal to thickness of slab, set flush with top of slab.
D. Saw Cut Contraction Joints: Saw cut joints before concrete begins to cool, within 4 to 12 hours after placing; use 3/16-inch-thick blade and cut at least 1 inch deep but not less than one quarter
(1/4) the depth of the slab.
3.6 CONCRETE FINISHING
A. Exposed Form Finish: Rub down or chip off and smooth fins or other raised areas 1/4 inch or more in height. Provide finish as follows:
1. Smooth Rubbed Finish: Wet concrete and rub with carborundum brick or other abrasive, not more than 24 hours after form removal.
B. Concrete Slabs: Finish to requirements of ACI 302.1R, and as follows:
1. Surfaces to Receive Thin Floor Coverings: "Steel trowel" as described in ACI 302.1R;
thin floor coverings include carpeting, resilient flooring, thin set quarry tile, and thin set ceramic tile.
a. Finish interior slab patching at an elevation slightly lower than adjacent floor slab to allow for application of floor leveling compound.
2. Other Surfaces to Be Left Exposed: Trowel as described in ACI 302.1R, minimizing burnish marks and other appearance defects.
3. Refer to drawings for detail for repairs to existing concrete slabs.
C. In areas with floor drains, maintain floor elevation at walls; pitch surfaces uniformly to drains at 1:100 nominal.
3.7 CURING AND PROTECTION
A. Comply with requirements of ACI 308R. Immediately after placement, protect concrete from premature drying, excessively hot or cold temperatures, and mechanical injury.
B. Maintain concrete with minimal moisture loss at relatively constant temperature for period necessary for hydration of cement and hardening of concrete.
C. Surfaces Not in Contact with Forms:
1. Initial Curing: Start as soon as free water has disappeared and before surface is dry. Keep continuously moist for not less than three days by water-fog spray.
2. Final Curing: Begin after initial curing but before surface is dry.
a. Curing Compound: Apply in two coats at right angles, using application rate recommended by manufacturer.
03 30 00 - 8
3.8 FIELD QUALITY CONTROL
A. Provide free access to concrete operations at project site and cooperate with appointed firm.
B. Concrete Tests: Testing laboratory retained by the Contractor may perform sampling and testing during concrete placement, as follows:
1. Sampling: ASTM C172.
2. Slump: ASTM C143, slump range 3" - 5".
3. Air Content: ASTM C31, one for each set of compressive strength specimens.
4. Compressive Strength: ASTM C39, 1 set for each 50 cu. yds. or fraction thereof each class of concrete; 1 specimen tested at 7 days, 1 specimen tested at 28 days, and 1 retained for later testing if required.
5. When tests indicated concrete strength below that specified, improper slump or air entrainment, or when visual defects indicate poor quality concrete has been place.
Contractor may, at its own expense, have additional tests made; including compression tests on cored cylinders in accord with ACI 318. IDOT Representative will order the removal of all nonconforming or defective concrete, and its replacement with concrete meeting project specifications.
3.9 DEFECTIVE CONCRETE
A. Test Results: The testing agency shall report test results in writing to IDOT Representative and
Contractor within 24 hours of test.
B. Defective Concrete: Concrete not complying with required lines, details, dimensions, tolerances or specified requirements.
C. Repair or replacement of defective concrete will be determined by the IDOT Representative.
The cost of additional testing shall be borne by Contractor when defective concrete is identified.
D. Do not patch, fill, touch-up, repair, or replace exposed concrete except upon express direction of IDOT Representative for each individual area.
3.10 PROTECTION
A. Do not permit traffic over unprotected concrete floor surface until fully cured.
END OF
SECTION
DIVISION 22 - PLUMBING
Section 22 11 23 - Facility Natural-Gas Piping
22 11 23 - 1
1.1 WORK INCLUDES
A. Base Bid:
1. Electrical Contractor Provide:
a. Natural gas piping above grade.
b. Unions and flanges.
c. Valves.
d. Pipe hangers and supports.
e. Strainers.
f. Regulators.
1.2 REFERENCES
A. American National Standards Institute:
1. ANSI Z21.15 - Manually Operated Gas Valves for Appliances, Appliance
Connector Valves and Hose End Valves.
B. American Society of Mechanical Engineers:
1. ASME B16.3 - Malleable Iron Threaded Fittings.
2. ASME B16.26 - Cast Copper Alloy Fittings for Flared Copper Tubes.
3. ASME B16.33 - Manually Operated Metallic Gas Valves for Use in Gas Piping
Systems Up to 125 psig (sizes 1/2 - 2).
4. ASME B31.9 - Building Services Piping.
5. ASME Section IX - Boiler and Pressure Vessel Code - Welding and Brazing
Qualifications.
C. ASTM International:
1. ASTM A53/A53M - Standard Specification for Pipe, Steel, Black and Hot-
Dipped, Zinc-Coated, Welded and Seamless.
2. ASTM B280 - Standard Specification for Seamless Copper Tube for Air
Conditioning and Refrigeration Field Service.
3. ASTM B749 - Standard Specification for Lead and Lead Alloy Strip, Sheet, and
Plate Products.
4. ASTM F708 - Standard Practice for Design and Installation of Rigid Pipe
Hangers.
D. American Welding Society:
1. AWS D1.1 - Structural Welding Code - Steel.
E. Manufacturers Standardization Society of the Valve and Fittings Industry:
22 11 23 - 2
1. MSS SP 58 - Pipe Hangers and Supports - Materials, Design and Manufacturer.
2. MSS SP 69 - Pipe Hangers and Supports - Selection and Application.
3. MSS SP 78 - Cast Iron Plug Valves, Flanged and Threaded Ends.
4. MSS SP 89 - Pipe Hangers and Supports - Fabrication and Installation Practices.
5. MSS SP 110 - Ball Valves Threaded, Socket-Welding, Solder Joint, Grooved and
Flared Ends.
F. National Fire Protection Association:
1. NFPA 54 - National Fuel Gas Code.
2. UL 842 - Valves for Flammable Fluids.
1.3 SYSTEM DESCRIPTION
A. Where more than one (1) piping system material is specified, provide compatible system components and joints. Use non-conducting dielectric connections when joining dissimilar metals in systems.
B. Provide flanges, unions, or couplings at locations requiring servicing. Use unions, flanges, or couplings downstream of valves and at equipment connections. Do not use direct welded or threaded connections to valves, equipment.
C. Provide pipe hangers and supports in accordance with ASME B31.9, ASTM F708, MSS SP 58, MSS SP 69, and MSS SP 89.
D. Use plug, ball, or butterfly valves for shut-off and to isolate equipment, part of systems, or vertical risers.
1.4 SUBMITTALS
A. Submit in accordance with Section 01 33 23 – “Shop Drawings, Product Data &
Samples” requirements.
B. Product Data:
1. Piping: Submit data on pipe materials, fittings, and accessories. Submit manufacturers catalog information.
2. Valves: Submit manufacturers catalog information with valve data and ratings for each service.
3. Hangers and Supports: Submit manufacturers catalog information including load capacity.
4. Piping Specialties: Submit manufacturers catalog information including capacity, rough-in requirements, and service sizes for the following:
a. Strainers.
b. Natural gas pressure regulators.
c. Natural gas pressure relief valves.
C. Design Data: Indicate pipe size. Indicate load carrying capacity of trapeze, multiple pipe, and riser support hangers.
22 11 23 - 3
D. Welders Certificates: Certify welders employed on the Work, verifying AWS qualification within previous twelve (12) months.
1.5 OPERATION AND MAINTENANCE DATA
A. Submit in accordance with Section 01 78 23 – “Operating and Maintenance” requirements.
B. Operation Data.
C. Include manufacturer’s descriptive literature, operating instructions, maintenance and repair data, and parts listing.
1.6 QUALITY ASSURANCE
A. Perform natural gas Work in accordance with NFPA 54.
B. Perform work in accordance with applicable code.
C. Perform Work in accordance with ASME B31.9 code for installation of piping systems and ASME Section IX for welding materials and procedures.
D. Perform Work in accordance with applicable code for welding hanger and support attachments to building structure.
E. Furnish shutoff valves complying with ASME B16.33 or ANSI Z21.15.
1.7 QUALIFICATIONS
A. Manufacturer: Company specializing in manufacturing products specified in this section with minimum three (3) years documented experience.
B. Installer: Company specializing in performing Work of this section with minimum three (3) years documented experience approved by manufacturer.
1.8 DELIVERY, STORAGE, AND HANDLING
A. Accept valves on site in shipping containers with labeling in place. Inspect for damage.
B. Protect piping and fittings from soil and debris with temporary end caps and closures.
Maintain in place until installation. Furnish temporary protective coating on cast iron and steel valves.
1.9 FIELD MEASUREMENTS
A. Verify field measurements prior to fabrication.
22 11 23 - 4
2. PRODUCTS
2.1 NATURAL GAS PIPING, ABOVE GRADE
A. Steel Pipe: ASTM A53/A53M Schedule 40 black:
1. Fittings: ASME B16.3, malleable iron, or ASTM A234/A234M forged steel welding type.
2. Joints: Threaded for pipe 2 in. and smaller; welded for pipe 2-1/2 in. and larger.
B. Copper Tubing: ASTM B88 (ASTM B88M), Type K or L ASTM B280, ACR annealed:
1. Fittings: ASME B16.26 cast bronze, compression type.
2. Joints: Flared.
2.2 UNIONS AND FLANGES
A. Unions for Pipe 2 in. and Smaller:
B. Ferrous Piping: Class 150, malleable iron, threaded.
C. Copper Piping: Class 150, bronze unions with brazed joints.
D. Dielectric Connections: Union with galvanized or plated steel threaded end, copper solder end, water impervious isolation barrier.
E. Flanges for Pipe 2-1/2 in. and Larger.
F. Ferrous Piping: Class 150, forged steel, slip-on flanges.
G. Copper Piping: Class 150, slip-on bronze flanges.
H. Gaskets: 1/16 in. thick preformed neoprene gaskets.
2.3 BALL VALVES
A. Acceptable Manufacturers:
1. Crane.
2. Hammond.
3. Milwaukee Valve Company.
4. NIBCO, Inc.
5. Stockham Valves & Fittings.
B. Ball Valves 1/4 in. to 1 in.: MSS SP 110, Class 125, two-piece, threaded ends, bronze body, chrome plated bronze ball, reinforced teflon seats, blow-out proof stem, lever handle, UL 842 listed for flammable liquids and LPG, full port.
22 11 23 - 5
C. Ball Valves 1-1/4 in. to 3 in.: MSS SP 110, Class 125, two-piece, threaded ends, bronze body, chrome plated bronze ball, reinforced teflon seats, blow-out proof stem, lever handle, UL 842 listed for flammable liquids and LPG, conventional port.
2.4 PLUG VALVES
A. Acceptable Manufacturers:
1. DeZURIK.
2. Flow Control Equipment, Inc.
3. Homestead Valve.
B. Plug Valves 2 in. and Smaller: MSS SP 78, Class 150 Class 300, semi-steel construction, square port, pressure lubricated, teflon packing, threaded ends. Furnish one (1) plug valve wrench for every ten plug-valves with minimum of one wrench.
C. Plug Valves 2-1/2 in. and Larger: MSS SP 78, Class 150 Class 300, semi-steel construction, square port, pressure lubricated, teflon packing, flanged ends. Furnish wrench-operated.
2.5 BUTTERFLY VALVES
A. Acceptable Manufacturers:
1. Crane Valve.
2. Hammond.
3. Milwaukee Valve Company.
4. NIBCO, Inc.
5. Stockham Valves & Fittings.
B. Butterfly Valves 2 in. and Smaller: MSS SP 67, 175 psi, bronze body, Viton seals, stainless steel trim handle UL 842 listed for gas service, threaded ends, full port.
2.6 PIPE HANGERS AND SUPPORTS
A. Acceptable Manufacturers:
1. Carpenter & Paterson Inc.
2. Creative Systems Inc.
3. Flex-Weld, Inc.
4. Globe Pipe Hanger Products Inc.
5. Michigan Hanger Co.
6. Superior Valve Co.
B. Conform to ASTM F708.
C. Hangers for Pipe Sizes 1/2 to 1-1/2 in.: Carbon steel, adjustable swivel, split ring.
D. Hangers for Pipe Sizes 2 in. and Larger: Carbon steel, adjustable, clevis.
22 11 23 - 6
E. Multiple or Trapeze Hangers: Steel channels with welded spacers and hanger rods.
F. Wall Support for Pipe 3 in. and Smaller: Cast iron hook.
G. Vertical Support: Steel riser clamp.
H. Floor Support: Cast iron adjustable pipe saddle, lock nut, nipple, floor flange, and concrete pier or steel support.
I. Copper Pipe Support: Carbon steel ring, adjustable, copper plated.
J. Sheet Lead: ASTM B749, 0.039 in. thick.
2.7 STRAINERS
A. Acceptable Manufacturers:
1. Mueller Steam Specialty.
2. O.C. Keckley Company.
3. Spirax Sarco, Inc.
B. 2 in. and Smaller: Screwed brass or iron body for 175 psig working pressure, Y pattern with 1/32 in. stainless steel perforated screen.
C. 2-1/2 in. to 4 in.: Flanged iron body for 175 psig working pressure, Y pattern with
3/64 in. stainless steel perforated screen.
D. 5 in. and Larger: Flanged iron body for 175 psig working pressure, basket pattern with 1/8 in. stainless steel perforated screen.
2.8 GAS PRESSURE REGULATOR
A. ANSI Z21.18 or ANSI Z21.18a, single stage, steel jacketed, corrosion-resistant pressure regulators. Include atmospheric vent, elevation compensator, with threaded ends for 2 inches and smaller and flanged ends for 2-1/2 inches and larger. Regulator pressure ratings, inlet and outlet pressures, and flow volume in standard cubic feet per hour of natural gas at specific gravity are as required by equipment.
1. Service Gas Pressure Regulators: Inlet pressure rating not less than natural gas distribution system service pressure.
2. Line Gas Pressure Regulators: Inlet pressure rating not less than system pressure.
3. Appliance Gas Pressure Regulators: Inlet pressure rating not less than system pressure with capacity and pressure setting matching appliance.
4. Acceptable Manufacturers:
a. Fisher Controls.
b. Lancaster by National Meter Parts, Inc.
c. Maxitrol Co.
d. Schlumberger Industries, Gas Div.
22 11 23 - 7
3. EXECUTION
3.1 EXAMINATION
A. Verify excavations are to required grade, dry, and not over-excavated.
3.2 PREPARATION
A. Ream pipe and tube ends. Remove burrs. Bevel plain end ferrous pipe.
B. Remove scale and dirt, on inside and outside, before assembly.
C. Prepare piping connections to equipment with flanges or unions.
3.3 INSTALLATION - INSERTS
A. Provide inserts for placement in concrete forms.
B. Provide inserts for suspending hangers from reinforced concrete slabs and sides of reinforced concrete beams.
C. Provide hooked rod to concrete reinforcement section for inserts carrying pipe 4 in.
and larger.
D. Where concrete slabs form finished ceiling, locate inserts flush with slab surface.
E. Where inserts are omitted, drill through concrete slab from below and provide through-bolt with recessed square steel plate and nut flush with top of slab.
3.4 INSTALLATION - PIPE HANGERS AND SUPPORTS
A. Install hangers and supports in accordance with ASME B31.9 ASTM F708 and MSS
SP 89.
B. Support horizontal piping hangers as scheduled.
C. Install hangers to provide minimum 1/2 in. space between finished covering and adjacent work.
D. Place hangers within 12 in. of each horizontal elbow.
E. Install hangers to allow 1-1/2 in. minimum vertical adjustment. Design hangers for pipe movement without disengagement of supported pipe.
F. Support vertical piping at every floor. Support riser piping independently of connected horizontal piping.
G. Where installing several pipes in parallel and at same elevation, provide multiple pipe hangers or trapeze hangers.
22 11 23 - 8
H. Provide sheet lead packing between hanger or support and piping.
I. Prime coat exposed steel hangers and supports in accordance with Painting Section.
Hangers and supports located in crawl spaces, pipe shafts, and suspended ceiling spaces are not considered exposed.
J. Provide clearance in hangers and from structure and other equipment for installation of insulation and access to valves and fittings.
K. Install pipe hangers and supports in accordance with Section 22 10 00 – “Plumbing
Piping and Fittings”.
3.5 INSTALLATION - ABOVE GROUND PIPING SYSTEMS
A. Install natural gas piping in accordance with NFPA 54.
B. Provide non-conducting dielectric connections wherever jointing dissimilar metals.
C. Route piping in orderly manner and maintain gradient.
D. Install piping to conserve building space and not interfere with use of space.
E. Group piping whenever practical at common elevations.
F. Install piping to allow for expansion and contraction without stressing pipe, joints, or connected equipment.
G. Sleeve pipe passing through partitions, walls and floors.
H. Provide clearance for installation of insulation and access to valves and fittings.
I. Provide support for utility meters in accordance with requirements of utility company.
J. Prepare pipe, fittings, supports, and accessories not pre-finished, ready for finish painting.
K. Install identification on piping systems including underground piping.
L. Install valves with stems upright or horizontal, not inverted.
M. Protect piping systems from entry of foreign materials by temporary covers, completing sections of the Work, and isolating parts of completed system.
N. Install gas pressure regulator with tee fitting between regulator and upstream shutoff valve. Cap or plug one (1) opening of tee fitting.
O. Install gas pressure regulator with tee fitting not less than ten (10) pipe diameters downstream of regulator. Cap or plug one (1) opening of tee fitting.
P. Install gas pressure regulator with independent vent full size opening on regulator and terminate outdoors.
22 11 23 - 9
3.6 FIELD QUALITY CONTROL
A. Pressure test natural gas piping in accordance with NFPA 54.
END 23 11 23
DIVISION 26 - ELECTRICAL
26 05 00 - Common Work Results for Electrical Systems
26 05 00 - 1
1.1 WORK INCLUDES
A. Base Bid:
1. Electrical Contractor Provide:
a. Electrical equipment coordination and installation.
b. Common electrical installation requirements.
1.2 RELATED WORK
A. Specified elsewhere:
1. 26 05 19 - Low-Voltage Electrical Power Conductors & Cables.
2. 26 05 26 - Grounding & Bonding for Electrical Systems.
3. 26 05 33 - Raceway & Boxes for Electrical Systems.
4. 26 05 53 - Identification for Electrical Systems.
5. 26 05 73 - Overcurrent Protective Device Coordination Study.
6. 26 24 16 - Panelboards.
7. 26 28 19 - Enclosed Switches.
8. 26 32 13 - Engine Generator and Transfer Switch.
1.3 QUALITY ASSURANCE
A. All work and materials shall be in accordance with the requirements and codes of the state of
Illinois and all other applicable bodies having jurisdiction.
B. If in the opinion of the contractor any part of the specification or plans do not comply with the laws, codes and regulations, that matter shall be referred in writing to the attention of the
IDOT Representative for a decision before proceeding with that part of the work. There shall be no changes in the drawings or specifications made without the approval of the IDOT
Representative.
C. Contractor shall obtain and pay for all licenses, permits, and inspections required by above laws, ordinances, and rules for entire electric wiring job called for in these Specifications and accompanying Plans.
D. Any minor changes in location of equipment, to include conduits, outlets, etc. from those shown on Plans, shall be made without extra charge if so directed by Owner’s Representative.
These changes shall be any changes in location that had new location been the bid-upon location would not have resulted in an increase in contract construction cost over that actually bid.
E. The Contractor shall furnish and install all equipment and materials necessary for a complete and operational installation of the electrical equipment, as specified herein and as shown on the Plans. The complete installation and wiring shall be done in a neat, workmanlike manner.
All electrical work shall comply with the requirements of 2023 NFPA 70 - National Electrical
26 05 00 - 2
Code (NEC), most current issue in force, and all other applicable local codes, laws, ordinances, and requirements in force. Electrical equipment shall be installed in conformance with the respective manufacturer’s directions and recommendations for the respective application.