About this file
This is a Subcontractor Summary Worksheet instruction document issued by the City of St. Petersburg for use by prime contractors bidding on the Historical Engineering Records Preservation project. The worksheet requires prime contractors to list all intended subcontractors, including their legal names, business addresses, contact information, trade classifications, and subcontract amounts. Bidders must complete and submit this worksheet with their bid proposal. The project involves digitizing approximately 65,000 microfiche slides, 20,000 aperture cards, and 200 reels of microfilm into searchable PDF files. The RFQ was released on March 27, 2026, with a submittal deadline of April 7, 2026, at 3:00 p.m. through the OpenGov Procurement portal. Questions must be submitted by March 31, 2026. The City will award the contract to one vendor.
Prime contractors may subcontract up to eighty percent of the contract work, provided that subcontractors are approved by the City and identified in the Subcontractor Summary Worksheet at the time of bid submission. Subcontractors cannot be changed or substituted after contract award and the pre-construction meeting without documented justification, which includes reasons such as contractor failure to execute a written contract at the specified price, lack of appropriate licensing, bankruptcy, ineligibility, performance failures, unsatisfactory work, or substantial delays. The City encourages participation by small business enterprises, women business enterprises, veteran-owned businesses, and minority business enterprises through a voluntary Subcontractor Utilization Plan with no minimum participation requirements mandated for award. Any SBE subcontractors used to meet SBE requirements must be replaced with other SBE subcontractors if substitution occurs, unless the prime contractor demonstrates that SBE requirements are being met through other means. Requests for subcontractor changes must be submitted in writing to the Procurement & Supply Management office.
View the file
Other files
Show all 25
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Instructions
| City of St. Petersburg |
| Subcontractor Summary Instructions |
WORKSHEET MUST BE COMPLETED AND SUBMITTED WITH YOUR BID
1. The Subcontractor Worksheet reflects the percentage of work which may be subcontracted for this project. Refer to Contract Standards, Instructions to Bidders, Article I-13, Subcontractors for applicable rules.
2. Enter the name of your company in the Prime Contractor field.
3. Enter the name and date of Prime Contractor employee completing this form.
4. Provide all information requested on each intended subcontractor. If subcontractors will NOT be used for this project, provide a written statement on the Subcontractor List indicating the same.
5. Subcontractors may not be changed or substituted once a Prime Contractor is awarded the project (and the pre-construction meeting held), except for the following reasons:
A. Subcontractor fails or refuses to execute a written contract for the scope of work as specified at the price specified;
B. Subcontractor is not appropriately licensed to perform the scope of work;
C. Subcontractor becomes bankrupt or insolvent;
D. Subcontractor is ineligible to perform the work on the project;
E. Subcontractor fails or refuses to perform its subcontract;
F. Engineer determines the work performed by the subcontractor is substantially unsatisfactory and not in substantial accordance with the plans and specifications;
G. Subcontractor is substantially delaying or disrupting the progress of the work.
Requests for changes to the Subcontractor List shall be made in writing to the Procurement & Supply Management, Attention: Contracts Compliance Manager at Stephanie.Swinson@stpete.org.
6. SBE subcontractors used to meet the SBE percentage requirement, if replaced, shall be replaced with a SBE subcontractor, unless the Prime Contractor demonstrates that SBE requirements are being met in another way.
7. Restrictions on subcontracting percentage and use of multiple-tier subcontractors do not apply to FDOT LAP or federally funded projects.
Subcontractor Worksheet
| City of St. Petersburg |
| Subcontractor Summary |
| Project Name: |
| Project Number: |
| Percentage of Contract Which May be Subcontracted: |
| Name of Prime Contractor: | Cells below will be "hidden" on the worksheet since they are only for Procurement's use. |
| Name/Date of Individual Completing this Form: |
| City of St. Petersburg SBE or MWBE Contractor Yes or No | Subcontractor's Name (Provide complete Legal Name) | Subcontractor's Primary Business Address | Name/Phone Number and Email Address of Subcontractor's Employee Responsible for Project Supervision | First or Second Tier Subcontractor* | Trade Classification(s) Being Subcontracted (List One Trade per Line) | Subcontract Amount ($) | Added (A) Deleted (D) | Reason Code | City Approver/Date | Add (A) and Delete (D) Legend |
| Example: Yes | XYZ Contractors, Inc. | 123 N. Burlington Ave., St. Petersburg, FL 33701 | Joe Jones - 727-555-555 Email - XYXCon@yahoo.com | First | Electrical | 13,234.00 | D | B | Employee XYZ/03-01-19 | A. Subcontractor fails or refuses to execute a written contract for the scope of work as specified at the price specified; |
| B. Subcontractor is not appropriately licensed to perform the scope of work; | ||||||||||
| C. Subcontractor becomes bankrupt or insolvent; | ||||||||||
| D. Subcontractor is ineligible to perform the work on the project; | ||||||||||
| E. Subcontractor fails or refuses to perform its subcontract; | ||||||||||
| F. Engineer determines the work performed by the Subcontractor is substantially unsatisfactory and not in substantial accordance with the Plans and Specifications; |
G. Subcontractor is substantially delaying or disrupting the progress of the work.
Total: 0.00
| *Only first and second tier subcontractors are permitted unless noted otherwise in the Contract Documents. | Contract Amount | |
| 0.00 | Amount Allowed to be Subcontracted |