This is a Subcontractor Summary Worksheet instruction document issued by the City of St. Petersburg, Florida, outlining requirements for subcontractor disclosure and management on city projects. The worksheet mandates that prime contractors submit detailed information on all intended subcontractors at the time of bid submission, including subcontractor legal names, business addresses, contact information, trade classifications, and subcontract amounts. For the Faith Community Housing Assistance Consultant project specifically, up to 80% of contract work may be subcontracted. Subcontractors cannot be changed or substituted after contract award and the pre-construction meeting without documented justification, such as contractor failure to execute contracts, lack of appropriate licensing, bankruptcy, ineligibility, substantial underperformance, or project delay. Small Business Enterprises (SBEs) or Minority/Women-Owned Business Enterprises (MWBE) used to meet participation requirements must be replaced with similarly certified firms if substitution becomes necessary. Only first and second-tier subcontractors are permitted unless the contract documents specify otherwise.
The worksheet requires prime contractors to designate whether subcontractors are first or second-tier providers and whether they are SBE or MWBE certified. All requested changes to the subcontractor list must be submitted in writing to the City's Procurement & Supply Management office, specifically to the Contracts Compliance Manager at Stephanie.Swinson@stpete.org, with provisions for adding, deleting, or modifying subcontractor information using standardized reason codes. The document includes a legend of seven specific grounds for subcontractor replacement, tracking columns for city approval and dates, and instructions that the worksheet must be completed and submitted with the bid proposal. The worksheet template provides fields for calculating total subcontract amounts against the overall contract amount and the allowable subcontracting percentage.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Faith_Community_Housing_Assistance_Consultant_(Addendum_#1_Revision).pdf | ||
| Vendor_Reference_Form.pdf | ||
| Faith_Community_Housing_Assistance_Consultant.pdf | ||
| Quote_Submittal_Requirements.pdf | ||
| Base_Agreement_.pdf | ||
| Subcontractor_Summary_Spreadsheet.xlsx | XLSX spreadsheet | |
| Subcontractor_Utilization_Plan.docx | DOCX document | |
| Faith_Community_Consultant_Proposal_Requirements.pdf | ||
| Faith_Community_Consultant_Evaluation_Criteria.pdf | ||
| Light_Construction_Agreement.docx | DOCX document | |
| Performance_&_Payment_Bond_.DOCX | DOCX document | |
| Public_Construction_Bond.docx | DOCX document | |
| Subcontractor_Summary_-_Sheltered_.xlsx | XLSX spreadsheet |
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Instructions
| City of St. Petersburg |
| Subcontractor Summary Instructions |
WORKSHEET MUST BE COMPLETED AND SUBMITTED WITH YOUR BID
1. The Subcontractor Worksheet reflects the percentage of work which may be subcontracted for this project. Refer to Contract Standards, Instructions to Bidders, Article I-13, Subcontractors for applicable rules.
2. Enter the name of your company in the Prime Contractor field.
3. Enter the name and date of Prime Contractor employee completing this form.
4. Provide all information requested on each intended subcontractor. If subcontractors will NOT be used for this project, provide a written statement on the Subcontractor List indicating the same.
5. Subcontractors may not be changed or substituted once a Prime Contractor is awarded the project (and the pre-construction meeting held), except for the following reasons:
A. Subcontractor fails or refuses to execute a written contract for the scope of work as specified at the price specified;
B. Subcontractor is not appropriately licensed to perform the scope of work;
C. Subcontractor becomes bankrupt or insolvent;
D. Subcontractor is ineligible to perform the work on the project;
E. Subcontractor fails or refuses to perform its subcontract;
F. Engineer determines the work performed by the subcontractor is substantially unsatisfactory and not in substantial accordance with the plans and specifications;
G. Subcontractor is substantially delaying or disrupting the progress of the work.
Requests for changes to the Subcontractor List shall be made in writing to the Procurement & Supply Management, Attention: Contracts Compliance Manager at Stephanie.Swinson@stpete.org.
6. SBE subcontractors used to meet the SBE percentage requirement, if replaced, shall be replaced with a SBE subcontractor, unless the Prime Contractor demonstrates that SBE requirements are being met in another way.
7. Restrictions on subcontracting percentage and use of multiple-tier subcontractors do not apply to FDOT LAP or federally funded projects.
Subcontractor Worksheet
| City of St. Petersburg |
| Subcontractor Summary |
| Project Name: |
| Project Number: |
| Percentage of Contract Which May be Subcontracted: 80% for Shelter Bid |
| Name of Prime Contractor: | Cells below will be "hidden" on the worksheet since they are only for Procurement's use. |
| Name/Date of Individual Completing this Form: |
| City of St. Petersburg SBE or MWBE Contractor Yes or No | Subcontractor's Name (Provide complete Legal Name) | Subcontractor's Primary Business Address | Name/Phone Number and Email Address of Subcontractor's Employee Responsible for Project Supervision | First or Second Tier Subcontractor* | Trade Classification(s) Being Subcontracted (List One Trade per Line) | Subcontract Amount ($) | Added (A) Deleted (D) | Reason Code | City Approver/Date | Add (A) and Delete (D) Legend |
| Example: Yes | XYZ Contractors, Inc. | 123 N. Burlington Ave., St. Petersburg, FL 33701 | Joe Jones - 727-555-555 Email - XYXCon@yahoo.com | First | Electrical | 13,234.00 | D | B | Employee XYZ/03-01-19 | A. Subcontractor fails or refuses to execute a written contract for the scope of work as specified at the price specified; |
| B. Subcontractor is not appropriately licensed to perform the scope of work; | ||||||||||
| C. Subcontractor becomes bankrupt or insolvent; | ||||||||||
| D. Subcontractor is ineligible to perform the work on the project; | ||||||||||
| E. Subcontractor fails or refuses to perform its subcontract; | ||||||||||
| F. Engineer determines the work performed by the Subcontractor is substantially unsatisfactory and not in substantial accordance with the Plans and Specifications; |
G. Subcontractor is substantially delaying or disrupting the progress of the work.
Total: 0.00
| *Only first and second tier subcontractors are permitted unless noted otherwise in the Contract Documents. | Contract Amount | |
| 0.00 | Amount Allowed to be Subcontracted |
&8Rev. January 2020 &10Page 1 of &P