Subcontractor_Summary_-_Sheltered_.xlsx
XLSX spreadsheet 33 KB Posted
- Attached to
- Repairing and raising of Maximo boat dock
- Solicitation number
- REQ- 26 - 079
- Issued by
- Pinellas County, Florida
About this file
This is a Subcontractor Summary worksheet instruction document issued by the City of St. Petersburg for the repair and raising of the Maximo Boat Dock project located at 4801 37th Street South, St. Petersburg, Florida. The document establishes guidelines for prime contractors bidding on the project to disclose all intended subcontractors and provides a standardized template for reporting subcontractor information, including the subcontractor's legal name, primary business address, project supervision contact information, trade classifications, and subcontract amounts. The worksheet must be completed and submitted with all bids and serves as the official record for subcontractor utilization throughout project execution. The City sets a maximum allowable subcontracting percentage at 80 percent of the total contract value, with restrictions limiting subcontractors to first or second tier only unless otherwise specified in contract documents.
The worksheet establishes strict controls on subcontractor changes after contract award, permitting substitutions only for documented reasons including failure to execute contracts at specified prices, lack of appropriate licensing, bankruptcy or insolvency, ineligibility to perform work, failure to perform, substantial unsatisfactory work performance, or substantial delays to project progress. All requests for subcontractor changes must be submitted in writing to the City's Contracts Compliance Manager at Stephanie.Swinson@stpete.org. The form includes provisions requiring that any Small Business Enterprise (SBE) or Minority/Women Business Enterprise (MWBE) subcontractors used to meet SBE percentage requirements be replaced with similarly certified subcontractors if substitution becomes necessary, unless the prime contractor demonstrates SBE requirements are being met through alternative means. The worksheet was revised in January 2020 and applies to all subcontracting arrangements for this City of St. Petersburg project.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Repairing_and_raising_of_Maximo_boat_dock.pdf | ||
| Public_Construction_Bond.docx | DOCX document | |
| Quote_Drawing.pdf | ||
| Light_Construction_legal_reviewed_RM_changes_26_079_Maximo_(1).pdf | ||
| Quote_Addendum.docx | DOCX document | |
| Subcontractor_Summary_-_Sheltered_.xlsx | XLSX spreadsheet | |
| Performance_&_Payment_Bond_.DOCX | DOCX document | |
| Subcontractor_Utilization_Plan.docx | DOCX document | |
| Subcontractor_Summary_Spreadsheet.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Instructions
| City of St. Petersburg |
| Subcontractor Summary Instructions |
WORKSHEET MUST BE COMPLETED AND SUBMITTED WITH YOUR BID
1. The Subcontractor Worksheet reflects the percentage of work which may be subcontracted for this project. Refer to Contract Standards, Instructions to Bidders, Article I-13, Subcontractors for applicable rules.
2. Enter the name of your company in the Prime Contractor field.
3. Enter the name and date of Prime Contractor employee completing this form.
4. Provide all information requested on each intended subcontractor. If subcontractors will NOT be used for this project, provide a written statement on the Subcontractor List indicating the same.
5. Subcontractors may not be changed or substituted once a Prime Contractor is awarded the project (and the pre-construction meeting held), except for the following reasons:
A. Subcontractor fails or refuses to execute a written contract for the scope of work as specified at the price specified;
B. Subcontractor is not appropriately licensed to perform the scope of work;
C. Subcontractor becomes bankrupt or insolvent;
D. Subcontractor is ineligible to perform the work on the project;
E. Subcontractor fails or refuses to perform its subcontract;
F. Engineer determines the work performed by the subcontractor is substantially unsatisfactory and not in substantial accordance with the plans and specifications;
G. Subcontractor is substantially delaying or disrupting the progress of the work.
Requests for changes to the Subcontractor List shall be made in writing to the Procurement & Supply Management, Attention: Contracts Compliance Manager at Stephanie.Swinson@stpete.org.
6. SBE subcontractors used to meet the SBE percentage requirement, if replaced, shall be replaced with a SBE subcontractor, unless the Prime Contractor demonstrates that SBE requirements are being met in another way.
7. Restrictions on subcontracting percentage and use of multiple-tier subcontractors do not apply to FDOT LAP or federally funded projects.
Subcontractor Worksheet
| City of St. Petersburg |
| Subcontractor Summary |
| Project Name: |
| Project Number: |
| Percentage of Contract Which May be Subcontracted: 80% for Shelter Bid |
| Name of Prime Contractor: | Cells below will be "hidden" on the worksheet since they are only for Procurement's use. |
| Name/Date of Individual Completing this Form: |
| City of St. Petersburg SBE or MWBE Contractor Yes or No | Subcontractor's Name (Provide complete Legal Name) | Subcontractor's Primary Business Address | Name/Phone Number and Email Address of Subcontractor's Employee Responsible for Project Supervision | First or Second Tier Subcontractor* | Trade Classification(s) Being Subcontracted (List One Trade per Line) | Subcontract Amount ($) | Added (A) Deleted (D) | Reason Code | City Approver/Date | Add (A) and Delete (D) Legend |
| Example: Yes | XYZ Contractors, Inc. | 123 N. Burlington Ave., St. Petersburg, FL 33701 | Joe Jones - 727-555-555 Email - XYXCon@yahoo.com | First | Electrical | 13,234.00 | D | B | Employee XYZ/03-01-19 | A. Subcontractor fails or refuses to execute a written contract for the scope of work as specified at the price specified; |
| B. Subcontractor is not appropriately licensed to perform the scope of work; | ||||||||||
| C. Subcontractor becomes bankrupt or insolvent; | ||||||||||
| D. Subcontractor is ineligible to perform the work on the project; | ||||||||||
| E. Subcontractor fails or refuses to perform its subcontract; | ||||||||||
| F. Engineer determines the work performed by the Subcontractor is substantially unsatisfactory and not in substantial accordance with the Plans and Specifications; |
G. Subcontractor is substantially delaying or disrupting the progress of the work.
Total: 0.00
| *Only first and second tier subcontractors are permitted unless noted otherwise in the Contract Documents. | Contract Amount | |
| 0.00 | Amount Allowed to be Subcontracted |