Statement of Work Summary: Supply and Installation of 80' x 112' Tent Structure
This Statement of Work defines requirements for sourcing, delivering, and installing an engineered tent structure at Volk Field Air National Guard Base in Wisconsin. The structure must provide a permanent-grade, climate-resilient covered area measuring approximately 80 feet by 112 feet with an open, column-free interior design featuring arched trusses and vertical sidewalls. The structure shall maintain a minimum interior clearance of 12 feet beneath the lowest structural element and be site-adapted to an existing concrete pad within a fenced compound.
The contractor must engineer and deliver a structure capable of withstanding northern tier Air Force environmental conditions, including heavy snow loads, high winds, hail, extreme cold, and rapid freeze-thaw cycles, in compliance with UFC and IBC standards. All fabric must be rated for 20+ year lifespan, desert tan in color, UV-resistant, and mildew-resistant. Metal components must be corrosion-resistant for cold-weather durability. Access requirements include vertical accordion-style fabric doors with 12 feet minimum overhead clearance on sidewalls and end walls, operable manually by a single individual, plus rigid personnel doors adjacent to fabric access doors for independent ingress/egress. Deliverables include engineered and fabrication drawings, snow and wind load certification, anchoring plans, warranty documentation, and operations/maintenance manuals. The contractor must provide a minimum 20-year fabric warranty and 10-year structural warranty covering defects in materials, workmanship, and environmental performance. All non-compliant items will be corrected or replaced at no additional cost to the government.
View the file
Who attaches OF 80
| Agency | Files |
|---|---|
| Department of the Army National Guard | 1 |
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK (SOW)
FOR
SUPPLY AND INSTALLATION OF 80’ X 112’ TENT STRUCTURE
PURPOSE
This Statement of Work (SOW) de�ines the requirements for sourcing, delivering, and installing an approximately 80’ x 112’ engineered tent structure at Volk Field Air National Guard Base (ANGB). The structure will provide a durable, climate-resilient covered area suitable for year-round use in a northern tier environment.
BACKGROUND
The designated installation area is located within a fenced compound at Volk Field CRTC. The government requires a permanent-grade tensioned fabric structure to protect mission-essential equipment and personnel from severe weather conditions typical of northern tier Air Force bases, including extreme cold, heavy snow loads, high winds, hail, and rapid freeze-thaw cycles.
SCOPE
The contractor shall provide all labor, materials, equipment, engineering, transportation, and installation services necessary to deliver a fully functional, anchored, and code-compliant tent structure. All dimensions provided are approximate and shall be veri�ied by the contractor prior to fabrication and installation.
TECHNICAL REQUIREMENTS
A. STRUCTURE DIMENSIONS AND CONFIGURATION
• Approximate footprint: 80 feet x 112 feet
• Interior design: Open, column-free clear span
• Structural system: Arched trusses spanning the full width
• Wall con�iguration: Vertical sidewalls and end walls
• Minimum interior clearance: 12 feet beneath lowest structural element
B. CLIMATE AND ENVIRONMENTAL PERFORMANCE
The structure must be engineered and rated to withstand northern tier Air Force Base environmental conditions, including:
• Snow load: Must meet or exceed local base-speci�ic design snow load requirements
• Wind load: Must meet or exceed local wind rating requirements
• Cold weather durability: Materials must resist brittleness, cracking, and thermal degradation
• Hail resistance: Fabric and structural components must withstand hail impact
• Temperature extremes: Must tolerate rapid temperature �luctuations and freeze-thaw cycles
C. FABRIC AND MATERIAL REQUIREMENTS
• Structure fabric shall be rated for a 20+ year lifespan
• Color: Desert tan or similar solid neutral color
• Fabric must be UV-resistant, mildew-resistant, and engineered for long-term outdoor exposure
• All metal components shall be corrosion-resistant and suitable for cold-weather environments
D. ANCHORING AND SITE ADAPTATION
• Structure shall be site-adapted to the existing concrete pad
• Anchoring system must be engineered for the pad’s thickness, strength, and condition
• Contractor shall verify pad suitability and propose corrective measures if required
ACCESS AND EGRESS REQUIREMENTS
A. FABRIC ACCESS DOORS
• Vertical accordion-style fabric doors shall be installed on both sidewalls and end walls
• Doors must provide 12 feet (minimum) of overhead clearance when fully open
• Doors must be operable manually by a single individual
• Door design must prevent binding or failure in cold weather
B. RIGID MAN DOORS
• Rigid personnel doors shall be installed adjacent to fabric access doors
• Placement must allow ingress/egress without opening the large fabric doors
• Doors must meet applicable safety, �ire, and egress requirements
INSTALLATION REQUIREMENTS
• Contractor shall verify all dimensions prior to fabrication
• Installation shall occur within the fenced area designated by the government
• Contractor shall provide all equipment necessary for safe installation in winter conditions
• All work shall comply with applicable federal, state, and local codes, including UFC and IBC standards
DELIVERABLES
• Engineered structural drawings
• Fabrication drawings and material speci�ications
• Snow load and wind load certi�ication
• Anchoring plan
• Warranty documentation
• Operations and maintenance manuals
WARRANTY
The contractor shall provide a minimum 20-year fabric warranty and a minimum 10-year structural warranty covering defects in materials, workmanship, and environmental performance.
GOVERNMENT RESPONSIBILITIES
• Provide access to the fenced installation area
• Provide any existing site drawings or pad speci�ications
• Coordinate installation schedule with base operations
ACCEPTANCE CRITERIA
The Government will inspect the completed structure to verify:
• Compliance with all dimensional, structural, and environmental requirements
• Proper anchoring and tensioning
• Smooth operation of all fabric and rigid doors
• Absence of defects, damage, or installation de�iciencies
• Items not meeting requirements will be corrected or replaced at no additional cost.
All questions regarding this Statement of Work shall be directed to the Volk Field Contracting Of�ice at WI.CRTC.VF.Contracting@us.af.mil mailto:WI.CRTC.VF.Contracting@us.af.mil