Statement of Work.pdf

PDF 277 KB Posted

Attached to
Construct Main Gate Canopy
Solicitation number
W50S8D26QA011
Issued by

About this file

This is a Statement of Work (SOW) for construction of a permanent overhead canopy structure at the 105th Airlift Wing Main Gate Entry Control Point in Newburgh, New York. The project, designated WHAY202001, has a Period of Performance of 180 calendar days and requires the contractor to furnish all personnel, equipment, tools, materials, supervision, and quality control necessary to complete the work. The contractor must perform three primary construction tasks: (1) construct an overhead protection structure (canopy) including excavation and concrete foundations, structural steel installation, metal roofing system, gutters, downspouts, and all electrical work with lighting fixtures connected to a designated power source; (2) perform modifications to existing perimeter fencing including demolition of fence sections, installation of new posts, fabric and gates to establish the new Entry Control Point configuration; and (3) complete civil site work including saw-cutting and removal of existing asphalt and concrete curbs, grading and compaction of sub-base, formation and pouring of new concrete curbs, placement of new asphalt paving, and application of pavement markings. All work must comply with Project WHAY202001 design drawings and specifications dated 20 APR 2023.

Work shall be performed during normal duty hours (0700-1600 Monday through Friday, excluding federal holidays) at Stewart Air National Guard Base, with all on-site activities coordinated through the Contracting Officer's Representative. The contractor must submit a comprehensive Phasing and Traffic Control Plan prior to mobilization to ensure the Main Gate Entry Control Point remains operational throughout construction. Additional requirements include obtaining background checks for all personnel requiring base access, maintaining adequate workforce for uninterrupted performance, confining all operations to COR-designated areas, providing required material and equipment submittals for Government approval, coordinating utility outages at least 14 calendar days in advance, and upon completion removing all temporary facilities and debris while submitting "As-Built" drawings in PDF and CAD formats and all manufacturer warranties and Operation & Maintenance manuals as part of project closeout.

View the file

Other files

File Type Posted
IMG_0326.jpg JPG image
SF 30 Solicitation Amendment W50S8D26QA011_0002.pdf PDF
SF 1442 - W50S8D26QA011_0002.pdf PDF
IMG_0325.jpg JPG image
RFI 2.pdf PDF
IMG_0327.jpg JPG image
Combined Drawing List - RFI_8 Revision C-102_C-501.pdf PDF
RFI 1.pdf PDF
Pre-Proposal Conference Minutes.pdf PDF
Pre-Proposal Conference Attendance Sheet.pdf PDF
Project Specifications.pdf PDF
SF 30 Solicitation Amendment W50S8D26QA011_0001.pdf PDF
SF 1442 - W50S8D26QA011_0001.pdf PDF
Wage Determination.pdf PDF
SF 1442 - W50S8D26QA011.pdf PDF
Supplemental Drawings.pdf PDF
Combined Drawing List.pdf PDF
Wage Determination.pdf PDF
Show all 18

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CUI

DEPARTMENT OF THE AIR FORCE

105th AIRLIFT WING (ANG)

ONE MAGUIRE WAY

NEWBURGH NY 12550-5075

STATEMENT OF WORK (SOW)

FOR

WHAY202001 – Main Gate Overhang

1.0 General:

1.1 Scope:

The contractor shall provide all personnel, equipment, tools, materials, supervision, and quality control necessary, except as specified in Paragraph 3.0 as Government Furnished, to perform work as defined in this PWS.

1.2 Background:

The 105th Airlift Wing Main Gate Entry Control Point (ECP) requires a permanent, all-weather overhead canopy to provide protection for Security Forces personnel during daily operations. This project will enhance security, safety, and operational effectiveness at the installation’s primary access point.

1.3 Period of Performance (PoP):

The Period of Performance shall be 180 calendar days.

1.4 General Information:

1.4.1 Quality Control (QC):

The contractor shall develop and maintain an effective QC Plan (QCP) to ensure services are performed in accordance with this PWS. The contractor shall develop and implement procedures to identify, prevent, and ensure non-recurrence of defective services. The contractor’s QCP is the means by which it assures itself that its work complies with the requirements of the contract.

1.4.2 Recognized Holidays:

The following are recognized US holidays. The contractor shall coordinate with the 105th Airlift Wing in advance if work will be planned on these days:

1.4.2.1 New Year’s Day: January 1st

1.4.2.2 Martin Luther King, Jr.’s Birthday

1.4.2.3 President’s Day

1.4.2.4 Memorial Day

1.4.2.5 Juneteenth: June 19th

1.4.2.6 Independence Day: July 4th

1.4.2.7 Labor Day

1.4.2.8 Columbus Day

1.4.2.9 Veteran’s Day: November 11th

1.4.2.10 Thanksgiving Day

1.4.2.11 Christmas Day

1.4.3 Place and Performance of Services:

Performance shall be at the 105th Airlift Wing, Stewart Air National Guard Base, Newburgh, NY. The contractor shall at all times maintain an adequate work force for the uninterrupted performance of all tasks defined within this PWS when the Government facility/installation is not closed for the above reasons. When hiring personnel, the contractor shall keep in mind that the stability and continuity of the work force are essential.

1.4.3.1 Unscheduled gate closures by the 105th Base Defense Squadron may occur at any time causing all personnel entering or exiting a closed installation to experience a delay.

This cannot be predicted or prevented. Contractors are not compensated for unexpected closures or delays. Vehicles operated by contractor personnel are subject to search pursuant to applicable regulations. Any moving violation of any applicable motor vehicle regulation may result in the termination of the contractor employee’s installation driving privileges.

1.4.3.2 The contractor’s employees shall become familiar with and obey the regulations of the installation; including fire, traffic, safety and security regulations while on the installation. Contractor employees should only enter restricted areas when required to do so and only upon prior approval. All contractor employees shall carry proper identification with them at all times. The contractor shall ensure compliance with all regulations and orders of the installation which may affect performance.

1.4.4 Security Requirements.

The contractor shall comply with all applicable installation/facility access and local security policies and procedures, which may be obtained from the Contracting Officer. The contractor shall also provide all information required for background checks to meet installation access requirements to be accomplished by installation 105th Base Defense Squadron. The contractor shall ensure compliance with all personal identity verification requirements as directed by DOD, HQDA and/or local policy. Should the Force Protection Condition (FPCON) change, the Government may require changes in contractor security matters or processes.

The base access procedures require the contractor, their employees, and subcontractors to submit a background check from the State of Residence of each individual who will need to be granted access to the base. If there are arrests and/or convictions, issuance of the badge is solely up to the discretion of the 105th Base Defense Squadron Command.

1.4.5 Special Qualifications:

The contractor shall ensure all employees possess all required licenses for operating the contractor supplied equipment including its proper implementation with the government’s equipment for successful performance of this contract.

1.4.6 Post Award Conference/Periodic Progress Meetings:

The contractor agrees to attend any post award conference convened by the KO in accordance with Federal Acquisition Regulations Subpart 42.5. The KO and other Government personnel, as appropriate, may meet periodically with the contractor to review the contactor’s performance. At these meetings, the Contacting Officer will apprise the contractor of how the Government views the contractor’s performance and the contractor shall apprise the Government of problems, if any, being experienced. The contractor shall resolve outstanding issues raised by the Government. Contractor attendance at these meetings shall be at no additional cost to the Government.

1.4.7 Contract Manager (CM):

The contactor shall designate a CM who shall ensure performance under this contract. The name of this person, and an alternate who shall act for the contractor when the CM is absent, shall be designated in writing to the KO. The CM or alternate shall have full authority to act for the contractor on all contract matters relating to daily operation of this contract. The CM shall work through the COR, (or the KO if a COR is not assigned), to resolve issues, receive technical instructions, and ensure adequate performance of services. The CM shall ensure that contractor employees do not perform any services outside the scope of the contract without an official modification issued by the KO. The CM shall ensure contractor employees understand that services performed outside the scope of the contract are performed wholly at the expense of the contractor.

1.4.8 Identification of Contractor Employees:

All contractor personnel attending meetings, answering Government telephones and working in other situations where their contractor status is not obvious to third parties are required to identify themselves as such to avoid creating an impression that they are Government employees. The contractor shall ensure that all documents or reports produced by contractor personnel are suitably marked as contractor products or that contractor participation is appropriately disclosed. The contractor’s status as a “contractor” shall be predominantly displayed in all correspondence types (to include signature blocks on e-mail) and dealings with Government or non-Government entities/ Contractor personnel shall wear identification badges distinguishing themselves as such. The badges shall have the company name, employee name and the word “contractor” displayed. The contractor shall retrieve all identification media (including vehicle passes) from their employees who depart employment for any reason. All identification media (i.e., badges and vehicles passes) shall be returned to the KO within 14 days of an employee’s departure.

1.4.9. Combating Trafficking in Persons:

The United States Government has adopted a zero tolerance policy regarding trafficking in persons. Contractors and contractor employees shall not engage in severe forms of trafficking in persons during the period of performance of the contract; procure commercial sex acts during the period of performance of the contract; or use forced labor in the performance of the contract. The Contractor shall notify its employees of the United States Government’s zero tolerance policy, the actions that will be taken against employees for violations of this policy. Such actions may include, but are not limited to, removal from the contract, reduction in benefits, or termination of employment. The contractor shall take appropriate action, up to and including termination, against employees or subcontractors that violate the US Government policy as described at RFO FAR 22.17.

1.4.10 Organizational Conflicts of Interest (OCI):

The contractor and subcontractor personnel performing services under this contract may receive, have access to or participate in the development of proprietary or source selection information (e.g., cost or pricing information, budget information or analyses, specifications or work statements, etc.) or perform evaluation services which may create a current or subsequent OCIs, as defined in RFO FAR Subpart 9.5. The contractor shall notify the KO immediately whenever it becomes aware that such access or participation may result in any actual or potential OCI and shall promptly submit a plan to the KO to avoid or mitigate any such OCI. The contractor’s mitigation plan will be determined to be acceptable solely at the discretion of the KO and in the event the KO unilaterally determines that any such OCI cannot be satisfactorily avoided or mitigated, the KO may affect other remedies as he or she deems necessary, including prohibiting the contractor from participation in subsequent contracted requirements which may be affected by the OCI.

1.4.11 Safety Requirements:

The contractor shall comply with all Occupational Safety and Health Act (OSHA), federal, state, and local laws, regulations, and requirements regarding safety, as applicable to the services provided under this contract. In the event safety laws or regulations change during the term of this contract, the contractor is required to comply as such laws come into effect.

2.0 Definitions and Acronyms:

2.1.1 CONTRACTOR. A supplier or vendor awarded a contract to provide specific supplies or service to the government. The term used in this contract refers to the prime.

2.1.2 CONTRACTING OFFICER (KO). A person with authority to enter into, administer, and or terminate contracts, and make related determinations and findings on behalf of the government. Note: The only individual who can legally bind the government.

2.1.3 CONTRACTING OFFICER'S REPRESENTATIVE (COR). An employee of the U.S.

Government designated by the KO to monitor contractor performance. Such appointment shall be in writing and shall state the scope of authority and limitations. This individual has authority to provide technical direction to the Contractor as long as that direction is within the scope of the contract, does not constitute a change, and has no funding implications. This individual does NOT have authority to change the terms and conditions of the contract.

2.1.4 DEFECTIVE SERVICE. A service output that does not meet the standard of performance associated with the Performance Work Statement.

2.1.5 DELIVERABLE. Anything that can be physically delivered and includes non-manufactured things such as meeting minutes or reports.

2.1.6 KEY PERSONNEL. Contractor personnel that are evaluated in a source selection process and that may be required to be used in the performance of a contract by the Key Personnel listed in the PWS. When key personnel are used as an evaluation factor in best value procurement, an offer can be rejected if it does not have a firm commitment from the persons that are listed in the proposal.

2.1.7 PHYSICAL SECURITY. Actions that prevent the loss or damage of Government property.

2.1.8 QUALITY ASSURANCE. The government procedures to verify that services being performed by the Contractor are performed according to acceptable standards.

2.1.9 QUALITY ASSURANCE SURVEILLANCE PLAN (QASP). An organized written document specifying the surveillance methodology to be used for surveillance of contractor performance.

2.1.10 QUALITY CONTROL. All necessary measures taken by the Contractor to assure that the quality of an end product or service shall meet contract requirements.

2.1.11 SUBCONTRACTOR. One that enters into a contract with a prime contractor. The Government does not have privity of contract with the subcontractor.

2.1.12 WORK DAY. The number of hours per day the Contractor provides services in accordance with the contract.

2.1.13 WORK WEEK. Monday through Friday, unless specified otherwise.

2.2 ACRONYMS:

AFARS - Army Federal Acquisition Regulation Supplement

IS - Information System(s)

AR - Army Regulation KO - Contracting Officer AT/OPSEC - Antiterrorism/Operational Security

OCI - Organizational Conflict of Interest

CFR - Code of Federal Regulations ODC - Other Direct Costs CONUS - Continental United States (excludes Alaska and Hawaii)

PII - Personally Identifiable Information

COR - Contracting Officer Representative PIPO - Phase In/Phase Out COTS - Commercial-Off-the-Shelf POC - Point of Contact DA - Department of the Army PRS - Performance Requirements Summary DD250 - Department of Defense Form 250 (Receiving Report)

PWS - Performance Work Statement

DD254 - Department of Defense Contract Security Requirement List

QA - Quality Assurance

DFARS - Defense Federal Acquisition Regulation Supplement

QAP - Quality Assurance Program

DOD - Department of Defense QASP - Quality Assurance Surveillance Plan FAR - Federal Acquisition Regulation QC - Quality Control GFP/M/E/S - Government Furnished Property/Material/Equipment/Services

QCP - Quality Control Program

IA - Information Assurance TE - Technical Exhibit

3.0 Government Furnished Property, Material, Equipment and Services

(GFP/M/E/S):

NONE

4.0 Contractor Furnished Property, Materials, and Equipment (CFP/M/E):

4.1 General:

Except for those items specifically stated to be Government-Furnished in Paragraph 3.0, the contractor shall furnish everything required to perform these services as indicated in Paragraph 1.1.

5.0 Requirement: The Contractor Shall perform the following:

5.1 Overhead Protection Structure (Canopy): The Contractor shall furnish all labor, materials, and equipment to construct the overhead canopy structure. This includes, but is not limited to, excavation and construction of concrete foundations and footings; installation of all structural steel members; installation of the metal roofing system, gutters, and downspouts; installation of all associated electrical work, including conduit, wiring, and lighting fixtures, and final connection to the designated power source. All work shall be in strict accordance with the project design drawings and specifications (Project WHAY202001, Main Gate Overhang, 100% B3 Submittal, dated 20 APR 2023).

5.2 Fence Modifications: The Contractor shall furnish all labor, materials, and equipment to perform modifications to the existing perimeter fencing. This includes careful demolition and removal of existing fence sections as indicated on the drawings; installation of new fence posts, fabric, and gates to establish the new ECP configuration; and ensuring all new fencing securely ties into the existing fence line, maintaining the integrity of the perimeter.

5.3 Curb Realignment and Associated Site Work: The Contractor shall furnish all labor, materials, and equipment to perform all required civil site work. This includes saw-cutting and removal of existing asphalt and concrete curbs; grading and compaction of the sub-base; formation and pouring of new concrete curbs; placement and compaction of new asphalt paving; and application of all new pavement markings (striping) to safely direct traffic flow as per the design drawings.

MISCELLANEOUS

• Work Hours: All on-site work shall be performed during normal duty hours, 0700-1600 Monday through Friday, excluding federal holidays. Work outside of these hours requires written approval from the Contracting Officer (CO) at least 48 hours in advance.

• Coordination and Site Access: The Contractor shall coordinate all on-site activities with the designated Contracting Officer’s Representative (COR). All contractor personnel shall comply with installation access requirements as directed by the 105th Security Forces Squadron. A list of all personnel requiring access shall be submitted to the COR at least 10 business days prior to the start of work.

• Traffic Control Plan: The Main Gate Entry Control Point (ECP) must remain operational for official and privately owned vehicles at all times during the Period of Performance. Prior to mobilization, the Contractor shall submit a comprehensive Phasing and Traffic Control Plan to the CO/COR for approval. This plan must detail how vehicle traffic will be safely routed around the construction area at all phases of the project.

• Staging and Storage: The Contractor shall confine all operations, including storage of materials and staging of equipment, to an area designated by the COR. The worksite shall be kept in a clean and orderly condition at all times.

• Submittals: The Contractor shall provide all required material and equipment submittals for Government approval prior to ordering or installing any materials.

• Utility Outages: The Contractor shall coordinate any required utility outages (specifically for electrical tie-in) with the COR at least 14 calendar days in advance to ensure minimal disruption to base operations.

• Project Closeout: Upon completion of all construction activities, the Contractor shall remove all temporary facilities, equipment, and debris from the site. The Contractor shall submit one complete set of "As-Built" drawings in both PDF and CAD format to the COR. All manufacturer warranties and Operation & Maintenance (O&M) manuals for installed equipment shall be delivered as part of the closeout package.