BASE O/E RPR/INST CHAIN-LINK FENCE
USACE / NAVFAC / AFCESA / NASA UFGS-01 11 00 (April 2006) Preparing Activity: NAVFAC Replacing without change UFGS-01110 (January 2006)
UNIFIED FACILITIES GUIDE SPECIFICATIONS
Latest change indicated by CHG tags
SECTION 01026
STATEMENT OF WORK
NOTE: This guide specification covers the requirements for a description of work covered in this contract and is required for use in all projects.
Comments and suggestions on this guide specification are welcome and should be directed to the technical proponent of the specification. A listing of technical proponents, including their organization designation and telephone number, is on the Internet.
Recommended changes to a UFGS should be submitted as a Criteria Change Request (CCR).
Use of electronic communication is encouraged.
This guide specification includes tailoring options for EFD and EFA regional requirements. Selection or deselection of a tailoring option will include or exclude that option in the section, but editing the resulting section to fit the project is still required.
Brackets are used in the text to indicate designer choices or locations where text must be supplied by the designer.
NOTE: When using this section, a Project Information Form should be filled out for the Contract Specialist. This form is available from the Construction Criteria Base website at http://www.ccb.org. The form is found in the Specification Library, NAVFAC Specifications Category, Project Information Form. For SOUTHNAVFANCENGCOM projects, do not use this Project Information Form.
NOTE: Include on the drawing:
1. Location of project.
2. Limits of contractor's work area.
3. Location of Government-furnished work.
4. Location of Government installed work.
5. Contractor's on-base route to site.
NOTE: See "FAC 5252.211-9301, Phased Construction Schedule."
PART 1 GENERAL
1.1 REFERENCES
NOTE: This paragraph is used to list the publications cited in the text of the guide specification. The publications are referred to in the text by basic designation only and listed in this paragraph by organization, designation, date, and title.
Use the Reference Wizard's Check Reference feature when you add a RID outside of the Section's Reference Article to automatically place the reference in the Reference Article. Also use the Reference Wizard's Check Reference feature to update the issue dates.
References not used in the text will automatically be deleted from this section of the project specification when you choose to reconcile references in the publish print process.
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
No references this section.
1.2 WORK COVERED BY CONTRACT DOCUMENTS
1.2.1 Project Description
NOTE: Describe the project and the types of work involved in sufficient detail so as to present a general picture which is self contained but does not refer to the drawings or to other parts of the specification. Mention peculiar or hazardous work, and monitoring of archaeological resources. Do not provide quantities in the description.
Furnish all labor, equipment, materials, and all incidental related services to perform replacement of Repairs/Installation of Chain-link Fencing and related work at Various Army Installations, on the Island of Oahu, Hawaii in accordance with the technical provisions prepared by the Directorate of Public Works, U.S. Army Garrison, Hawaii. Fence installation shall conform to UFC 4-022-03 Security Fences and Gates and FE-7 Chain Link Security Fence Details. The scope of work includes by this contract does not cover Fence Posts, Chain-Link Fencing or Chain-Link Fence related work which might arise as part of the contract to repair or renovate a building or group of buildings. The work covered by this contract does not include projects awarded by The U.S. Army Engineering District, Honolulu, excluding the Medical Facilities under Tripler (TAMC), to be designated during the contract period.
1.3 ESTIMATED QUANTITIES
The estimated quantities of work, indicated herein, are for information of
The prospective Contractors. The actual quantities ordered may be more or
Less than the estimated quantities.
1.4 LOCATIONS
NOTE: Include station name and geographic location in the blank provided.
The location of work sites shall be as follows:
Fort Shafter Area
Fort Shafter Fort DeRussy Tripler Army Medical Center Aliamanu Military Reservation Schofield Barracks Area
Schofield Barracks (includes East Range & Leilehua Golf Course, Wheeler Army Airfield, and Helemano Military Reservation The exact locations will be shown by the Contracting Officer.
1.5 ITEMS OF WORK
See Contract Schedule.
1.6 EXISTING WORK
In addition to "FAR 52.236-9, Protection of Existing Structures, Equipment, Utilities, and Improvements":
a. Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.
b. Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work shall be in a condition equal to or better than that which existed before new work started.