Specs_Underground Utilities and Stormwater Improvements-05-26-2020.pdf
PDF 2 MB Posted
- Attached to
- Combined Underground Utilities and Storm Water Improvements, Moore Air Base, Edinburg, Texas
- Solicitation number
- 12639522R0041
About this file
This is a solicitation for combined underground utilities and storm water improvements at Moore Air Base in Edinburg, Texas. The solicitation seeks bids for construction services including removal of existing structures and pavement, clearing and grubbing, excavation, grading, utility trenching, pipe laying, reinforced concrete work, seeding, and site finishing. Responses are due by [date redacted], with work to be completed by [date redacted]. The selected contractor will be responsible for erosion and sediment controls throughout construction.
View the file
Other files
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
©Stanley Consultants, Inc. 2020
Project Manual for
USDA-APHIS-PPQ
Moore Air Base Underground Utilities and Stormwater Improvements USDA Contract No: AG-6395-C-16-0119
Edinburg, Texas
Issued for Bidding May 2020
00 01 02.doc
Project Manual for
USDA-APHIS-PPQ
Moore Air Base Underground Utilities and Stormwater Improvements USDA Contract No: AG-6395-C-16-0119
Edinburg, Texas
5/26/2020
Texas Registration #136708 License Exp. Date: 09-30-2020 Texas Firm Registration No. F-174
Texas Registration #102678 License Exp Date: 12-31-2020 Texas Firm Registration No. F-174
Texas Registration #130984 License Exp. Date: 03-31-2021 Texas Firm Registration No. F-174
Texas Registration #116530 License Exp. Date: 12-31-2020 Texas Firm Registration No. F-174
Texas Registration #134005 License Exp. Date: 03-31-2021 Texas Firm Registration No. F-174
27100.13.00 TABLE OF CONTENTS
ms1952 SECTION 00 01 10 - Page 1
USDA-APHIS-PPQ
MOORE AIR BASE
UNDERGROUND UTILITIES AND STORMWATER IMPROVEMENTS
USDA CONTRACT NO: AG-6395-C-16-0119
EDINBURG, TEXAS
PROCUREMENT AND CONTRACTING REQUIREMENTS GROUP
Resp.
Charge Section Title Page
DIVISION 00 PROCUREMENT AND CONTRACTING REQUIREMENTS
JJM 00 01 15 Drawing List 1 thru 3
SPECIFICATIONS GROUP
GENERAL REQUIREMENTS SUBGROUP
Resp.
Charge Section Title Page
DIVISION 01 GENERAL REQUIREMENTS
JJM 01 11 00 Summary of Work 1 thru 2 JJM 01 20 00 Price and Payment Procedures 1 thru 2 Request for Information 1 JJM 01 25 13 Product Substitution Procedures 1 thru 2 Product Substitution Request Form 1 JJM 01 30 00 Administrative Requirements 1 thru 3 JJM 01 33 00 Submittal Procedures 1 thru 7 Submittal Transmittal 1 JJM 01 40 00 Quality Requirements 1 thru 4 JJM 01 41 00 Regulatory Requirements 1 JJM 01 45 33-13 Stormwater Pollution Prevention Plan 1 thru 6 JJM Operator Certification Stormwater Pollution Prevention Plan 1 JJM Inspection Form 1 JJM 01 50 00 Temporary Facilities and Controls 1 thru 4 JJM 01 60 00 Product Requirements 1 thru 3 LJL 01 64 13 Filter System Installation 1 JJM 01 70 00 Execution and Closeout Requirements 1 thru 2 JJM 01 77 00 Closeout Requirements 1 thru 2 JJM 01 78 00 Closeout Submittals 1 thru 2
SPECIFICATIONS GROUP
FACILITY CONSTRUCTION SUBGROUP
DIVISION 02 EXISTING CONDITIONS
JJM 02 41 00 Demolition 1 to 4
DIVISION 03 CONCRETE
JWW 03 10 00 Concrete Forming and Accessories 1 to 4 JWW 03 30 00 Cast-In-Place Concrete 1 to 15
DIVISION 05 METALS
JWW 05 10 00 Structural Metal Framing 1 to 6 JWW 05 50 00 Metal Fabrications 1 to 3
TABLE OF CONTENTS 27100.13.00
Page 2 - SECTION 00 01 10 ms1952
Resp.
Charge Section Title Page
FACILITY SERVICES SUBGROUP
DIVISION 22 PLUMBING
LJL 22 12 23-31 Hydropneumatic Pressure System 1 to 2
DIVISION 26 ELECTRICAL
EEL 26 05 00 Common Work Results for Electrical 1 to 21 EEL 26 05 33 Above-Grade Raceway 1 to 7 EEL 26 05 43 Below-Grade Raceway 1 to 8
SITE AND INFRASTRUCTURE SUBGROUP
DIVISION 31 EARTHWORK
JJM 31 05 19-13 Geotextiles for Earthwork 1 to 2 JJM 31 10 00 Site Clearing 1 JJM 31 23 00 Excavation and Fill 1 to 13
DIVISION 32 EXTERIOR IMPROVEMENTS
JJM 32 11 23 Aggregate Base Courses 1 JJM 32 12 16 Asphaltic Paving 1 to 4 JJM 32 13 13 Concrete Paving 1 to 5 JJM 32 15 00 Aggregate Surfacing 1 to 2 JJM 32 16 23 Sidewalks 1 to 2 JJM 32 92 19 Seeding 1 to 5
DIVISION 33 UTILITIES
JJM 33 05 16-13 Precast Concrete Utility Structures 1 to 4 LJL 33 11 00 Water Utility Distribution Piping 1 to 8 LJL 33 30 00 Sanitary Sewerage Utilities 1 to 13 JJM 33 42 00 Culverts 1 to 3
PROCESS EQUIPMENT SUBGROUP
DIVISION 40 PROCESS INTEGRATION
DDE 40 05 00 Common Work Results for Process Systems 1 to 7 DDE 40 91 00 Primary Process Measuring Devices 1 to 8 DDE 40 91 00-19 Sample Calibration Report 1 Transmitter Calibration 1 Contact Closure/Switch 1 Valves 1 Loop Calibration 1 General Analog Device, Type 1 DDE 40 95 13 Process Control Panels and Hardware 1 to 11 DDE 40 96 15 Control System Operational Description 1 to 3
DIVISION 43 PROCESS GAS AND LIQUID HANDLING, PURIFICATION AND STORAGE EQUIPMENT
LJL 43 21 13 Centrifugal Water Pump 1 to 6
27100.13.00 DRAWING LIST
ms1952 SECTION 00 01 15 - Page 1
Drawing No.
Title Rev.
No.
GENERAL
GG01 COVER SHEET 0
GG02 INDEX SHEET 0
GG03 GENERAL LEGEND, NOTES 0
GG04 ELECTRICAL LEGEND 0
GG05 ABBREVIATIONS 0
GG06 NOT USED
GG07 SWPPP AND REMOVALS KEY MAP 0
GG08 SWPPP AND REMOVALS -SHEET 1 0
GG09 SWPPP AND REMOVALS -SHEET 2 0
GG10 SWPPP AND REMOVALS -SHEET 3 0
GG11 SWPPP AND REMOVALS -SHEET 4 0
GG12 SWPPP AND REMOVALS -SHEET 5 0
GG13 SWPPP AND REMOVALS -SHEET 6 0
GG14 SITE ACCESS PLAN -SHEET 1 0
GG15 SITE ACCESS PLAN -SHEET 2 0
GG16 TXDOT STANDARD DETAILS -SHEET 1 0
GG17 TXDOT STANDARD DETAILS -SHEET 2 0
GG18 TXDOT STANDARD DETAILS -SHEET 3 0
GG19 TXDOT STANDARD DETAILS -SHEET 4 0
GG20 TXDOT STANDARD DETAILS -SHEET 5 0
GG21 TXDOT STANDARD DETAILS -SHEET 6 0
GG22 TXDOT STANDARD DETAILS -SHEET 7 0
GG23 CITY OF EDINBURG-STANDARD DETAILS 0
GG24 SANITARY SEWER DETAIL SHEET 0
GG25 SIDEWALK DETAIL SHEET 0
STORMWATER SHEETS
CU100 OVERALL SITE PLAN -STORMWATER KEY PLAN 0
CU101 STORMWATER PLAN -SHEET 1 0
CU102 STORMWATER PLAN -SHEET 2 0
CU103 STORMWATER PLAN -SHEET 3 0
CU104 STORMWATER PLAN -SHEET 4 0
CU105 STORMWATER PLAN -SHEET 5 0
CU106 STORMWATER PLAN -SHEET 6 0
CU107 MAIN DITCH PROFILE-STORMWATER-SHEET 1 0
CU108 MAIN DITCH PROFILE-STORMWATER-SHEET 2 0
CU109 MAIN DITCH PROFILE-STORMWATER-SHEET 3 0
CU110 DITCH PROFILES STORMWATER 0
CU111 STORMWATER - TYPICAL SECTIONS 0
CU112 STORMWATER - CIVIL DETAILS - SHEET 1 0
CU113 STORMWATER - CIVIL DETAILS - SHEET 2 0
CU114 STORMWATER - CIVIL DETAILS - SHEET 3 0
DRAWING LIST 27100.13.00
Page 2 - SECTION 00 01 15 ms1952
Title Rev.
No.
CU123 ALIGNMENT TABLES - SHEET 1 0
CU124 ALIGNMENT TABLES - SHEET 2 0
SANITARY SEWER SHEETS
CU200 EXISTING SANITARY SEWER-SERVICE TAPS & ABANDONMENTS-KEY PLAN 0
CU201 EXISTING SANITARY SEWER-SERVICE TAPS & ABANDONMENTS-SHEET 1 0
CU202 EXISTING SANITARY SEWER-SERVICE TAPS & ABANDONMENTS-SHEET 2 0
CU203 EXISTING SANITARY SEWER-SERVICE TAPS & ABANDONMENTS-SHEET 3 0
CU204 EXISTING SANITARY SEWER-SERVICE TAPS & ABANDONMENTS-SHEET 4 0
CU205 EXISTING SANITARY SEWER-SERVICE TAPS & ABANDONMENTS-SHEET 5 0
CU220 OVERALL SITE PLAN-SANITARY SEWER KEY PLAN 0
CU221 SANITARY SEWER PLAN & PROFILE-SHEET 1 0
CU222 SANITARY SEWER PLAN & PROFILE-SHEET 2 0
CU223 SANITARY SEWER PLAN & PROFILE-SHEET 3 0
CU224 SANITARY SEWER PLAN & PROFILE-SHEET 4 0
CU225 SANITARY SEWER PLAN & PROFILE-SHEET 5 0
CU226 SANITARY SEWER PLAN & PROFILE-SHEET 6 0
CU227 SANITARY SEWER PLAN & PROFILE-SHEET 7 0
CU228 SANITARY SEWER PLAN & PROFILE-SHEET 8 0
CU229 SANITARY SEWER PLAN & PROFILE-SHEET 9 0
CU230 SANITARY SEWER PLAN & PROFILE-SHEET 10 0
CU231 SANITARY SEWER PLAN & PROFILE-SHEET 11 0
CU232 SANITARY SEWER PLAN & PROFILE-SHEET 12 0
CU233 UTILITY CORRIDOR SECTIONS 0
ELECTRIC SHEETS
EP100 OVERALL SITE PLAN-ELECTRIC KEY PLAN 0
EP101 SITE ELECTRICAL PLAN-SHEET 1 0
EP102 SITE ELECTRICAL PLAN-SHEET 2 0
EP103 SITE ELECTRICAL PLAN-SHEET 3 0
EP104 SITE ELECTRICAL PLAN-SHEET 4 0
EP105 SITE ELECTRICAL PLAN-SHEET 5 0
EP106 SITE ELECTRICAL PLAN-SHEET 6 0
EP107 SITE ELECTRICAL PLAN-SHEET 7 0
EP107A SITE ELECTRICAL PLAN-SHEET 7A 0
EP107B SITE ELECTRICAL PLAN-SHEET 7B 0
EP108 SITE ELECTRICAL PLAN-SHEET 8 0
EP109 SITE ELECTRICAL PLAN-SHEET 9 0
EP109A SITE ELECTRICAL PLAN-SHEET 9A 0
EP110 SITE ELECTRICAL PLAN-SHEET 10 0
EP110A SITE ELECTRICAL PLAN-SHEET 10A 0
EP111 SITE ELECTRICAL PLAN-SHEET 11 0
EP112 SITE ELECTRICAL PLAN-SHEET 12 0
EP113 SITE ELECTRICAL PLAN-SHEET 13 0
27100.13.00 DRAWING LIST
ms1952 SECTION 00 01 15 - Page 3
Title Rev.
No.
EP114 SITE ELECTRICAL PLAN-SHEET 14 0
EP115 SITE ELECTRICAL PLAN-SHEET 15 0
EP116 SITE ELECTRICAL PLAN-SHEET 16 0
EP117 SITE ELECTRICAL PLAN-SHEET 17 0
EP118 SITE ELECTRICAL PLAN-SHEET 18 0
EU501 SITE ELECTRICAL DETAILS-SHEET 1 0
EU502 SITE ELECTRICAL DETAILS-SHEET 2 0
EU503 SITE ELECTRICAL DETAILS-SHEET 3 0
EU504 SITE ELECTRICAL DETAILS-SHEET 4 0
EU505 SITE ELECTRICAL DETAILS-SHEET 5 0
EU506 SITE ELECTRICAL DETAILS-SHEET 6 0
EO00 ELECTRICAL OVERALL-ONE-LINE DIAGRAM 0
EO01 COMMUNICATION OVERALL-ONE-LINE DIAGRAM 0
EO02 SITE ELECTRICAL PRIMARY-CABLE SCHEDULE - SHEET 1 0
EO03 SITE ELECTRICAL PRIMARY-CABLE SCHEDULE - SHEET 2 0
EO04 SITE ELECTRICAL SECONDARY-CABLE SCHEDULE 0
EO05 SITE ELECTRICAL-EXISTING TRANSFORMERS 0
EO06 SITE ELECTRICAL-NEW TRANSFORMER REQUIREMENTS 0
EO07 SITE ELECTRICAL-SECTIONALIZING CABINETS ANDPAD MOUNTED SWITCHES 0
EO08 SITE ELECTRICAL-NEW ELECTRICAL MANHOLES 0
EO09
SITE ELECTRICAL-COMMUNICATION CONDUIT AND-CABLE SCHEDULE - SHEET
1 0
EO10
SITE ELECTRICAL-COMMUNICATION CONDUIT AND-CABLE SCHEDULE - SHEET
2 0
IRRIGATION WATER SHEETS
PC01 RAW WATER IRRIGATION PLAN-SHEET 1 0
PC02 RAW WATER IRRIGATION PLAN-SHEET 2 0
PS01 RAW WATER IRRIGATION SYSTEM-STRUCTURAL NOTES 0
PS02
RAW WATER IRRIGATION SYSTEM-FOUNDATION AND SLAB PLAN AND
DETAILS 0
PS03 RAW WATER IRRIGATION SYSTEM-SUNSHADE ROOF PLAN AND DETAILS 0
PM01 RAW WATER IRRIGATION SYSTEM-MECHANICAL PLAN 0
PM02 RAW WATER IRRIGATION SYSTEM-MECHANICAL SECTIONS AND DETAILS 0
PE01 RAW WATER IRRIGATION SYSTEM-ELECTRICAL SCHEMATIC 0
PE01A RAW WATER IRRIGATION SYSTEM-PANEL LAYOUT 0
PE02 RAW WATER IRRIGATION SYSTEM-ELECTRICAL AND GROUNDING PLAN 0
PE03 RAW WATER IRRIGATION SYSTEM-ELECTRICAL DETAILS 0
PE04 RAW WATER IRRIGATION SYSTEM-PANEL SCHEDULE 0
PE06 ELECTRICAL COMMUNICATION-FIBER ROUTING 0
27100.13.00 SUMMARY OF WORK
ms1952 SECTION 01 11 00 - Page 1
PART 1 GENERAL
1.01 WORK COVERED BY CONTRACT DOCUMENTS
A. Work of this Agreement comprises the following general construction located on Moore Air Base in Edinburg, Texas for the United States Department of Agriculture (USDA) APHIS PPQ.
1. Stormwater conveyance improvements.
2. New gravity sanitary sewer system, building service reconnections, abandonment of existing sanitary sewer pipes and manholes, and site restoration.
3. New raw water system for irrigation purposes including installation of the Government-furnished filter. Furnish and installation of pumps, hydropneumatic bladder tank and associated piping, instrumentation and electrical work; sunshade and concrete slab; raw water distribution piping and reinstatement of service connections.
4. New electrical and communication infrastructure including:
a. Underground conduit system to include duct spacers, marking tape, pull cords, and above grade utility markers.
b. Cast in place or pre-cast electrical manholes and communication handholes at locations shown.
c. Quazite or Electrimold Box Pad per drawings for pad mounted electrical primary switches based on S&C PME – 9 compartmental switch per drawings. Height to top of box pad will vary based on water level. Where flooding may occur a concrete pad will be required with a box pad extension on top of pad.
d. Concrete pads for pad mounted transformers.
e. 4 way direct buried sectionalizing cabinets based on Hubbell per drawings.
f. Grounding at manholes.
5. Installation of a OS2 single mode 12 strand fiber optic cable in new ductbank system from existing elevated water storage tank to existing water treatment plant. At each end location provide fiber optic industrial closet housing with integral closet connector panels populated with 6 duplex LC termination and pigtails for fusion splicing. See drawings for cable designation COS2-EWT/WTP requirement and routing.
a. Programming integration of elevated water storage tank fiber optic I/O into existing water treatment plant control panel and SCADA system for indication.
1.02 AGREEMENT
A. Construct Work under single lump sum Agreement.
1.03 WORK SEQUENCE
A. Construct Work in stages to accommodate the Government's use of premises during construction period; coordinate construction schedule and operations with the Government's Representative.
Contractor shall propose work sequence, subject to review by the Government’s Representative.
1.04 CONTRACTOR USE OF PREMISES
A. Contractor shall have complete and exclusive use of premises within the construction limits, indicated on the drawings, for execution of work.
B. Coordinate use of premises under direction of the Government’s Representative. Contractor shall confine construction equipment, storage of materials and equipment and operations of workers to areas permitted by law, ordinances, permits, or requirements of Contract Documents, and shall not unreasonably encumber premises with construction equipment or other material or equipment.
C. Assume full responsibility for protection and safekeeping of items, under this Agreement, stored on Site.
D. Move any stored items, under Contractor's control, which interfere with operations of the Government or separate contractor.
SUMMARY OF WORK 27100.13.00
Page 2 - SECTION 01 11 00 ms1952
E. Do not block base parking areas or roadways unless designated on drawings or coordinated with the Government’s Representative at least 7 days in advance.
F. Obtain and pay for use of additional storage or Work areas needed for operations.
1.05 GOVERNMENT OCCUPANCY
A. The Government will occupy premises during entire period of construction for conduct of its normal operations. Cooperate with the Government's Representative in all construction operations to minimize conflict, and to facilitate the Government usage.
1. Maintain existing sanitary sewer and water distribution system in substantially continuous operation during construction, making and removing temporary connections as necessary.
2. Perform Work hazardous to operation of existing sanitary sewer and water distribution system or which will require interruption of service at times specifically approved by the Government.
PART 2 PRODUCTS
NOT USED
PART 3 EXECUTION
END OF SECTION
27100.13.00 PRICE AND PAYMENT PROCEDURES
ms1952 SECTION 01 20 00 - Page 1
1.01 SCHEDULE OF VALUES
A. Submit a printed schedule on Contractor's standard form or electronic media (Gantt format or similar).
B. Submit Schedule of Values in duplicate within 15 days after date of the Government-Contractor Agreement.
C. Include within each line item, a direct proportional amount of Contractor's overhead and profit.
D. Revise schedule to list approved Change Orders, with each Application for Payment.
1.02 APPLICATIONS FOR PAYMENT
A. Submit Contractor's electronic media driven form.
B. Content and format: Use Schedule of Values for listing items in Application for Payment.
C. Submit an updated construction schedule with each Application for Payment.
D. Payment period: Submit at intervals stipulated in Agreement.
E. Submit with transmittal letter as specified for Submittals in Section 01 33 00.
1.03 CHANGE PROCEDURES
A. Submittals: Submit name of individual authorized to receive change documents, and be responsible for informing others in Contractor's employ or Subcontractors of changes to Work.
B. Government’s Engineering Representative will advise of minor changes in Work not involving an adjustment to Contract Price or Contract Time by issuing supplemental instructions on Government’s Engineering Representative’s Instruction to Contractor (ITC) Form.
C. Contractor may propose changes by submitting a request for change to Government’s Engineering Representative, describing proposed change and its full effect on Work. Include a statement describing reason for change, and effect on Contract Price and Contract Time with full documentation and a statement describing effect on Work by separate or other contractors. Document any requested substitutions in accordance with Section 01 25 13. Requests for change received after 2:00 pm EST will be considered received the next business day for calculating suspense date. The Government requires a minimum of 14 days to review.
D. Stipulated price Change Order: Based on proposal request and Contractor's fixed price quotation or Contractor's request for a Change Order as approved by Government’s Engineering Representative.
E. Construction Change Directive: Government’s Engineering Representative may issue a directive, instructing Contractor to proceed with a change in Work, for subsequent inclusion in a Change Order.
Document will describe changes in Work, and designate method of determining any change in Contract Price or Contract Time. Promptly execute change.
F. Time and material Change Order: Submit itemized account and supporting data after completion of change, within time limits indicated in Conditions of Contract. Government’s Engineering Representative will determine change allowable in Contract Price and Contract Time as provided in Contract Documents.
G. Maintain detailed records of work done on time and material basis. Provide full information required for evaluation of proposed changes, and to substantiate costs for changes in Work.
PRICE AND PAYMENT PROCEDURES 27100.13.00
Page 2 - SECTION 01 20 00 ms1952
H. Document each quotation for a change in cost or time with sufficient data to allow evaluation of quotation.
I. Execution of Change Orders: Government’s Engineering Representative will issue Change Orders for signatures of parties as provided in Conditions of Contract.
J. Correlation of Contractor submittals:
1. Promptly revise Schedule of Values and Application for Payment forms to record each authorized
Change Order as a separate line item and adjust Contract Price.
2. Promptly revise progress schedules to reflect any change in Contract Time, revise sub-schedules to adjust times for other items of work affected by change, and resubmit.
3. Promptly enter changes in Project Record Documents.
1.04 REQUEST FOR INFORMATION
A. Questions regarding conflicts or intent of the Contract Documents shall be submitted by Contractor on attached Request for Information (RFI) form. RFIs received after 2:00 pm EST will be considered received the next business day for calculating suspense date. The Government requires a minimum of 14 days to review.
1.05 DEFECT ASSESSMENT
A. Replace Work, or portions of Work, not conforming to specified requirements.
B. If, in opinion of Government’s Engineering Representative, it is not practical to remove and replace Work, Government’s Engineering Representative will direct an appropriate remedy or adjust payment.
C. Authority of Government’s Engineering Representative to assess defect and identify payment adjustment, is final.
D. Nonpayment for rejected products: Payment will not be made for rejected products for any of following:
1. Products wasted or disposed of in a manner that is not acceptable.
2. Products determined as unacceptable before or after placement.
3. Products not completely unloaded from transporting vehicle.
4. Products placed beyond lines and levels of required Work.
5. Products remaining on hand after completion of Work.
6. Loading, hauling, and disposing of rejected products.
SC2656 R1 0503
REQUEST FOR INFORMATION
RFI No.:
Contract No.
and Name:
Date:
Contractor: Government:
Engineer:
Subject:
Drawing Reference: Spec Section:
Information Required (Be Specific):
Contractor Representative Date
Reply:
Engineer Representative Date
THIS IS NOT A CHANGE IN SCOPE AUTHORIZATION. IF, IN YOUR OPINION, THIS RESPONSE INVOLVES WORK WHICH CHANGES THE CONTRACT PRICE OR TIME, YOU MUST SUBMIT A PROPOSAL OR A NOTICE AS REQUIRED
IN THE CONTRACT DOCUMENTS.
27100.13.00 PRODUCT SUBSTITUTIONS PROCEDURES
ms1952 SECTION 01 25 13 - Page 1
1.01 SUBSTITUTIONS
A. For period of 30 days after effective date of Agreement, Government’s Engineering Representative will consider formal requests from Contractor for substitution of products in place of those specified.
After end of that period, requests will be considered only in case of product unavailability or other conditions beyond control of Contractor.
B. Submit request for substitution for consideration using attached Product Substitution Request Form.
Limit each request to one proposed Substitution. Support each request with:
1. Complete data substantiating compliance of proposed substitutions with requirements stated in
Contract Documents. Burden of proof is on proposer.
a. Product identification, including manufacturer's name and address.
b. Manufacturer's literature; identify:
1) Product description.
2) Reference standards.
3) Performance and test data.
c. Samples, as applicable.
d. Name and address of similar projects on which product has been used, and date of each installation.
2. Itemized comparison of proposed substitution with product specified; list significant variations.
3. Data relating to changes in construction schedule.
4. Any effect of substitution on separate contracts.
5. List of changes required in other work or products.
6. Accurate cost data comparing proposed substitution with product specified. Amount of any net change to Contract Price.
7. Designation of required license fees or royalties.
8. Designation of availability of maintenance services, sources, or replacement materials.
C. Substitutions will not be considered for acceptance when:
1. They are indicated or implied on Shop Drawings.
2. They are requested directly by Subcontractor or supplier.
3. Acceptance will require substantial revision of Contract Documents.
D. Substitute products shall not be ordered or installed without written notification from Government’s Engineering Representative of the Government's acceptance.
E. Government’s Engineering Representative will determine acceptability of proposed substitutions.
1.02 CONTRACTOR'S REPRESENTATION
A. In making formal request for substitution Contractor represents that:
1. It has investigated proposed product and has determined that it is equal to or superior in all respects to that specified.
2. It will provide same warranties or Bonds for substitution as for product specified or as required by the Government.
3. It will coordinate installation of accepted substitution into Work, and will make such changes as may be required for Work to be complete in all respects.
4. It waives claims for additional costs caused by substitution which may subsequently become apparent.
5. Cost data is complete and includes related costs under its Agreement, but not:
a. Costs under separate contracts.
b. Government’s Engineering Representative’s costs for redesign or revision of Contract Documents.
6. It will reimburse the Government for charges of Government’s Engineering Representative or Government’s Engineering Representative’s subconsultants for evaluating any proposed substitute, whether proposed substitute is accepted or rejected.
PRODUCT SUBSTITUTION PROCEDURES 27100.13.00
Page 2 - SECTION 01 25 13 ms1952
1.03 GOVERNMENT’S ENGINEERING REPRESENTATIVE DUTIES
A. Review Contractor's requests for substitution with reasonable promptness and advise the Government.
B. Notify Contractor in writing of the Government's decision to accept or reject requested substitution.
PRODUCT SUBSTITUTION REQUEST FORM
To:
Project:
Specified Item:
Section Page Paragraph Description
The undersigned request consideration of the following:
PROPOSED SUBSTITUTION
Attached data includes product description, specifications, drawings, photographs, performance, and test data adequate for evaluation of the request; applicable portions of the data are clearly identified.
Attached data also includes a description of changes to the Contract Documents that the proposed substitution will require for its proper installation.
The undersigned certifies that the following paragraphs, unless modified by attachments are correct:
1. The proposed substitution does not affect dimensions shown on Drawings.
2. The undersigned will pay for changes to the building design, including engineering design, detailing, and construction costs caused by the requested substitution.
3. The proposed substitution will have no adverse affect on other trades, the construction schedule, or specified warranty requirements.
4. Maintenance and service parts will be locally available for the proposed substitution.
The undersigned further states that the function, appearance, and quality of the proposed substitution are equivalent or superior to the specified item.
Submitted by:
Signature For use by Engineer/Architect
Firm � Approved � Approved as noted
Address � Not Approved � Received too late
By
Date Date
Telephone Remarks
Attachments
27100.13.00 ADMINISTRATIVE REQUIREMENTS
ms1952 SECTION 01 30 00 - Page 1
1.01 COORDINATION AND PROJECT CONDITIONS
A. Coordinate scheduling, submittals, and Work of the various sections of the Project Manual to ensure efficient and orderly sequence of installation of interdependent construction elements, with provisions for accommodating items installed later.
B. Verify utility requirements and characteristics of operating equipment are compatible with building utilities. Coordinate work of various sections having interdependent responsibilities for installing, connecting to, and placing in service, such equipment.
C. Coordinate completion and clean-up of Work of separate sections in preparation for Substantial Completion.
D. After the Government occupancy of premises, coordinate access to site for correction of defective Work and Work not in accordance with Contract Documents, to minimize disruption of the Government's activities.
1.02 PROJECT SITE ADMINISTRATION
A. Contractor shall provide competent, suitably qualified personnel to survey and lay out Work and perform construction as required by Contract Documents. Contractor shall at all times maintain good discipline and order at site.
B. Except in connection with safety or protection of persons or Work or property at site or adjacent thereto, and except as otherwise indicated in Contract Documents, all Work at site shall be performed during regular working hours, and Contractor shall not permit overtime work or performance of Work on Saturday, Sunday, or any legal holiday without the Government's written consent given after prior written notice to the Government’s Engineering Representative.
C. Incompetent or incorrigible employees shall be dismissed from Work by Contractor or its representative when requested by Government’s Engineering Representative or Contracting Officer's Representative, and such persons shall not again be permitted to return to Work without written consent of Government’s Engineering Representative.
D. Workmanship shall be of best quality.
1.03 FIELD ENGINEERING
A. Employ a Land Surveyor registered in the State of Texas and acceptable to the Government.
B. Contractor shall locate and protect survey control and reference points. Promptly notify Government’s Engineering Representative of any discrepancies discovered.
C. Control datum for survey is that shown on Drawings.
D. Verify set-backs and easements; confirm drawing dimensions and elevations.
E. Provide field engineering services. Establish elevations, lines, and levels, utilizing recognized engineering survey practices.
F. Submit a copy of site drawing and certificate signed by the Land Surveyor that the elevations and locations of the Work are in conformance with the Contract Documents.
G. Maintain a complete and accurate log of control and survey work as it progresses.
ADMINISTRATIVE REQUIREMENTS 27100.13.00
Page 2 - SECTION 01 30 00 ms1952
H. Protect survey control points prior to starting site work; preserve permanent reference points during construction.
I. Promptly report to the Government the loss or destruction of any reference point or relocation required because of changes in grades or other reasons.
J. Replace dislocated survey control points based on original survey control. Make no changes without prior written notice to Government’s Engineering Representative.
1.04 PROJECT MEETINGS
A. Representatives of Contractor, Subcontractors and suppliers attending meetings shall be qualified and authorized to act on behalf of entity each represents.
B. Preconstruction meeting:
1. The Government will schedule a meeting after 15 days after Notice to proceed.
2. Location: designated by the Government.
3. Attendance:
a. Governments representative.
b. Resident Project Representative.
c. Government’s Engineering Representative, as requested by the Government.
d. Contractor's superintendent.
e. Contractor’s Quality Control individual.
f. Contractor’s Safety individual.
g. Major Subcontractors.
h. Major suppliers.
i. Others as appropriate.
4. Agenda:
a. Execution of the Government-Contractor Agreement if not already complete.
b. Submission of executed bonds and insurance certificates.
c. Distribution of Contract Documents.
d. Submission of list of Subcontractors, list of products, schedule of values, and progress schedule.
e. Designation of personnel representing the parties in Contract.
f. Procedures and processing of field decisions, submittals, substitutions, applications for payments, proposal request, Change Orders, and Contract closeout procedures.
g. Scheduling.
h. The Government will prepare meeting agenda and Contractor shall record minutes and distribute copies within 2 days after meeting to participants, with copies to Government’s Engineering Representative, the Government, participants, and those affected by decisions made.
C. Site mobilization meeting:
1. The Government will schedule a meeting at the Project site prior to Contractor occupancy.
2. Attendance required: Government, Contractor, Contractor's Superintendent, Contractor’s Quality
Control and Safety individuals, and major Subcontractors.
3. Agenda:
a. Use of premises by the Government and Contractor.
b. Government's requirements.
c. Construction facilities and controls provided by the Government.
d. Temporary utilities provided by the Government.
e. Survey layout.
f. Security and housekeeping procedures.
g. Schedules.
h. Application for payment procedures.
i. Procedures for testing.
j. Procedures for maintaining record documents.
k. Requirements for start-up of equipment.
l. Inspection and acceptance of equipment put into service during construction period.
27100.13.00 ADMINISTRATIVE REQUIREMENTS
ms1952 SECTION 01 30 00 - Page 3
4. Contractor will record minutes and distribute copies within 2 days after meeting to participants, with copies to Government’s Engineering Representative, the Government, participants, and those affected by decisions made.
D. Progress meetings:
1. Schedule and administer meetings throughout progress of the Work at periodic intervals.
2. The Government will hold called meetings as required by progress of Work.
3. Location of meetings: Project field office of the Government.
4. Contractor will prepare agenda with copies for participants.
5. Attendance:
a. Government’s Engineering Representative, and its professional consultants as needed.
b. Contractor and Subcontractors as appropriate to agenda.
c. Suppliers as appropriate to agenda.
d. Others.
6. Suggested agenda:
a. Review, approval of minutes of previous meeting.
b. Review of Work progress since previous meeting.
c. Two week look back and two week look ahead.
d. Field observations, problems, conflicts.
e. Problems which impede construction schedule.
f. Review of off-site fabrication, delivery schedules.
g. Corrective measures and procedures to regain projected schedule.
h. Revisions to construction schedule.
i. Progress, schedule, during succeeding Work period.
j. Coordination of schedules.
k. Review submittal schedules; expedite as required.
l. Maintenance of quality standards.
m. Pending changes and substitutions.
n. Review proposed changes for:
1) Effect on construction schedule and on completion date.
2) Effect on other contracts of Project.
3) Other business.
7. Contractor will record minutes and distribute copies within 2 days after meeting to participants, with copies to Government’s Engineering Representative, the Government, participants, and those affected by decisions made.
PART 2 PRODUCTS
NOT USED
27100.13.00 SUBMITTAL PROCEDURES
ms1952 SECTION 01 33 00 - Page 1
1.01 SUBMITTAL PROCEDURES
A. Submit electronically when required by Specification Sections. Contact Government’s Engineering Consultant as listed below for submittal instructions.
1. Consulting Engineer
Mr. Jason Meyer Email: MeyerJason@stanleygroup.com Stanley Consultants, Inc.
5775 Wayzata Blvd., Ste 300 Minneapolis, Minnesota 55416-1235
2. Government’s Project Manager Mr. Fikru Taye Email: Fikru.Taye@usda.gov
USDA, APHIS, ASD, ESB
4700 River Road, Unit 115 (3A-03-41) Riverdale, MD 20737-1238
B. Submittals shall be in English language.
C. Weights, measures, and units shall be English units with SI metric values following in parenthesis.
D. Symbols and drawings shall conform to ANSI Y32.2/IEEE 315/CSA Z99.
1.02 CONTRACTOR RESPONSIBILITIES
A. Review submittals prior to submission.
B. Determine and verify:
1. Field measurements.
2. Field construction criteria.
3. Catalog numbers and similar data.
4. Conformance to Specifications.
C. Coordinate each submittal with other submittals and with requirements of Work and of Contract Documents.
D. Notify Government’s Engineering Consultant in writing, at time of submission, of any deviations in submittals from requirements of Contract Documents. Any such deviations permitted by Government’s Engineering Consultant will require modifications of Contract Documents.
E. Provide space on Shop Drawings for Contractor and Government’s Engineering Consultant stamps.
F. When Shop Drawings are revised for resubmission, identify all changes made since previous submission.
G. Submittals containing language imposing duties on others (such as verification of dimensions or supply of related information) inconsistent with contract language shall be null and void.
H. Submittals shall not be used as media for inquiries for information or for verification of information that must be supplied by others to Contractor. Inquiries or verification of information shall be made by separate Contractor submittal using Request for Information (RFI) process.
I. Begin no fabrication or Work which requires submittal review until return of submittals by Government’s Engineering Consultant with stamp, as either "Reviewed", “Reviewed as Noted", or “Reviewed as Noted-Resubmit.”
SUBMITTAL PROCEDURES 27100.13.00
Page 2 - SECTION 01 33 00 ms1952
J. Distribute copies of reviewed submittals that carry Government’s Engineering Consultant stamp as either "Reviewed" or "Reviewed as Noted" as appropriate. Instruct parties to promptly report any inability to comply with requirements.
K. Submittals not requested will not be recognized or processed.
1.03 GOVERNMENT’S ENGINEERING CONSULTANT DUTIES
A. Review required submittals with reasonable promptness and in accord with schedule, only for general conformance to design concept of Project and compliance with information given in Contract Documents. Review shall not extend to means, methods, sequences, techniques, or procedures of construction or to safety precautions or program incident thereto. Review of a separate item as such will not indicate approval of assembly in which item functions.
B. Affix stamp and initials or signature, and indicate requirements for resubmittal, or review of submittal.
Government’s Engineering Consultant’s action on submittals is classified as follows:
1. Reviewed: Submittal has been reviewed and appears to be in conformance to design concept of
Project and Contract Documents. Contractor may proceed with fabrication of work in submittal.
2. Reviewed As Noted: Submittal has been reviewed and appears to be in conformance to design concept of Project and Contract Documents, except as noted by reviewer. Contractor may proceed with fabrication of work in submittal with modifications and corrections as indicated by reviewer.
3. Reviewed As Noted-Resubmit: Submittal has been reviewed and appears to be in conformance to design concept of Project and Contract Documents, except as noted by reviewer. Contractor may proceed with fabrication of work in submittal with modifications and corrections as indicated by reviewer. Contractor shall make any corrections indicated by reviewer and resubmit for review.
4. Resubmit: Submittal has been reviewed and appears not to be in conformance to design concept of Project or with Contract Documents. Contractor shall not proceed with fabrication of work in submittal, but instead shall make any corrections required by reviewer and resubmit for review.
5. Returned without Review: Submittal is being returned without having been reviewed because: 1) not required by Contract Documents; 2) grossly incomplete; 3) indicates no attempt at conformance to Contract Documents; 4) cannot be reproduced; 5) lacks Contractor's completed approval stamp; or 6) lacks design professional's seal when required by law or Contract Documents. If submittal is required by Contract Documents, Contractor shall not proceed with Work as detailed in submittal, but instead shall correct defects and resubmit for review.
6. For Information Only: Submittal has not been reviewed but is being retained for informational purposes only.
7. Void: Submittal is voided because it is no longer required or has been superseded by another submittal.
C. Return one electronic copy of submittals to Contractor. Contractor shall make additional distribution as required.
D. Review of submittals shall not relieve Contractor from responsibility for any variation from Contract Documents unless Contractor has, in writing, called Government’s Engineering Consultant’s attention to such variation at time of submission, and Government’s Engineering Consultant’s has given written concurrence pursuant to Contract Documents to specific variation, nor shall any concurrence by Government’s Engineering Consultant or other reviewer relieve Contractor from responsibility for errors or omissions in submittals.
1.04 SHOP DRAWINGS SUBMITTALS
A. Submit for review for limited purpose of checking for conformance to information given and design concept expressed in Contract Documents. Produce copies and distribute in accordance with article “Submittal Procedures” and for record documents purposes as described in Section 01 70 00.
B. Designate in construction schedule, or in separate coordinated submittal schedule, dates for submission and dates that reviewed submittals will be needed.
ms1952 SECTION 01 33 00 - Page 3
C. Make submittals promptly in accordance with approved schedule, and in such sequence as to cause no delay in Work or in work of other contractors.
D. Present in clear and thorough manner, complete with respect to dimensions, design criteria, materials of construction, and like information to enable review of information as required.
E. Details shall be identified by reference to sheet and detail, schedule or room numbers shown on Drawings.
F. Indicate special utility and electrical characteristics, utility connection requirements, and location of utility outlets for service for functional equipment and appliances.
G. Equipment which is identified on Contract Documents with tag number or name shall be identified on Shop Drawing with same tag.
H. Schedule submittals to expedite Project. Coordinate submission of related items.
I. For each submittal for review, allow 14 days to complete review process. Submittals received after 2:00 pm EST will be considered received the next business day for calculating suspense date
J. Identify variations from Contract Documents and product or system limitations which may be detrimental to successful performance of completed Work.
K. Shop Drawings shall be submitted in electronic format.
1. Submit electronic copy to Government’s Engineering Consultant via E-mail or post in file-share site.
2. Submittal Transmittal form (see pdf attached) shall be provided for each submittal. MSWord template will be provided after award.
3. Text documents shall be submitted in .pdf format except for the shop drawing Transmittal Form.
4. Drawings shall be submitted in .pdf or .tif format.
5. Electronic submittal shall be suitable for reproduction in black and white.
L. Submittals shall contain:
1. Date of submission and dates of any previous submissions.
2. Project title and number.
3. Contract identification.
4. Names of:
a. Contractor.
b. Supplier.
c. Manufacturer.
5. Identification of product, with Specification section number and article number.
6. Field dimensions, clearly identified as such.
7. Relation to adjacent or critical features of Work or materials.
8. Applicable standards, such as ASTM or Federal Specification numbers.
9. Identification of deviations from Contract Documents.
10. Identification of revisions on resubmittals.
11. An 8" x 3" blank space for Contractor and reviewer stamps.
12. Indication of Contractor's approval, initialed or signed, with wording substantially as follows:
"Contractor represents to the Government and Government’s Engineering Consultant that Contractor has either determined and verified all quantities, dimensions, field construction criteria, materials, catalog numbers, and similar data, or assumes full responsibility for doing so and has reviewed or coordinated each submittal with requirements of Work and Contract Documents."
13. If Contract Documents include performance specifications stating required results which can be verified as meeting stipulated criteria, so that further design by Contractor prior to fabrication is necessary, Submittal depicting such design must be prepared under seal of professional engineer registered in appropriate state and Submittal shall be signed and sealed in accordance with applicable regulations and with following certification statement:
Page 4 - SECTION 01 33 00 ms1952
"I hereby certify that this engineering document was prepared by me or under my direct personal supervision, that I am a duly registered professional engineer under laws of state of Texas and I accept responsibility for adequacy of this document to meet criteria stipulated in Contract Documents."
M. Product Data:
1. Mark each copy to identify applicable products, models, options, and other data. Supplement manufacturers' standard data to provide information specific to this Project.
2. Indicate product utility and electrical characteristics, utility connection requirements, and location of utility outlets for service for functional equipment and appliances.
N. Design data:
1. Submit for Government’s Engineering Consultant’s knowledge as contract administrator or for the
Government.
2. Submit for information for limited purpose of assessing conformance with information given and design concept expressed in Contract Documents.
O. Test reports:
1. Submit for Government’s Engineering Consultant’s knowledge as contract administrator or for the
Government.
2. Submit test reports for information for limited purpose of assessing conformance with information given and design concept expressed in Contract Documents.
P. Certificates:
1. When specified in individual specification sections, submit certification by manufacturer, installation/application subcontractor.
2. Indicate material or product conforms to or exceeds specified requirements. Submit supporting reference data, affidavits, and certifications as appropriate.
3. Certificates may be recent or previous test results on material or product, but must be acceptable to reviewer.
Q. Manufacturer's instructions:
1. When specified in individual specification sections, submit printed instructions for delivery, storage, assembly, installation, adjusting, and finishing, to Government’s Engineering Consultant for delivery to the Government in quantities specified for Product Data.
2. Indicate special procedures, perimeter conditions requiring special attention, and special environmental criteria required for application or installation.
R. Manufacturer's field reports: Submit report within 20 days of observation for information.
S. Proposed products list:
1. Within 15 days after date of Notice to Proceed, submit list of major products proposed to Engineer for use, with name of manufacturer, trade name, and model number of each product.
2. For products specified only by reference standards, give manufacturer, trade name, model or catalog designation, and reference standards.
1.05 RESUBMISSION REQUIREMENTS
A. Make any corrections or changes in submittals required by Government’s Engineering Consultant and resubmit until stamped as either "Reviewed," "Reviewed as Noted," or “For Information Only.”
B. Text and depictions changed on Submittal shall be back-circled (clouded).
C. Government’s Engineering Consultant will assume that portions of Submittal not back-circled have not been changed by Contractor from previous submission.
D. Indicate revision number and date in document revision block.
ms1952 SECTION 01 33 00 - Page 5
1.06 DISTRIBUTION
A. Distribute reproductions of Shop Drawings which carry Engineer stamp as either "Reviewed" or "Reviewed as Noted" to:
1. Job site file.
2. Record Documents file.
3. Other affected contractors.
4. Subcontractors.
5. Supplier or fabricator.
1.07 CONSTRUCTION PROGRESS DOCUMENTATION
A. Construction progress schedules:
1. Submit initial schedules to Government’s Engineering Consultant within 15 days after date established in Notice to Proceed. After review, resubmit required revised data within ten days.
B. Form of schedules:
1. Prepare schedules in form of horizontal bar chart.
a. Provide separate horizontal bar for each trade or operation.
b. Horizontal time scale: Identify first work day of each week.
c. Scale and spacing: To allow space for notations and future revisions.
d. Minimum sheet size: 11 x 17.
2. Format of listings: Chronological order of start of each item of Work.
3. Identification of listings: By major Specification Section numbers.
C. Construction progress schedule shall show:
1. Complete sequence of construction by activity, with Contract Price breakdown at each stage.
2. Dates for beginning, and completion of, each major element of construction specifically listing:
a. Site clearing.
b. Site utilities.
c. Foundation Work.
d. Structural framing.
e. Subcontractor Work.
f. Equipment installations.
g. Finishes.
3. Projected percentage of completion for each item, as of first day of each month.
D. Submittal schedule shall show: Dates for Contractor’s submittals
E. Provide subschedules to define critical portions of prime schedules.
F. Progress revisions:
1. Indicate progress of each activity to date of submission.
2. Show changes occurring since previous submission of schedule:
a. Major changes in scope.
b. Activities modified since previous submission.
c. Revised projections of progress and completion.
d. Other identifiable changes.
3. Provide narrative report as needed to define:
a. Problem areas, anticipated delays, and impact on schedule.
b. Corrective action recommended, and its effect.
c. Effect of changes on schedules of other prime contractors.
G. Distribution copies of reviewed schedules to:
1. Job site file.
2. Subcontractors.
3. Other concerned parties.
Page 6 - SECTION 01 33 00 ms1952
H. Instruct recipients to report promptly to Contractor, in writing, any problems anticipated by projects shown in schedules.
1.08 PHOTOGRAPHIC DOCUMENTATION
A. Provide photographs of Site and construction throughout progress of Work.
B. Submit photographs electronically each month.
1.09 VIDEO DOCUMENTATION OF EXISTING CONDITIONS
A. After construction staking and prior to excavation, perform video recording along route of new sanitary and storm sewers, irrigation water, and electrical and communications conduits. Recording shall document significant features that may be affected by construction activity.
B. Provide labor, equipment, and materials for televising and complete video documentation of route of sewers.
C. Viewing shall be in upstream direction along sewer routes. Recording shall be consecutive and continuous along sewer route.
D. Personnel and equipment:
1. Furnish equipment, supplies, and materials necessary to complete Work as specified.
2. Equipment not giving proper results shall be replaced.
E. Video camera and other components shall provide clean, clear, and sharp color picture.
F. Video recording:
1. Provide complete color video recording of areas along route of new sewers. Video recording media produced shall be compatible with Government's video equipment.
2. Produce video recordings of sufficient quality to allow proper in-house viewing with minimum of distortion; no image tearing.
3. Provide voice narration on video recording to document following information:
4. Name of base, street, and date upon which video inspection was made.
5. Description of special features, i.e. cracked pavements, special landscaping, etc.
6. Stop camera at special features for minimum of 10 seconds to allow for photographic documentation.
7. Deliver video recording to Government’s Engineering Representative who, after review, will deliver recording to Government for permanent records.
8. Label each recording to identify sewer and limits of coverage.
G. Recording procedure:
1. Camera shall be moved at uniform rate consistent with amount of detail being recorded
2. Take necessary steps and adopt procedures to ensure optimum viewing conditions.
1.10 SAFETY PROCEDURES MANUAL
A. Prepare and submit to Government, within 15 days after date of the Government-Contractor Agreement, safety procedures manual defining Contractor's safety program for work on site. Manual shall include:
1. Safety responsibilities of Contractor's personnel.
2. Description of Contractor's safety program.
3. Requirements of use of personal protective equipment.
4. General safety-related rules of conduct.
5. Fire prevention measures.
6. Accident reporting procedures.
7. Procedures for hot work (welding, cutting, etc.), overhead work, and work in enclosed, confined spaces (tank, boiler, etc.). Reference 29 CFR Part 1910.
ms1952 SECTION 01 33 00 - Page 7
8. Contact persons with current phone numbers for:
a. Contractor
b. Facility Safety Officer
c. Local Fire Department
d. Local Police Department
1.11 SUBMITTAL TRANSMITTAL FORM PROCEDURES
A. Submittals shall be accompanied by completed copies of Submittal Transmittal form, bound herein.
An electronic version of transmittal form is available and may be obtained from Government’s Engineering Consultant. Reproduce additional copies required.
B. Submit 2 copies of transmittal form for initial submittals and resubmittals. Sequentially number transmittal form. Revise submittals with original number and sequential alphabetic suffix.
C. Prior to submittal, complete information under heading “Contractor's Transmittal.”
D. Government’s Engineering Consultant will complete information under “Reviewer's Action.”
E. Do not include submittals for more than one section of Specifications on Submittal Transmittal form.
F. Identify project title, location, and number and contract title and number.
G. Identify preparer name and, submittal…
This is the start of the file's text. The full file is on GovTribe.