This is a solicitation for repairs to the Vertical Lift Railroad Bridge over the Cape Cod Canal in Buzzards Bay, Massachusetts. The U.S. Army Corps of Engineers seeks mechanical, electrical, and structural repairs including replacement of lower span lock motors and wear plates, replacement and adjustment of guide rollers, and structural repairs to the bridge spires. Bids are due by January 31, 2023, with award anticipated by March 15, 2023 and work required to be complete by November 15, 2023. The solicitation involves replacement of mechanical and electrical components, structural steel repairs, and coatings work.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amendment 0011.pdf | ||
| Amendment 0010.pdf | ||
| Amendment 0009.pdf | ||
| Amendment 0008 - Revised-Sheet_M-501.pdf | ||
| Amendment 0008.pdf | ||
| Amendment 0008 - Revised-Sheet_M-103.pdf | ||
| Amendment 0007.pdf | ||
| Amendment 0006.pdf | ||
| Amendment 0005.pdf | ||
| Amendment 0004 - CAP-129_M-103.pdf | ||
| Amendment 0004 - CAP-129_M-502.pdf | ||
| Amendment 0004.pdf | ||
| Amendment 0004 - CAP-129_M-102.pdf | ||
| Amendment 0004 - CAP-129_M-501.pdf | ||
| Amendment 0003.pdf | ||
| Amendment 0002.pdf | ||
| Amendment 0001.pdf | ||
| Drawings.pdf | ||
| Solicitation.pdf |
Show all 19
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Solicitation Number:
W912WJ21B0021
Repairs to the Vertical Lift Railroad Bridge
Cape Cod Canal Buzzards Bay, Massachusetts
Construction Solicitation and Specifications
October 2021
Repairs to the Railroad Bridge, Cape Cod Canal, Buzzards Bay, MA
PROJECT TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
01 11 00 SUMMARY OF WORK
01 22 00 MEASUREMENT AND PAYMENT
01 30 00 ADMINISTRATIVE REQUIREMENTS
01 33 00 SUBMITTAL PROCEDURES
01 33 29 SUSTAINABILITY REPORTING
01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS
01 42 00 SOURCES FOR REFERENCE PUBLICATIONS
01 45 00 QUALITY CONTROL
01 45 01 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM)
01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS
01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS
01 74 19 CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL
01 78 00 CLOSEOUT SUBMITTALS
DIVISION 05 - METALS
05 50 10 METALS - GUIDE ROLLER ASSEMBLIES
05 50 13 MISCELLANEOUS METAL FABRICATIONS FOR SPIRE REPAIR WORK
05 50 15 CIVIL WORKS FABRICATIONS
DIVISION 23 - MECHANICAL
23 03 00 BASIC MECHANICAL MATERIALS AND METHODS (MOTOR REPLACEMENT)
DIVISION 26 - ELECTRICAL
26 20 00 INTERIOR DISTRIBUTION SYSTEM
26 27 00 BRIDGE CONTROL SYSTEM
DIVISION 34 - TRANSPORTATION
34 82 00 MECHANICAL MAINTENANCE
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 1
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 11 00
PART 1 GENERAL
1.1 WORK COVERED BY CONTRACT DOCUMENTS
1.1.1 Work in Railroad Right-of-Way
1.1.2 Preliminary Work
1.1.3 Previous Work by Others
1.2 SITE PHOTOGRAPHS
1.3 REFERENCES
1.4 SUBMITTALS
1.5 PROTECTION OF EXISTING STRUCTURES, UTILITIES, AND WORK
1.5.1 General
1.5.2 Debris Control
1.5.3 Existing Electrical Circuits
1.5.4 Cape Cod Canal Television (CCTV) Cameras
1.5.5 Video Control Cable
1.5.6 Radio Antennae
1.5.7 Counterweight Ropes and Guides
1.5.8 Sheave Trunnion and Trunnion Bearings
1.6 SUPERINTENDENCE BY THE CONTRACTOR
1.7 PROJECT/SITE CONDITIONS
1.7.1 Site Security
1.8 WORK SEQUENCE AND SCHEDULING
1.8.1 Hours of Operations
1.8.2 Coordination
1.8.3 Work Sequence
1.8.3.1 Two-Week Schedule of Work Activities
1.8.3.2 Initial Project Schedule
1.8.3.3 Periodic Schedule Updates
1.8.4 Organization at the Site
1.8.4.1 General
1.8.4.2 Rate of Progress
1.9 CONSTRUCTION OPERATIONAL RESTRICTIONS
1.9.1 Alterations to Typical Operational Restrictions
1.10 CONTRACTOR'S USE OF FACILITIES AND HAULING ROUTES
1.11 CONTRACTOR USE OF PREMISES
1.11.1 Access to the Site and Storage/Staging Areas
1.11.2 Temporary Facilities, Utilities, and Storage Areas
1.11.3 Work Limits
1.11.4 Use of Lift Span
1.11.5 Contractor Use of Canal Channel
1.11.6 Construction Access Plan
1.11.7 Protection and Security
1.11.8 Work By Other Contractors
1.11.9 Emergency Contacts
1.11.10 Damaged Property
1.11.11 Contractor's Receipt of Supplies
1.11.12 Daily Clean Up
1.11.13 Government Sanitary Facilities
SECTION 01 11 00 Page 1
SUMMARY OF WORK
1.12 PHOTOGRAPHIC/VIDEO SURVEY
1.13 QUALITY ASSURANCE
1.14 GENERAL SAFETY REQUIREMENTS
1.14.1 General
1.14.2 Contractor's Project Superintendent
1.15 ENVIRONMENTAL PROTECTION
1.16 PRECONSTRUCTION CONFERENCE
1.17 AS-BUILT DRAWINGS
1.17.1 Preparation of As-Built Drawings
1.18 RECORD DRAWINGS
1.18.1 Final Record Drawing Annotation
1.18.2 Preparation and Submission of Record Drawings
1.18.3 Record Drawing Re-Submission Requirements
PART 2 PRODUCTS (Not Applicable)
PART 3 EXECUTION (Not Applicable)
-- End of Section Table of Contents --
SECTION 01 11 00 Page 2
SECTION 01 11 00
PART 1 GENERAL
1.1 WORK COVERED BY CONTRACT DOCUMENTS
The general description below is given to indicate the approximate scope of this project only. It does not limit the work required under the project drawings and specifications.
The work of this project includes replacement of the lower span lock motor/gear drive assembly on the North and South piers, replacement of the North and South pier wear plates to their original thickness and the replacement of the upper and lower southeast guide rollers. The remaining guide rollers shall be assessed and adjusted as required to be within the defined operational tolerances. Completion of each portion of the work shall require immediate testing to confirm acceptable operation before the bridge will be allowed to be placed back into normal service. The steel spires on both towers will be rehabilitated. This includes installing steel plates, bars, and angles, and installing bolted repairs throughout the spires.
The Contractor shall note that scheduling and coordination of this project is critical, as work is not allowed on the bridge, except for work that takes place in the bridge spires, from 01 May through 15 October, inclusive of any year. Work in the bridge spires may be performed at any time of year as long as no obstructions to bridge traffic and operation are necessary. Refer to Subpart 1.8 WORK SEQUENCE AND SCHEDULING and Subpart 1.9 CONSTRUCTION OPERATIONAL RESTRICTIONS for coordination requirements associated with the Railroad Bridge and the Cape Cod Canal.
During this time period when work is not allowed on the bridges, the Contractor shall perform preliminary work, as defined in Subpart 1.1.2 "Preliminary Work".
The work of this project poses significant falling hazards. The Contractor shall implement fall protection measures as specified in this document.
The Contractor is strongly encouraged to visit the project site to ascertain current conditions. Failure to complete a site visit and failure to identify obvious site conditions does not constitute a valid claim for a differing site condition once the work is executed.
1.1.1 Work in Railroad Right-of-Way
It is anticipated that the work will not require the use of rail lines and the Contractor storage and setup will be placed well clear of the railroad track. However, the Contractors on-site employees shall be required to attend a two hour Rail Worker Safety training session at the Cape Cod Canal Field Office as part of the mobilization.
If the Contractors operation constrains rail operations beyond the approved downtime coordinated with and approved by the Contracting Officer, the Contractor is responsible for providing insurance, flaggers, SECTION 01 11 00 Page 3
SUMMARY OF WORK
worker safety training, and identifying all other requirements established by the railroad when working within the railroad right-of-way.
1.1.2 Preliminary Work
A. Verification of all existing conditions with field measurements, shop drawing approval process, ordering of materials, and associated preparation.
B. Procurement of all materials. Several major items will have a significant delivery lead time that will affect the time for the start of field construction. The Contractor shall identify these items and their impacts clearly on their project schedule. The Contractor shall also submit a list of items impacted by significant delivery lead items to the Contracting Officer prior to the start of construction.
C. Once all materials have been received at the bridge site, dismantling and replacement operations can begin. The Contractor shall submit a request in writing to the Contracting Officer if temporary dismantling to field verify is required prior to materials being at the site. Included in that request shall be the Contractor's plan to dismantle and reassemble parts to ensure operation of bridge is not impacted for longer than the time agreed upon by the following: Contracting Officer and the Cape Cod Canal Marine Traffic Controller.
D. Once all materials have been received at the bridge site, dismantling and replacement operations can begin. A mobilization of the storage area and administrative equipment shall begin before the scheduled arrival of all material.
1.1.3 Previous Work by Others
A. Abrasive blast cleaning and painting all the metalwork of the bridge to bare metal and performing miscellaneous structural, mechanical, and electrical rehabilitation work, that did not require a closure of the bridge of more than eight hours at a time. The work also included interior and exterior rehabilitation of the north and south tower machinery and sheave rooms. Windows and doors were replaced in the operator and electrical rooms.
B. The railroad miter joints at each end of the lift span and on both adjacent ends of the tower spans were replaced in a recent emergency repair contract. The limits of this track system repairs are indicated on the plans.
C. The tower spires were rehabilitated with replacement of numerous diagonal members.
D. The Operator/Control House roofing, doors and windows were replaced with new materials.
E. Replacement of the existing elevator and elevator related architectural, structural steel, electrical and mechanical components.
1.2 SITE PHOTOGRAPHS
Photographs taken during a site visit in February 2021 by U.S. Army Corps of Engineers personnel showing the existing conditions of project features are attached at the end of the specification. The photographs are
SECTION 01 11 00 Page 4 attached for informational purposes only. The Contractor shall make his own investigations of existing conditions in the field prior to the start of work.
1.3 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
AMERICAN RAILWAY ENGINEERING & MAINTENANCE-OF-WAY ASSOCIATION
(AREMA)
AREMA Manual for Railway Engineering
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 385-1-1 (2014) Safety and Health Requirements Manual
ERDC/ITL TR-12-1 (2015) A/E/C Graphics Standard, Release 2.0
ERDC/ITL TR-12-6 (2015) A/E/C CAD Standard, Release 6.0
1.4 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Initial Project Schedule ; G, RO
In accordance with the contract clauses, the Contractor shall, within 15 days after receipt of Notice to Proceed (NTP) or as otherwise determined by the Contracting Officer, submit for approval a practicable project schedule. When changes are authorized that result in contract time extensions, the Contractor shall submit a revised project schedule for approval by the Contracting Officer.
Two-Week Schedule of Work Activities
In addition to the scheduling and notification requirements specified elsewhere in the contract, the Contractor shall provide to the Contracting Officer a detailed schedule of work activities, which the Contractor intends to perform over the following two week period (Monday thru Friday for two weeks).
Construction Access Plan ; G, RO
Drawings shall include catalog cuts, erection details, alignment procedure, manufacturer's descriptive data and installation instructions, and templates. Design calculations shall also be submitted to demonstrate the structural adequacy of the proposed system and to analyze loadings that will be imposed on the
SECTION 01 11 00 Page 5
Railroad Bridge superstructure.
Photographic/Video Survey ; G, RO
The Contractor shall submit a pre-construction photographic/video survey as described in this section.
SD-07 Certificates
Periodic Schedule Updates ; G, RO
Request Application ; G, RO
Request Application to work outside the hours of operation.
SD-11 Closeout Submittals
As-Built Drawings ; G, DO
As-built drawings, which are paper mark-ups and scanned PDF's of the paper mark-ups, showing all deviations which have been made from the contract drawings, shall be submitted to the Contracting Officer for approval at the completion of work. See Subpart AS-BUILT DRAWINGS for record keeping and submittal requirements.
Record Drawings ; G, DO
Record drawings, which are CAD files showing all deviations which have been made from the contract drawings, shall be submitted to the Contracting Officer for approval at the completion of work. See Subpart RECORD DRAWINGS for record keeping and submittal requirements.
1.5 PROTECTION OF EXISTING STRUCTURES, UTILITIES, AND WORK
1.5.1 General
The Contractor shall protect the existing bridge structures and all utilities from damage or interruption of service. Damage or any interruption of service resulting from the Contractor's operations shall be repaired or service restored promptly at the expense of the Contractor.
1.5.2 Debris Control
Care shall be taken that no bridge material, pieces of support structures, debris, or any materials whatsoever, fall into the canal or to the ground. Should debris or construction materials fall from the bridges inadvertently, prompt corrective action shall be taken to prevent further occurrences and the fallen items shall be secured and removed. The Contractor shall take all precautions practicable to prevent items from falling from the bridges. Debris deposited on horizontal surfaces of the superstructure and piers shall be collected and disposed of properly.
Sweeping of debris off the bridge to the land or water below will not be permitted. No falling debris will be tolerated as the Canal is continually open to marine traffic.
1.5.3 Existing Electrical Circuits
Electrical circuits on the bridge consist of lighting for the towers and
SECTION 01 11 00 Page 6 operator's house, aerial cables run in one of two catenaries extending from each tower of the bridge, navigation lighting for marking the channel.
1.5.4 Cape Cod Canal Television (CCTV) Cameras
Two CCTV cameras on the north tower of the bridge shall not be removed and shall be protected from damage during the construction operations, if work is near the location of the cameras. Protective covers shall be placed over the cameras during construction in their vicinity. The Marine Traffic Controller shall be notified when the cameras are taken out of service. Covers shall be removed at the end work in the vicinity, or at the end of the day. The Contractor shall protect the microwave reflection board on the north tower.
1.5.5 Video Control Cable
A special video control cable is attached to the north tower for operation of the cameras. A 25 pair telephone cable and a fiber optic cable are also attached to the north tower for the control of the radio base station in the tower. Use extreme care to protect these cables from damage.
1.5.6 Radio Antennae
Radio antennae for the railroads and various Federal and State agencies are located on both towers. The Contractor shall protect the antennae and helix cabling from damage at all times. Severe electrical shock and RF burn will result from touching these antennae and helix cabling during a transmission.
1.5.7 Counterweight Ropes and Guides
Protect all counterweight ropes and guides and both elevator shafts and hoisting equipment from debris attaching to or impacting the operation of these systems.
1.5.8 Sheave Trunnion and Trunnion Bearings
Protect all counterweight rope sheaves and trunnion bearings from debris attaching to or impacting the operation of these systems.
1.6 SUPERINTENDENCE BY THE CONTRACTOR
A. At all times during the performance of the contract and until the work is completed and accepted, the Contractor shall directly superintend the work and have on the worksite a competent project superintendent who is satisfactory to the Contracting Officer and has the authority to act for the Contractor.
B. The qualified superintendent, and competent alternate, shall be capable of reading, writing, and conversing fluently in the English language.
C. The project superintendent must have a minimum of 10 years experience in construction with at least 5 of those years as a superintendent on projects similar in size and complexity. The individual must be familiar with the requirements of EM 385-1-1 and have experience in the areas of hazard identification and safety compliance. The individual must be capable of interpreting a critical path schedule and construction drawings. The qualification requirements for the alternate superintendent
SECTION 01 11 00 Page 7 are the same as for the project superintendent. The Contracting Officer may request proof of the superintendent's qualifications at any point in the project if the performance of the superintendent is in question.
D. The project superintendent is primarily responsible for managing and coordinating day-to-day production and schedule adherence on the project.
The superintendent is required to attend partnering meetings, and quality control meetings.
E. The project superintendent shall maintain a physical presence at the site at all times and be responsible for all construction and related activities at the site, except as otherwise acceptable to the Contracting Officer.
F. The Project Superintendent is subject to removal by the Contracting Officer for non-compliance with requirements specified in the contract and for failure to manage the project to insure timely completion.
Furthermore, the Contracting Officer may issue an order stopping all or part of the work until satisfactory corrective action has been taken. No part of the time lost due to such stop orders is acceptable as the subject of claim for extension of time for excess costs or damages by the Contractor.
1.7 PROJECT/SITE CONDITIONS
1.7.1 Site Security
The Contractor shall report any vandalism, suspicious activities or devices to the Contracing Officer or local police as soon as possible.
The Contracting Officer will notify the Contractor of any heightened security measures and will expect vigilant monitoring of equipment, grounds and security fencing while working. At a heightened security posture, there may be work areas that are restricted. The Contracting Officer will notify the Contractor of these restricted areas, and work may be delayed or restricted or will be performed in these areas under the direct supervision of U.S. Army Corps of Engineers personnel.
1.8 WORK SEQUENCE AND SCHEDULING
1.8.1 Hours of Operations
Normal work hours are from 7:00 a.m. through 5:30 p.m., Monday through Friday. The Contractor will not be permitted to work on Saturday, Sunday, Patriots Day (a Massachusetts State holiday), or on Federal legal holidays unless otherwise authorized by the Contracting Officer. The exclusion of work on Saturday, Sunday, and legal holidays has been considered in computing the performance time of this contract. The following legal holidays and work restrictions will be observed:
January 1st (No work scheduled) Third Monday in January (No work scheduled) Third Monday in February (No work scheduled) Last Monday of May June 19th July 4th 1st Monday of September 2nd Monday of October November 11th Fourth Thursday of November
SECTION 01 11 00 Page 8
December 25th (No work scheduled)
When one of the above designated legal holidays falls on a Sunday, the following Monday will be observed as a legal holiday. When a legal holiday falls on a Saturday, the preceding Friday is observed as a holiday. Requests to deviate from the schedule presented in the Article titled "Phasing of Work" shall be made in writing to the Contracting Officer. Every effort will be made to accommodate such requests that are not detrimental to maintaining the flow of traffic or to the completion of the contract work.
Work outside the normal hours of operation requires Contracting Officer approval. The request to work outside the hours of operation shall be made in writing to the Contracting Officer 10 calendar days prior to such work to allow arrangements to be made by the Government. The request application shall include specific dates, hours, location, type of work to be performed, contract number and project title, and names of all individuals who will be working outside the hours of operations. During periods of darkness, the different parts of the work shall be lighted in a manner approved by the Contracting Officer. Approval will not be given to perform work on the bridge from 01 May through 31 December, inclusive of any year.
1.8.2 Coordination
Continuous Contractor coordination with the Cape Cod Canal Marine Traffic Controller and the Massachusetts Coastal Railroad (freight operations) and the Cape Cod Central Railroad (passenger operations) is a contract requirement to accomplish this work. Both the Massachusetts Coastal Railroad and the Cape Cod Central Railroad are subsidiaries of Iowa Pacific Holdings. The Contractor's superintendent or his designated representative shall maintain radio contact with the Railroads and the Canal Marine Traffic Controller at all times during the performance of the work.
Should the Contractor utilize any railroad track based equipment, defined as the track, ties, signals or appurtances (not the bridge), or perform work in or encroaching on the railroad right-of-way, access to non US Government owned property will be required. The Contractor shall be solely responsible for coordinating with the railroad companies to determine additional railroad requirements for such work in the right-of-way, and the Contractor shall comply with all of these requirements as a condition of this contract. These requirements may include, but are not limited to, flaggers and training for Contractor employees. If the Contractor does not utilize railroad track based equipment, or performs no work in or encroaching on the railroad right-of-way, the only contract requirement will be to take the railroad worker protection training.
Contact information for the above is as follows:
Massachusetts Coastal Railroad 68 Center Street #201 Hyannis, Massachusetts 02601 Telephone: 508-771-8400
Cape Cod Central Railroad 252 Main Street Hyannis, Massachusetts 02601
SECTION 01 11 00 Page 9
508-771-3800
Cape Cod Canal Marine Traffic Controller Telephone: 978-318-8500 VHF Radio Channels 13, 14, 16
1.8.3 Work Sequence
1.8.3.1 Two-Week Schedule of Work Activities
In addition to the scheduling and notification requirements specified elsewhere in this section, the Contractor shall provide to the Contracting Officer a detailed schedule of work activities, including requested dates and times of 8 hour periods with the bridge remaining in the lowered or raised position and work may be performed without rail or marine traffic, which the Contractor intends to perform over the following two week period (Sunday through Saturday for two weeks). The schedule of work activities shall be updated and submitted by the Contractor to the Contracting Officer on a weekly basis, by noon on every Thursday during the prosecution of work period.
1.8.3.2 Initial Project Schedule
The initial project schedule shall be in the form of a chart graphically indicating the sequence proposed to accomplish each work feature or operation pursuant to FAR Clause 52.236-15 "Schedules for Construction Contracts". Show in the schedule the proposed sequence to perform the work and dates contemplated for starting and completing all schedule activities. The chart shall be prepared to show the starting and completion dates of all work features on a linear horizontal time scale beginning with date of Notice to Proceed and indicating calendar days to completion. The scheduling of the entire project is required. Provide a schedule that is a forward planning as well as a project monitoring tool.
The Contractor shall indicate on the chart the important work features or operations that are critical to the timely overall completion of the project. Key dates for such important work features and portions of work features are milestone dates and shall be so indicated on the chart.
Failure to develop the Project Schedule to an appropriate level of detail will result in its disapproval. The Contracting Officer will consider, but is not limited to, the following characteristics and requirements to determine appropriate level of detail:
1. Activity Durations
2. Design and Permit Activities
3. Procurement Activities
4. Mandatory Tasks
a. Submission, review and acceptance of SD-01 Preconstruction Submittals (individual activity for each).
b. Submission, review and acceptance of features requiring design completion and submission, review and acceptance of design packages.
c. Submission of mechanical/electrical/information systems layout drawings.
SECTION 01 11 00 Page 10
d. Long procurement activities
e. Submission and approval of O & M manuals.
f. Submission and approval of as-built drawings.
g. Submission and approval of installed equipment lists.
h. Submission and approval of test data, and reports
i. Show Government and other agency activities that could impact progress. These activities include, but are not limited to:
approvals, acceptance, design reviews, environmental permit approvals by State regulators, inspections, utility tie-in, Government Furnished Equipment (GFE), etc.
This schedule will be the medium through which the timeliness of the Contractor's construction effort is appraised. Anticipated adverse weather delay days shall be included in the schedule.
Submit the Initial Project Schedule for approval within 30 calendar days after notice to proceed is issued. No payment will be made for work items not fully detailed in the Project Schedule.
An Early Completion Schedule is an Initial Project Schedule (IPS) that indicates all scope of the required contract work will be completed before the contractually required completion date.
No IPS indicating an Early Completion will be accepted without being fully resource-loaded (including crew sizes and manhours) and the Government agreeing that the schedule is reasonable and achievable.
The Government is under no obligation to accelerate work items it is responsible for to ensure that the early completion is met nor is it responsible to modify incremental funding (if applicable) for the project to meet the contractor's accelerated work.
1.8.3.3 Periodic Schedule Updates
An updated schedule showing actual progress shall be submitted monthly and with each pay request. Changes to the base-line schedule shall be outlined in a narrative describing the reason for the change.
1.8.4 Organization at the Site
1.8.4.1 General
The Contractor shall employ ample personnel and sufficient equipment to accomplish the work of this contract in the least amount of time, within the prosecution period specified in SPECIAL CONTRACT REQUIREMENTS, Clause
COMMENCEMENT, PROSECUTION AND COMPLETION OF WORK (APR 1984) FAR 52.211-10.
1.8.4.2 Rate of Progress
Should the Contractor fail to maintain a satisfactory rate of progress in accordance with the Contractor's approved progress schedule, the Contracting Officer may require that additional personnel and equipment be placed on the work and weekend and overtime work be performed, in order
SECTION 01 11 00 Page 11 that the work be brought up to schedule and maintained.
1.9 CONSTRUCTION OPERATIONAL RESTRICTIONS
a. The lift span is normally in the up position. The span is lowered for all Railroad traffic and maintenance work.
b. The Contractor shall accommodate railroad traffic across the Bridge at all times. Railroad traffic will generally occur close to the times shown on the "Train Schedule" listing below. However, deviations from the schedule as listed are expected and can be coordinated to facilitate work. Therefore, daily coordination with the Bridge Operators is required to ensure that the Bridge is operational for the passage of trains.
Typically the Contractor should expect not more than a continuous 8 hour period during the workday in which to perform work without rail or marine traffic, or special written request of the Contracting Officer to extend this period. All work that limits the operation of the Bridge or the passage of trains shall be completed or removed a minimum of 60 minutes prior to train passage. When the 8 hour period is over, or the approved special request for additional time, the Contractor shall be expected to allow the Bridge to move up and down freely and to allow the passage of rail and marine traffic without interference. All Contractor personnel shall be off of the Bridge during the passage of rail traffic.
c. All work shall be scheduled and performed in a manner to ensure that no restriction will be placed on the normal flow of marine navigation, unless special arrangements have been made with the Contracting Officer.
Bridge moves to facilitate work must be requested from, and coordinated with Canal Marine Traffic Control. Marine Traffic will be given priority unless 24 hours advanced notice is provided. The bridge may not remain in the lowered position for more than 30 minutes unless a request has been made 24 hours in advance, or no marine traffic is in the area. These extended down periods will not exceed 1 hour. Special arrangements will be required for continuous periods of work between one (1) to eight (8) hours long with the bridge in the lowered position. The Contractor shall coordinate with the Cape Cod Canal Manager, or designee, and the issuance of a U.S. Coast Guard "Notice to Mariners" three months in advance of when the scheduled work will be required. Special arrangements will also be required for any rigging and scaffolding needed below the span that reduces the vertical clearance under the Bridge. The minimum clearance at mean high water shall be 130 feet to the bottom of all temporary equipment. All reductions in the vertical clearance under the Bridge require coordination with the Canal Manager, or designee, and the issuance of a U.S. Coast Guard "Notice to Mariners" three months in advance of the scheduled work.
d. The Contractor shall ensure that the bridge is properly balanced at all times. All use of tools or equipment that may affect the balance of the span will require the Contractor to furnish and install balance blocks on the Bridge counterweights.
e. Provide key personnel hand-held VHF radios. The radios shall be capable of communicating with the bridge operating personnel when bridge movements are being made. Appoint one person to be sure workers are in a safe position during bridge moves and to communicate, as necessary, with the bridge operators before, during, and after a bridge move. A minimum 30 minute time period is required to clear all personnel to safety before the bridge moves.
SECTION 01 11 00 Page 12
Train Schedule and Required Bridge Movements
Use of the Railroad Bridge and operation of the lift span for the passage of trains will be required during the construction period of this contract. Required time frames for anticipated bridge movements are listed below. These times, and the number of required movements, are subject to change.
Note: A "bridge movement" is defined as the lift span moving from the raised position to the lowered position and then back to the raised position again after the passage of a train. The entire movement process typically requires between 15 and 30 minutes to complete.
A. Monday through Friday, all year:
1 to 2 bridge movements between 0700 and 1100 1 bridge movement between 1630 and 1900
1.9.1 Alterations to Typical Operational Restrictions
A. Railroad: The Contractor shall make a written request to extend the period of time in which railroad activity will be disrupted at least 2 weeks prior to the requested date. The Contractor shall not move ahead with any work that will disrupt railroad traffic without written approval from the Contracting Officer.
B. Marine Traffic: The Contractor shall make a written request to extend the period of time in which Marine Traffic activity will be disrupted by vertical or horizontal clearance restrictions at least 90 days prior to the requested date per Subpart 1.9 CONSTRUCTION OPERATIONAL RESTRICTIONS, Paragraph B, Subpart 1.11.4 "Use of Lift Span", and Subpart 1.11.5 "Contractor Use of Canal Channel". The Contractor shall not move ahead with any work that will disrupt marine traffic without written approval from the Contracting Officer.
1.10 CONTRACTOR'S USE OF FACILITIES AND HAULING ROUTES
The Contractor shall be responsible for the following:
(1) Determining the trucking and hauling routes and associated restrictions to and from the work, to include the coordination for the use of such routes with local, State, and Federal authorities.
(2) Complying with all local, State, and Federal regulations and restrictions when using any facilities or hauling routes.
1.11 CONTRACTOR USE OF PREMISES
1.11.1 Access to the Site and Storage/Staging Areas
Access to the project site is limited to the specified dates scheduled for work and as indicated on the contract drawings. The Contractor is responsible for maintaining access necessary for its equipment, material, and plant to and from the work area.
Access to temporary facilities and storage/staging areas shall be as specified in Section 01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND
CONTROLS.
SECTION 01 11 00 Page 13
1.11.2 Temporary Facilities, Utilities, and Storage Areas
The Contractor shall conform to Section 01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS regarding temporary facilities, temporary utilities, and storage areas. Confine all operations (including storage of materials) on Government premises to areas authorized or approved by the Contracting Officer. The Contractor shall hold and save the Government, its officers and agents, free and harmless from liability of any nature occasioned by the Contractor's performance.
1.11.3 Work Limits
Work shall be restricted to the limits of the work as shown on the contract drawings and to storage areas as indicated in Section 01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS, as shown on the contract drawings, and as indicated by the Contracting Officer.
1.11.4 Use of Lift Span
The lift span may be used by the Contractor up to once per week, when the lift span is operational, and only for the purpose of delivering materials and equipment to the lift span and towers. No additional use of the lift span will be permitted. The lift span may not be used by the Contractor to transport Contractor personnel on and off of the Bridge.
All Contractor use of the lift span will be subject to the approval of the Contracting Officer and dependent on the passage of scheduled or unscheduled train and marine traffic. All Bridge movements shall be scheduled in advance with the Contracting Officer and the Marine Traffic Controller. For use of the lift span for 60 minutes or less, the Contractor shall submit a request for approval to the Contracting Officer and Marine Traffic Controller a minimum of 24 hour notice prior to the desired bridge movement. All Contractor use of the lift span for a period exceeding 60 minutes requires submission of a request for approval to the Contracting Officer and Marine Traffic Controller 7 calendar days prior to the desired bridge movement.
1.11.5 Contractor Use of Canal Channel
The Government does not anticipate work to occur from the water. If the Contractor chooses to do so, the Contractor shall be required to coordinate requirements with the Cape Cod Canal Marine Traffic Control.
Any reductions in the horizontal clearance of the Canal channel due to barge or work vessel activity will require prior coordination with the Canal Manager, or designee, and the issuance of a U.S. Coast Guard "Notice to Mariners" three months in advance of the scheduled work.
1.11.6 Construction Access Plan
Access to the project site is limited as specified above and as shown on the drawings. The Contractor shall devise its own means of accessing the lift span and towers for the transport of personnel, equipment, and materials, as necessary to accomplish the work within the specified time period. The plan for accessing the Bridge shall be submitted to the Contracting Officer for review and approval. No obstacles shall encroach upon the railroad clearances prescribed in AREMA, Chapter 28.
SECTION 01 11 00 Page 14
1.11.7 Protection and Security
a. Protection to Contractor personnel or their equipment cannot be provided at the worksite by the Government.
b. The Contractor shall protect all its personnel, Government personnel, and the general public from injury.
c. The Contractor shall conduct all its work so as to prevent injury or unsafe conditions during construction.
1.11.8 Work By Other Contractors
During the performance period of this contract, no other work is anticipated to occur by other contractors.
1.11.9 Emergency Contacts
The Contractor shall provide a list of emergency contacts to be used in the event of an emergency. The list shall include the contact names, addresses, and telephone numbers. As changes occur and additional information becomes available, correct and change the information contained in previous lists.
1.11.10 Damaged Property
Work shall proceed in a manner which will minimize disturbance or risk of damage to structures and surrounding lands. The Contractor shall repair such items damaged in the course of carrying out the work at no additional cost to the Government. All repairs shall match similar existing items in all aspects. All replacements shall be in kind.
1.11.11 Contractor's Receipt of Supplies
The Contractor shall be responsible for all arrangements for the receipt of materials and supplies at the job site. Government personnel are not permitted to receive or sign for items delivered to the site.
1.11.12 Daily Clean Up
The Contractor shall at all times keep rubbish from entering surrounding lands and water. Rubbish accumulated at the temporary facilities shall be removed from the premises daily.
1.11.13 Government Sanitary Facilities
Toilet facilities are not available on site for the Contractor's use. The Contractor shall provide portable toilets for its personnel and subcontractors as specified in Section 01 50 00 TEMPORARY CONSTRUCTION
FACILITIES AND CONTROLS.
1.12 PHOTOGRAPHIC/VIDEO SURVEY
The Contractor shall perform a pre-construction photographic/video survey at the project site. This pre-construction survey shall include still photographs and/or videos in sufficient quantity to fully document the existing condition of all features of the Railroad Bridge within the work area which may be impacted by construction activities, such as steel structure, guide rollers, utilities, and other pertinent features. A
SECTION 01 11 00 Page 15 written narrative shall be prepared by the Contractor which organizes and summarizes the findings of the pre-construction survey photographs and/or videos. Each item shall be identified as "to remain", "to be removed and reset", "to be removed and replaced", or "to be demolished or discarded".
The condition of each item shall also be documented. The written narrative, together with the photographs and/or videos, shall constitute a "Pre-construction Survey Report", which shall be submitted to the Contracting Officer for approval. No on-site work shall be performed until this "Pre-construction Survey Report" has been approved. Damage to items remaining or to be reused caused by the Contractor's operations shall be repaired by the Contractor at no additional expense to the Government.
1.13 QUALITY ASSURANCE
A. All items of work not addressed in the contract documents shall be completed in strict accordance with the manufacturers’ specifications.
B. The Government is not obligated to inspect the Contractor’s work, or to protect the Contractor from the consequences of its work. Government inspections are a general examination of the Contractor’s conduct and workmanship and are solely for the purpose of the Government.
Government-designated Quality Assurance Representatives (QARs) do not have the authority to accept work, nor is a Government inspection to be construed as conclusive.
C. Government agents including QARs and project engineers are not authorized to change the contract without the written approval of the Contracting Officer; this lack of authority extends to all situations in which the action of these agents could be construed as constituting a change.
D. The quality of workmanship is subject to audit by Government or Government-designated QARs at any time during the contract. The Contractor shall cooperate fully and provide all information necessary for this audit.
E. The Contractor shall submit all requests for changes in writing to the Contracting Officer. Do not proceed with changes without possession of written authorization of the Contracting Officer.
F. The Contractor shall not conceal any work unless the Contracting Officer has approved all items of work which are to be concealed. The Contractor shall notify the Contracting Officer of its intention to conceal work at least 24 hours in advance of concealment.
1.14 GENERAL SAFETY REQUIREMENTS
1.14.1 General
The Contractor shall take all necessary precautions in observing safety regulations in accordance with Section 01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS, and shall assume the responsibility to guard against causing of fires and/or explosions and to protect Government property. The Contractor shall perform the work in a manner consistent with security and with fire safety regulations especially with regards to ingress and egress. Temporary closures shall not compromise life safety, security or fire safety.
SECTION 01 11 00 Page 16
1.14.2 Contractor's Project Superintendent
The Contractor's project superintendent shall take an active role in enforcing the safety requirements by participation in safety conferences, hazard analysis, tool box meetings, walk-through inspections, correction of violations, etc., and including that of any subcontractor's work.
1.15 ENVIRONMENTAL PROTECTION
To provide for control of all environmental pollution arising from construction activities, the Contractor and its subcontractors, in the performance of this contract, shall comply with Section 01 57 19 ENVIRONMENTAL PROTECTION, and all applicable federal, state, and local laws and regulations concerning environmental protection pollution control and abatement.
1.16 PRECONSTRUCTION CONFERENCE
The Contracting Officer will conduct a preconstruction conference with key Contractor personnel. The purpose of the conference is to review contract requirements and to establish a working relationship between the Contractor's Staff and the U.S. Army Corps of Engineers personnel who will be closely associated with the project. During the conference, the Contracting Officer will inform the Contractor concerning Job Safety, Quality Control, Labor Relations, and Environmental Protection. The Contractor's Superintendent, Quality Control Representative, and Site Safety and Health Officer (SSHO) shall attend this conference.
1.17 AS-BUILT DRAWINGS
Maintain at the jobsite one set of paper full-size contract drawings marked to show all deviations that have been made from the contract drawings, including buried or concealed construction and utility features revealed during the course of construction. Record the horizontal and vertical location of all buried utilities that differ from the contract drawings. These drawings shall be available for review by the Contracting Officer at all times. Upon completion of the work, submit the original marked set of prints to the Contracting Officer for approval. Also, provide PDFs of the current working redlines and/or markups complying with the as-built drawings and markup requirements. Requests for partial payments will not be approved if the marked prints and PDF files are not current, and request for final payment will not be approved until the marked prints and PDF files are submitted to and approved by the Contracting Officer.
1.17.1 Preparation of As-Built Drawings
The entries shall be made in the jobsite set of prints at the time field changes are made, pertinent information collected, or need for corrections established, as a continuing process during the life of the contract. As revised drawings are issued by the Contracting Officer, revised prints shall be introduced into the set to replace the superseded drawings and all applicable notations previously made on the superseded drawings transferred to the current prints. Carefully prepared sketches, not less than 8-1/2" x 11", may be used to depict changes or added information in lieu of notations on the actual prints. Staple sketches to the prints affected by the change. All plan views, sections, elevations, profiles, diagrams, details, or schedules affected by a change shall be marked up as required to reflect the change. All notations or changes made on the
SECTION 01 11 00 Page 17 prints shall be in sufficient detail to clearly depict the change.
Colored pens or pencils shall be used to make notations on the record prints as follows:
Red pen or pencil shall be employed to indicate added or corrected work or information.
Green pen or pencil shall be used to show the deleted or incorrectly depicted work or information.
Blue or black pen or pencil shall be used to show information not to be recorded on the drawings but included on the marked-up prints for explanatory or clarification purposes for the benefit of the Contracting Officer.
1.18 RECORD DRAWINGS
The record drawings are the final compilation of actual conditions reflected in the as-built drawings. The record drawings are CAD files produced from the source drawing files and marked-up as-built drawings.
The Contractor shall request the full set of electronic drawings, in the source CAD format, for Record Drawing preparation, after award and at least 30 days prior to required use. The Government will provide one set of "as-designed" electronic CAD files in AutoCAD Version 2019. The CAD files are provided to enable preparation of record drawings. If discrepancies exist between the CAD files and the contract PDF drawings, correct the CAD files to show the contract PDF drawings. The Government has no responsibility to modify any GFM due to changes in the design that occur after award.
The Contractor shall prepare the CAD drawing files in AutoCAD Version 2019 or later format.
If additional drawings are required, prepare them using the specified electronic file format applying the same graphic standards specified for original drawings, ERDC/ITL TR-12-6 and ERDC/ITL TR-12-1 . The title block and drawing border to be used for any new final record drawings must be identical to that used on the contract drawings.
If a sheet needs to be added between two sequential sheets, append a Supplemental Drawing Designator in accordance with ERDC/ITL TR-12-6 , "Adding a Drawing Sheet", and ERDC/ITL TR-12-1 , "Adding or Deleting Drawing Sheets and Index Sheet Procedures".
Provide electronic PDF files of all CAD contract drawings sheets associated with the record drawing submittal. Compile and organize the PDF set to match the contract drawings.
1.18.1 Final Record Drawing Annotation
When final revisions have been completed, show the wording "RECORD DRAWING AS-BUILTS" followed by the name of the Contractor in letters at least 3/16 inch high on the cover sheet drawing. Show the wording "RECORD DRAWING AS-BUILTS" in the revision block of each drawing.
1.18.2 Preparation and Submission of Record Drawings
Within 30 days after Government approval of all of the working as-built
SECTION 01 11 00 Page 18 drawings, prepare the final CAD record drawings and submit CAD and PDF drawing files. Also submit all external references (x-refs), plot style files, and all other required CAD resource files. The Government will promptly return one set of prints annotated with any necessary corrections. Within 7 calendar days revise the CAD files accordingly at no additional cost and submit one set of final CAD files and PDF files to the Government. Drawing files and storage media submitted will become the property of the Government upon final approval. Failure to submit final record drawings as specified will be cause for withholding any payment due under this contract. Approval and acceptance of final record drawings must be accomplished before final payment is made.
1.18.3 Record Drawing Re-Submission Requirements
If elements of a record drawing submittal are rejected, provide the following for each re-submission, in addition to any information required in Section 01 33 00 SUBMITTAL PROCEDURES:
A. Re-submit all CAD components, including updated content in response to Government comments.
B. Provide a copy of all Government review comments.
C. Provide a disposition/response to each Government review comment for a back-check of the re-submission deliverable.
PART 2 PRODUCTS (Not Applicable)
PART 3 EXECUTION (Not Applicable)
-- End of Section --
SECTION 01 11 00 Page 19
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 22 00
MEASUREMENT AND PAYMENT
PART 1 GENERAL
1.1 CONTRACT COST BREAKDOWN
1.2 JOB PAYMENT ITEMS
1.3 BIDDING SCHEDULE - PAYMENT ITEMS
PART 2 PRODUCTS (Not Applicable)
PART 3 EXECUTION (Not Applicable)
SECTION 01 22 00 Page 1
SECTION 01 22 00
MEASUREMENT AND PAYMENT
PART 1 GENERAL
1.1 CONTRACT COST BREAKDOWN
The Contractor must furnish within 30 days after the date of Notice to Proceed, and prior to the submission of its first partial payment estimate, a breakdown of its job pay items or items which will be reviewed by the Contracting Officer as to propriety of distribution of the total cost to the various accounts. Any unbalanced items as between early and late payment items or other discrepancies will be revised by the Contracting Officer to agree with a reasonable cost of the work included in the various items. This Contract cost breakdown will then be utilized as the basis for progress payments to the Contractor.
1.2 JOB PAYMENT ITEMS
Payment items for the work of this contract for which contract job payments will be made are listed in the BIDDING SCHEDULE and described below. The job price and payment made for each item listed shall constitute full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for which separate payment is not otherwise provided.
1.3 BIDDING SCHEDULE - PAYMENT ITEMS
Payment items for the work of this contract on which the contract progress payments will be based are listed in the BIDDING SCHEDULE and are described below.