The document is a comprehensive electrical and lighting specification for the High Point Community Park project (PID 002998A) in Pinellas County, Florida, prepared by Engineering Matrix, Inc. The specification details the electrical requirements for the park's infrastructure, covering various electrical systems including raceways, boxes, grounding, identification, panelboards, fuses, controllers, surge protective devices, and exterior and athletic lighting. The project involves installing electrical systems for multi-purpose fields, basketball courts, lighting, playground, walking trail, picnic shelter, and restroom facilities.

The specification is funded through ARPA (American Rescue Plan Act) and provides extensive technical requirements for electrical installations, including specific guidelines for product selection, installation methods, quality assurance, and performance standards. The electrical systems are designed to meet NFPA 70 (National Electrical Code), NEMA standards, and local building codes. The project emphasizes safety, durability, and energy efficiency, with specifications for LED lighting, surge protection, grounding systems, and detailed installation requirements. The electrical infrastructure is intended to support the park's various recreational amenities with a focus on reliability, performance, and long-term maintenance.

View the file

Other files

Show all 24

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SPECIAL PROVISIONS

FOR ELECTRICAL

FOR

HIGH POINT COMMUNITY PARK

PID 002998A

ELECTRICAL AND LIGHTING

SPECIFICATION: E-1

ELECTRICAL AND LIGHTING

SPECIFICATION: E-1

10/11/2023

TABLE OF CONTENTS

DIVISION 26—ELECTRICAL

© Engineering Matrix, Inc. (22-0110.2)

26 05 00 ............ COMMON WORK RESULTS FOR ELECTRICAL

26 05 19 ............ LOW-VOLTAGE ELECTRICAL POWER CONDUCTORS AND CABLES

26 05 26 ............ GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS

26 05 29 ............ HANGERS AND SUPPORTS FOR ELECTRICAL SYSTEMS

26 05 33 ............ RACEWAY AND BOXES FOR ELECTRICAL SYSTEMS

26 05 53 ............ IDENTIFICATION FOR ELECTRICAL SYSTEMS

26 24 16 ............ PANELBOARDS

26 28 13 ............ FUSES

26 29 13 ............ ENCLOSED CONTROLLERS

26 43 13 ............ SURGE PROTECTIVE DEVICES (SPDs)

26 56 00 ............ EXTERIOR LIGHTING

26 56 68 ............ EXTERIOR ATHLETIC LIGHTING

This item has been digitally signed and sealed by Stanley P. Newton, P.E. on the date adjacent to the seal. Printed copies of this document are not considered signed and sealed and the signature must be verified on any electronic copies.

ELECTRICAL AND LIGHTING

SPECIFICATION: E-1

10/11/2023

TABLE OF CONTENTS

THIS PAGE INTENTIONALLY LEFT BLANK

ELECTRICAL AND LIGHTING

SPECIFICATION: E-1

10/11/2023

26 05 00

COMMON WORK RESULTS FOR ELECTRICAL

E-1

SECTION 26 05 00

PART 1 GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.

B. Basic electrical requirements specifically applicable to Division 26 Electrical.

1.2 SECTION INCLUDES

A. Basic Electrical Requirements specifically applicable to Division 26 Sections, in addition to

Division 01 General Requirements.

1.3 INTENT

A. It is the intention of these specifications and drawings to call for finished work, tested, and ready for operation. Wherever the word "provide" is used, it shall mean "furnish and install complete and ready for use."

B. Minor details not usually shown or specified, but necessary for the proper installation and operation, shall be included in the work, the same as if herein specified or shown.

1.4 SURVEYS AND MEASUREMENTS

A. Base all measurements, both horizontal and vertical from established bench marks. All work shall agree with these established lines and levels. Verify all measurements at site and check the correctness of same as related to the work. All material take-offs for the site shall be field measured prior to bids.

1.5 DRAWINGS

A. Drawings are diagrammatic and indicate the general arrangement of systems and work included in the contract. Drawings are not to be scaled. The architectural drawings and details shall be examined for exact location of fixtures and equipment. Where they are not definitely located, this information shall be obtained from the Architect.

B. If directed by the Architect or Engineer, the Contractor shall, without extra charge, make reasonable modifications in the layout as needed to prevent conflict with work of other trades or for proper execution of the work.

ELECTRICAL AND LIGHTING

SPECIFICATION: E-1

10/11/2023

26 05 00

C. At the time of each shop drawing submission, the Contractor shall call the Engineer's attention (in writing) to, and plainly mark on shop drawings, any deviations from the Contract Documents.

D. Samples, drawings, specifications, catalogs, submitted for approval, shall be properly labeled indicating specific service for which material or equipment is to be used, location, section and article number of specifications governing, Contractor's name, and name of job.

All equipment shall be labeled to match labeling on contract documents.

E. Catalogs, pamphlets, or other documents submitted to describe items on which approval is being requested, shall be specific and identification in catalog, pamphlet, etc. of item submitted shall be clearly made in ink. Data of a general nature will not be accepted.

F. Approval rendered on shop drawings shall not be considered as a guarantee of measurements or building conditions. Where drawings are approved, said approval does not mean that drawings have been checked in detail; said approval does not in any way relieve the Contractor from his responsibility or necessity of furnishing material or performing work as required by the contract drawings and specifications.

G. All shop drawings shall be submitted to the A/E by Contractor no later than 30 days from the day of contract award.

H. Failure of the Contractor to submit shop drawings in ample time for checking shall not entitle him to an extension of contract time, and no claim for extension by reason of such default will be allowed.

I. Submit all Division 16 submittals at one (1) time in one (1) integral group. Piece-by-piece submission of individual items will not be acceptable. Engineer may check contents of each submittal set upon initial delivery; if not complete as set forth herein, submittal sets may be returned to Contractor without review and approval and will not be accepted until made complete.

J. At the close of the job, prior to final review, five (5) bound copies of the following shall be submitted by transmittal letter to the Engineer for review and acceptance.

1. Equipment warranties

2. Contractor's warranty

3. Parts list and manuals for all equipment

4. Operating Instructions (in writing)

5. Written instructions on maintenance and care of the system

1.6 REFERENCES

A. ANSI/NFPA 70—National Electrical Code.

B. State Requirements for Educational Facilities (SREF), Chapter 4, Section 453, of the Florida Building Code.

C. NFPA 101—Life Safety Code.

ELECTRICAL AND LIGHTING

SPECIFICATION: E-1

10/11/2023

26 05 00

D. Florida Department of Education Accessibility Guidelines and Requirements.

1.7 SUBMITTALS

A. Submit under provisions of Division 1.

B. Proposed Products List: Include Products specified in the following Sections, but not limited to:

1. Section 26 05 19 ............ Low-Voltage Electrical Power Conductors and Cables.

2. Section 26 05 26 ............ Grounding and Bonding for Electrical Systems.

3. Section 26 05 29 ............ Hangers and Supports for Electrical Systems.

4. Section 26 05 33 ............ Raceway and Boxes for Electrical Systems.

5. Section 26 05 53 ............ Identification for Electrical Systems.

6. Section 26 24 16 ............ Panelboards.

7. Section 26 28 13 ............ Fuses.

8. Section 26 29 13 ............ Enclosed Controllers.

9. Section 26 43 13 ............ Surge Protective Devices (SPDs).

10. Section 26 56 00 ............ Exterior Lighting.

11. Section 26 56 68 ............ Exterior Athletic Lighting.

C. It shall be understood that review of shop drawings by the Engineer does not supersede the requirement to provide a complete and functioning system in compliance with the Contract Documents.

1.8 SUBSTITUTIONS

A. Materials and equipment are specified herein by a single or by multiple Manufacturers to indicate quality and performance required. The drawings are based upon equipment scheduled on drawings and specified. If another Manufacturer is considered for substitution during the bidding process, the Electrical Contractor shall be responsible for coordinating all electrical, mechanical, structural, or architectural changes. Comparable equipment Manufacturers which are listed as equals shall be considered as substitutes. Manufacturers other than the basis of design shall submit a catalog information and 1/4" scale plan and section drawings showing proper fit and all clearances for maintenance items.

B. Substitutions of other Manufacturer's will be considered for use if, in the Engineers opinion, the item requested for substitution is equal to that specified. The Contractor shall provide to the Engineer a typed comparative list of the basis of design and the proposed substitute.

ELECTRICAL AND LIGHTING

SPECIFICATION: E-1

10/11/2023

26 05 00

Request for approval of substitutions or equals prior to bid must be made in writing. The approval of any substitutions or equals prior to bid shall not be construed as a shop drawing approval. The substitute or equal must be submitted as described in the specifications and meet all the requirements of the specifications and drawings.

C. All requests for substitutions shall be submitted as described in paragraph 1.07, B., and specifically indicate any and all differences or omissions between the product specified as basis of design and the product proposed for substitution.

D. Where the Contractor proposes to use an item of equipment other than that specified or detailed on the drawing, which requires any redesign of the structure, partitions, foundations, piping, wiring, or any other part of the mechanical or electrical, all such redesign, and all new drawings and detailing required therefore, shall be prepared by the Subcontractor at his own expense and submitted to the Architect/Engineer for approval.

E. Where such approved deviation requires quantity and arrangement of equipment from that specified or indicated on the drawings, any other additional equipment required by the system, at no additional cost to the Owner.

1.9 COOPERATION WITH OTHER TRADES

A. Give full cooperation to other trades and furnish in writing to the General Contractor, with copies to the Architect, any information necessary to permit the work of all trades to be installed satisfactorily and with the least possible interference or delay.

B. When work installed under this Division will be in close proximity to, or will interfere with work of other trades, assist in working out space conditions to make a satisfactory adjustment. If so directed by the Engineer/Architect, prepare composite working drawings and sections at a suitable scale not less than 1/4" = 1'0", clearly showing how work is to be installed in relation to the work of other trades. If the work is installed before coordinating with other trades, or so as to cause any interference with work of other trades, make all the necessary changes in work to correct the condition without extra charge.

C. Furnish to other trades, as required, all necessary templates, patterns, setting plans, and shop details for the proper installation of work and for the purpose of coordinating adjacent work.

1.10 ELECTRICAL UTILITY COORDINATION

A. The contractor shall arrange with Utility Company for permanent electric service including payment of Utility Company charges for service.

B. Service shall be underground Service Entrance. System Voltage: 120/240 volts, single phase, three-wire, 60 Hertz.

C. Utility Company: Duke Energy.

D. Install service entrance in accordance with Utility Company's rules and regulations.

ELECTRICAL AND LIGHTING

SPECIFICATION: E-1

10/11/2023

26 05 00

1.11 PROTECTION

A. Protect all work and material provided under this Division from damage. All damaged equipment work or material provided under this Division shall be replaced with new. Rebuilts are not acceptable.

B. Protect all work and equipment until inspected, tested, and accepted. Protect work against theft, injury, or damage; and carefully store material and equipment received on site which are not immediately installed. Close open ends of work with temporary covers or plugs during storage and construction to prevent entry of obstructing material.

1.12 SCAFFOLDING, RIGGING, AND HOISTING

A. Provide all scaffolding, rigging, hoisting, and services necessary for erection and delivery into the premises of any equipment and apparatus furnished. Remove same from premises when no longer required.

1.13 REMOVAL OF RUBBISH

A. This Contractor shall at all times keep premises free from accumulations of waste materials or rubbish caused by his employees or work. At completion of work he shall remove all his tools, scaffolding, materials, and rubbish from the building and site. He shall leave the premises and his work in a clean, orderly, and acceptable condition.

1.14 SAFETY

A. This Contractor shall comply with Section 107 of the Contract Work Hours and Safety

Standards Act (40 U.S.C.333), Title 29—Labor, Chapter XIII, Bureau of Standards, Department of Labor, Part 1518—Safety and Health Regulations for Construction; and that his housekeeping and equipment be maintained in such a manner that they comply with the Florida Industrial Commission Safety Code and Regulations of the Federal Williams— Steiger Occupational Safety and Health Act of 1970 (OSHA), wherein it states that the Contractor shall not require any laborer or mechanic employed in the performance of the contract to work in surroundings or under working conditions which are unsanitary, hazardous, or dangerous to his health and safety.

1.15 SUPERVISION

A. This Contractor shall provide a competent, experienced, full time superintendent who is acceptable to the Architect/Engineer and Owner, and who is authorized to make decisions on behalf of the Contractor.

1.16 MATERIAL AND WORKMANSHIP

A. All materials and apparatus required for the work, except as specifically specified otherwise, shall be new, of first-class quality, and shall be furnished, delivered, erected, connected and finished in every detail, and shall be so selected and arranged as to fit properly into the building spaces. Where no specific kind or quality of material is given, a first-class standard article as approved by the Engineer shall be furnished. Refer to substitutions in this Section.

B. Unless otherwise specifically indicated on the plans or specifications, all equipment and materials shall be installed with the approval of the Architect and Engineer in accordance

ELECTRICAL AND LIGHTING

SPECIFICATION: E-1

10/11/2023

26 05 00 with the recommendations of the Manufacturer. This includes the performance of such tests as the Manufacturer recommends.

1.17 QUIET OPERATION AND VIBRATION

A. All work shall operate under all conditions of load without any sound or vibration which is objectionable in the opinion of the Engineer and the Owner. In case of moving machinery, sound, or vibration noticeable outside of room in which it is installed, or annoyingly noticeable inside its own room, will be considered objectionable. Sound or vibration conditions considered objectionable by the Engineer and the Owner shall be corrected in an approved manner at no additional expense to the Owner.

1.18 FOUNDATIONS, SUPPORTS, PIERS, ATTACHMENTS

A. This Contractor shall furnish and install all necessary foundations, supports, pads, bases and piers required for all equipment furnished under this Division, and shall submit drawings to the Architect and Engineer for approval before purchase, fabrication or construction of same.

B. For all floor mounted equipment, provide concrete pads which extend six inches (6") beyond equipment base in all directions with top edge chamfered. Inset six inches (6") steel dowel rods into floors to anchor pads. Shop drawings of all foundations and pads shall be submitted to the Architect and Engineer for approval before same are constructed.

C. Construction of foundations, supports, pads, bases, and piers where mounted on the floor, shall be the same materials and same quality of finish as the adjacent and surrounding flooring material.

D. All equipment, unless shown otherwise, shall be securely attached to the building structure in an approved manner. Attachments shall be of a strong and durable nature and any attachments that are, in the opinion of the Architect and the Engineer, not strong enough shall be replaced as directed.

1.19 ACCESS DOORS FOR WALLS AND CEILINGS

A. Provide flush panel access doors with a 16 gauge steel frame and a 14 gauge steel door panel.

B. Finish is to be primed painted steel.

C. Provide concealed hinges which allow the door to open 175 degrees and have a removable pin.

D. Provide access doors with a locked flush mounted vandal proof spanner head operated steel cams.

E. Provide 1-1/2 hour "B" label door for rated chase walls.

F. Furnish masonry anchors for installation in masonry walls and metal lath wings with casing bead for plaster installation.

G. Provide a minimum 2'-0" by 2'-0" access doors unless shown or noted otherwise on the drawings.

ELECTRICAL AND LIGHTING

SPECIFICATION: E-1

10/11/2023

26 05 00

H. Access doors for chase walls shall be mounted 16" off the finish floor.

I. Access doors for electrical equipment shall be a minimum of 12" larger than equipment all around.

1.20 REGULATORY REQUIREMENTS

A. Conform to applicable Codes and Standards as follows:

1. Standard:

a. Certain standard materials and installation requirements are described by reference to standard specifications. These standards are as follows:

NEMA ....... National Electrical Manufacturers Association.

UL ............. Underwriters Laboratories.

ANSI ......... American National Standards Institute.

For additional standards and requirements see other sections of the specifications.

Whenever a reference is made to a standard, installation and materials shall comply with the latest published edition at the time project is bid unless otherwise specified herein.

2. Codes and Rules:

a. All material furnished and all work installed shall comply with the following codes as they apply to this project:

NFPA 70 and NFPA 101.

Regulations of the Florida Industrial Commission Concerning Safety.

Applicable County, State, and Local Building Codes.

Local and State Fire Marshal Rules and Regulations.

Chapter 4A-47, Florida Administrative Code - Uniform Fire Safety Standards for Elevators.

Occupational Safety and Health Agency Standards (OSHA).

Florida State Board of Health Rules and Regulations.

Florida Building Code.

Applicable codes shall be those adopted by the authority having jurisdiction at the time project is bid.

3. Permits, Fees and Inspections

ELECTRICAL AND LIGHTING

SPECIFICATION: E-1

10/11/2023

26 05 00

a. The Contractor shall give all necessary notices, obtain all permits and pay all government fees, sales taxes and other costs, including utility connections or extensions, in connection with this work; file all necessary approvals of all governmental departments having jurisdiction.

b. Obtain all required certificates of inspection for his work and deliver to the

Owner/Engineer the same certificates before request for acceptance and final payment for the work.

c. The Contractor shall include in the work, without extra cost to the Owner, any labor, materials, services, apparatus and drawings required to comply with all applicable laws, ordinances, rules and regulations.

d. The Contractor shall inform the Engineer of any work or materials which conflict with any of the applicable codes, standards, laws and regulations before submitting his bid.

B. Conform to Florida Department of Education Accessibility Guidelines and Requirements.

1.21 PROJECT/SITE CONDITIONS

A. Install Work in locations shown on Drawings, unless prevented by Project conditions.

B. Prepare drawings showing proposed rearrangement of Work to meet Project conditions, including changes to Work specified in other Sections. Obtain permission of Architect/Engineer before proceeding.

C. The Contractor shall inform the Engineer of any work or materials which conflict with any of the applicable codes, standards, laws and regulations before submitting his bid.

D. The scope of the work included under this Division of the Specifications shall include complete electrical systems as shown on the plans and as specified herein. The General Conditions and Special Conditions of these specifications shall form a part and be included under this Section of the Specifications. Provide all supervision, labor, material, equipment, machinery, factory trained personnel, and any and all other items necessary to complete the electrical systems. All items of equipment are specified in the singular; however, provide and install the number of items of equipment as indicated on the drawings, and as required for complete systems.

1.22 SEQUENCING AND SCHEDULING

A. Construct Work in sequence under provisions of Division 1.

ELECTRICAL AND LIGHTING

SPECIFICATION: E-1

10/11/2023

26 05 00

1.23 LICENSE

A. The Subcontracting Firm for the electrical and systems installation shall be licensed by the State of Florida and the local authorities, regularly engaged in the installation of electrical systems and other related equipment. The Subcontracting Firm shall be familiar with all local conditions including interpretations, codes and shall have at least 5 years of successful installation experience on similar projects of the same magnitude and scope.

The Subcontracting Firm shall list at least three projects it has successfully completed over the last five years for proof of experience of this caliber. This list shall be included with submittals for review by Architect/Engineer. The Subcontracting Firm shall hold a Florida State Certified Electrical Contractor license for this project. The Subcontracting firm for the fire alarm system shall be a certified "EF" installer.

1.24 AS-BUILT DRAWINGS

A. This Contractor shall provide AutoCad as-built drawings and copies of each AutoCad file on

CD before final payment will be issued.

*** END OF SECTION 26 05 00 ***

ELECTRICAL AND LIGHTING

SPECIFICATION: E-1

10/11/2023

26 05 00

ELECTRICAL AND LIGHTING

SPECIFICATION: E-1

10/11/2023

26 05 19

LOW-VOLTAGE ELECTRICAL POWER CONDUCTORS AND CABLES

SECTION 26 05 19

1.2 SUMMARY

A. This Section includes the following:

1. Building wires and cables rated 600 V and less.

2. Connectors, splices, and terminations rated 600 V and less.

3. Sleeves and sleeve seals for cables.

4. Conductor sizes are based on copper.

B. Related Sections include the following:

1. Section 26 05 33 ............ Raceway And Boxes For Electrical Systems.

2. Section 26 05 53 ............ Identification For Electrical Systems.

1.3 REFERENCES

A. ANSI/NFPA 70—National Electrical Code.

B. NEMA WC5—Thermoplastic Insulated Wire and Cable for the Transmission and Distribution of Electrical Energy.

1.4 DEFINITIONS

A. EPDM: Ethylene-propylene-diene terpolymer rubber.

B. NBR: Acrylonitrile-butadiene rubber.

1.5 SUBMITTALS

A. Product Data: For each type of product indicated.

1.6 QUALITY ASSURANCE

A. Electrical Components, Devices, and Accessories: Listed and labeled as defined in NFPA 70, Article 100, by a testing agency acceptable to authorities having jurisdiction, and marked for intended use.

ELECTRICAL AND LIGHTING

SPECIFICATION: E-1

10/11/2023

26 05 19

B. Comply with NFPA 70 where wire and cable is not shown.

1.7 COORDINATION

A. Set sleeves in cast-in-place concrete, masonry walls, and other structural components as they are constructed.

B. Determine required separation between cable and other work.

PART 2 PRODUCTS

2.1 CONDUCTORS AND CABLES

A. Available Manufacturers: Subject to compliance with requirements, manufacturers offering products that may be incorporated into the Work include, but are not limited to, the following:

B. Manufacturers: Subject to compliance with requirements, provide products by one of the following:

1. Alcan Products Corporation; Alcan Cable Division.

2. American Insulated Wire Corp.; a Leviton Company.

3. General Cable Corporation.

4. Senator Wire & Cable Company.

5. Southwire Company.

C. Copper Conductors: Comply with NEMA WC 70.

D. Conductor Insulation: Comply with NEMA WC 70 for Types THHN-THWN and XHHW.

E. Multiconductor Cable: Comply with NEMA WC 70 for Type SO with ground wire.

2.2 CONNECTORS AND SPLICES

1. AFC Cable Systems, Inc.

2. Hubbell Power Systems, Inc.

3. O-Z/Gedney; EGS Electrical Group LLC.

4. 3M; Electrical Products Division.

ELECTRICAL AND LIGHTING

SPECIFICATION: E-1

10/11/2023

26 05 19

5. Tyco Electronics Corp.

C. Description: Factory-fabricated connectors and splices of size, ampacity rating, material, type, and class for application and service indicated.

D. No splices shall be permitted in underground locations.

2.3 SLEEVES FOR CABLES

A. Steel Pipe Sleeves: ASTM A 53/A 53M, Type E, Grade B, Schedule 40, galvanized steel, plain ends.

B. Coordinate sleeve selection and application with selection and application of firestopping specified in Division 07 Section "Penetration Firestopping."

2.4 SLEEVE SEALS

1. Advance Products & Systems, Inc.

2. Calpico, Inc.

3. Metraflex Co.

4. Pipeline Seal and Insulator, Inc.

C. Description: Modular sealing device, designed for field assembly, to fill annular space between sleeve and cable.

1. Sealing Elements: EPDM interlocking links shaped to fit surface of cable or conduit.

Include type and number required for material and size of raceway or cable.

2. Pressure Plates: Carbon steel. Include two for each sealing element.

3. Connecting Bolts and Nuts: Carbon steel with corrosion-resistant coating of length required to secure pressure plates to sealing elements. Include one for each sealing element.

PART 3 EXECUTION

3.1 CONDUCTOR MATERIAL APPLICATIONS

A. Feeders: Copper. Solid for No. 10 AWG and smaller; stranded for No. 8 AWG and larger.

B. Branch Circuits: Copper. Solid for No. 10 AWG and smaller; stranded for No. 8 AWG and larger.

ELECTRICAL AND LIGHTING

SPECIFICATION: E-1

10/11/2023

26 05 19

3.2 CONDUCTOR INSULATION AND MULTICONDUCTOR CABLE APPLICATIONS AND WIRING

METHODS

A. Service Entrance: Type THHN-THWN-XHHW, single conductors in raceway.

B. Exposed Feeders: Type THHN-THWN, single conductors in raceway.

C. Feeders Concealed in Ceilings, Walls, Partitions, and Crawlspaces: Type THHN-THWN, single conductors in raceway.

D. Feeders Concealed in Concrete, below Slabs-on-Grade, and Underground: Type THHN- THWN, single conductors in raceway.

E. Feeders Installed below Raised Flooring: Type THHN-THWN, single conductors in raceway.

F. Feeders in Cable Tray: Type THHN-THWN, single conductors in raceway.

G. Exposed Branch Circuits, Including in Crawlspaces: Type THHN-THWN, single conductors in raceway.

H. Branch Circuits Concealed in Ceilings, Walls, and Partitions: Type THHN-THWN, single conductors in raceway.

I. Branch Circuits Concealed in Concrete, below Slabs-on-Grade, and Underground: Type

THHN-THWN, single conductors in raceway.

J. Branch Circuits Installed below Raised Flooring: Type THHN-THWN, single conductors in raceway.

K. Cord Drops and Portable Appliance Connections: Type SO, hard service cord with stainless-steel, wire-mesh, strain relief device at terminations to suit application.

L. Class 1 Control Circuits: Type THHN-THWN, in raceway.

M. Class 2 Control Circuits: Type THHN-THWN-TFFN, in raceway.

3.3 INSTALLATION OF CONDUCTORS AND CABLES

A. Conceal cables in finished walls, ceilings, and floors, unless otherwise indicated.

B. Use manufacturer-approved pulling compound or lubricant where necessary; compound used must not deteriorate conductor or insulation. Do not exceed manufacturer's recommended maximum pulling tensions and sidewall pressure values.

C. Use pulling means, including fish tape, cable, rope, and basket-weave wire/cable grips, that will not damage cables or raceway.

D. Concealed Dry Interior Locations: Use only building wire and cable (all types) in raceway.

E. Exposed Dry Interior Locations: For feeders, branch circuits, and class 1 remote control circuits, use only building wire in raceway. For class 2 or 3 control cable and power limited fire protective signaling cables run in raceway.

ELECTRICAL AND LIGHTING

SPECIFICATION: E-1

10/11/2023

26 05 19

F. Above Accessible Ceilings: For feeders, branch circuits and class 1 remote control cables use only building wire in raceway. For class 2 or 3 remote control cables run exposed. For power limited fire protective signaling cables run in raceway.

G. Wet or Damp Interior Locations: For feeders, branch circuits and class 1 remote control cables use only building wire in raceway. For class 2 or 3 remote control cable and power limited fire protective signaling cables run in raceway.

H. Exterior Locations: For feeders, branch circuits and class 1 remote control cables use only building wire run in raceway. For class 2 or 3 remote control cables and fire protective signaling cables run in raceway.

I. Underground Installations: For feeders, branch circuits and class 1 remote control cables use only building wire run in raceway. For class 2 or 3 remote control cables and for power limited fire protective signaling cables run in raceway.

J. Use wiring methods indicated on Drawings.

K. Each branch circuit shall have a dedicated neutral conductor. Shared neutrals on multiwire branch circuits are not acceptable.

L. Use 10 AWG conductors for 20 ampere, 120 volt branch circuits longer than 75 feet.

M. Use 10 AWG conductors for 20 ampere, 277 volt branch circuits longer than 200 feet.

N. All conductors size #6 and smaller shall be color coded insulation. Equipment grounding conductors #6 and smaller to have green or bare exterior finish per NEC 250-119(A).

Grounded conductors (neutral) #6 and smaller to have a white or grey exterior finish per NEC 200-6. Conductors size #4 and larger shall be color code by use of colored plastic tape applied within 6" of each conductor end. All color coding shall be with the same color being used with its respective phase or bus through the entire job as follows:

240/120 VOLTS

Phase A ....... Black Phase B ....... Red Phase C ...... Blue Neutral ......... White Ground ........ Green

O. Grounding conductors shall be identified with a continuous outer finish that is either green, or green with one or more yellow stripe.

P. Protect exposed cable from damage.

Q. Support cables above accessible ceiling, using spring metal clips or plastic cable ties to support cables from structure. Do not rest cable on ceiling panels.

R. Neatly train and lace wiring inside boxes, equipment, and panelboards.

S. Clean conductor surfaces before installing lugs and connectors.

ELECTRICAL AND LIGHTING

SPECIFICATION: E-1

10/11/2023

26 05 19

T. Make splices, taps, and terminations to carry full ampacity of conductors with no perceptible temperature rise.

U. Use split bolt connectors for copper conductor splices and taps, 6 AWG and larger. Tape uninsulated conductors and connector with electrical tape to 150 percent of insulation rating of conductor.

V. Use solderless pressure connectors with insulating covers for copper conductor splices and taps, 8 AWG and smaller.

W. Terminate spare conductors with electrical tape.

X. Use insulated spring wire connectors with plastic caps for copper conductor splices and taps, 10 AWG and smaller.

Y. Splice only in accessible junction boxes. No splices shall be permitted in underground locations.

Z. Identify and color-code conductors and cables according to Division 26 Section "Identification for Electrical Systems."

3.4 SLEEVE INSTALLATION FOR ELECTRICAL PENETRATIONS

A. Coordinate sleeve selection and application with selection and application of firestopping

B. Concrete Slabs and Walls: Install sleeves for penetrations unless core-drilled holes or formed openings are used. Install sleeves during erection of slabs and walls.

C. Use pipe sleeves unless penetration arrangement requires rectangular sleeved opening.

D. Fire-Rated Assemblies: Install sleeves for penetrations of fire-rated floor and wall assemblies unless openings compatible with firestop system used are fabricated during construction of floor or wall.

E. Cut sleeves to length for mounting flush with both wall surfaces.

F. Extend sleeves installed in floors 2 inches above finished floor level.

G. Seal space outside of sleeves with grout for penetrations of concrete and masonry.

H. Interior Penetrations of Non-Fire-Rated Walls and Floors: Seal annular space between sleeve and cable, using joint sealant appropriate for size, depth, and location of joint according to Division 07 Section "Joint Sealants."

I. Fire-Rated-Assembly Penetrations: Maintain indicated fire rating of walls, partitions, ceilings, and floors at cable penetrations. Install sleeves and seal with firestop materials according to Division 07 Section "Penetration Firestopping."

J. Roof-Penetration Sleeves: Seal penetration of individual cables with flexible boot-type flashing units applied in coordination with roofing work.

ELECTRICAL AND LIGHTING

SPECIFICATION: E-1

10/11/2023

26 05 19

K. Aboveground Exterior-Wall Penetrations: Seal penetrations using sleeves and mechanical sleeve seals. Size sleeves to allow for 1-inch annular clear space between pipe and sleeve for installing mechanical sleeve seals.

L. Underground Exterior-Wall Penetrations: Install cast-iron "wall pipes" for sleeves. Size sleeves to allow for 1-inch annular clear space between cable and sleeve for installing mechanical sleeve seals.

3.5 SLEEVE-SEAL INSTALLATION

A. Install to seal underground exterior-wall penetrations.

B. Use type and number of sealing elements recommended by manufacturer for cable material and size. Position cable in center of sleeve. Assemble mechanical sleeve seals and install in annular space between cable and sleeve. Tighten bolts against pressure plates that cause sealing elements to expand and make watertight seal.

3.6 FIRESTOPPING

A. Apply firestopping to electrical penetrations of fire-rated floor and wall assemblies to restore original fire-resistance rating of assembly according to Division 07 Section "Penetration Firestopping."

*** END OF SECTION 26 05 19 ***

ELECTRICAL AND LIGHTING

SPECIFICATION: E-1

10/11/2023

26 05 19

ELECTRICAL AND LIGHTING

SPECIFICATION: E-1

10/11/2023

26 05 26

GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS

SECTION 26 05 26

A. This Section includes methods and materials for grounding systems and equipment.

1. Underground distribution grounding.

1.3 SYSTEM DESCRIPTION

A. Ground the electrical service system neutral at service entrance equipment to metallic water service, concrete encased rebar, building steel, and to supplementary grounding electrodes.

B. Ground each separately-derived system neutral to nearest effectively grounded metallic water pipe, concrete encased rebar, nearest effectively grounded building structural steel member, and separate grounding electrode.

C. Provide communications system grounding conductor at point of service entrance and connect to separate grounding electrode.

D. Bond together system neutrals, service equipment enclosures, exposed non-current carrying metal parts of electrical equipment, metal raceway systems, grounding conductor in raceways and cables, receptacle ground connectors, and plumbing systems.

E. Install lightning surge protection on all service entrances as shown on drawings. Lightning surge protector shall have a minimum withstand rating of a Class "C" test.

F. Bond metallic gas piping with #4 AWG copper conductor.

1.4 SUBMITTALS

A. Product Data: For each type of product indicated.

B. Other Informational Submittals: Plans showing dimensioned as-built locations of grounding features specified in Part 3 "Field Quality Control" Article, including the following:

1. Test wells.

2. Ground rods.

3. Ground rings.

ELECTRICAL AND LIGHTING

SPECIFICATION: E-1

10/11/2023

26 05 26

4. Grounding arrangements and connections for separately derived systems.

5. Grounding for sensitive electronic equipment.

C. Qualification Data: For testing agency and testing agency's field supervisor.

D. Field quality-control test reports.

E. Operation and Maintenance Data: For grounding to include the following in emergency, operation, and maintenance manuals:

1. Instructions for periodic testing and inspection of grounding features at test wells, ground rings, and grounding connections for separately derived systems based on

NETA MTS.

a. Tests shall be to determine if ground resistance or impedance values remain within specified maximums, and instructions shall recommend corrective action if they do not.

b. Include recommended testing intervals.

1.5 QUALITY ASSURANCE

A. Testing Agency Qualifications: An independent agency, with the experience and capability to conduct the testing indicated, that is a member company of the InterNational Electrical Testing Association or is a nationally recognized testing laboratory (NRTL) as defined by OSHA in 29 CFR 1910.7, and that is acceptable to authorities having jurisdiction.

1. Testing Agency's Field Supervisor: Person currently certified by the InterNational

Electrical Testing Association to supervise on-site testing specified in Part 3.

B. Electrical Components, Devices, and Accessories: Listed and labeled as defined in NFPA 70, Article 100, by a testing agency acceptable to authorities having jurisdiction, and marked for intended use.

C. Comply with UL 467 for grounding and bonding materials and equipment.

D. Grounding system resistance shall not exceed 10 ohms.

E. Use suitable test instrument to measure resistance to ground of system. Perform testing in accordance with test instrument manufacturer's recommendations using the fall-of-potential method. Submit test results to Engineer for review and approval immediately upon completing the test and prior to energizing new utility service. The testing shall include sufficient ground resistant data readings from distances up 100 feet away from the ground triad in order to plot a distinct plateau between two distinctive slopes.

2.1 CONDUCTORS

A. Insulated Conductors: Copper wire or cable insulated for 600 V unless otherwise required by applicable Code or authorities having jurisdiction.

ELECTRICAL AND LIGHTING

SPECIFICATION: E-1

10/11/2023

26 05 26

B. Bare Copper Conductors:

1. Solid Conductors: ASTM B 3.

2. Stranded Conductors: ASTM B 8.

3. Tinned Conductors: ASTM B 33.

4. Bonding Cable: 28 kcmil, 14 strands of No. 17 AWG conductor, 1/4 inch in diameter.

5. Bonding Conductor: No. 4 or No. 6 AWG, stranded conductor.

6. Bonding Jumper: Copper tape, braided conductors, terminated with copper ferrules;

1-5/8 inches wide and 1/16 inch thick.

7. Tinned Bonding Jumper: Tinned-copper tape, braided conductors, terminated with copper ferrules; 1-5/8 inches wide and 1/16 inch thick.

C. Grounding Bus: Rectangular bars of annealed copper, 1/4 by 4 inches in cross section, unless otherwise indicated; with insulators, length as required for number of terminations plus 25 percent future capacity.

2.2 CONNECTORS

A. Listed and labeled by a nationally recognized testing laboratory acceptable to authorities having jurisdiction for applications in which used, and for specific types, sizes, and combinations of conductors and other items connected.

B. Bolted Connectors for Conductors and Pipes: Copper or copper alloy, bolted pressure-type, with at least two bolts.

1. Pipe Connectors: Clamp type, sized for pipe.

C. Welded Connectors: Exothermic-welding kits of types recommended by kit manufacturer for materials being joined and installation conditions.

2.3 GROUNDING ELECTRODES

A. Ground Rods: Copper-clad; sectional type, 3/4 inch by 10 feet in diameter, two (2) rods coupled together for overall length of 20 feet.

3.1 APPLICATIONS

A. Conductors: Install solid conductor for No. 10 AWG and smaller, and stranded conductors for No. 8 AWG and larger, unless otherwise indicated.

ELECTRICAL AND LIGHTING

SPECIFICATION: E-1

10/11/2023

26 05 26

B. Underground Grounding Ring Conductors: Install bare-copper conductor, No. 4/0 AWG minimum when indicated on the drawings to provide.

1. Bury at least 24 inches below grade.

2. Duct-Bank Grounding Conductor: Bury 12 inches above duct bank when indicated as part of duct-bank installation.

C. Isolated Grounding Conductors: Green-colored insulation with continuous yellow stripe. On feeders with isolated ground, identify grounding conductor where visible to normal inspection, with alternating bands of green and yellow tape, with at least three bands of green and two bands of yellow.

D. Grounding Bus: Install in electrical and telephone equipment rooms, in rooms housing service equipment, and elsewhere as indicated.

1. Install bus on insulated spacers 1 inch, minimum, from wall, 6 inches above finished floor, unless otherwise indicated.

E. Conductor Terminations and Connections:

1. Pipe and Equipment Grounding Conductor Terminations: Bolted connectors.

2. Underground Connections: Welded connectors, except at test wells and as otherwise indicated.

3. Connections to Ground Rods at Test Wells: Bolted connectors.

4. Connections to Structural Steel: Clamp connectors.

3.2 GROUNDING UNDERGROUND DISTRIBUTION SYSTEM COMPONENTS

A. Comply with IEEE C2 grounding requirements.

B. Grounding Connections to Manhole Components: Bond exposed-metal parts such as inserts, cable racks, pulling irons, ladders, and cable shields within each manhole or handhole, to ground rod or grounding conductor. Make connections with No. 4 AWG minimum, stranded, hard-drawn copper bonding conductor. Train conductors level or plumb around corners and fasten to manhole walls. Connect to cable armor and cable shields as recommended by manufacturer of splicing and termination kits.

3.3 EQUIPMENT GROUNDING

A. Install insulated equipment grounding conductors with all feeders and branch circuits.

B. Install insulated equipment grounding conductors with the following items, in addition to those required by NFPA 70:

1. Feeders and branch circuits.

2. Lighting circuits.

3. Receptacle circuits.

ELECTRICAL AND LIGHTING

SPECIFICATION: E-1

10/11/2023

26 05 26

4. Single-phase motor and appliance branch circuits.

5. Three-phase motor and appliance branch circuits.

6. Flexible raceway runs.

7. Armored and metal-clad cable runs.

8. Busway Supply Circuits: Install insulated equipment grounding conductor from grounding bus in the switchgear, switchboard, or distribution panel to equipment grounding bar terminal on busway.

9. Computer and Rack-Mounted Electronic Equipment Circuits: Install insulated equipment grounding conductor in branch-circuit runs from equipment-area power panels and power-distribution units.

C. Signal and Communication Equipment: For telephone, alarm, voice and data, and other communication equipment, provide No. 4 AWG minimum insulated grounding conductor in raceway from grounding electrode system to each service location, terminal cabinet, wiring closet, and central equipment location.

1. Service and Central Equipment Locations and Wiring Closets: Terminate grounding conductor on a 1/4-by-4-by-12-inch grounding bus.

2. Terminal Cabinets: Terminate grounding conductor on cabinet grounding terminal.

D. Metal and Concrete Poles Supporting Outdoor Lighting Fixtures: Install grounding electrode and a separate insulated equipment grounding conductor in addition to grounding conductor installed with branch-circuit conductors. Provide ground rod at each location.

3.4 INSTALLATION

A. Grounding Conductors: Route along shortest and straightest paths possible, unless otherwise indicated or required by Code. Avoid obstructing access or placing conductors where they may be subjected to strain, impact, or damage.

B. Common Ground Bonding with Lightning Protection System: Comply with NFPA 780 and

UL 96 when interconnecting with lightning protection system. Bond electrical power system ground directly to lightning protection system grounding conductor at closest point to electrical service grounding electrode. Use bonding conductor sized same as system grounding electrode conductor, and install in conduit.

C. Ground Rods: Drive rods until tops are 2 inches below finished floor or final grade, unless otherwise indicated.

1. Interconnect ground rods with grounding electrode conductor below grade and as otherwise indicated. Make connections without exposing steel or damaging coating, if any.

ELECTRICAL AND LIGHTING

SPECIFICATION: E-1

10/11/2023

26 05 26

D. Test Wells: Ground rod driven through drilled hole in bottom of handhole. Handholes are specified in Division 26 Section "Underground Ducts and Raceways for Electrical Systems," and shall be at least 12 inches deep, with cover.

1. Test Wells: Install at least one test well for each service, unless otherwise indicated.

Install at the ground rod electrically closest to service entrance. Set top of test well flush with finished grade or floor.

E. Bonding Straps and Jumpers: Install in locations accessible for inspection and maintenance, except where routed through short lengths of conduit.

1. Bonding to Structure: Bond straps directly to basic structure, taking care not to penetrate any adjacent parts.

2. Bonding to Equipment Mounted on Vibration Isolation Hangers and Supports: Install so vibration is not transmitted to rigidly mounted equipment.

3. Use exothermic-welded connectors for outdoor locations, but if a disconnect-type connection is required, use a bolted clamp.

F. Grounding and Bonding for Piping:

1. Metal Water Service Pipe: Install insulated copper grounding conductors, in conduit, from building's main service equipment, or grounding bus, to main metal water service entrances to building. Connect grounding conductors to main metal water service pipes, using a bolted clamp connector or by bolting a lug-type connector to a pipe flange, using one of the lug bolts of the flange. Where a dielectric main water fitting is installed, connect grounding conductor on street side of fitting. Bond metal grounding conductor conduit or sleeve to conductor at each end.

2. Water Meter Piping: Use braided-type bonding jumpers to electrically bypass water meters. Connect to pipe with a bolted connector.

3. Bond each aboveground portion of gas piping system downstream from equipment shutoff valve.

G. Ground Ring (when identified and called for on the drawings): Install a grounding conductor, electrically connected to each building structure ground rod and to each indicated item, extending around the perimeter of item indicated.

1. Install copper conductor not less than No. 4/0 AWG for ground ring and for taps to building steel.

2. Bury ground ring not less than 24 inches from building foundation.

H. Ufer Ground (Concrete-Encased Grounding Electrode): Fabricate according to NFPA 70, using a minimum of 20 feet of bare copper conductor not smaller than No. 4 AWG.

1. If concrete foundation is less than 20 feet long, coil excess conductor within base of foundation.

ELECTRICAL AND LIGHTING

SPECIFICATION: E-1

10/11/2023

26 05 26

2. Bond grounding conductor to reinforcing steel in at least four locations and to anchor bolts. Extend grounding conductor below grade and connect to building grounding grid or to grounding electrode external to concrete.

3.5 FIELD QUALITY CONTROL

A. Testing Agency: Owner will engage a qualified testing and inspecting agency to perform field tests and inspections and prepare test reports.

B. Testing Agency: Engage a qualified testing and inspecting agency to perform the following field tests and inspections and prepare test reports:

C. Perform the following tests and inspections and prepare test reports:

1. After installing grounding system but before permanent electrical circuits have been energized, test for compliance with requirements.

2. Test completed grounding system at each location where a maximum ground-resistance level is specified, at service disconnect enclosure grounding terminal, and at individual ground rods. Make tests at ground rods before any conductors are connected.

a. Measure ground resistance not less than two full days after last trace of precipitation and without soil being moistened by any means other than natural drainage or seepage and without chemical treatment or other artificial means of reducing natural ground resistance.

b. Perform tests by fall-of-potential method according to IEEE 81.

3. Prepare dimensioned drawings locating each test well, ground rod and ground rod assembly, and other grounding electrodes. Identify each by letter in alphabetical order, and key to the record of tests and observations. Include the number of rods driven and their depth at each location, and include observations of weather and other phenomena that may affect test results. Describe measures taken to improve test results.

D. Report measured ground resistances that exceed the following values:

1. Main service equipment and distribution gear.

2. Separately derived system (i.e., transformers, uninterruptible power supply, engine generators).

3. Grounding system resistance shall not exceed 10 ohms.

E. Excessive Ground Resistance: If resistance to ground exceeds specified values, notify Architect/Engineer promptly and include recommendations to reduce ground resistance.

F. Supplement by adding additional ground rods to achieve 10 ohms.

*** END OF SECTION 26 05 26 ***

ELECTRICAL AND LIGHTING

SPECIFICATION: E-1

10/11/2023

26 05 26

ELECTRICAL AND LIGHTING

SPECIFICATION: E-1

10/11/2023

26 05 29

HANGERS AND SUPPORTS FOR ELECTRICAL SYSTEMS

SECTION 26 05 29

A. This Section includes the following:

1. Hangers and supports for electrical equipment and systems.

2. Construction requirements for concrete bases.

3. Supports/safety wire and chains for light fixtures and equipment.

1. Division 26 Section "Interior Lighting and Theatrical Lighting."

1.3 DEFINITIONS

A. EMT: Electrical metallic tubing.

B. IMC: Intermediate metal conduit.

C. RMC: Rigid metal conduit.

1.4 PERFORMANCE REQUIREMENTS

A. Design supports for multiple raceways capable of supporting combined weight of supported systems and its contents.

B. Design equipment supports capable of supporting combined operating weight of supported equipment and connected systems and components.

1.5 SUBMITTALS

A. Product Data: For the following:

1. Steel slotted support systems.

2. Nonmetallic slotted support systems.

ELECTRICAL AND LIGHTING

SPECIFICATION: E-1

10/11/2023

26 05 29

B. Shop Drawings: Signed and sealed by a qualified professional engineer. Show fabrication and installation details and include calculations for the following:

1. Trapeze hangers. Include Product Data for components.

2. Steel slotted channel systems. Include Product Data for components.

3. Nonmetallic slotted channel systems. Include Product Data for components.

4. Equipment supports.

C. Welding certificates.

1.6 QUALITY ASSURANCE

A. Welding: Qualify procedures and personnel according to AWS D1.1/D1.1M, "Structural

Welding Code - Steel."

B. Comply with NFPA 70.

1.7 COORDINATION

A. Coordinate size and location of concrete bases. Cast anchor-bolt inserts into bases.

Concrete, reinforcement, and formwork requirements are specified in Division 03.

B. Coordinate installation of roof curbs, equipment supports, and roof penetrations. These items are specified in Division 07 Section "Roof Accessories."

2.1 SUPPORT, ANCHORAGE, AND ATTACHMENT COMPONENTS

A. Steel Slotted Support Systems: Comply with MFMA-4, factory-fabricated components for field assembly.

1. Available Manufacturers:…