About this file

The document is a Florida Trench Safety Act Certification and Disclosure Statement, which is a mandatory compliance form for construction contractors working on projects in Florida. The form is specifically related to the High Point Community Park project in Pinellas County, requiring bidders to acknowledge and comply with state excavation safety standards established by federal guidelines (29 C.F.R. Section 1926.650 Subpart P). Contractors must disclose their proposed trench safety measures, including the linear feet of trench excavation and associated safety techniques, though these costs are for informational purposes and do not constitute the full extent of safety compliance obligations.

The document emphasizes that the disclosed costs do not limit the contractor's responsibility to ensure full compliance with trench safety requirements. Contractors are explicitly warned that they may need to extend additional funds at no extra cost to the county to meet safety standards. The form requires detailed documentation of safety measures, units of measure, quantities, and associated costs, with a clear stipulation that failure to complete the form may result in the bid being declared non-responsive. The form serves as a critical risk management and safety documentation tool for construction projects involving trenching and excavation work.

View the file

Other files

Show all 24

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FLORIDA TRENCH SAFETY

FLORIDA TRENCH SAFETY ACT

CERTIFICATION AND DISCLOSURE STATEMENT

The undersigned acknowledges the requirements of the Florida Trench Safety Act (Section 553.60 et. seq. Florida Statutes).

A. The Bidder further acknowledges that the Florida Trench Safety Act, (the Act) establishes the Federal excavation safety standards set forth at 29 C.F.R. Section 1926.650 Subpart P, as the interim state standard until such time as the state of Florida, through its Department of Labor and Employment Security, or any successor agency, adopts, updates, or revises said interim standard. This State of Florida standard may be supplemented by special shoring requirements established by the State of Florida or any of its political subdivisions.

B. The Bidder, as Contractor, shall comply with all applicable excavation/trench safety standards.

C. The contractor shall consider the geotechnical data available from the County, if any, the Contractor's own sources, and all other relevant information in its design of the trench safety system to be employed on the subject Project. The Contractor acknowledges sole responsibilities for the selection of the data on which it relies in designing the safety system, as well as for the system itself.

D. The amounts that the Bidder has set forth for pipe installation includes the following excavation/trench safety measures and the linear feet of trench excavated under each safety measure. These units, costs, and unit values shall be disclosed solely for the purpose of compliance with procedural requirements of the Act. No adjustment to the Agreement Time or price shall be made for any difference in the actual number of linear feet of trench excavation, except as may be otherwise provided in these Contract Documents.

Trench Safety Measure (Description)

Units of Measure

(LF, SF)

Unit (Quantity)

Unit Cost

Extended Cost

1. $ $

2. $ $

3. $ $

4. $ $

5. $ $ For Information Only, Not for Payment Purposes $

FLORIDA TRENCH SAFETY

Bidder may use additional sheets as necessary to extend this form. Failure to complete the above may result in the bid being declared non-responsive.

A. The amount disclosed as the cost of compliance with the applicable trench safety requirements does not constitute the extent of the Contractor’s obligation to comply with said standards. The Contractor shall extend additional sums at no additional cost to the County, if necessary, to comply with the Act (except as otherwise be provided).

B. Acceptance of the bid to which this certification and disclosure applies in no way represents that the County or its representatives has evaluated and thereby determined that the above costs are adequate to comply with the applicable trench safety requirements nor does it in any way relieve the Contractor of its sole responsibility to comply with the applicable trench safety requirements.