Specifications_Nogales Waterline Connection.pdf
PDF 1 MB Posted
- Solicitation number
- 127EAX26Q0016
- Issued by
-
Department of Agriculture Forest Service
About this file
This document is a specifications package for the Nogales Ranger Station Waterline Connection project, issued by the U.S. Forest Service (Southwest Region 03, Coronado National Forest) in July 2025.
The project involves constructing approximately 115 linear feet of new 6-inch potable waterline to connect the Nogales Ranger Station to Valle Verde Water Company's existing water main, transitioning the station from an on-site well to municipal water supply. The base bid work includes: furnishing and installing a new 6-inch water meter to replace the existing 1-inch meter; installing the waterline with all necessary fittings, valves, and appurtenances; capping existing 8-inch and 4-inch waterlines while maintaining service to the Ruby House and warehouse sprinkler system; installing a 2-inch double check valve assembly at the warehouse overhead fill station; installing a 2-inch air release valve and 2-inch post flushing hydrant at specified locations; and carefully removing and replacing existing fencing crossed by the waterline. The optional bid includes furnishing and installing a 6-inch Reduced Pressure Principle Zone Assembly with concrete slab, enclosure, and testing, contingent upon water pressure verification and cross-connection control requirements. Key materials specified include ductile iron and PVC pipe, AWWA-compliant backflow prevention devices, cast-in-place or precast concrete (minimum 3,000 psi), and NSF-certified plumbing components for potable water contact. All work must comply with current editions of the International Building Code, American Water Works Association standards, OSHA regulations, and Arizona Department of Environmental Quality requirements. The contractor is responsible for obtaining all necessary permits, coordinating with Valle Verde Water Company and Santa Cruz County, protecting existing utilities and site vegetation, performing hydrostatic testing at 150 psi minimum, disinfecting new waterlines with chlorine, and providing as-built drawings and operation/maintenance documentation upon project completion.
View the file
Other files
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SOUTHWEST REGION 03
CORONADO NATIONAL FOREST
SANTA CRUZ COUNTY
NOGALES RANGER STATION
WATERLINE CONNECTION TO VALLE VERDE
SPECIFICATIONS
U.S. FOREST SERVICE
July 2025
Table of Contents
DIVISION 1 – GENERAL REQUIREMENTS
SECTION 01 11 00 – SUMMARY OF WORK
SECTION 01 20 00 – MEASUREMENT AND PAYMENT
SECTION 01 31 00 – PROJECT MANAGEMENT AND COORDINATION
SECTION 01 33 00 – SUBMITTALS
SECTION 01 45 00 – QUALITY CONTROL
SECTION 01 50 00 – TEMPORARY FACILITIES AND CONTROLS
SECTION 01 71 13 – MOBILIZATION
SECTION 01 77 00 – CLOSEOUT PROCEDURES
DIVISION 2 – EXISTING CONDITIONS
SECTION 02 41 19 – SELECTIVE DEMOLITION
DIVISION 3 – CONCRETE
SECTION 03 30 00 – CAST-IN-PLACE CONCRETE OR PRE-CAST CONCRETE
DIVISION 22 – PLUMBING
SECTION 22 11 13 – BACKFLOW PREVENTERS
SECTION 22 11 50 – HYDRANTS
DIVISION 31 – EARTHWORK
SECTION 31 11 00 – CLEARING AND GRUBBING
SECTION 31 23 16 – EXCAVATION AND BACKFILL FOR UTILITIES
DIVISION 33 – UTILITIES
SECTION 33 11 13 – PIPE, FITTINGS AND SPECIALTIES
SECTION 33 11 23 – WATERLINES AND APPURTENANCES
SECTION 33 12 16 – VALVES
SECTION 33 12 18 – VALVE BOXES AND ENCLOSURES
SECTION 33 12 33 – METERS
NOGALES RANGER STATION [Type here] SUMMARY OF WORK WATERLINE CONNECTION Page | 3 | 01 11 00
DIVISION 1 – GENERAL REQUIREMENTS
SECTION 01 11 00 – SUMMARY OF WORK
PART 1 GENERAL
1.1 PROJECT INFORMATION
A. Project Identification: Nogales Ranger Station – Waterline Extension to Connect to Valle Verde Water Company (Valle Verde WC or VVWC).
1. Project Location: Nogales Ranger Station, 303 Old Tucson Road, Nogales, Arizona.
B. PROJECT BID
1. This project includes a BASE BID and OPTIONAL BID.
a. Optional Bid includes the complete installation of a 6-inch Reduced Pressure Principle Zone Assembly, if required, after consultation with Valle Verde WC. The following condition and test can determine if the RPPZ assembly will be necessary.
1) Condition:
a) Cross Connection device necessary after review of existing and new cross connection control devices on the Nogales Ranger Station Water System Site Plan. If determined there is no adequate cross connection control protection, the RPPZ assembly shall be installed.
b) The existing distribution system includes existing RPPZ assemblies on the landscape irrigation system and the fire hydrant protection units.
New double check valve assembly will be installed for existing 2-inch overhead fill station (with no hose connection) with air gap.
2) Test:
a) Contractor shall determine if PRV is required after coordination with Valle Verde Water Company and verification of static water pressure at the meter location.
b) The ideal static pressure range is typically 40-80 psi. If the static pressure exceeds 80 psi, a PRV will be required by plumbing code.
C. BASE BID: The work consists of:
1. Connect to Valle Verde WC water main off of government property within utility easement. The following coordinate is location of existing 1-inch water meter:
Latitude: 34.425960
Longitude: -110.962112
Constructing approximately 115 lineal feet of new 6-inch potable waterline from nearby private regulated water system known as Valle Verde Water Company. This water company operates and is managed as a private water company under Southwestern Utility Management.
The waterline connection is to connect Valle Verde Company to the Nogales Ranger
WATERLINE CONNECTION Page | 4 | 01 11 00
Station distribution system for potable water and fire protection system. The existing well at Nogales Ranger Station will be disconnected as the water source.
2. Furnish and install a new 6-inch water meter as recommended or purchased from Valle Verde Water Company to replace the existing 1-inch water meter to accommodate the ranger station’s existing 6-inch water main (combination potable water and fire protection system).
3. Install approximately 115-lineal feet of 6-inch potable water line to connect to existing Nogales water distribution system at location, AS SHOWN ON DRAWING.
4. Carefully remove all existing fencing crossing new waterline installation and make all necessary repairs and/or replacements, as needed, to return to original functionality.
5. Furnish and install components to cap existing 8-inch waterline after tee to Ruby House service connection, AS SHOWN ON DRAWING. Service to Ruby House shall remain functional.
6. Furnish and install components to cap 4-inch waterline to disconnect the gravity feed from the tank, AS SHOWN ON DRAWING. The water service connection providing water to sprinkler system for warehouse shall remain functional.
7. Furnish and install 2-inch double check valve assembly (DCVA) between the potable water system and the overhead fill station at the warehouse, including fittings for future maintenance and shut-off such as valves and unions, AS SHOWN ON
DRAWING.
8. Furnish and install 2-inch air release valve and valve box at location, AS SHOWN
ON DRAWING.
9. Furnish and install 2-inch post flushing hydrant including shut off valve and valve box at location, AS SHOWN ON DRAWING. There will be a dead end main at the end of the existing 4-inch waterline.
10. Furnish and install all fittings including valves, valve boxes, and unions to allow isolation for major fittings and/or equipment for future maintenance purposes.
D. OPTIONAL BID. The work consists of:
1. Furnish and install new 6-inch Reduced Pressure Principle Zone (RPZ) assembly (testable) at location AS SHOWN ON DRAWING.
2. Furnish and install a new RPZ enclosure with manageable access areas for testing and repair without removing entire enclosure. Enclosure shall be equipped with lockable access doors and/or lid to protect against theft or vandalism.
WATERLINE CONNECTION Page | 5 | 01 11 00
E. Site Photos:
Existing 1-inch Meter Warehouse – Exterior Plumbing
Location of Existing 1-inch Meter (blue pin)
WATERLINE CONNECTION Page | 6 | 01 11 00
1.2 WORK RESTRICTIONS
A. Contractor’s Use of Premises: During construction, Contractor will have limited use of site indicated. Contractor’s use of premises is limited only by Government’s right to perform work or employ other contractors on portions of Project and as follows:
1. FS will occupy premises during construction. Perform construction only during normal working hours 7:30 to 4:30 Monday thru Friday, other than holidays, unless otherwise agreed to in advance by Owner. Clean up work areas and return to usable condition at the end of each work period.
2. Driveways, Walkways, and Entrances: Keep driveways and entrances serving premises clear and available to government, Forest Service employees, and emergency vehicles at all times. Do not use these areas for parking or storage of materials.
B. Contractor shall at all times conduct his/her operations to ensure the least inconvenience to the public and employees.
C. Confine storage of materials to areas as approved by the COR.
D. Contractor shall provide adequate signing and barricades and take necessary safety measures to protect the public during all construction operations. Contractor shall minimize disturbance of all undisturbed areas.
E. Preservation of Natural Features: Confine all operations to work limits of the project.
Prevent damage to natural surroundings. Restore damaged areas, repairing or replacing damaged trees and plants, at no additional expense to the Government.
1. Provide temporary barriers to protect existing trees and plants and root zones.
2. Do not remove, injure, or destroy trees or other plants without prior approval. Consult with COR and remove agreed on roots and branches that interfere with construction.
3. Do not fasten ropes, cables, or guy wires to existing trees.
4. Carefully supervise excavating, grading, filling, and other construction operations near trees to prevent damage.
F. Existing Utilities
1. There is an existing sewerline, fenceline “F” line, existing “UT” utility line (UT- Underground telephone), electrical lines (well service feeder, annunciator wiring, fire alarm auxiliary to warehouse, Ruby House service feeder, warehouse feeder), and telecommunication/data lines.
2. Coordinate with local authorities having jurisdiction including the Forest Service.
3. There is electricity available on this site. Contractor is responsible for providing own connection to the power source.
4. There is water available at the site.
5. Sanitary facilities for construction workers shall be furnished and maintained by the Contractor during the life of the contract.
6. The Contractor shall always ensure the safety of the employees and public.
7. The Contractor shall provide adequate warnings of environmental and safety
WATERLINE CONNECTION Page | 7 | 01 11 00 hazards.
8. The Contractor shall coordinate with the COR on the proposed waterline alignment to minimize resource damage.
1.3 Field Verification
A. Bidders are encouraged to visit the site, compare the specifications with any work in place, and inform themselves of all conditions, including other work, if any, being performed. Failure to visit the site will in no way relieve the successful bidder from the necessity of furnishing any materials or performing any work that may be required to complete work in accordance with specifications, without additional cost to the Government.
B. Information regarding the sites of the work provided in specifications is believed to be reasonably correct, but the Government does not warrant either the completeness or accuracy of such information, and it is the responsibility of the contractor to verify all information independently and to make other examinations of the conditions to be encountered during construction.
C. The contractor acknowledges that he/she has investigated and satisfied himself/herself as to the conditions affecting the work, including, but not restricted to, those bearing upon transportation, disposal, handling and storage of materials, availability of labor, water, electric power, roads, and conditions of the ground, the character of equipment and facilities needed prior to and during prosecution of the work. The contractor further acknowledges that he/she is satisfied as to the character, quality, and quantity of surface and subsurface materials or obstacles to be encountered insofar as this information is reasonably ascertainable from as inspection of the sites. Any failure by the contractor to acquaint himself/herself with the available information will not relieve him/her from the responsibility for estimating properly the difficulty or cost of successfully performing the work.
1.4 Precautionary Measures
A. Protection of Work: The Contractor shall take precautions to protect all work during the construction period. The Contractor shall provide and maintain adequate protection during severe weather conditions to prevent damage to the work, materials, and equipment. The existing elements of the buildings or other features such as utilities shall remain undamaged and structurally sound during all phases of this contract. Any damage to existing structures, utilities or their functional elements resulting from the Contractor’s work at the sites shall be immediately repaired at no additional cost to the Government.
B. Safety: The Contractor is responsible for safeguarding employees, public, existing facilities, and forest resources from his/her operations. All operations shall comply with the requirements and restrictions of OSHA, the Arizona Occupational Safety and Health Code, and the Workman’s Compensation Board. The Contractor shall erect signs and barricades to make unguarded operations safe as required. Signs and barricades shall be maintained at night and on weekends. Precautions such as safely storing materials shall be practiced preventing injury to others in the area.
C. Security: Security is not provided by the Government. The Contractor shall take all precautions deemed necessary to secure the worksites, improvements and equipment.
WATERLINE CONNECTION Page | 8 | 01 11 00
This may include security fencing at the Contractor’s discretion.
1.5 Material Sources
A. All materials shall be obtained from commercial sources unless noted otherwise.
Materials referred to by trade name, make, or catalog number shall be regarded as establishing a standard of quality; substitutions of equal quality can be made by submitting a data sheet of the proposed substituted item to the Contracting Officer’s Representative, for approval.
1.6 Clean up and Disposal – Non-Hazardous Waste
A. Waste accumulation in approved containers and material staging is allowed at the site.
Disposal of waste material will be off National Forest Land and in compliance with local, state, and federal laws regarding disposal of construction waste. Before final acceptance of the project by the Government, the Contractor shall remove from Government land all waste materials and rubbish resulting from this work.
1.7 Applicable Codes and Standards
A. All work shall conform to the latest editions of the International Building Code, American Welding Society Code, American Water Works Association, National Electrical Code, National Sanitation Foundation, Occupational Health and Safety Administration (OSHA), Arizona Department of Environmental Quality (ADEQ), and the American Institute of Steel Construction. All environmental codes, including RCRA and NESHAP, shall be adhered to by the Contractor.
1.8 Special Permits
A. For electrical work or any other permits required by County, State, or Federal laws or regulations shall be obtained by the Contractor.
PART 2 PRODUCTS – Not Applicable To This Section
PART 3 EXECUTION – Not Applicable To This Section
END OF SECTION 01 11 00
NOGALES RANGER STATION [Type here] MEASUREMENT AND PAYMENT WATERLINE CONNECTION Page | 9 | 01 20 00
DIVISION 1 – GENERAL REQUIREMENT
SECTION 01 20 00 – MEASUREMENT AND PAYMENT
PART 1 GENERAL
1.1 SUMMARY
A. Measurement and payment for contract work will be made only for and under those pay items included in the SCHEDULE OF ITEMS. All other work and materials will be considered incidental to and included in the payment of the pay items in the SCHEDULE
OF ITEMS.
1.2 PAYMENT
A. One of the following methods of measurement for determining final payment is DESIGNATED on the SCHEDULE OF ITEMS for each pay item.
1.3 DETERMINATION OF QUANTITIES
A. Perform, or cause to be performed, all measurements of quantities of materials incorporated into the work processes that are to be measured under the provisions of the contract.
B. Quantity Measurements:
1. Make all measurements for computation of quantities for all work items except those specified for payment by Actual Quantity (AQ), Design Quantity (CQ), or Lump Sum Quantity (LSQ).
2. Compute the quantities for periodic progress payments; the Contracting Officer will compute the quantities for final payment based on measurements taken by the Contractor and recommended by the COR.
3. All Contractor measurements are subject to verification by the Government.
4. Submit all field notes, calculation sheets, and other data used to determine quantities.
5. Verify, in writing, as to the accuracy of the measurements and computations submitted.
1.4. UNITS OF MEASUREMENT
A. Cubic Yard (CY): A measurement computed by one of the following methods:
1. Excavation, Embankment, or Borrow.
a. Measurement computed by the average end area method from measurements made longitudinally along a centerline or reference line.l
2. Material in Place or Stockpile.
a. Measurement computed using the dimensions of the in-place material.
B. Loose Cubic Yard (CY): A measurement computed by one of the following methods:
1. Material in the Delivery Vehicle.
WATERLINE CONNECTION Page | 10 | 01 20 00
a. Measurement computed using measurements of material in the hauling vehicles are the point of delivery. Load vehicles to at least their water level capacity.
Leveling of the loads may be required when vehicles arrive at the delivery point
C. Each (EA): One complete unit, which may consist of one or more parts.
D. Linear Foot (LF): As applicable, measure the work along its length from end-to-end;
parallel to the base or foundation; along the top; along the front face; or along the invert.
Do not measure overlaps.
E. Lump Sum (LS): Do not measure directly. The bid amount is complete payment for all work described in the contract, including necessary materials, equipment, and labor needed to complete the work for that item. The quantity is designated as “1”. Estimated quantities of lump sum work shown in the contract are approximate.
F. Square Foot (SF): Measure on a plane parallel to the surface being measured.
1.4 METHOD OF MEASUREMENT
A. One of the following methods of measurement for determining final payment is designated on the Schedule of Items for each Pay Item:
1. Actual (Contract) Quantity (AQ)
a. The quantity to be paid is the quantity listed in the bid schedule. The contract quantity will be adjusted for authorized changes that affect the quantity, or the errors made in computing this quantity. If there is evidence that a quantity specified as a contract quantity is incorrect, submit calculations, drawings, or other evidence indicating why the quantity is in error and request in writing that the quantity be adjusted.
2. Estimated (Design) Quantities (DQ)
a. Per FAR52.211-18 Variation in Estimated Quantity, if the quantity of a unit-priced item in this contract is an estimated quantity and the actual quantity of the unit-priced item varies more than 15 percent above or below the estimated quantity, an equitable adjustment in the contract price shall be made upon demand of either party. The equitable adjustment shall be based upon any increase or decrease in costs due solely to the variation above 115 percent or below 85 percent of the estimated quantity. If the quantity variation is such as to cause an increase in the time necessary for completion, the Contractor may request, in writing, an extension of time, to be received by the Contracting Officer within 10 days from the beginning of the delay, or within such further period as may be granted by the contracting officer before the date of final settlement of the contract. Upon the receipt of a written request for an extension the Contracting Officer shall ascertain the facts and make an adjustment for extending the completion date as, in the judgement of the Contracting Officer, is justified.
3. Lump Sum Quantities (LSQ):
a. The bid amount is complete for all work described in the contract and necessary to complete the work for that pay item. The quantity is designated as “1”.
Estimated quantities of lump sum work shown in contract are approximate.
PART 2 PRODUCTS (NOT USED).
PART 3 EXECUTION (NOT USED)
WATERLINE CONNECTION Page | 11 | 01 20 00
END OF SECTION 01 20 00
NOGALES RANGER STATION [Type here] PROJECT MANAGEMENT AND COORDINATION WATERLINE CONNECTION Page | 12 | 01 31 00
DIVISION 1 – GENERAL REQUIREMENT
SECTION 01 31 00 – PROJECT MANAGEMENT AND COORDINATION
PART 1 GENERAL
1.1 SUMMARY
A. This work shall consist of coordination with adjacent property owner for access and repairs to any fencing, utilities, or components damaged during the waterline installation.
B. Any disruption of services, including vehicular access, electric, communications, water and/or wastewater, shall be communicated and coordinated with COR.
C. Contractor shall provide at least 72 hour notice to CO prior to any scheduled events of any disruption of services. This will allow time for CO to inform the employees and residents.
1.2 RELATED SECTIONS
A. 01 11 00 SUMMARY OF WORK
PART 2 PRODUCTS – None
PART 3 EXECUTION
3.1 VALLE VERDE WATER COMPANY (VVWC)
A. Contractor shall notify Valle Verde WC at start of contract to inform the timeline of the start of construction and proposed completion.
B. Contractor shall coordinate on the request to upgrade to the 6-inch meter and shall obtain the meter from VVWC for installation.
C. All permits necessary for construction and occupancy of the project shall be obtained by the Contractor,
3.2 COUNTY AND LOCAL AGENCY
A. Santa Cruz County: All work shall comply with local regulations.
B. All permits necessary for construction of the project shall be obtained by the Contractor.
3.3 ADJACENT NEIGHBORING OWNER(S)
A. Adjacent Business/Company (name unknown): The current occupying owner shall be notified to gain access on neighboring property.
B. All components damaged and/or temporarily removed will be repaired/replaced to allow the waterline construction to be completed. This includes existing fencing crossing the new alignment of the waterline connection from Valle Verde WC to the Nogales Ranger Station.
PART 4 MEASUREMENT AND PAYMENT
NOGALES RANGER STATION [Type here] PROJECT MANAGEMENT AND COORDINATION WATERLINE CONNECTION Page | 13 | 01 31 00
4.1 MEASUREMENT
A. Work under this section will not be measured for payment but is included in all other items in the contract.
4.2 PAYMENT
A. Separate payment will not be made.
END OF SECTION 01 31 00
NOGALES RANGER STATION [Type here] SUBMITTALS WATERLINE CONNECTION Page | 14 | 01 33 00
DIVISION 1 – GENERAL REQUIREMENT
SECTION 01 33 00 – SUBMITTALS
A. This section includes administrative and procedural requirements for submitting shop drawings, product data, samples and other miscellaneous submittals.
1.2 SECTION REQUIREMENTS
A. SPECIFIED PRODUCTS
1. When a product, model number, part number, etc. is specified herein, it is implied a substitute product with the same performance specifications may be submitted as an Approved Equal, subject to final approval by the Contracting Officer.
B. DEFINITIONS
1. Submittals requirements are specified in the technical sections. Submittals are identified by titles as follows:
a. Preconstruction Submittals: Submittals which are required prior to start of construction work, issuance of contract notice to proceed, or commending work at the site. This includes, but not limited to:
i. List of proposed Subcontractors
ii. Construction progress schedule
iii. Health and safety plan
iv. Work plan
v. Quality Control (QC) plan
vi. Bonding
b. Shop Drawings: Drawings, diagrams, and schedules specifically prepared to illustrate some portion of the work. Diagrams and instructions from a manufacturer or fabricator for use in producing the product and as aids to the Contractor for integrating the product or system into the project. Drawings prepared by or for the Contractor to show how multiple systems and interdisciplinary work will be coordinated.
c. Product Data: Catalog cuts, illustrations, schedules, diagrams, performance charts, instructions and brochures illustrating size, physical appearance, and other characteristics of materials, systems or equipment for some portion of the work.
d. Samples:
1) Fabricated or un-fabricated physical examples of materials, equipment or workmanship that illustrate functional and aesthetic characteristics of a material or product and establish standards by which the work can be judged.
2) Color samples from the manufacturer’s standard line (or custom color
WATERLINE CONNECTION Page | 15 | 01 33 00 samples if specified) to be used in selecting or approving colors for the project.
e. Design Data:
1) Design calculations, mix designs, analyses or other data pertaining to a part of the work.
2) Design submittals, design substantiation submittals and extensions of design submittals.
3) Design calculations, mix designs, analyses or other data pertaining to a part of the work.
f. Test Reports:
1) Report which includes finding of a test made at the job site or on a sample taken from the job site, on portion of work during or after installation.
g. Certificates: Statements printed on the manufacturer’s letterhead and signed by responsible officials of manufacturer of product, system, or material attesting that the product, system, or material meets specification requirements. Must be dated after award of the project contract and clearly name the project.
h. Manufacturer’s Instructions: Preprinted material describing installation of a product, system, or material, including special notices and MSDS concerning impedances, hazards, and safety precautions.
i. Operation and Maintenance Data
1) Data that is furnished by the manufacturer, or the system provider, to the product, system, or equipment operating and maintenance personnel, including manufacturer’s help and product line necessary to maintain the product, system, or equipment.
C. VARIATIONS
1. Submit one copy of the Contracting Officer’s Representative for approval on the items required herein.
2. Submittal specifications are to be submitted in the following format:
a. The specifications and salient qualities of the item specified in the contract.
b. The specifications and salient qualities of the submittal item.
c. A listing of the differences and a comparison between the two, including but not limited to the structural qualities, operational qualities, any modifications necessary to accomplish installation of unit and guarantee and warranty.
d. A cost comparison between the specified and submitted item(s) with the cost reduction benefit to the Government or adequate justification for a cost increase to the Government.
e. Shop drawings of submitted item(s) including wiring or layout diagrams.
3. If there are any modifications necessary to facilitate installation, a set of drawings showing installation of specified item and a set showing how the submittal item will be installed.
4. Submittals will be waived if Contractor furnishes exact item used for design when
WATERLINE CONNECTION Page | 16 | 01 33 00 manufacturer’s model, size, etc. are shown in the contract.
PART 2 PRODUCTS
2.1 Government Approval (GA) Submittals
A. Written and graphic information that requires Contracting Officer’s responsible action.
2.2 For Information Only (FIO) Submittals
A. Written information that does not require Contracting Officer’s approval.
B. Submittals may be rejected for not complying with requirements.
2.3 MANUFACTURER’S PRODUCT DATA
A. Contractor shall provide two (2) copies of all manufacturer’s data for all items furnished under this contract. This submittal shall include at a minimum product name and model number, product description, technical data and color samples (if required).
2.4 MANUFACTURER’S INSTRUCTIONS
A. The Contractor shall provide two (2) copies of all of the manufacturer’s installation and maintenance instructions (written and/or drawings) to the COR prior to installation.
2.5 Submittals are required per the following sections:
A. Section 01 45 00 Quality Control
1. Contractor’s Designation of Superintendent
2. Construction Schedule
3. Quality Control Plan
B. Section 01 77 00 Closeout Procedures
1. As-Built (Record) Drawings – Show actual installations where work varies from that shown originally.
2. Operation and Maintenance Data: Submit one copy of manual.
C. Section 03 30 00 Cast-in-Place Concrete | Pre-cast Concrete
1. Concrete: Design mix, product data, compressive strength, air content, etc.
2. Pre-cast concrete – Product data and specifications.
1. For meter and any concrete slab(s).
3. Reinforcement – Product data, Specifications.
4. Admixtures – Product data, Specifications.
D. Section 22 11 13 – Backflow Preventers
1. Reduced-Pressure Principle Zone Assembly – product data, specifications
2. Double Check Valve Assembly – product data, specifications
3. Pipe Wrap Tape – product data, specifications
E. Section 22 11 50 – Post Flushing Hydrant
1. Post Flushing Hydrant – product data, specifications
WATERLINE CONNECTION Page | 17 | 01 33 00
F. Section 33 11 13 – Pipe, Fittings and Specialties
1. Pressure Pipe and Fittings – Product data, Specifications
2. Pipe and Fittings – Product data, Specifications
3. Specialties – Product data, Specifications
4. Pipe Supports – product data, specifications
G. Section 33 12 16 – Valves
1. Valves – Product data, specifications
2. Air Release Valve – Product data, specifications
H. Section 33 12 18 – Valve Boxes and Enclosures
1. Valve Box – Product data, specifications
2. Valve Meter Box – Product data, specifications
3. Backflow Preventer Enclosures – Product data, specifications
I. Section 33 12 33 – Meters
1. Meter – Product data, specifications, and written approval and receipt from Valle Verde WC.
PART 3 PRODUCTS - Not Applicable To This Section
PART 4 EXECUTION - Not Applicable To This Section
END OF SECTION 01 33 00
NOGALES RANGER STATION [Type here] QUALITY CONTROL WATERLINE CONNECTION Page | 18 | 01 45 00
SECTION 01 45 00 – QUALITY CONTROL
A. The work shall consist of providing quality control in conformance with the Inspection of Construction provisions of this contract to ensure compliance with the drawings, specifications, and provisions of the contract and measuring the quantities of completed work in conformance with the provisions of the applicable specifications. The Contractor shall provide all personnel, equipment, tests, and reports to meet the requirements of this specification.
PART 2 PRODUCTS - Not Applicable To This Section
PART 3 EXECUTION
3.1 QUALITY CONTROL SYSTEM
A. The Contractor shall provide and maintain a quality control system that will ensure that all services, supplies, and construction required under this contract conform to the contract requirements. The contractor shall perform, or cause to be performed, the sampling, inspection, and testing required to substantiate that all supplies, services, and construction conform to the contract requirements.
3.2 QUALITY CONTROL PLAN
A. The contractor shall submit in writing the following:
1. Authorities and responsibilities of inspection and testing personnel.
2. Experience and qualifications of inspection and testing personnel to be assigned and location of any (for hire) testing facility to be used.
B. The contractors proposed quality control plan shall be submitted to the COR for review prior to the contractor commencing work. The COR shall approve or disapprove the plan within 10 business days. Construction work shall not begin prior to the contractor's receipt of written approval of the quality control plan.
C. The contractor shall submit to the COR in writing any proposed changes to the approved plan. Proposed changes shall not be put into effect until approved in writing by the COR.
3.3 SAMPLING & TESTING
A. The contractor shall provide and maintain appropriate measuring and testing devices, equipment, and supplies to accomplish the required measurement, testing and inspection in a timely manner. The contractor shall take samples and perform inspections and tests necessary to achieve the quality of construction required by the contract and manufacturer. Sampling and testing frequency for specific items shall be as
NOGALES RANGER STATION [Type here] QUALITY CONTROL WATERLINE CONNECTION Page | 19 | 01 45 00 defined in the specifications.
3.4 RECORDS
A. The contractor shall maintain current records of all inspections and tests performed at the jobsite & make them available to the COR upon request.
B. The contractor shall certify in writing that all inspections were performed in accordance with specifications. All testing and inspection records shall be submitted to the COR upon completion of the project.
3.5 CERTIFICATIONS & MEASUREMENTS
A. Offsite Produced Materials. The Contractor shall furnish certificates executed by the manufacturer, supplier, or vendor, stipulating that all offsite produced materials incorporated into the work meet the applicable requirements as shown on the drawings or specifications.
B. Quantity Measurement. The Contractor shall make all measurements for computation of quantities for all work items except those specified for payment by Design Quantity (DQ) or Lump Sum (LS). The Contractor shall compute the quantities for periodic progress payments; the COR will compute the quantities for final payment based on measurements taken by the Contractor. All measurements are subject to verification.
The Contractor shall submit all field notes, calculation sheets, and other data used to determine quantities. The Contractor shall certify in writing as to the accuracy of the measurements and computations submitted.
3.6 REPAIR AND PROTECTION
A. General: On completion of testing, inspecting, sample taking, and similar services, repair damaged construction and restore substrates and finishes.
B. Repair and protection are Contractor’s responsibility, regardless of the assignment of responsibility for quality-control services.
END OF SECTION 01 45 00
NOGALES RANGER STATION [Type here] TEMPORARY FACILTIES AND CONTROL WATERLINE CONNECTION Page | 20 | 01 50 00
SECTION 01 50 00 – TEMPORARY FACILITIES AND CONTROLS
1.1 SECTION REQUIREMENTS
A. Use Charges – There will be no charge for use to construct the waterline.
B. Water and Electric Power: Available from existing system without metering and without payment of use charges. Provide connections and extensions of services as required for construction operations.
C. Electric Service: Comply with NECA, NEMA, and UL standards and regulations for temporary electric service. Install service to comply with NFPA°70.
PART 2 PRODUCTS
2.1 MATERIALS
A. Safety Fencing: Highly visible, 48 inches, polyethylene, orange.
B. Wood Enclosure: Plywood
C. Safety Cones: Reflective Traffic Cones, Channelizer Cone, Delineator Posts with 10-lb Base
2.2 TEMPORARY FACILITIES
A. Provide temporary storage and use areas, and other support facilities as necessary for construction operations.
PART 3 EXECUTION
3.1 TEMPORARY UTILITY INSTALLATION
A. General: Install temporary service or connect to existing service.
1. Arrange with utility company and C.O., for a time when service can be interrupted, if necessary, to make connections for temporary services.
3.2 SECURITY AND PROTECTION FACILITIES INSTALLATION
A. Provide protection, operate temporary system, and conduct construction as required to comply with environmental regulations and minimize possible air, waterway, and subsoil contamination or pollution or other undesirable effects.
B. Provide measures to prevent soil erosion and discharge of soil-bearing water runoff and airborne dust to undisturbed areas.
C. Tree Protection: Install temporary fencing located as indicated or outside the drip line of trees to protect vegetation from damage from construction operations. Protect tree root systems from damage, flooding, and erosion.
NOGALES RANGER STATION [Type here] TEMPORARY FACILTIES AND CONTROL WATERLINE CONNECTION Page | 21 | 01 50 00
D. Furnish and install site enclosure fence in a manner that will prevent people and animals from easily entering open areas.
E. Barricades: Comply with requirements of authorities having jurisdiction for erecting adequate barricades.
F. Provide temporary enclosures for protection of construction, in progress and completed, from exposure, foul weather, other construction operations, and similar activities.
3.3 OPERATION, TERMINATION, AND REMOVAL
A. Minimize waste and abuse, limit availability of temporary system/facilities to essential and intended uses.
B. Remove each temporary system/facility when need for its service has ended, when it has been replaced by authorized use of a permanent system, or no later than Substantial Completion.
C. At Substantial Completion, repair, and clean permanent facilities used during construction period.
PART 4 MEASUREMENT AND PAYMENT
4.1 MEASUREMENT
A. Work under this section will not be measured for payment but will be considered incidental in all other items in the contract.
Separate payment will not be made.
END OF SECTION 01 50 00
NOGALES RANGER STATION [Type here] MOBILIZATION WATERLINE CONNECTION Page | 22 | 01 71 13
SECTION 01 71 13 – MOBILIZATION
A. The work shall consist of preparatory work and operations necessary for the movement of personnel, equipment, supplies and incidentals to the project site. This includes all work and operations that must be performed or that cause costs to be incurred prior to beginning work on the various items on the project site.
PART 2 PRODUCTS - Not Applicable To This Section
PART 3 EXECUTION – Not Applicable To This Section
PART 4 MEASUREMENT AND PAYMENT
4.1 MEASUREMENT
A. Progress payments will be made as follows:
The Contractor can request payment for performance and payment bonds. The amount of the premium, including coinsurance and reinsurance agreements, will be paid upon receipt of evidence of full payment to the surety. When separate payment for bonding cost is made, the bonding cost will be subtracted from the total contract amount for this pay item and the balance paid in accordance with the progress payment schedule outlined below:
(a) When 5 percent or more of the original contract amount is earned from other pay items, 50 percent of the amount for mobilization, or 5 percent of the original contract amount, whichever is less, will be paid.
(b) When 10 percent or more of the original contract amount is earned from other pay items, 100 percent of the amount for mobilization, or 10 percent of the original contract amount, whichever is less, will be paid.
(c) Upon completion of all work on the project, any unpaid amount for mobilization will be paid.
Any bonding costs in excess of the total contract amount of this pay item will be paid under one or more other pay items under this contract as determined by the Contracting Officer. In no circumstance will the total amount of this contract be increased as a result of bonding costs exceeding the total contract amount of this pay item.
The total of all payments shall not exceed the original contract amount for this item.
4.2 BASIS OF PAYMENT
PAY ITEM PAY UNIT
017113(01) Mobilization…………………………………….. Lump Sum
NOGALES RANGER STATION [Type here] MOBILIZATION WATERLINE CONNECTION Page | 23 | 01 71 13
END OF SECTION 01 71 13
NOGALES RANGER STATION [Type here] CLOSEOUT PROCEDURES WATERLINE CONNECTION Page | 24 | 01 77 00
DIVISION 1 – GENERAL REQUIREMENT
SECTION 01 77 00 – CLOSEOUT PROCEDURES
PART 1 GENERAL
1.1 SUMMARY
A. This Section includes administrative and procedural requirements for contract closeout.
1.2 CLOSEOUT SUBMITTALS
A. Operation and Maintenance Data: Submit one copy of manual.
B. As-Built Drawings: Submit one set of marked-up prints.
1.3 SUBSTANTIAL COMPLETION PROCEDURES
A. With the Contracting Officer, prepare a list of items to be completed and corrected (punch list).
B. Submittals Prior to Substantial Completion: Before requesting Substantial Completion inspection, complete the following:
1. Submit closeout submittals including as-built prints, operation and maintenance manual, warranties, final certifications, and similar documents.
2. Submit maintenance material submittals specified in other sections, including tools, spare parts, extra materials, and similar items and deliver to COR.
C. Procedures Prior to Substantial Completion: Before requesting Substantial Completion inspection, complete the following:
1. Deliver keys to CO.
2. Complete startup and testing of systems and equipment.
3. Remove temporary facilities and controls.
4. Complete final cleaning requirements.
5. Touch up and otherwise repair and restore any existing site components to existing conditions.
D. Inspection: Submit a written request for inspection for Substantial Completion. On receipt of request, the Contracting Officer will proceed with inspection or advise Contractor of unfulfilled requirements. The Contracting Officer will prepare the certificate of substantial completion after inspection or will advise Contractor of items that must be completed or corrected.
1.4 FINAL COMPLETION PROCEDURES
A. Submittals Prior to Final Completion: Before requesting inspection for determining final completion, complete the following:
1. Submit copy of certificate of Contracting Officer’s Substantial Completion inspection list of items to be completed or corrected (punch list), showing that each
NOGALES RANGER STATION [Type here] CLOSEOUT PROCEDURES WATERLINE CONNECTION Page | 25 | 01 77 00 item has been completed or otherwise resolved.
2. Submit a written request for final inspection for acceptance. On receipt of request, the Contracting Officer will either proceed with inspection or notify Contractor of unfulfilled requirements.
1. Reinspection: Request reinspection when the Work identified in previous inspections as incomplete is completed or corrected
PART 2 PRODUCTS
2.1 OPERATION AND MAINTENANCE DOCUMENTATION
A. Directory: Prepare operation and maintenance data, listing items and their location to facilitate ready access to desired information.
B. Organize data and include the following:
1. Manufacturer’s operation and maintenance documentation.
2. Maintenance and service schedules.
3. Copies of warranties. Include procedures to follow and required notifications for warranty claims.
2.2 RECORD DRAWINGS
A. Maintain a set of prints of the Contract Drawings incorporating new and revised drawings as modifications are issued. Mark to show actual installation where installation varies from that shown originally. Record information in an acceptable drawing technique.
PART 3 EXECUTION
A. Existing Conditions: The existence and location of underground and other utilities and construction indicated as existing are not guaranteed. Before beginning sitework, investigate and verify the existence and location of underground utilities, electrical and sewer, and other construction affecting the work.
PART 4 MEASUREMENT AND PAYMENT
4.1 MEASUREMENT
A. There will be no separate measurement for this section.
4.2 PAYMENT
A. This work is incidental to other items in the contract and direct separate item payment will not be made.
END OF SECTION 01 77 00
NOGALES RANGER STATION [Type here] SELECTIVE DEMOLITION WATERLINE CONNECTION Page | 26 | 02 41 19
DIVISION 2 – EXISTING CONDITIONS
SECTION 02 41 19 – SELECTIVE DEMOLITION
A. This section includes properly capping existing sections of 4-inch and 8-inch waterlines. The 4-inch waterline will disconnect the source from the onsite existing gravity line which provides water to the warehouse fire sprinkler system. The 8-inch waterline will be disconnected from the pressurized system from the well.
B. The proposed waterline alignment will be crossing two existing fences. The Forest Service owns the fence on government land and the other fence is on the neighboring property. Contractor shall carefully, temporarily remove fencing (at a strategic location for minimal replacement to maintain structural integrity) to provide room for equipment to install the new waterline. The fences shall be repaired and mended to return to original function.
C. Items indicated to be removed and salvaged remain government property unless noted otherwise. Carefully detach from existing construction, in a manner to prevent damage, and deliver to COR. Include fasteners or brackets needed for reattachment elsewhere.
D. Salvage – 1-inch Valle Verde Water Meter.
E. Predemolition Photographs: Show existing conditions of adjoining construction and site improvements. Submit before Work begins.
F. It is not expected that hazardous materials will be encountered in the Work. If hazardous materials are encountered, do not disturb, immediately notify COR.
Hazardous materials will be removed under a separate contract.
PART 2 PRODUCTS
2.1 PERFORMANCE REQUIREMENTS
A. Regulatory Requirements: Comply with EPA regulations and with hauling and disposal regulations of authorities having jurisdiction.
B. Standards: Comply with ANSI/ASSE A10.6 and NFPA 241.
C. Salvage Items: Existing 1-inch meter in place. Contractor shall return 1-inch meter to Valle Verde Water Company.
PART 3 EXECUTION
3.1 DEMOLITION
A. Protect existing services/systems indicated to remain against damage during selective demolition operations.
B. Locate, identify, shut off, disconnect, and seal or cap off indicated utility services.
C. Provide temporary barricades and other protection required to prevent injury to people and damage to adjacent buildings and facilities to remain.
D. Provide and maintain shoring, bracing, and structural supports as required to preserve stability and prevent movement, settlement, or collapse of existing features to remain
NOGALES RANGER STATION [Type here] SELECTIVE DEMOLITION WATERLINE CONNECTION Page | 27 | 02 41 19 and to prevent unexpected or uncontrolled movement or collapse of construction being demolished.
E. Requirements for Site Reuse:
1. Maintain existing nonstructural elements (fence, gates, etc.) not indicated to be demolished; do not demolish such existing construction beyond indicated limits.
F. Neatly cut openings and holes plumb, square, and true to dimensions required. Use cutting methods least likely to damage construction to remain or adjoining construction.
G. Remove demolition waste materials from Project site and legally dispose of them in an EPA approved landfill. Do not burn demolished materials.
H. Return adjacent structures and improvements of dust, dirt, and debris caused by selective demolition operations.
I. Return adjacent areas to condition existing before selective demolition operations began.
PART 4 – MEASUREMENT AND PAYMENT
4.1 MEASUREMENT
All capped waterline sections shall be properly backfilled and compacted. The remaining sections of line shall be abandoned and left in place. The work for the following items will be paid as a lump sum quantity.
A. Completely furnishing and installing proper 4” cap to line from gravity water line, AS SHOWN ON DRAWING. Cap shall be installed after the 4-inch tee to continue to provide water source from existing 4-inch potable waterline.
B. Completely furnishing and installing proper 8” cap on existing waterline at location, AS SHOWN ON DRAWING. The waterline will continue to provide water to Ruby House and existing 8” waterline shall be capped to remove service from existing well and pressurized line.
C. Completely return the temporarily removed sections of fences belonging to the Forest Service and the adjacent neighbor to the original functionality of the fence.
4.2 PAYMENT
A. Payment will be made at the contract unit price as listed in the “Schedule of Items” for quantities measured and accepted as follows:
Pay Item Description Pay Unit
024119(01) Selective Demolition including: LS 4-inch capping, 6-inch capping, Fenceline removal and replacement
END OF SECTION 02 41 19
NOGALES RANGER STATION [Type here] CAST-IN-PLACE CONCRETE WATERLINE CONNECTION Page | 28 | 03 30 00
DIVISION 3 – CONCRETE
SECTION 03 30 00 – CAST-IN-PLACE CONCRETE OR PRE-CAST CONCRETE
A. Section Includes:
1. The work specified herein includes purchase, delivery, construction and installation of materials to construct a concrete slab on grade or a precast concrete structure, including construction of compacted subgrade to support the following:
1. 6-inch Reduced Pressure Zone Assembly. Concrete slab shall extend beyond the enclosure edges at minimum 1-foot around all sides to mount the enclosure to the concrete.
2. 6-inch Meter assembly, including all related plumbing and appurtenances, AS SHOWN ON DRAWING.
1) Meter vault shall be coordinated with Verde Valle WC on approval of type of vault for meter reading compatibility, if required.
2. Contractor shall submit size of concrete slab and concrete vault for review and approval by COR prior to any start of construction.
3. When the concrete structures or parts of concrete structures are precast, the work shall also include transporting, installing, and as required, erecting the units.
B. Submittals:
1. Product Data and Design Mixture
1. Minimum 28-day compressive strength, 3,000 psi
2. Nominal maximum aggregate size: Course size #67 Aggregate
2. Pre-cast Concrete
1. Submit data information for review and approval, prior to ordering.
C. Ready-Mixed Concrete Manufacturer Qualifications: Complies with ASTM C94/C94M.
PART 2 PRODUCTS
2.1 PERFORMANCE REQUIREMENTS
A. Comply with ACI 301, “Specification for Structural Concrete”, and with ACI 117, “Specifications for Tolerances for Concrete Construction and Materials.”
2.2 MATERIALS
A. Reinforcing Bars: ASTM A 615/A 615M, Grade 60 (Grade 420), deformed.
B. Plain Steel Wire: ASTM A 82/A 82M, as drawn.
C. Plain-Steel Welded Wire Reinforcement: ASTM A 185/A 185M, as drawn, flat sheet.
D. Portland Cement: ASTM C 150, Type I or II.
E. Fly Ash: ASTM C 618, Class C or F.
WATERLINE CONNECTION Page | 29 | 03 30 00
F. Ground Granulated Blast-Furnace Slag: ASTM C 989, Grade 100 or 120.
G. Silica Fume: ASTM C 1240, amorphous silica.
H. Aggregates: ASTM C 33, Class 3M coarse aggregate or better, graded.
I. Air-Entraining Admixture: ASTM C 260.
J. Chemical Admixtures: ASTM C 494, water reducing and accelerating and water reducing and retarding. Do not use calcium chloride or admixtures containing calcium chloride.
K. Synthetic Fiber: ASTM C 1116/C 1116M, Type III, polypropylene fibers, 1/2 to 1-1/2 inches (13 to 38 mm) long.
2.3 CONCRETE MIXTURES
A. Prepare design mixtures, proportioned according to ACI 301.
B. Normal-Weight Concrete:
1. Minimum Compressive Strength: 3000 psi (20.7 MPa) at 28 days.
2. Maximum Water-Cementitious Materials Ratio: [0.50] [0.45] [0.40] <Insert ratio>.
3. Slump Limit: [4 inches (100 mm)] [5 inches (125 mm)] [8 inches (200 mm) for concrete with verified slump of 2 to 4 inches (50 to 100 mm) before adding high-range water-reducing admixture or plasticizing admixture] <Insert dimension>, plus or minus 1 inch (25 mm).
4. Air Content: Maintain within range permitted by ACI 301. Do not allow air content of floor slabs to receive troweled finishes to exceed 3 percent.
C. Measure, batch, mix, and deliver concrete according to ASTM C 94/C 94M.
1. When air temperature is above 90 deg F (32 deg C), reduce mixing and delivery time to 60 minutes.
2.4 FIELD CONDITIONS
A. Cold-Weather Placement: Comply with ACI 301 and ACI 306.1 and as follows.
1. Protect concrete work from physical damage or reduced strength that could be caused by frost, freezing actions, or low temperatures.
2. When average high and low temperature is expected to fall below 40°F for three successive days, maintain delivered concrete mixture temperature within the temperature range required by ACI 301.
3. Do not use frozen materials or materials containing ice or snow.
4. Do not place concrete in contact with surfaces less than 35°F other than reinforcing steel.
5. Do not use calcium chloride, salt, or other materials containing antifreeze agents or chemical accelerators unless otherwise specified and approved in mixture designs.
B. Hot-Weather Placement: Comply…