Schedule of Items - Coronado National Forest Nogales Ranger Station New Waterline Connection

This document is a pricing schedule for a federal construction contract to install a new waterline connection at the Nogales Ranger Station within the Coronado National Forest, Nogales Ranger District. The schedule itemizes nine base bid line items and one optional bid line item, with bidders required to provide unit prices and calculate totals for each component of the project.

The base bid items include: mobilization (1 lump sum); selective demolition encompassing waterline cap removal and fence removal/replacement (1 lump sum); a 2-inch double check valve assembly with supports, testing, and mounting (1 lump sum); a 2-inch post-flushing hydrant with valve and valve box (1 lump sum); 6-inch waterline installation including fittings, trenching, and backfill at 115 linear feet (unit priced per LF); a 4-inch valve and valve box (1 each); two 6-inch valves and valve boxes (2 each); a 2-inch air release valve and valve box (1 each); and a 6-inch water meter with concrete meter vault and plumbing (1 each). The optional bid item consists of a 6-inch reduced pressure principle zone assembly with concrete slab, aggregate, wrap, testing, and lockable enclosure (1 lump sum). Bidders must complete unit prices for all items, calculate line item totals, provide a base bid total, an optional bid total, and a grand total combining both base and optional bids.

View the file

Other files

Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PAY ESTIMATED METHOD UNIT

ITEM DESCRIPTION QUANTITY OF UNIT PRICE TOTAL

NO. MEASUREMENT

017113(01) Mobilization 1 LSQ LS

024119(01)

Selective Demolition including:

· 4-inch waterline cap

· 6-inch waterline cap

· Fence Removal and Replacement (FS & Adjacent Property)

1 LSQ LS

221113(01) 2-inch Double Check Valve Assembly incl supports, tape, testing and mount

1 LSQ LS

221150(01) 2-inch Post Flushing Hydrant Incl. Valve & Valve Box

1 LSQ LS

331123(01) 6-inch Waterline incl.

fittings, trenching & backfill

115 AQ LF

331216(01) 4-inch Valve & Valve Box 1 AQ EA

331216(02) 6-inch Valve & Valve Box 2 AQ EA

331216(03) 2-inch Air Release Valve & Valve Box

1 AQ EA

331233(01) 6-inch Water Meter incl Concrete Meter Vault & Plumbing

1 AQ EA

BASE BID TOTAL =

Schedule of Items

CORONADO NATIONAL FOREST

NOGALES RANGER DISTRICT

Nogales Ranger Station New Waterline Connection

BASE BID ITEMS:

PAY ESTIMATED METHOD UNIT

ITEM DESCRIPTION QUANTITY OF UNIT PRICE TOTAL

NO. MEASUREMENT

221113(02)

6-inch Reduced Pressure Principle Zone Assembly incl. conc slab, agg, wrap, testing & lockable enclosure

1 LSQ LS

OPTIONAL BID TOTAL =

BASE BID TOTAL =

OPTIONAL BID TOTAL =

(BASE BID + OPTIONAL BID) GRAND TOTAL =

OPTIONAL BID ITEM: