Specifications.pdf
PDF 20 MB Posted
- Attached to
- Siding Replacement Federal contract opportunity
- Solicitation number
- 140P6426B0003
About this file
This is a comprehensive project specifications document for siding replacement work at Indiana Dunes National Park in Porter, Indiana, addressing three buildings: B-101 (Ranger Station), B-104 (Headquarters), and B-105 (Pump House). The base bid scope includes removal of existing siding and exterior rigid insulation from all three buildings, evaluation and replacement of OSB and framing (estimated 10%), addition of framing to achieve 16" spacing (estimated 10%), fascia inspection and replacement (estimated 10%), window sill and trim replacement (25%), relocation of electrical conduits and gas plumbing lines, removal of abandoned penetrations, installation of fiber cement trim boards, surface preparation and painting of concrete tank areas, installation of insulated ZIP System R-Sheathing panels with integrated weather-resistant barrier (2" R-9), and installation of new fiber cement lap siding with paint finishing. Completion is required within 120 calendar days of Notice to Proceed, with work generally performed Monday through Friday, 7:00 AM to 4:00 PM, in compliance with National Park Service regulations and federal environmental standards.
Two bid options are included: Option 1 provides EPDM roof replacement for B-101 (8,960 SF) and B-105 (586 SF) with R-30 insulation minimum, including new gutters, downspouts, and metal flashing; Option 2 covers aluminum-clad wood window replacement for 9 windows in B-101 and 13 windows in B-104, including rotten wood frame replacement, caulking, and painting. Products specified include Huber Engineered Woods ZIP System R-Sheathing with seam tape and liquid flashing, James Hardie HZ5 fiber cement lap siding (Toasted Brown color), polyisocyanurate roof insulation with cover board, EPDM roofing from approved manufacturers (Carlisle, Firestone, GenFlex, Johns Manville, Verisco), aluminum-clad wood windows from H Window Company/Marvin/Pella, and exterior paint systems per MPI standards. Key contractor requirements include submission of preconstruction safety plan, construction schedule with detailed breakdown, subcontractor list, quality control plan, waste management plan, accident prevention program, daily progress reports, and photo documentation of existing conditions, progress, and completion. The project is 100% set aside for Total Small Businesses under NAICS code 236220 (construction wage rates apply), with firm-fixed-price contracting and evaluation criteria detailed in the full solicitation.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_140P6426B0003_Amd_0002.pdf | ||
| Questons_and_Answers__2_0002.pdf | ||
| Revised_Specifications_0002.pdf | ||
| Sol_140P6426B0003_Amd_0001.pdf | ||
| Questions_and_Answers_0001.pdf | ||
| Revised_Bid_Schedule_0001.xlsx | XLSX spreadsheet | |
| Sol_140P6426B0003.pdf | ||
| Limitations_on_Subcontracting_Report.xlsx | XLSX spreadsheet | |
| Notice_to_Contractors.pdf | ||
| Bid_Schedule.xlsx | XLSX spreadsheet | |
| DOL_Wage_Determination.pdf |
Show all 11
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Div. 1 V. 2023-11-11 Page | 1
Indiana Dunes National Park 1100 Mineral Springs Road
Replace Siding at the Headquarters (B-101, B-104, B-105)
PMIS 304973
Drawing No: N/A
PROJECT SPECIFICATIONS
NATIONAL PARK SERVICE
2025-07-01
Div. 1 V. 2023-11-11 Page | 2
TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
Section 01 10 00 - Division 01 Short Form General Requirements
DIVISION 06 – WOOD, PLASTICS AND COMPOSITE PRODUCTS
Section 06 16 13.53 – Insulating Air & Moisture Resistance Sheathing (Base Bid)
DIVISION 07 – THERMAL AND MOISTURE PROTECTION
Section 07 46 46 – Fiber Cement Siding (Base Bid) Section 07 53 23 – EPDM ROOFING (Bid Option 1)
DIVISION 08 – OPENINGS
Section 08 52 00 Aluminum Clad Wood Windows (Bid Option 2)
DIVISION 09 – FINISHES
Section 09 91 13 Exterior Painting (Base Bid)
APPENDIX
A. DRAWINGS, QUANTITIES & PICTURES
1. Ranger Station B-101
2. Headquarters B-104
3. Pump House B-105
B. Photos
1. Ranger Station B-101
2. Headquarters B-104
3. Pump House B-105
C. 3D MODEL
2. https://hover.to/3d/16287043/model/16284422
3. Headquarters B-104 https://hover.to/3d/16222778/model/16220129
4. Pump House B-105 https://hover.to/3d/16287394/model/16284773 https://hover.to/3d/16287043/model/16284422
Div. 1 V. 2023-11-11 Page | 3
SECTION 01 10 00
DIVISION 1 SHORT FORM GENERAL REQUIREMENTS
PART 1 – GENERAL
ITEM 1 - DESCRIPTION OF WORK
1.1 Background: The three buildings are part of the Headquarters which was part of the Nike Missile
Site that was constructed from 1954 to 1956. Building 104 and B105 were part of the original Nike Missile base configuration while building B-101 was built around 1980. The Headquarters area has been submitted for approval as a National Register of Historic Places.
1.2 Work Covered by the Contract Documents:
A. Project Location: 1100 Mineral Springs Rd. Porter In 46304
B. Work consists of:
1. This project consists of the siding replacement of three buildings: B101 (Ranger Station), B104 (Head Quarters) and B105 (Pump House).
a) Remove all existing siding & exterior Rigid Insulation
b) Evaluate condition of existing OSB and framing. Review with COR to identify areas for replacement. Replace as necessary (For bid purposes, assume 10% of existing OSB and wall framing to be replaced).
c) Identify where existing framing exceeds 16" spacing. Review with COR to review existing conditions and identify area for additional framing. Add additional framing to match existing which decreases spacing to 16" or less (For bid purposes, assume that additional framing is added along 10% of existing walls).
d) Inspect the existing fascia condition on all the three buildings and assume that 10% needs to be replace due to be damage or rotten conditions.
e) The contractor shall inspect all windows on the three buildings and determine which sills and surrounding wood trim require replacement. For windows that are not flush with the wall, this trim sits closer to the window frame and may have a “step” or reveal between the window and the wall surface. Assume twenty-five percent (25%) to be replace including 25% of the total window sills, regardless of condition, to ensure a consistent finished appearance and long-term durability.
Additionally, all window trim located above the newly installed wall siding shall be removed and replaced in full.
f) Remove all exterior mounted conduits or exposed wire & re-install under the new siding to hide, as possible. Coordinate with COR for shutdown periods. See Appendix B for more details. All this work needs to be done by a certified electrician in the state of Indiana.
g) Disconnect & re-install gas plumbing lines and all penetrations and hide under the new siding as possible. Coordinate with COR for shutdown periods. See Appendix B for more details. All this work shall be done by certified plumber.in the state of Indiana
h) Re-install communication cables into conduits under the new siding. Coordinate with COR for shutdown periods. See Appendix B for more details.
i) Remove abandoned wires, electrical boxes or any other abandoned wall or soffit penetrations. See Appendix B for more details.
Div. 1 V. 2023-11-11 Page | 4
j) Replace all wood trim below the sofit with Fiber Cement trim board, follow manufacturer installation recommendations. Trim varies from 9-12 inches; the contractor shall verify all the dimensions to match existing.
k) B-105 - Pump House: Prepare surface and paint concrete tank surface area (17' x 30') Height (2'-10")
l) B-104 – Headquarters: All gutters and downspouts to remain. (Paint gutters after re-installation)
m) B-101 & B-104 Paint front porches including, timber beams, columns and ceiling see color codes under section 07 46 46 page 28.
n) Install an insulated structural sheathing panel with integrated WRB over existing sheathing. Provide 2" (R-9) ZIP System R-Sheathing panels as manufactured by Huber Engineered Woods, or approved equal. (https://www.huberwood.com/zip-system/insulated-r-sheathing)
o) Install an insulated structural sheathing panel with integrated WRB over existing exposed CMU, as depictedin Appendix B. Provide 2" (R-9) ZIP System R- Sheathing panels as manufactured by Huber EngineeredWoods, or approved equal.
p) Install new fiber cement LAP siding. Siding Cement to be paint after installation see color codes under section 07 46 46 page 28.
https://www.huberwood.com/zip-system/insulated-r-sheathing https://www.huberwood.com/zip-system/insulated-r-sheathing
Div. 1 V. 2023-11-11 Page | 5
NOTE NO. COMMENTS
1 Electrical connection to be removed. Lower AC drains close to the ground and under new siding.
2 Hose bibb to remain 3 Drain to remain.
4 Horn - to be removed.
5 Light and two antennas to remain 6 Building Sign to Remain 7 Wall feature light to remain 8 Drain to remain.
9 Light feature to remain.
10 Vent to remain.
11 Arrowhead to remain.
12 Light feature to remain.
13 Light feature to remain.
14 Intercom & Doorbell to remain.
15 "NOTICE 24 HR VIDEO" sign to remain.
16 To be removed 17 Horn - to remain.
18 Vent to remain.
19 Door keypad - to remain.
20 Camera - to remain 21 Re-install Electrical circuit behind the new siding.
22 Install a new drain behind new siding.
23 Re-Install split unit 2 feet from existing ground.
24 Remove vent 25 Re-Install and lower the Mini split unit 2 ft from the existing ground.
26 Re-Install electric circuit behind the new siding.
27 Re-route communication cable to minimize visibility.
28 Re-route communication cable to minimize visibility.
29 Re-route communication cable to minimize visibility.
30 Removed electric meter box and install OSB, insulation and cover with a weather barrier before install new siding.
31 Remove Exhaust Fan and install OSB, insulation and cover with a weather barrier before install new siding.
32 Remove Vent and install OSB, insulation and cover with a weather barrier before install new siding.
33 Remove galvanize pipe and cover with new siding. Seal the hole accoring to International Building Code and Manufacturer recommendations.
34 Remove PVC Pipe and cover wall penetration with new siding. Seal the hole according to International Building Code and Manufacturer recommendations.
35 Light feature to remain.
36 Remove Camera.
37 Re-Install electric circuit behind the new siding.
38 Re-Install Mini Split Unit under the existing window or between the two windows keep 12"-24" from the existing ground. (Two Units)
38A Paint Porch (Beams, Columns, ceiling and decking to match new NPS dark brown color. See Spec for specific code color.)
B101 - Ranger Station (See Appendix B)
TABLE A. SIDING REPLACEMENT
Div. 1 V. 2023-11-11 Page | 6
NOTE NO. COMMENTS
39 "BLDG 104" Sign to remain.
40 Wall Light Feature to remain.
41 Drain - Lower to ground level and install below new siding.
42 Drain - Lower to ground level and install below new siding.
43 Roof Light Feature to remain.
44 Wall Light Feature to remain.
45 Water hose bibb to remain.
46 Re-Install Electrical Circuit and Mini Split copper lines behind the new Siding.
47 Wall Light Feature to remain.
48 Hose Bibb to remain.
49 Seal wall properly and cover with new siding.
50 Remove Electrical panel, conduits and all abandoned circuits.
51 Remove Electrical panel, conduits and all abandoned circuits.
52 Install new Siding and Trim.
53 Remove Exhaust Fan and install studs insulation and siding on the entire wall.
54 Re-Route Gas Line before install siding.
55 Electrical & Fiberoptic to remain.
56 Confirm Electrical is abandon ed and remove.
57 Electrical to remain.
58 Antenna to remain.
59 Light Feature to remain.
60 Paint Porch (Beams, Columns, ceiling and decking to match new NPS dark brown color. See Spec for specific code color.)
NOTE NO. COMMENTS
1 Light Feature to remain.
2 Horn to be remove and cover with insulation, new siding and trim.
3 Electrical component to be remove and cover with insulation and new siding.
4 Relocate electrical tubing under new siding and do not cover electrical boxes or LB boxes.
5 Relocate electrical tubing under new siding and do not cover electrical boxes or LB boxes.
6 Electrical meter to remain.
GENERAL NOTES:
1. THE CONTRACTOR SHALL VERIFY ALL THE DIMENSIONS IN THE FIELD.
2. THE CONTRACTOR SHALL VERIFY STUDS LOCATION, INSULATION SIZE AND WEATHER BARRIER INSTALLATION TO
MEET MANUFACTURERS REQUIREMENTS.
B105 - Pump House (See Appendix A)
B104 - Headquarters (See Appendix B) TABLE A. SIDING REPLACEMENT (Cont.)
TABLE A. SIDING REPLACEMENT (Cont.)
Div. 1 V. 2023-11-11 Page | 7
2. Bid Option 1 – Roof replacement: Includes the replacement of the EPDM roof for building B101 (Ranger Station) & B105 (Pump House)
a) Install New EPDM Flat Roof on B-101 Ranger Station (Install new gutters 130 L.F. with four downspouts 9ft height ea. + three extensions of 3 ft ea.). (See Specifications and Pictures) Install metal flashing, boots, and replace fascia and any rotten or damaged decking. (Assume replacement of 10% of roof framing for estimating purposes)
b) Replace Vinyl Soffit B-101 with same material and shape. Seal all surroundings to avoid bug intrusion.
c) Install New EPDM Flat Roof on B-105 Pump House. (See Specifications and Pictures) Install metal flashing, boots, and replace fascia and any rotten or damaged decking. assume replacement of 10% of roof framing for estimating purposes.
Table No. 1
BLDG NO NAME DECKING
REQUIRED
INSULATION
TOP ROOF
LAYER
AREA (SF)
B101 RANGER STATION WOOD R30 EPDM (BLACK) 8,960
B105 PUMP HOUSE WOOD R30 EPDM (BLACK) 586
GENERAL NOTES:
1. THE CONTRACTOR SHALL VERIFY ALL THE DIMENSIONS IN THE FIELD.
2. THE CONTRACTOR SHALL TAKE ROOF CORE TO CONFIRM EXISTING ROOF LAYERS AND INSULATION.
3. NEW INSULATION NEED TO MEET A MINIMUM OF R30.
4. THE CONTRACTOR SHALL INCLUDE IN THEIR PROPOSAL IF THE PERIMETTER FASCIA NEED TO BE RAISE
TO MEET THE NEW INSULATION REQUIREMENTS.
5. THE CONTRACTOR SHALL FOLLOW MANUFACTURER RECOMMENDATIONS FOR TAPER INSULATION
PANELS INSTALLATION TO PROVIDE POSITIVE DRAINAGE AWAY FROM THE WALLS AND THE BUILDING.
HEAD QUARTERS
EPDM ROOF REPLACEMENT
Div. 1 V. 2023-11-11 Page | 8
3. Bid Option 2 – Windows Replacements
a) Demolition: Removal and disposal of 21 windows. (B101 & B105). See exact locations on Appendix B.
b) Building 101: Replace Windows and rotten wood frame, & (windows wood sides, top and sill) (9 Windows in total) (Two - 65x45, Two - 26x49, One-39x49, Two- 36x42 and Two-25x44), Include caulking and painting.
c) Building 104: Replace Windows and rotten wood frame, & (windows wood sides, top and sill) (13 Windows in total) (Twelve - 37x42, and One - 37x36), Include caulking and painting.
BLDG NO. NAME NO. MATERIAL OPENING DETAILS
WG1 WOOD 65"X45" INCLUDE INSIDE WOOD FRAME SILL AND WALL TRIM
WG2 WOOD 65"X45" INCLUDE INSIDE WOOD FRAME SILL AND WALL TRIM
WG3 WOOD 26"X49" INCLUDE INSIDE WOOD FRAME SILL AND WALL TRIM
WG4 WOOD 26"X49" INCLUDE INSIDE WOOD FRAME SILL AND WALL TRIM
WG5 WOOD 39"X49" INCLUDE INSIDE WOOD FRAME SILL AND WALL TRIM
WG6 WOOD 36"X42" INCLUDE INSIDE WOOD FRAME SILL AND WALL TRIM
WG7 WOOD 36"X42" INCLUDE INSIDE WOOD FRAME SILL AND WALL TRIM
WG8 WOOD 25"X44" INCLUDE INSIDE WOOD FRAME SILL AND WALL TRIM
WG9 WOOD 25"X44" INCLUDE INSIDE WOOD FRAME SILL AND WALL TRIM
W1 WOOD 37"X42" INCLUDE INSIDE WOOD FRAME SILL AND WALL TRIM
W2 WOOD 37"X42" INCLUDE INSIDE WOOD FRAME SILL AND WALL TRIM
W3 WOOD 37"X42" INCLUDE INSIDE WOOD FRAME SILL AND WALL TRIM
W4 WOOD 37"X42" INCLUDE INSIDE WOOD FRAME SILL AND WALL TRIM
W5 WOOD 37"X42" INCLUDE INSIDE WOOD FRAME SILL AND WALL TRIM
W6 WOOD 37"X42" INCLUDE INSIDE WOOD FRAME SILL AND WALL TRIM
W7 WOOD 37"X42" INCLUDE INSIDE WOOD FRAME SILL AND WALL TRIM
W8 WOOD 37"X42" INCLUDE INSIDE WOOD FRAME SILL AND WALL TRIM
W9 WOOD 37"X42" INCLUDE INSIDE WOOD FRAME SILL AND WALL TRIM
W10 WOOD 37"X42" INCLUDE INSIDE WOOD FRAME SILL AND WALL TRIM
W11 WOOD 37"X42" INCLUDE INSIDE WOOD FRAME SILL AND WALL TRIM
W12 WOOD 37"X42" INCLUDE INSIDE WOOD FRAME SILL AND WALL TRIM
W13 WOOD 37"X36" INCLUDE INSIDE WOOD FRAME SILL AND WALL TRIM
GENERAL NOTES:
1. THE CONTRACTOR SHALL VERIFY ALL THE DIMENSIONS IN THE FIELD.
2. REPLACE ALL ROTTEN OR DAMAGE WOOD FRAME & WINDOWS WOOD SIDES, TOP AND SILL.
3. INCLUDE CAULKING AND PAINT.
4. THE CONTRACTOR SHALL FOLLOW MANUFACTURER RECOMMENDATION FOR PROPER DRAINAGE AND AVOID AIR INTRUSSION.
TABLE D. WINDOWS REPLACEMENT (BID-OPTION 2)
HEAD QUARTERS
B101
B104
RANGER STATION
HEADQUARTERS
Div. 1 V. 2023-11-11 Page | 9
C. All work will be performed under a single contract.
D. Period of performance: Work shall be completed within 120 days calendar days of the start date provided on the Notice to Proceed.
1. Clarification: The Notice to Proceed will be issued with a period of performance that is all inclusive of supply lead times, material deliveries, decommissioning, installation, anticipated average weather days for location, final commissioning, and acceptance of completed work. The contractor will be expected to provide a project schedule with adequate critical path details to ensure all work is completed within the stated calendar days from issuance of the Notice to Proceed. If weather impacts project beyond typical average weather patterns, contractor shall provide documentation in request for additional days.
1.3 Existing Condition Protections:
A. Preservation of Historical and Archeological Fabric:
a) The Historic and Archeological Data Preservation Act of 1974 provides for the preservation of historical and archeological data that might otherwise be lost as the result of alterations to the terrain caused by a federal or federally licensed activity or program.
b) IF, in connection with operations under this contract, the Contractor, subcontractors, or employees of any of them, discovers, encounters or becomes aware of any possible historical or archeological remains or data, objects or sites of cultural value on the project area, such as historical ruins, graves or grave markers, fossils, or artifacts not specifically noted within the contract. The Contractor shall immediately suspend all operations in the vicinity and continue work in other areas outside a 50 foot radius of discovery and notify the Contracting Officer immediately. When safe to do so, follow up in writing with photographs within 2 days, giving the location and nature of the findings. No objects of cultural resource value may be removed. Contracting Officer will contact other entities as required.
c) Where appropriate by reason of discovery, the Contracting Officer may order delays in the time of performance and/or changes in the work. If such delays and/or changes are ordered, the time of performance and contract price shall be adjusted in accordance with Changes clause.
d) The Contractor will be responsible for protecting the cultural resources within and adjacent to the project area from damage. In addition, the Contractor will be liable for all damage to the cultural resources caused by their actions or the actions of their agents or representatives. The Contractor shall immediately notify the Contracting Officer or their representative if any damage occurs to any cultural resource and immediately suspend work in the area in which damage has occurred until authorized to proceed.
v. The Contractor agrees to include this language within all subcontracts.
B. The structure or structures involved in this project are not historic.
C. There is no excavation required for this project.
ITEM 2 – PROTECTING EXISTING UTILITIES
Div. 1 V. 2023-11-11 Page | 10
2.1 Protecting Existing Utilities: Notify Contracting Officer (CO), Contracting Officer’s Representative
(COR) and utility companies as required to request location services prior to and to coordinate any excavation/digging operations, and/or for demolition if within Scope of Work.
2.2 Contractor shall be responsible for locating and preventing damage to known utilities on site or indoors. If contractor damage occurs, alert CO and COR as soon as safely possible, and repair utility at no additional expense to the Government. If damage occurs to an unknown utility, contact CO and COR as soon as safely possible.
2.3 Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Government or others unless permitted under the following conditions and then only after arranging to provide temporary utility services according to requirements indicated below:
A. Notify CO and COR not less than two business days in advance of proposed utility interruptions.
B. Hours for Utility Shutdowns: Shutdowns shall not exceed 2 to 3 hours. Temporary provisions will be needed by the Contractor for periods longer than stated allowance or if required for critical systems as determined by COR.
ITEM 3 - CONTRACTOR’S USE OF PREMISES
3.1 Conduct of Operations: At all times the contractor shall conduct his operations in conformance with the rules and regulations promulgated by the Secretary of the Interior for the National Park Service, and applicable park rules and regulations prescribed by the Park Superintendent.
https://www.nps.gov/indu/learn/management/compendium.htm
A. Communications: Contractor shall provide the Contracting Officer and COR with methods of communications including land and/or cell phone numbers (note some areas of work have limited service coverage), email and in case of emergency 24-hour contact options for duration of time operations.
B. No signs or advertisements (except those specified herein and as required for safety) shall be displayed on the construction site or within the park unless approved by the Contracting Officer.
C. Smoking is not permitted within any Federal building or within 25 feet of entrances, operable windows, or outdoor air intakes.
D. Public Use of Site: Contractor shall at all times conduct operations to ensure the least inconvenience to the public. N/A
3.2 On-site work hours: Work shall be generally performed during normal business working hours of
7:00 AM - 4 PM., Monday through Friday, except when otherwise indicated. Work on Saturdays, Sundays, Federal holidays, early morning, or at night may not be performed without prior consent from the CO and COR. Submit requests for work outside of the stated normal business hours to the CO and COR for approval at least 48 hours in advance of the work.
The following Federal holidays are observed by the National Park Service:
New Year’s Day Inauguration Day
Div. 1 V. 2023-11-11 Page | 11
Martin Luther King, Jr’s Birthday Washington’s Birthday Memorial Day Juneteenth National Independence Day Independence Day Labor Day Columbus Day Veterans Day Thanksgiving Day Christmas Day
• Note: Any of the above holidays falling on a Saturday will be observed on the preceding
Friday; holidays falling on Sunday will be observed on the following Monday. The specific day that each holiday is recognized for each year can be found at the following site: Federal Holidays (opm.gov).
3.3 Contractor Use of Site:
A. General: Contractor shall have limited use of the site for construction operations. Limit use of premises to construction area as shown on site plan. Do not disturb portions of Project site beyond areas in which the Work is indicated.
B. Driveways and Entrances: Keep driveways, access roads, and entrances serving premises clear and available to Government, Government's employees, and emergency vehicles at all times. Do not use these areas for parking or storage of materials. Schedule deliveries to minimize use of driveways and entrances.
C. Do Not disturb site outside of noted disturbance area, including earthwork, and clearing of vegetation, to:
1. 10 feet around the building perimeter.
Contractor shall provide appropriate matts for equipment on turf areas to reduce soil compaction. Contractor shall remediate soil compaction as directed to do so by the CO/COR.
D. Utilities
1. General: Cost or use charges for temporary facilities shall be included in the Contract
Sum as required.
2. Water Service: Water from existing water system is available for use without metering and without payment of use charges. Provide connections and extensions of services as required for construction operations without any additional permit costs. Use resources wisely and minimize waste of water.
3. Electric Power Service: Electric power from existing system is available for use without metering and without payment of use charges. Provide connections and extensions of services as required for construction operations without any additional permit costs. Power may or may not meet your construction power tool requirements, provide generators if questionable. Use power in a resourceful manner and avoid excess power waste.
4. Sanitary Operations:
https://www.opm.gov/policy-data-oversight/pay-leave/federal-holidays/#url=2022 https://www.opm.gov/policy-data-oversight/pay-leave/federal-holidays/#url=2022
Div. 1 V. 2023-11-11 Page | 12
a. Toilets: Contractor must provide toilets for contractor personnel, sufficiently lighted and ventilated toilet facilities in weatherproof, sight proof, handicap accessible (if required), sturdy enclosures with privacy locks. Coordinate with COR for approved location if not shown on attached site plan.
E. Security and Protection facilities:
1. Environmental Protection: Provide protection, operate temporary facilities, and conduct construction in ways and by methods that comply with state and federal environmental regulations and that minimize possible air, waterway, and subsoil contamination or pollution or other undesirable effects.
2. Cleaning of Equipment: The Contractor shall ensure that prior to moving on to the Project Area, all equipment, is free of soil, seeds, vegetative matter, or other debris that could contain or hold seeds. Ensure that all equipment has been pressure washed and is free of exotic species prior to start-up of operations and moving of equipment to Project Area.
Equipment shall be considered free of soil, seeds, and other debris when a visual inspection does not disclose such material. Disassembly of equipment components or specialized inspection tools are not required.
3. Tree and Plant protection is not required for this project.
4. Pest Control: Follow best practices to minimize attraction and harboring of rodents, roaches, and other pests and to perform extermination and control procedures at regular intervals so Project will be free of pests and their residues at project completion. Perform control operations lawfully, using environmentally safe materials.
5. Temporary Enclosures: Not required.
6. Hot Work Permit: Not Required
3.4 Storage - Staging Areas:
A. Confine Storage of materials and equipment to the project staging area noted on the plans/aerial. Specific storage units shall be provided by the contractor and exact location within staging area shown in appendix A below may be discussed at the preconstruction briefing. All storage units provided by the contractor shall be in a clean and acceptable condition to the COR. Security of the materials and equipment on site is the Contractor’s responsibility.
3.5 Preservation of Natural Features: N/A
3.6 Hauling Restrictions: Contractor shall verify and be responsible for the path accessing the site and obtaining / maintaining all local, state and federal permits/licenses associated with hauling/road requirements and dumping of materials associated with the project.
3.7 Waste Removal, Recycling, and General Housekeeping:
A. Keep project site in a neat, orderly, and safe condition at all times.
1. Contractor is responsible for providing dumpsters for waste and recycling and for removing all waste created by the project. Contractor shall recycle to the highest degree possible and empty dumpsters as necessary to avoid debris on site.
Coordinate with COR for approved dumpster locations prior to commencing construction.
Div. 1 V. 2023-11-11 Page | 13
2. Dispose of waste materials and recycling legally outside the park. The contractor shall not use park dumpsters.
3. Address Recycling: Government goal is to salvage and recycle as much nonhazardous construction waste as possible. Use sustainable methods to the extent possible during this project, recycling material as much as possible within local means. Maintain accurate documentary records for submittal of all recycled materials used including fly ash and slag cement.
4. For all waste and recycling removals offsite, contractors shall provide estimates and/or tickets to quantify material weights and report back to the park, submit to COR for review and record filing.
3.8 Occupancy Requirements for Buildings:
A. Existing Buildings:
1. Full Government Occupancy: Government will occupy buildings that will be under construction during the entire contract period. Cooperate with Government during construction operations to minimize conflicts and facilitate Government usage. Perform the Work so as not to interfere with Government's day-to-day operations. Maintain existing exits, unless otherwise indicated. Contractor will maintain access to existing walkways, corridors, and other adjacent occupied or used facilities. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from the CO or COR. Contractor will maintain existing building in a weather tight condition throughout construction period. Repair damage caused by construction operations. Protect building and its occupants during construction period.
B. New /Existing Buildings Unoccupied:
1. N/A
3.9 Photo Documentation:
A. Contractor must provide existing condition, progress, and completion photos. All photos shall be in focus, show maximum range of depth of field general photo and then close up detail photo as needed. Shall be in JPEG digital form and submitted preferably electronically by email or optional via CD-R Archival Gold or DVD-R Archival Gold media with printed labels and 8 mega pixels minimum within 7 days from time of taken or as approved by COR.
B. Existing Condition Images:
1. Before starting construction, take color, dated, digital images of project site and adjacent property/roads/etc. that may be impacted by construction activity/traffic. Include existing items to remain or be salvaged from different vantage points and with context for location identification.
C. Construction Progress Images:
Div. 1 V. 2023-11-11 Page | 14
1. Document all sub-surface work/ trenches etc. prior to backfill with photos covering enough overall field view to show location and then zoom in for details. (Locations and dimensions shall also be noted on as built drawing set.)
2. Maintain organized index for photos with date, description, etc.
3. Additional images as needed when questions or emergency situations occur. Submit within 24 hours.
D. Completion Images:
1. Document all completed work within scope of work.
2. Maintain organized index for photos with date, description, etc..
3. Additional images as needed when questions or emergency situations occur. Submit within 24 hours.
3.10 Fire and Life Safety:
A. As a minimum, conduct one weekly 15 minute "toolbox" safety meetings. These meetings shall be conducted by a foreman or supervisor and attended by all construction personnel at the worksite. Topics need to coincide with work scheduled for the following week. Document and submit meeting minutes to the CO and COR within one day after the meeting and document the meetings on the daily reports.
B. Comply with the requirements of NFPA 241 (Standard for Safeguarding Construction, Alteration, and Demolition Operations). Take all necessary precautions to prevent fire during construction. Provide adequate ventilation during use of volatile or noxious substances.
C. Store and handle hazardous materials in accordance with manufacturers and OSHA
29CFR1926 Subpart D requirements 1926 | Occupational Safety and Health Administration (osha.gov). Maintain readily available, on site, MSDS/Safety Data Sheets (SDS) for each chemical.
1. Immediately report all spills of hazardous materials to the CO, COR, and park.
2. Maintain a spill emergency response kit.
3. Train employees how to respond to a spill and use the emergency response kit.
3.11 Noise and Acoustics Management
A. Contractor shall not have personal radios or other media sources and they shall not be broadcast within NPS property.
B. Noise Control: Perform operations to minimize noise. Perform noise-producing work in less sensitive hours of the day or week as directed by the Contracting Officer or COR.
C. Repetitive and/or intermittent, high-level noise: Permitted only during Daytime.
a) Do not exceed the following dB(A) limitations at 50 feet: 70 dB(A) More than 12 minutes in any hour, 80 dB(A) More than 3 minutes in any hour. 2. Maximum permissible construction equipment noise levels at 50 feet: Compressors 75 dB(A), Pneumatic Tools 80 dB(A), Pumps 75 dB(A), Saws 75 dB(A), Generators 75dB(A), Vibrators 75 dB(A) 3. Ambient Noise maximum noise levels (dB) for receiving noise area at property line shall be as follows. Residential receiving area: Daytime 65 dB Nighttime 45 dB. Commercial/Industrial receiving area:
Daytime: 67 dB Nighttime: 65 dB
ITEM 4 - COMMENCEMENT, PROSECUTION, AND COMPLETION
https://www.osha.gov/laws-regs/regulations/standardnumber/1926 https://www.osha.gov/laws-regs/regulations/standardnumber/1926
Div. 1 V. 2023-11-11 Page | 15
4.1 The Contractor shall commence work in accordance with the terms and conditions of the contract.
Contractor shall coordinate and incorporate long lead and delivery time items within the schedule.
ITEM 5 - EXAMINATION OF THE SITE
5.1 All bidders are urged to visit the job site and examine existing conditions before submitting bids.
Contractors will be accountable for understanding existing conditions. No cost changes for items visible during site visit will be allowed.
ITEM 6 - ABBREVIATIONS
6.1 The list of abbreviations, standards and organizations which may be used in/referred within the
Construction Specifications or Special Provisions, may be found linked from the listed page below. On the home page, follow the link under “Contracting and Procurement” labeled “NPS Reference Standards.” https://www.nps.gov/orgs/1671/do-business-with-us.htm
ITEM 7 - ACCIDENT PREVENTION
7.1 Description: The work of this section consists of establishing and implementing an effective accident prevention program (APP) and providing a safe environment for all personnel and visitors.
7.2 Submittals:
A. Accident Prevention (Safety) Plan (APP): Submit a site-specific accident prevention (safety) plan. The Plan shall be written to comply with OSHA and project requirements (a generic plan is not acceptable) including but not limited to the following:
1. Name and qualifications of responsible supervisor to carry out the program.
2. First aid and rescue procedures.
3. Training, both initial and continuing.
4. Outline of each phase of the work, the hazards associated with each major phase, and the methods proposed to provide for property protection and safety of the public, National Park Service personnel, and Contractor's employees. Identify the work included under each phase, with a Job Hazard Analysis (JHA)/Job Safety Analysis (JSA), etc. A sample JHA template may be provided upon request.
5. Planning for possible emergency situations, such as cave-ins, earthquake, explosions, fires, floods, power outages, slides, and windstorms. Such planning shall take into consideration the nature of construction, site conditions, and degree of exposure of persons and property.
6. Contractor to identify nearest location of medical facility for emergencies
7. Recognition that works will be performed in remote areas with limited communication or cell phone coverage if applicable.
8. Supplemental hazard specific plans may be required IAW 29 CFR 1926 or 1910.
B. Meeting and Inspection Reports: Safety Meetings: As a minimum, conduct 15 minute
"toolbox" safety meetings. These meetings shall be conducted by a foreman and attended by all construction personnel at the worksite. Submit a report of safety meetings and inspections to CO and COR within one day after the meeting and document the meetings on the daily reports.
https://www.nps.gov/orgs/1671/do-business-with-us.htm
Div. 1 V. 2023-11-11 Page | 16
7.3 Qualification of Employees:
A. Ensure that employees are physically qualified to perform their assigned duties in a safe manner to include operators of vehicles and equipment. Provide operating instructions for all equipment.
B. Do not allow employees to work whose ability or alertness is impaired because of drugs, fatigue, illness, intoxication, or other conditions that may expose themselves or others to injury.
7.4 Accident Reporting: The Contractor shall report all accidents to the CO and COR as soon as safely possible and assist the CO and COR and other officials as required in the investigation of the accident.
7.5 First Aid Facilities: Provide access to facilities for the number of employees and appropriate to the hazards associated with the types of ongoing construction work at the site.
7.6 Emergency Instructions: Post telephone numbers and reporting instructions for ambulance, physician, hospital, fire department, and police in conspicuous locations at the work site.
7.7 Personal Protective Equipment (PPE): It is the Contractor's responsibility to require all those working on or visiting the site to wear necessary protective equipment at all times.
A. PPE must meet requirements of applicable ANSI standards. Selection shall conform to OSHA 29CFR 1926 Subpart E.
B. A hard hat use area shall be designated by the Contractor. The hard hat area shall be posted by the Contractor in a manner satisfactory to the Contracting Officer.
C. All PPE will be serviceable at all times. At a minimum, maintain 2 sets of PPE including hard hats and all other Accident Prevention Plan required equipment.
7.8 Hazardous Materials: It shall be the responsibility of all operators and contractors, functioning within the park to properly cleanup, mitigate and remediate if necessary, all unauthorized discharges of hazardous materials or non-hazardous chemical and biological products released from fleet and/or other support vehicles or stationary sources. Response shall be consistent with guidelines established by federal, state, and local regulations, and as outlined within the operator's Safety or Hazardous Materials Business Plan.
A. If a spill, leak, or other release occurs, the operator shall as soon as possible, without impeding cleanup, notify the local 911 Emergency Response, COR and or the National Park Service Emergency Dispatch.
ITEM 8 - PRECONSTRUCTION CONFERENCE
8.1 If the Contracting Officer decides to conduct a preconstruction conference, the successful offeror will be notified and will be required to attend. The Contracting Officer’s notification will include specific details regarding the date, time, and location of the conference, any need for attendance by subcontractors, and information regarding the items to be discussed. See Item 9.1C below.
ITEM 9 - SUBMITTALS
Div. 1 V. 2023-11-11 Page | 17
9.1 General Contracting Submittal Procedures:
A. General: Prepare and submit submittals required by individual Technical Specification Sections. Types of submittals are indicated in individual specific sections.
1. CM-16 Transmittal Form: All submittals shall be transmitted via electronic email using
National Park Service form CM-16 form. The form will be provided by the Contracting Officer. No action will be taken on a submittal item unless accompanied by the CM-16 transmittal form. Submit completed CM-16 forms to the CO and the COR
B. Submittal List: administrative required submittals are listed below in 9.1.C and does not include technical section submittal requirements included in each technical section.
C. Preconstruction Conference Submittal: Satisfactory evidence of liability insurance coverage and workman’s compensation, and any applicable bonds, must be submitted within 10 calendar days of Notice of Award. The following items are to be submitted prior to the Preconstruction Conference or as specified at the CO’s discretion. The timeline for the documents to be submitted will be addressed at the pre-construction conference for those items that were not received and approved prior. Notice to Proceed may not be issued, and the Contracting Officer will consider other contractual remedies if not resolved as directed.
Work shall not commence until written Notice to Proceed has been issued. Contracting Officer will notify Contractor of tentative date for the Pre-Construction Conference:
1. Letter designating Project Superintendent.
2. Construction Schedule. (Must include shop drawings, procurement time including long lead time items, mobilization, trade work progression and completion at minimum.)
3. A comprehensive breakdown of the Schedule of Values.
4. Accident Prevention (Safety) Plan (see section 7 of this document).
5. A list of Subcontractors for this project.
6. Written statements from subcontractors certifying compliance with applicable labor standard clauses (SF1413).
7. Quality Control Plan.
8. Waste Management Plan. N/A
9. Temporary Storm Water Pollution Prevention Plan (SWPPP or UPPP) Submitted to AHJ
(Authority Having Jurisdiction). N/A
10. Indoor Air Quality (IAQ) Management Plan. N/A
11. Contractors Commissioning Plan. N/A
12. Historic Preservation Treatment Plan Submitted to AHJ (Authority Having Jurisdiction).
N/A
13. List of Construction Permits. Include the following information for each permit: N/A
a. Name of Permit.
b. The Agency(ies) with Jurisdiction issuing the permit.
c. Information required from the Government to complete the permit application.
9.2 Project Submittal Process (Shop Drawings, Product Data, and Samples): Contracting Officer will provide sample cover sheet and a list of required submittals is included in each technical specification or attached at the end of this document.
A. Shop Drawings: Indicate all coordinating materials and work impacting the installation coordination, connection details, anchorage requirements, hardware locations, and installation details and locations.
Div. 1 V. 2023-11-11 Page | 18
1. Submit Shop Drawings according to Part 9.1 of this section to include one digital file (.PDF or .TIF) and two full size hardcopy documents to COR.
B. Product Data: Provide component construction and specification data sheets, anchorage requirements and any other product specific data.
1. Submit Product Data according to Part 9.1 of this section to include one digital file (.PDF or .TIF) to COR.
C. Samples: Submit 2 color samples 4” x 6” minimum in size for all product color selections.
Paint samples shall be actual paint finish drawdown for all project colors.
1. Submit Samples CM-16 Transmittal Form according to Part 9.1 of this section to include one digital file (.PDF or .TIF) and physical samples of actual material to COR.
D. For submittals specified above, forward submittals to Contracting Officer and COR at least 15 days before need for approval (depends on length of project).
E. After approving submittals, Contracting Officer and/or COR will return one copy to the
Contractor. If submittals are not approved, Contracting Officer will return all copies to Contractor with reasons for rejection. Resubmit, identifying changes. Any work done before approval shall be at Contractor's own risk.
9.3 Approved Equals: All brand names noted are subject to ‘or equal’ products. If an item in this solicitation is identified as “brand name or equal” or lists more than 1 manufacturer, the description of the proposed item must reflect the characteristics and level of quality that will satisfy the Government’s needs as demonstrated by the salient physical, functional, or performance characteristics that “equal” products must meet and/or exceed that as specified in the solicitation or relevant specification. Contractor shall incorporate and be responsible for all collateral costs due to the or equal proposed as required to provide a complete project.
A. For each item proposed as an “approved equal,” submit supporting data, including:
1. Drawings and samples as appropriate.
2. Comparison of the characteristics of the proposed item with that specified and with the salient characteristics provided.
3. Changes required in other elements of the work because of the substitution.
4. Name, address, and telephone number of vendor.
5. Manufacturer’s literature regarding installation, operation, and maintenance, including schematics for electrical and hydraulic systems, lubrication requirements, and parts lists.
Describe availability of maintenance service, and state source of replacement materials.
B. A request for approval constitutes a representation that General Contractor:
1. Has investigated and shall provide documentation in request showing that the proposed item is equal or superior in all respects to the salient characteristics specified.
2. Will meet or exceed warranties for the proposed item specified.
3. Has determined that the proposed item is compatible with interfacing items.
4. Will coordinate the installation of an approved item and make all changes required in other elements of the work because of the substitution.
5. Waives all claims for additional expenses that may be incurred as a result of the substitution.
Div. 1 V. 2023-11-11 Page | 19
C. Approved Equals will be evaluated and approved/disapproved during the submittal process.
9.4 Schedule of Values: Submit the Schedule of Values a minimum of one week prior to the
Preconstruction Conference for COR review. Schedule of Values shall include defined work line items with cost break downs including labor, material, and equipment for COR approval.
9.5 Progress Reporting: The initial Construction Schedule and Schedule of Values are required a minimum of one week prior to the Preconstruction Conference. After the Notice to Proceed is issued and after on-site work begins, progress will be documented via daily logs and by providing an updated Construction Schedule and Schedule of Values when requested, but minimally with each pay application. Submit digital copy electronically (PDF preferred) of all required documents.
Construction Schedules are normally in bar chart form and indicate estimated starting and completion dates for each part of the work. For a pay application to be reviewed and processed in a timely manner, the following information must either be submitted prior to or accompany submission of the pay application:
A. Daily/weekly progress reports during construction as part of the administration process.
B. Updated Schedule of Values: Breakdown each lump-sum item into component work activities used in the schedule, for which progress payments may be requested. The Schedule of Values will form the basis for payment. The work activities broken out within the schedule of values shall be integrated into and made a logical part of the construction baseline schedule submitted under this specification. The total costs for the component work activities shall equal the contract price for that lump-sum item. The Contracting Officer may request data to verify accuracy of dollar values. A sample Schedule of Values format may be provided upon request.
ITEM 10 – TEMPORARY SERVICES
10.1 It is the Contractor’s responsibility to provide temporary services, equipment, tools, and skilled labor as required for the chosen means and methods to perform the work in accomplishing this Contract.
ITEM 11 - PROJECT CLOSEOUT
11.1 Description: The work of this section consists of final cleanup, closeout submittals, final inspection procedures working toward Final Acceptance.
11.2 Cleaning: Remove all tools, equipment, surplus materials, and rubbish. Move attic stock to location coordinated with COR. At time of final inspection, project shall be thoroughly clean and ready for intended use. Inspector holds the right to reschedule if project is not ready for inspection.
11.3 Completion and Final Inspection: Contractor shall submit written certification of project completion and request a final inspection to the Contracting Officer and COR. The Contracting Officer or designee will make an inspection within 10 days of receipt of request or at a mutually agreeable time.
A. If the work is determined to be complete following the final inspection with minor comments, the COR will prepare and provide the Contractor a Punch List noting outstanding items to be addressed.
Div. 1 V. 2023-11-11 Page | 20
B. If the work is not determined to be complete following the final inspection, the Contracting Officer will notify Contractor in writing, stating reasons. Contractor, after completing the work according to the Contract Documents, shall resubmit completion and request a new final inspection. Re-inspection costs may be charged against the Contractor in accordance with the Inspection of Construction contract clause.
C. Contractor shall complete the Punch List within 30 calendar days, or a time directed by the
CO.
D. Once Contractor completes all items of work on the Punch List and all contractually required items are accepted, Contracting Officer will issue Letter of Final Acceptance of Work and request the final pay application.
E. If the Contractor fails to complete the work within the time frame, the Contracting Officer may correct the work with an appropriate reduction in contract price or charge for re-inspection costs in accordance with the Inspection of Construction contract clause.
F. Disposition of any permits and warranties required by the specifications in this section.
11.4 Final Acceptance of the Work: After all punch list deficiencies have been corrected, a Letter of
Final Acceptance will be issued. A Release of Claims document must be executed and submitted to the Contracting Officer before final payment can occur.
11.5 Warranties
A. Construction Warranty shall be based on date of final acceptance of the work and remain in effect for one year.
B. Provide all manufacturer warranty information of products installed organized by Division. All contact information, extent of coverage and conditions shall be clearly noted as well as date of overall final acceptance.
C. Information shall include operation and maintenance manuals for each warranted product.
ITEM 12 - DEFINITION OF CONTRACT LINE ITEMS
12.1 Summary
A. The intent of this section is to explain, in general, what is and what is not included in a contract line item, and the limits or cut off points where one item ends, and another begins.
B. If no contract line item exists for a portion of the work, include the costs in a related item.
12.2 List of Contract Line Items
A. Contract Line-Item No. CLIN 010 Siding and Roof Replacement
1. This item consists of CLIN 010 Siding and Roof Replacement.
2. Payment will be made per the contract and percentage of completion level.
END OF SECTION
INSULATING AIR & MOISTURE RESISTANT SHEATHING 21 | P a g e
SECTION 06 16 13.53 (BASE BID)
SECTION 06 16 13.53
INSULATING AIR & MOISTURE RESISTANT SHEATHING (BASE BID)
PART 2 - GENERAL
2.1 SECTION INCLUDES
A. Insulating wall sheathing with integral weather-resistive barrier
2.2 ACTION SUBMITTALS
A. Product Data: Product Data: For each type of sheathing product. Include manufacturer’s technical data indicating performance properties
B. Shop Drawings: Indicating location and extent of sheathing, accessories, and assemblies.
Include details of joints, corners, and penetrations.
2.3 INFORMATIONAL SUBMITTALS
A. Evaluation Reports: From ICC-ES, for wood sheathing and seam tape and flashing.
B. Product Certifications: From manufacturer, indicating that sheathing products comply with indicated ICC-ES Acceptance Criteria.
C. Documentation indicating that products comply with requirements of 2024 Indiana Building Code.
D. Warranty: Sample unexecuted copy of manufacturer warranty.
2.4 CLOSEOUT SUBMITTALS
A. Warranty: Executed copy of manufacturer special warranties.
2.5 QUALITY ASSURANCE
A. Wall sheathing meeting requirements for water-resistive barrier in accordance with ICC-ES AC310 – Water-resistive Membranes Factory-bonded to Wood-based Structural Sheathing, Used as Water-resistive Barriers.
2.6 DELIVERY, STORAGE, AND HANDLING
A. Comply with manufacturer's written instructions for protection of sheathing products from weather prior to installation.
INSULATING AIR & MOISTURE RESISTANT SHEATHING 22 | P a g e
2.7 WARRANTY
A. Manufacturer's Warranty: Manufacturer’s standard form in which sheathing manufacturer agrees to repair or replace sheathing products that demonstrate deterioration or failure under normal use due to manufacturing defects within warranty period specified, when installed according to manufacturer's instructions.
1. Warranty Period for Sheathing Products: 30 years from date of Substantial Completion.
PART 3 - PRODUCTS
3.1 MANUFACTURERS
A. Huber Engineered Woods LLC, Charlotte NC; Phone: (800) 933-9220; Website:
www.huberwood.com (Or Approved Equal)
3.2 PERFORMANCE REQUIREMENTS
A. Air-Barrier Assembly Air Leakage: Less than 0.04 cfm/sq. ft. at 1.57 lbf/sq. ft. (0.2 L/s x sq. m at 75 Pa), per ASTM E2357 – Standard Test Method for Determining Air Leakage of Air Barrier Assemblies
B. Water-Vapor Permeance, Facer: Minimum 12 perms (689 ng/Pa x s x sq. m), when tested in accordance with ASTM E96/E96M – Standard Test Methods for Water Vapor Transmission of Materials.
3.3 MATERIALS - GENERAL
A. Certified Wood: Provide sheathing produced from wood…
This is the start of the file's text. The full file is on GovTribe.