This file contains detailed technical specifications for replacing fused and obsolete electrical panels at the VA Hudson Valley Healthcare System's Montrose Campus in New York (Project #620-15-111). The project involves removing existing obsolete fused panelboards and installing replacement panelboards in Buildings 1, 3, 4, 5, 6, 7, 12, and 14, with consideration for consolidation of branch circuiting per VA Electrical Design guidelines and NEC requirements.

The specifications detail requirements for electrical installations, low-voltage conductors and cables, grounding systems, raceways and boxes, panelboards, and surge protective devices. Key technical requirements include: copper conductors only (aluminum prohibited), THHN-THWN insulation, minimum #12 AWG wire size, rigid steel or IMC conduit for most applications, new panelboards with copper bus bars rated minimum 10,000A symmetrical short-circuit current, and integral surge protective devices where shown. The contractor must coordinate with the facility for all utility shutdowns, maintain continuous service to critical systems, and phase work to minimize disruptions. The project includes 270 calendar days for construction completion from Notice to Proceed, with an additional 10 days for final cleanup and inspection.

View the file

Other files

Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Replace Fused and Obsolete Electrical Panels Project Number: 620-15-111 Construction Documents Specifications

Northeast Infrastructure, LLC 34 Brown Street

Honesdale, PA 18431 July 12, 2024

VA Hudson Valley Healthcare System 2094 Albany Post Road Montrose, NY 10548

THIS PAGE IS INTENTIONALLY LEFT BLANK

Replace Fused and Obsolete Electrical Panels Project No. 620-15-111 Construction Documents Montrose VAMC, Montrose, NY 07-12-2024

00 01 10 - 1

DEPARTMENT OF VETERANS AFFAIRS

VHA MASTER SPECIFICATIONS

TABLE OF CONTENTS

Section 00 01 10

SECTION NO. DIVISION AND SECTION TITLES DATE

DIVISION 00 - SPECIAL SECTIONS

00 01 15 List of Drawing Sheets 05-20

DIVISION 01 - GENERAL REQUIREMENTS

01 00 00 General Requirements 11-21 01 32 16.15 Project Schedules (Small Projects – Design/Bid/Build 11-21 01 33 23 Shop Drawings, Product Data, and Samples 06-21 01 35 26 Safety Requirements 11-21 01 42 19 Reference Standards 11-20 01 45 00 Quality Control 02-21 01 45 29 Testing Laboratory Services 11-18 01 57 19 Temporary Environmental Controls 01-21 01 74 19 Construction Waste Management 04-22

DIVISION 02 – EXISTING CONDITIONS

02 41 00 Demolition 08-17

DIVISION 03 – CONCRETE

(Not Used)

DIVISION 04 – MASONRY

04 05 13 Masonry Mortaring 10-17 04 05 16 Masonry Grouting 01-21 04 20 00 Unit Masonry 08-17

DIVISION 05 – METALS

(Not Used)

DIVISION 06 – WOOD, PLASTICS AND COMPOSITES

(Not Used)

DIVISION 07 - THERMAL AND MOISTURE PROTECTION

07 84 00 Firestopping 01-21 07 92 00 Joint Sealants 04-22

00 01 10 - 2

DIVISION 08 - OPENINGS

(Not Used)

DIVISION 09 – FINISHES

09 22 16 Non-Structural Metal Framing 06-18 09 51 00 Acoustical Ceilings 12-18 09 91 00 Painting 01-21

DIVISION 10 – SPECIALTIES

(Not Used)

DIVISION 11 – EQUIPMENT

(Not Used)

DIVISION 12 – FURNISHINGS

(Not Used)

DIVISION 13 - SPECIAL CONSTRUCTION

(Not Used)

DIVISION 14– CONVEYING EQUIPEMENT

(Not Used)

DIVISION 21- FIRE SUPPRESSION

(Not Used)

DIVISION 22 – PLUMBING

(Not Used)

DIVISION 23 – HEATING, VENTILATING, AND AIR

CONDITIONING (HVAC)

(Not Used)

DIVISION 25 – INTEGRATED AUTOMATION

(Not Used)

DIVISION 26 – ELECTRICAL

26 05 11 Requirements for Electrical Installations 01-16

00 01 10 - 3

26 05 19 Low-Voltage Electrical Power Conductors and Cables 01-17 26 05 26 Grounding and Bonding for Electrical Systems 01-17 26 05 33 Raceway and Boxes for Electrical Systems 01-18 26 24 16 Panelboards 01-18 26 43 13 Surge Protective Devices 01-17

DIVISION 27 – COMMUNICATIONS

(Not Used)

DIVISION 28 – ELECTRONIC SAFETY AND SECURITY

(Not Used)

DIVISION 31 – EARTHWORK

(Not Used)

DIVISION 32 – EXTERIOR IMPROVEMENTS

(Not Used)

DIVISION 33 – UTILITIES

(Not Used)

DIVISION 34 – TRANSPORTATION

(Not Used)

DIVISION 48 – Electrical Power Generation

(Not Used)

00 01 15 - 1

SECTION 00 01 15

LIST OF DRAWINGS

The drawings listed below accompanying this specification form a part of the contract.

Drawing No. Title

GENERAL:

GI-001 COVER SHEET

SITE:

CS-100 CAMPUS SITE PLAN

ICRA:

ICRA-01 ICRA GENERAL REQUIREMENTS & CLASS

IDENTIFICATION SCHEDULE

ARCHITECTURAL:

A-001 ARCHITECTURAL NOTES, ABBREVIATIONS, & DETAILS

A-100 BUILDING 1 FIRST FLOOR & BUILDING 7 GROUND

FLOOR ARCHITECTURAL NEW WORK PLANS

ELECTRICAL:

E-001 ELECTRICAL SYMBOLS, NOTES, AND ABBREVIATIONS

ED-100 BUILDING 1 GROUND AND FIRST FLOOR ELECTRICAL

POWER DEMOLITION PLANS

ED-101 BUILDING 1 FIRST FLOOR ELECTRICAL LIGHTING

DEMOLITION PLAN

ED-102 BUILDING 1 PARTIAL DEMOLITION ONE-LINE DIAGRAM

AND PANELBOARD SCHEDULES

E-103 BUILDING 1 GROUND FLOOR AND FIRST FLOOR

ELECTRICAL POWER NEW WORK PLANS

E-104 BUILDING 1 FIRST FLOOR ELECTRICAL LIGHTING NEW

WORK PLAN

E-105 BUILDING 1 PARTIAL NEW WORK ONE-LINE DIAGRAM &

PANELBOARD AND LIGHTING FIXTURE

SCHEDULES

ED-106 BUILDING 3 GROUND FLOOR ELECTRICAL POWER

DEMOLITION PLAN

00 01 15 - 2

ELECTRICAL CONTINUED:

ED-107 BUILDING 3 GROUND FLOOR ELECTRICAL LIGHTING

DEMOLITION PLAN

ED-108 BUILDING 3 PARTIAL DEMOLITION ONE-LINE DIAGRAM

AND PANELBOARD SCHEDULES

E-109 BUILDING 3 GROUND FLOOR ELECTRICAL POWER NEW

WORK PLAN

E-110 BUILDING 3 GROUND FLOOR ELECTRICAL LIGHTING NEW

WORK PLAN

E-111 BUILDING 3 PANELBOARD SCHEDULES

ED-112 BUILDING 4 GROUND FLOOR ELECTRICAL POWER

DEMOLITION PLAN

ED-113 BUILDING 4 GROUND FLOOR ELECTRICAL LIGHTING

DEMOLITION PLAN

ED-114 BUILDING 4 STAIRWELL ELECTRICAL LIGHTING

DEMOLITION PLANS

ED-115 BUILDING 4 PARTIAL DEMOLITION ONE-LINE DIAGRAM

AND PANELBOARD SCHEDULES

E-116 BUILDING 4 GROUND FLOOR ELECTRICAL POWER NEW

WORK PLAN

E-117 BUILDING 4 GROUND FLOOR ELECTRICAL LIGHTING NEW

WORK PLAN

E-118 BUILDING 4 STAIRWELL ELECTRICAL LIGHTING NEW

WORK PLANS

E-119 BUILDING 4 PARTIAL NEW WORK ONE-LINE DIAGRAM

AND PANELBOARD SCHEDULES

ED-120 BUILDING 5 GROUND FLOOR ELECTRICAL POWER

DEMOLITION PLAN

ED-121 BUILDING 5 GROUND FLOOR ELECTRICAL LIGHTING

DEMOLITION PLAN

ED-122 BUILDING 5 STAIRWELL ELECTRICAL LIGHTING

DEMOLITION PLANS

ED-123 BUILDING 5 PARTIAL DEMOLITION ONE-LINE DIAGRAM

AND PANELBOARD SCHEDULE

E-124 BUILDING 5 GROUND FLOOR ELECTRICAL POWER NEW

WORK PLAN

00 01 15 - 3

ELECTRICAL CONTINUED:

E-125 BUILDING 5 GROUND FLOOR ELECTRICAL LIGHTING NEW

WORK PLAN

E-126 BUILDING 5 STAIRWELL ELECTRICAL LIGHTING NEW

WORK PLANS

E-127 BUILDING 5 PARTIAL NEW WORK ONE-LINE DIAGRAM

AND PANELBOARD SCHEDULES

ED-128 BUILDING 6 GROUND FLOOR ELECTRICAL POWER

DEMOLITION PLAN

ED-129 BUILDING 6 GROUND FLOOR ELECTRICAL LIGHTING

DEMOLITION PLAN

ED-130 BUILDING 6 STAIRWELL ELECTRICAL LIGHTING

DEMOLITION PLANS

ED-131 BUILDING 6 PARTIAL DEMOLITION ONE-LINE DIAGRAM

AND PANELBOARD SCHEDULES

E-132 BUILDING 6 GROUND FLOOR ELECTRICAL POWER NEW

WORK PLAN

E-133 BUILDING 6 GROUND FLOOR ELECTRICAL LIGHTING NEW

WORK PLAN

E-134 BUILDING 6 STAIRWELL ELECTRICAL LIGHTING NEW

WORK PLANS

E-135 BUILDING 6 PARTIAL NEW WORK ONE-LINE DIAGRAM

AND PANELBOARD SCHEDULES

ED-136 BUILDING 7 GROUND FLOOR ELECTRICAL POWER

DEMOLITION PLAN

ED-137 BUILDING 7 GROUND FLOOR ELECTRICAL LIGHTING

DEMOLITION PLAN

ED-138 BUILDING 7 STAIRWELL ELECTRICAL LIGHTING

DEMOLITION PLANS

ED-139 BUILDING 7 PARTIAL DEMOLITION ONE-LINE DIAGRAM

AND PANELBOARD SCHEDULES

E-140 BUILDING 7 GROUND FLOOR ELECTRICAL POWER NEW

WORK PLAN

E-141 BUILDING 7 GROUND FLOOR ELECTRICAL LIGHTING NEW

WORK PLAN

00 01 15 - 4

ELECTRICAL CONTINUED:

E-142 BUILDING 7 STAIRWELL ELECTRICAL LIGHTING NEW

WORK PLANS

E-143 BUILDING 7 PARTIAL NEW WORK ONE-LINE DIAGRAM

AND PANELBOARD SCHEDULES

ED-144 BUILDING 12 GROUND FLOOR ELECTRICAL POWER

DEMOLITION PLAN

ED-145 BUILDING 12 GROUND FLOOR ELECTRICAL LIGHTING

DEMOLITION PLAN

ED-146 BUILDING 12 STAIRWELL ELECTRICAL LIGHTING

DEMOLITION PLANS

ED-147 BUILDING 12 PARTIAL DEMOLITION ONE-LINE DIAGRAM

AND PANELBOARD SCHEDULE

E-148 BUILDING 12 GROUND FLOOR ELECTRICAL POWER NEW

WORK PLAN

E-149 BUILDING 12 GROUND FLOOR ELECTRICAL LIGHTING

NEW WORK PLAN

E-150 BUILDING 12 STAIRWELL ELECTRICAL LIGHTING NEW

WORK PLANS

E-151 BUILDING 12 PARTIAL NEW WORK ONE-LINE DIAGRAM

AND PANELBOARD SCHEDULES

ED-152 BUILDING 14 GROUND FLOOR ELECTRICAL POWER

DEMOLITION PLAN

ED-153 BUILDING 14 GROUND FLOOR ELECTRICAL LIGHTING

DEMOLITION PLAN

ED-154 BUILDING 14 STAIRWELL ELECTRICAL LIGHTING

DEMOLITION PLANS

ED-155 BUILDING 14 PARTIAL DEMOLITION ONE-LINE DIAGRAM

AND PANELBOARD SCHEDULES

E-156 BUILDING 14 GROUND FLOOR ELECTRICAL POWER NEW

WORK PLAN

E-157 BUILDING 14 GROUND FLOOR ELECTRICAL LIGHTING

NEW WORK PLAN

E-158 BUILDING 14 STAIRWELL ELECTRICAL LIGHTING NEW

WORK PLANS

00 01 15 - 5

ELECTRICAL CONTINUED:

E-159 BUILDING 14 PARTIAL NEW WORK ONE-LINE DIAGRAM

AND PANELBOARD SCHEDULES

E-500 ELECTRICAL DETAILS

- - - E N D - - -

01 00 00 - i

SECTION 01 00 00

GENERAL REQUIREMENTS

TABLE OF CONTENTS

1.0 SAFETY REQUIREMENTS

1.1 GENERAL INTENTION

1.2 STATEMENT OF BID ITEM(S)

1.3 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR

1.4 CONSTRUCTION SECURITY REQUIREMENTS

1.5 OSHA REQUIREMENTS-SAFETY AND HEALTH REGULATIONS

1.6 SPECIFIC MEDICAL CENTER FIRE & SAFETY POLICIES, PROCEDURES, AND

REGULATIONS

1.7 FIRE SAFETY

1.8 HOT WORK PERMIT

1.8.5 ELECTRICAL WORK PERMIT

1.9 OPERATIONS AND STORAGE AREAS

1.10 ALTERATIONS

1.11 INFECTION PREVENTION MEASURES

1.12 DISPOSAL AND RETENTION

1.13 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES,

AND IMPROVEMENTS

1.14 RESTORATION

1.15 WARRANTY MANAGEMENT

1.16 PHYSICAL DATA

1.17 AS-BUILT DRAWINGS

1.18 USE OF ROADWAYS

1.19 TEMPORARY USE OF MECHANICAL AND ELECTRICAL EQUIPMENT

1.20 TEMPORARY USE OF EXISTING ELEVATORS

1.21 TEMPORARY TOILETS

1.22 AVAILABILITY AND USE OF UTILITY SERVICES

1.23 TELEPHONES

1.24 INSPECTION AND TESTS

1.25 TESTS

1.26 INSTRUCTIONS

1.27 GOVERNMENT FURNISHED PROPERTY

1.28 RELOCATED EQUIPMENT ITEMS

1.29 HISTORIC PRESERVATION

1.30 SMOKE BARRIER PENETRATION PERMIT

01 00 00 - ii

1.31 CONTRACTOR PARKING

1.32 CONTRACTOR IDENTIFICATION BADGES

1.33 CONFINED SPACE ENTRY

1.34 ACCESS INTO KEYED AREAS

1.35 PROTECTIVE CLOTHING/EQUIPMENT

1.36 FEDERAL POLICE

1.37 LOST AND FOUND

1.38 REMOVAL OF GOVERNMENT PROPERTY

1.39 SEXUAL HARASSMENT

1.40 DRUGS AND ALCOHOL

1.41 FIREARMS AND EXPLOSIVES

1.42 INJURY ACCIDENTS

1.43 RECREATIONAL FACILITIES

1.44 DUST AND FUME CONTROL

1.45 NOISE

1.46 INSPECTION AND APPROVAL

1.47 SUBMITTALS

1.48 CONTRACT WORK HOURS

1.49 CONSTRUCTION SIGN

1.50 PHOTOGRAPHIC DOCUMENTATION

1.51 SCHEDULES FOR CONSTRUCTION CONTRACTS

1.52 MINIMUM HOURLY RATE OF WAGES

1.53 PUNCH LIST OMISSIONS

01 00 00 - 1

SECTION 01 00 00

GENERAL REQUIREMENTS

1.0 SAFETY REQUIREMENTS

Refer to section 01 35 26, SAFETY REQUIREMENTS for safety and infection control requirements.

1.1 GENERAL INTENTION

A. The General Contractor and its sub-subcontractors (Hereinafter the

“Contractor”) shall completely prepare site at the Montrose Campus

(hereinafter “Campus” or “Medical Center”) for the removal of existing obsolete fused panelboards and installation of replacement panelboards required by contract drawings and specifications (the “Project”).

B. Visits to the site by Bidders may be made only by appointment with the

Medical Center Engineering COR.

C. Testing of materials is the responsibility of the Contractor. All testing is to be performed by qualified, licensed testing firms, names and a minimum of 3 testing firms shall be submitted to be approved by the COR. Before placement and installation of work subject to tests by testing laboratory, the Contractor shall notify the COR in sufficient time to enable testing firm personnel to be present at the site in time for proper taking and testing of specimens and field inspection, if elected, by a government representative. Prior notice shall be not less than three workdays unless otherwise designated by the COR. Three qualified testing agencies shall be submitted with their associated qualifications for review and approval by VA COR.

D. Offices of Northeast Infrastructure LLC (hereinafter the “Engineer”), will render certain technical and oversight services during construction. Such services shall be considered as advisory to the VA and shall not be construed as expressing or implying a contractual act of the VA without affirmations by the COR.

E. All employees of Contractor including subcontractors shall comply with

VA security management program and obtain permission of the VA police, be identified with a VA issued photo ID, and restricted from unauthorized access. All contractor visitors and employees identified as not having proper identification will be dismissed from the Medical

Center grounds until such time as proper ID has been obtained. All employees of the Contractor and subcontractors will be required to be made available to Police Service at the Campus to apply for photo

01 00 00 - 2 identification badge and fingerprinting following badge production the employee shall return in person to receive issue of the badge. The

Contractor shall furnish the names of all employees scheduled to work on this project to the VA COR within ten days of the Notice to Proceed

(NTP). The contractor shall identify on the construction schedule of work the date for start of work of short term specialty subcontractors and two weeks prior to start of work process identification badge verification for employee issue prior to starting of work (Employees not issued identification badges will have to leave the site at no addition cost to the government.)

F. Subcontractors performing work on this project shall be licensed and insured. All work required for the Project shall be performed by licensed/certified journeyman or registered apprentices. The number of apprentices used to execute the Project shall not at any time exceed the number of licensed/certified journeyman. The journeyman shall carry at all times when on VA property a copy of their license or certification. Copies of all Insurance and licenses/certifications shall be furnished to the COR within 10 business days from the Notice to Proceed.

G. Training:

1. Beginning July 31, 2005, all employees of the Contractor shall have

10-hour OSHA certified Construction Safety course and /or other relevant competency training, as determined in writing by VA COR.

2. Submit training records of all such employees for approval before the start of work.

H. Superintendent and Project Manager

1. The Superintendent shall be a direct employee of the General/Prime

Contractor and have authority to act as an authorized representative of the General/Prime Contractor, responsible for the day-to-day operations at the construction site, planning, quality control, verification of delivery of approved material and equipment, subcontractor coordination responsibilities and execution of the complete Project as per the contract documents. The Superintendent shall have a minimum of five (5) years’ experience in the building construction industry as a construction/project superintendent and shall be licensed in one of the building construction trades relevant to the Project. In addition, the Superintendent shall have

01 00 00 - 3 sufficiently completed a 30-hour OSHA training for construction safety. The General Contractor shall at the onset of the Project, no later than 30 calendar days following the NTP, submit to the VA COR for approval a resume and any relevant training certifications and licenses for the Superintendent. The VA COR reserves the right to reject any proposed superintendent that does not meet the above minimum qualifications.

2. The Superintendent shall be dedicated exclusively to the Project once approved by the COR and until the completion of all Project construction activities and shall not be responsible for administering or managing in any capacity any other work site on behalf of the General/Prime Contractor or other third party. The superintendent shall have no hands-on construction interaction.

3. The Superintendent shall sign-in at the beginning of each day of work and Sign-out at the end of the work day at the COR’s office. No work shall be performed by any contractors or subcontractors without the presence of the Superintendent at the actual work site.

4. On a weekly basis, the Superintendent shall provide written job site inspection reports based on a walkthrough of the construction site with the COR.

5. The Superintendent shall be responsible for submitting daily work logs to the VA COR at the end of every work day.

6. The General/Prime Contractor shall also provide services of a

Project Manager whose responsibilities will include but not be limited to providing support to the Superintendent at the job site and shall be responsible for finance-related tasks and scheduling.

7. The VA’s Engineering Service Office is open during normal weekday business hours, 8:00 AM – 4:30 PM

8. Off-duty hours check-in shall be first arranged with the VA COR for approval.

I. Electrical Work Permit

The contractor shall complete the VA Electrical Work Permit with the

COR and submit to the COR a minimum of 48 hours prior to start of electrical work within the facility.

J. The contractor shall have all employees working on this project have a background testing for Tuberculosis with results available upon request from the Medical Center. The contractor will provide a signed memo

01 00 00 - 4 stating the employee’s name and date of last Tuberculosis test on company letter head.

1.2 STATEMENT OF BID ITEM(S)

- A.ITEM I, Electrical Work: Work includes all labor, material, equipment and supervision to perform the required electrical construction work on this project including the removal of obsolete fused panelboards:

- Building 1; Panel ID B-1-1-112

- Building 3; Panel ID B-3-G-13-L

- Building 3; Panel ID B-3-G-7

- Building 3; Panel ID B-3-G-8A-F

- Building 4; Panel ID B-4-G-9A-X

- Building 4; Panel ID B-4-G-7-A

- Building 5; Panel ID B-5-G-5/7

- Building 6; Panel ID B-6-G-13

- Building 6; Panel ID B-6-G-X-9

- Building 7; Panel ID B-7-G-15

- Building 7; Panel ID B-7-G-X-9

- Building 7; Panel ID B-7-G-8A

- Building 7; Panel ID B-7-G-8

- Building 12; Panel ID B-12-G-8A-X

- Building 14; Panel ID B-14-G-17-G

- Building 14; Panel ID B-14-G-12B-E-R

- Building 14; Panel ID B-14-G-12B-X-L

- Building 14; Panel ID B-14-G-9-A

Under this scope of work replacement panelboards are to be installed for the associated panelboards with consideration taken for consolidation of associated branch circuiting per VA Electrical Design guidelines and NEC requirements. The panelboards are to be relocated in dedicated electrical spaces that are provided or identified under this project.

A. Base Bid - The Contractor will furnish all new materials, equipment, supervision, and personnel necessary to accomplish the Project as shown on the drawings and specifications and perform work specified herein and comply with VA regulations, procedures and conditions for work at the Medical Center and any applicable codes as per requirements of all governing agencies. Contractor will be responsible to coordinate and

01 00 00 - 5 schedule work to minimize to short duration any shutdowns. Phasing shall be coordinated with the VA COR to ensure minimal shutdowns during construction. See associated phasing documentation associated with the

Construction Documents. Refer to section 1.9 for phasing.

B. Bid Alternates – N/A

1.3 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR

A. AFTER AWARD OF CONTRACT, two (2) sets of specifications and drawings will be furnished.

B. Additional sets of drawings may be made by the Contractor, at

Contractor's expense, from reproducible sepia prints furnished by the

VA COR. Such sepia prints shall be returned to the VA COR immediately after printing is completed.

1.4 CONSTRUCTION SECURITY REQUIREMENTS

A. Security Plan:

1. The security plan defines both physical and administrative security procedures that will remain effective for the entire duration of the

Project. Submit Security Plan #3 to the VA for approval.

2. The Contractor is responsible for assuring that all sub-contractors working on the Project and their employees also comply with these regulations.

B. Security Procedures:

1. The Contractor’s employees shall not enter the Project site without an appropriate badge. They may also be subject to inspection of their personal effects when entering or leaving the Project site.

2. For working outside the “regular hours” as defined in the contract, the Contractor shall give 3 days’ notice to the COR so that security arrangements can be provided for the employees. This notice is separate from any notices required for utility shutdown described later in this section.

3. No photography of VA premises is allowed without written permission of the COR.

4. VA reserves the right to close down or shut down the Project site and order Contractor’s employees off the premises in the event of a national emergency. The Contractor may return to the site only with the written approval of the COR.

01 00 00 - 6

C. Key Control:

1. The Contractor shall provide duplicate keys and lock combinations to the VA COR for the purpose of security inspections of every area of

Project including tool boxes and parked machines and take any emergency action.

2. The Contractor shall turn over all permanent lock cylinders to the

VA locksmith for permanent installation.

D. Document Control:

1. Before starting any work, the General Contractor/Sub Contractors shall submit an electronic security memorandum describing the approach to following goals and maintaining confidentiality of

“sensitive information”.

2. The General Contractor is responsible for safekeeping of all drawings, project manual and other project information. This information shall be shared only with those with a specific need to accomplish the project.

3. Certain documents, sketches, videos or photographs and drawings may be marked “Law Enforcement Sensitive” or “Sensitive Unclassified”.

Secure such information in separate containers and limit the access to only those who will need it for the project. Return the information to the COR upon request.

4. These security documents shall not be removed or transmitted from the project site without the written approval of COR.

5. All paper waste or electronic media such as CD’s and diskettes shall be shredded and destroyed in a manner acceptable to the VA.

6. Notify the COR and Site Security Officer immediately when there is a loss or compromise of “sensitive information”.

7. All electronic information shall be stored in specified location following VA standards and procedures using an Engineering Document

Management Software (EDMS).

a. Security, access and maintenance of all project drawings, both scanned and electronic shall be performed and tracked through the

EDMS system.

b. “Sensitive information” including drawings and other documents may be attached to e-mail provided all VA encryption procedures are followed.

01 00 00 - 7

E. Motor Vehicle Restrictions

1. Vehicle authorization request shall be required for any vehicle entering the site and such request shall be submitted 24 hours before the date and time of access. Access shall be restricted to picking up and dropping off materials and supplies.

2. A limited number of (2 to 5) permits shall be issued for General

Contractor and its employees for parking in designated areas only.

1.5 OSHA REQUIREMENTS-SAFETY AND HEALTH REGULATIONS

A. Contractors are required to comply with the Occupational Safety and

Health Standard found in CFR 1910 and 1926. Copies of these statements can be acquired from the Superintendent of Documents, U.S. Government

Printing Office Washington, D.C. 20420.

B. In addition, the Contractor will be required to comply with all applicable Medical Center fire, safety, and security regulations, policies and procedures. Each of the Contractor's employees, inclusive of subcontractors and their employees will be required to read this section, sign, and acknowledge understanding. Signed acknowledgment must be filed with the COR prior to any employee's assignment to the work site.

C. Contractor, along with other submittals, and at least two weeks prior to bringing any materials on-site, must submit a complete list of chemicals the contractor will use and safety data sheets for all hazardous materials brought on-site.

D. Severe or constant violations may result in an immediate work stoppage or request for a Compliance Officer from the Occupational Safety and

Health Administration.

1.6 SPECIFIC MEDICAL CENTER FIRE & SAFETY POLICIES, PROCEDURES, AND

REGULATIONS

A. Introduction

1. The safety and fire protection of patients, employees, members of the public and government is one of the continuous concerns of this

Medical Center.

2. Contractors, their supervisors, and employees are required to comply with Medical Center policies to ensure the occupational safety and health of all. Failure to comply may result in work stoppage.

3. While working at this Medical Center, contractors are responsible for the Occupational Safety and Health of their employees.

01 00 00 - 8

Contractors are required to comply with the applicable OSHA standards found in 20 CFR 1910 for general industry and 29 CFR 1926 for construction. Failure to comply with these standards may result in work stoppage and a request to the Area director of OSHA for a compliance office to inspect the work site.

4. Contractors are to comply with the requirements found in the

National Fire Protection Association (NFPA) #241, "Building construction and Demolition Operation".

5. Questions regarding occupational safety and health issues can be addressed to the Medical Center Safety and Occupational Health

Specialist (ext. 2321 at Montrose Campus).

B. Fires

All fires must be reported. In the event of a fire in the work area, use the nearest pull box station and also notify Medical Center staff in the immediate area. Emergency notification can also be accomplished by dialing ext. 2222 at Montrose Campus. This is the fire department emergency phone only. Be sure to give the exact location from where you are calling. If a contractor has experienced a fire and it was rapidly extinguished, you still must notify the fire department (ext. 2332 at

Montrose Campus) so that an investigation of the fire can be accomplished. Delay in reporting a fire is unacceptable.

C. Fire Alarms, Smoke Detection, And Sprinkler System

If the nature of your work requires the deactivation of the fire alarm, smoke detection or sprinkler system, you must notify the Medical Center

Fire Department. Notification must be made well in advance so that ample time can be allowed to deactivate the system and provide an alternative measure for fire protection. Under no circumstance is a contractor allowed to deactivate any of the fire protection systems in this Medical Center.

D. Smoke Detectors

False alarms will not be tolerated. You are required to be familiar with the location of the smoke detectors in your work area. When performing cutting, burning, or welding or any other operation that may cause smoke or dust, you must take steps to temporarily cover smoke detectors in order to prevent false alarms. Failure to take the appropriate action will result in the COR assessing actual costs for government response for each false alarm that is preventable. Prior to

01 00 00 - 9 covering the smoke detectors, the contractor will notify the VAMC Fire

Department, who will also be notified when the covers are removed.

E. Hot Work Permit

1. If the nature of the work requires the use of welding equipment, cutting torch, soldering equipment or the performance of processes which produce sparks, heat or combustion, it will be required that the contractor notify the VA COR no less than one day in advance of such work. The VAMC Fire Department will inspect the work area and issue a "Hot Work Permit" authorizing the performance of such work.

2. A "Hot Work Permit" will be issued only for the period necessary to perform such work. In the event the time necessary will exceed one day, a "Hot Work Permit" may be issued for the period needed;

however, the VAMC Fire Department will inspect the area daily.

3. Contractors will not be allowed to perform hot work processes without the appropriate permit.

F. Temporary Enclosures

Only non-combustible materials will be used to construct temporary enclosures for barriers at this Medical Center. Plastic materials and fabrics used to construct dust barriers must conform to NFPA #701, Standard Methods of fire Tests for Flame-Resistant Textiles and Films.

G. Flammable Liquids

All flammable liquids will be kept in approved safety containers. Only the amount necessary for your immediate work will be allowed in the building. Flammable liquids must be removed from the building at the end of each day.

H. Compressed Gas Cylinders

Compressed gas shall be secured in an upright position at all times. A suitable cylinder cart will be used to transport compressed gas cylinders. Only those compressed gas cylinders necessary for immediate work will be allowed in occupied buildings. All others will be stored outside of buildings in a designated area. The contractor will comply with applicable standards for compressed gas cylinders found in 29 CFR

1910 and 1926 (OSHA).

I. Internal Combustion Engine-Powered Equipment

Equipment powered by an internal combustion engine such as saws, compressors, generators, etc., will not be used in an occupied

01 00 00 - 10 building. Special consideration may be given for unoccupied buildings only if the OSHA and NFPA requirements have been met.

J. Power Activated Tools

In the event power activated tools are on the job site. Power activated tools will be kept in a secured manner at all times. When not in use, the tools will be kept locked up. When in use, the operator will have the tool under his/her immediate control.

K. Tools

1. Under no circumstances are tools, equipment and other items of work to be left unattended for any reason. All tools, equipment and items of work must be under the immediate control of the employee.

2. If for some reason a work area must be left unattended, then it will be required that the tools and other equipment be placed in an appropriate box or container and locked. All tool boxes, containers or any other devices used for the storage of tools and equipment will be provided with a latch and padlock. All tool boxes, containers or any other device used for the storage of tools and equipment will be locked at all times except for putting in and removing tools.

3. All doors to work areas will be closed and locked when rooms are left unattended. Failure to comply with this directive will be considered a violation of VA Regulation 1.218(b), "Failure to comply with signs of directive and restrictive nature posted for safety purposes", subject to a $50.00 fine. Subsequent similar violations may result in both imposition of such a fine as well, as the COR taking action under the Contract's "Accident Prevention Clause", (FAR 52.236-13) to suspend all contract work until such violations may be satisfactorily resolved or under FAR 52.236-5 "Material and

Workmanship Clause" to remove from the work site any personnel deemed by the COR to be careless to the point of jeopardizing the welfare of Facility patients of staff.

4. The contractor must report to the VA Police Department, Extension

2509, any tools or equipment that is missing.

5. Tools and equipment found unattended will be confiscated and removed from the work area.

01 00 00 - 11

L. Ladders

It is required that ladders not be left unattended in an upright position. Ladders must be attended at all times or taken down and securely chained to a stationary object.

M. Scaffolds

All scaffolds will be attended at all times. When not in use, an effective barricade (fence) will be erected around the scaffold to prevent use by unauthorized personnel.

N. Excavations

All excavations left unattended shall be protected with a barricade suitable to prevent entry by unauthorized persons.

O. Storage

The contractor must make prior arrangements with the VA COR for the storage of building materials. Storage will not be allowed to accumulate in Medical Center Buildings.

P. Trash And Debris

The contractor must remove all trash and debris from the work area on a daily basis. Trash and debris will not be allowed to accumulate in the buildings and will be allowed to accumulate outside the buildings for future pick-up. The contractor is responsible for making arrangements for the removal of trash from the Medical Center Facility.

Q. Protection Of Floors

It may be necessary at times to take steps to protect floors from dirt, debris, paint, etc. A tarp or other protective covering shall be used.

However, the contractor must maintain a certain amount of floor space for the safe passage of pedestrian traffic. Common sense must be used in this manner.

R. Signs

Signs must be placed at the entrance to work areas warning people of the construction activities. Signs must be suitable for the condition of the work. Small pieces of paper with printing or writing are not acceptable. The VAMC Safety Officer can be consulted in this matter.

S. Accidents And Injuries

Contractors must report all accidents and injuries involving employees.

The contractor may use the VAMC Health Center, located on the ground floor of Building #3, Room 16 of the Campus.

01 00 00 - 12

T. Fire/Smoke Barrier Penetration Permit

1. If the nature of the work requires the penetration of a fire/smoke partition or barrier the contractor must obtain the proper fire/smoke barrier penetration permit. The VAMC Fire Department will inspect the work area and issue a "Fire/Smoke Barrier Penetration

Permit" authorizing the performance of such work.

2. A "Fire/Smoke Barrier Permit" will be issued only for the period necessary to perform such work. In the event the time necessary will exceed one day, a "Fire/Smoke Barrier Permit" may be issued for the period needed; however, the VAMC Fire Department will inspect the area daily.

3. Contractors will not be allowed to make any penetrations without the appropriate permit. See Attachment "B" for the standard form for obtaining a "Fire/Smoke Barrier Permit".

U. Confined Space Entry

The Contractor shall comply with and have documented Confined Space

Entry Procedures available at the site at all times as required by OSHA

29 CFR 1910.146. The Contractor shall also comply with any state, and/or local requirements that are more restrictive than federal requirements. Contractor is responsible for coordinating with HVHCS’ established policy on Confined Space. All MANHOLE OR OTHER CONFINED

SPACE ENTRIES (AS DEFINED BY OSHA AT 29 CFR 1910.146) PERFORMED BY

CONTRACT PERSONNEL SHALL BE PERFORMED IN STRICT CONFORMANCE WITH THE

HVHCS’ CONFINED SPACE ENTRY PERMIT PROGRAM. THE CONTRACT SHALL CONTACT

THE VA COR FOR SUCH PERMITS AT LEAST TWO WORKING DAYS PRIOR TO THE

PERMIT BEING NEEDED FOR WORK.

1.7 FIRE SAFETY

A. Applicable Publications: Publications listed below form part of this general requirements specification to the extent referenced.

Publications are referenced in text by basic designations only.

1. American Society for Testing and Materials (ASTM):

E84-2007.............Surface Burning Characteristics of Building

Materials

2. National Fire Protection Association (NFPA):

10-2006..............Standard for Portable Fire Extinguishers

30-2003..............Flammable and Combustible Liquids Code

01 00 00 - 13

51B-2003.............Standard for Fire Prevention During Welding, Cutting and Other Hot Work

70-2005..............National Electrical Code

241-2004.............Standard for Safeguarding Construction, Alteration, and Demolition Operations

3. Occupational Safety and Health Administration (OSHA):

29 CFR 1926..........Safety and Health Regulations for Construction

B. Fire Safety Plan: Establish and maintain a fire protection program in accordance with 29 CFR 1926. Prior to start of work, prepare a plan detailing Project-specific fire safety measures, including periodic status reports, and submit to VA COR and Facility Safety Manager for review for compliance with contract requirements in accordance with

Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA AND SAMPLES Prior to any worker for the contractor or subcontractors beginning work, they shall undergo a safety briefing provided by the Contractor’s competent person per OSHA requirements. This briefing shall include information on the construction limits, VAMC safety guidelines, means of egress, break areas, work hours, locations of restrooms, use of VAMC equipment, etc.

Documentation shall be provided to the VA COR that individuals have undergone contractor’s safety briefing.

C. Site and Building Access: Maintain free and unobstructed access to facility emergency services and for fire, police and other emergency response forces in accordance with NFPA 241.

D. Separate temporary facilities, such as trailers, storage sheds, and dumpsters, from existing buildings and new construction by distances in accordance with NFPA 241. For small facilities with less than 6 m (20 feet) exposing overall length, separate by 3m (10 feet).

E. Temporary Construction Partitions:

1. Install and maintain temporary construction partitions to provide smoke-tight separations between construction areas and adjoining areas. Construct partitions of gypsum board or treated plywood

(flame spread rating of 25 or less in accordance with ASTM E84) on both sides of fire retardant treated wood or metal steel studs.

Extend the partitions through suspended ceilings to floor slab deck or roof. Seal joints and penetrations. At door openings, install

Class C, ¾ hour fire/smoke rated doors with self-closing devices.

01 00 00 - 14

2. Install one-hour temporary construction partitions as shown on drawings to maintain integrity of existing exit stair enclosures, exit passageways, fire-rated enclosures of hazardous areas, horizontal exits, smoke barriers, vertical shafts and openings enclosures.

3. Close openings in smoke barriers and fire-rated construction to maintain fire ratings. Seal penetrations with listed through-penetration firestop materials in accordance with specifications.

F. Temporary Heating and Electrical: Install, use and maintain installations in accordance with 29 CFR 1926, NFPA 241 and NFPA 70.

G. Means of Egress: Do not block exiting for occupied buildings,

1. including paths from exits to roads. Minimize disruptions and

2. coordinate with VA COR and facility Safety Manager.

H. Egress Routes for Construction Workers: Maintain free and unobstructed egress. Inspect daily. Report findings and corrective actions weekly to the VA COR and facility Safety Manager.

I. Fire Extinguishers: Provide and maintain extinguishers in construction areas and temporary storage areas in accordance with 29 CFR 1926, NFPA

241 and NFPA 10. Superintendent shall maintain records of monthly inspection of each fire extinguisher on the site. All subcontractors shall present fire extinguishers to the superintendent for inspection and documentation. Fire extinguishers shall display tag for date of inspection and initial of superintendent.

J. Flammable and Combustible Liquids: Store, dispense and use liquids in accordance with 29 CFR 1926, NFPA 241 and NFPA 30.

K. Existing Fire Protection: Do not impair automatic sprinklers, smoke and heat detection, and fire alarm systems, except for portions immediately under construction, and temporarily for connections. Provide fire watch for impairments more than 4 hours in a 24-hour period. Request interruptions in accordance with Section, OPERATIONS AND STORAGE AREAS, and coordinate with VA COR and facility Safety Manager. All existing or temporary fire protection systems (fire alarms, sprinklers) located in construction areas shall be tested as coordinated with the medical center. Parameters for the testing and results of any tests performed shall be recorded by the medical center and copies provided to the VA

COR.

01 00 00 - 15

L. Hot Work: Perform and safeguard hot work operations in accordance with

NFPA 241 and NFPA 51B. Coordinate with VA COR. Obtain permits from facility Safety Manager/Fire Department at least 24 hours in advance.

Designate contractor's responsible Project-site fire prevention program manager to permit hot work. See paragraph 1.8 (Hot Work Permit) for additional information

M. Fire Hazard Prevention and Safety Inspections: Inspect entire construction areas weekly. Coordinate with, and report findings and corrective actions weekly to VA COR and facility Safety Manager.

N. Smoking: Smoking is prohibited in and adjacent to construction areas inside existing buildings and additions under construction. In separate and detached buildings under construction, smoking is prohibited except in designated smoking rest areas.

O. Dispose of waste and debris in accordance with NFPA 241. Remove from buildings daily.

P. Perform other construction, alteration and demolition operations in accordance with 29 CFR 1926.

Q. If required, submit documentation to the VA COR that personnel have been trained in the fire safety aspects of working in areas with impaired structural or compartmentalization features.

R. All temporary heating equipment shall be installed in accordance with requirements of applicable NFPA Standards and manufacturer’s instructions.

S. All flammable liquids shall be handled, stored, and used in accordance with NFPA Standard No. 30-1990.

T. All temporary electrical wiring and equipment used for construction shall be installed and used in accordance with pertinent provisions of

NFPA Standard No. 70-1990.

U. All construction activities not already covered above shall be in accordance with the latest edition of NFPA no. 241-1898 Standard for

Safeguarding Construction, Alteration, and Demolition Operations, in effect at time of contract award.

1.8 HOT WORK PERMIT

A. The Contractor is responsible for requesting a “Hot “Work” permit each day prior to commencing any cutting, burning, and welding or open torch work. The permit is requested and obtained through the Fire Department following an inspection by the Fire Department and COR of the intended

01 00 00 - 16 area of use. The permit once issued will be for a maximum duration of one (1) day, after which a renewal, if required, must be requested by the Contractor.

B. Before approving any “Hot Work” permit, the Contractor’s authorized representative, the COR, and other representatives of the Dept. of

Veterans Affairs shall inspect the work area and confirm that precautions have been taken to prevent fire in accordance with NFPA

Standard No. 51B. Following a positive inspection, a representative of the Fire Dept. will issue the “Hot Work” permit.

C. In areas of “Hot Work” the following precautions are considered essential:

1. Sprinklers are in service where installed.

2. Cutting, welding, and other open flame torches are in good repair.

3. Within 15 feet of the actual work:

a. Floors swept clean of combustible materials.

b. No combustible materials or flammable liquids are present.

c. All wall and floor openings are covered.

d. Covers suspended beneath work to collect sparks.

4. When working on enclosed equipment and in confined space, equipment and area is free of flammable vapors.

5. Fire watch provided during and 30 minutes after operation (60 minutes for torch applied roofing operations.

1.8.5 ELECTRICAL WORK PERMIT

A. The Contractor is responsible for ensuring that a Licensed Journeyman

Electrician by a State or Local jurisdiction is present during any and all electrical work activities during this project.

B. The contractor shall not perform any work on live electrical circuits without an approved Electrical Energized Work Permit is approved.

C. Before approving any “Energized Electrical Work” permit, the

Contractor’s authorized representative, the COR, and other representatives of the Dept. of Veterans Affairs shall discuss the proposed work and confirm that this work needs to be completed on a live circuit.

1.9 OPERATIONS AND STORAGE AREAS

A. The Contractor shall confine all operations (including storage of materials) on Government premises to areas authorized or approved by the VA COR. The Contractor shall hold and save the Government, its

01 00 00 - 17 officers and agents, free and harmless from liability of any nature occasioned by the Contractor's performance.

B. Temporary buildings (e.g., storage sheds, shops, offices) and utilities may be erected by the Contractor only with the approval of the VA COR and shall be built with labor and materials furnished by the Contractor without expense to the Government. The temporary buildings and utilities shall remain the property of the Contractor and shall be removed by the Contractor at its expense upon completion of the work.

With the written consent of the VA COR, the buildings and utilities may be abandoned and need not be removed.

C. The Contractor shall, under regulations prescribed by the COR, use only established roadways, or use temporary roadways constructed by the

Contractor when and as authorized by the COR. When materials are transported in prosecuting the work, vehicles shall not be loaded beyond the loading capacity recommended by the manufacturer of the vehicle or prescribed by any Federal, State, or local law or regulation. When it is necessary to cross curbs or sidewalks, the

Contractor shall protect them from damage. The Contractor shall repair or pay for the repair of any damaged curbs, sidewalks, or roads.

D. Working space and space available for storing materials shall be as determined by the VA COR. The Contractor shall consider that storage of excavated materials on roadways, walkways and parking areas is prohibited. Remote stockpile location shall be as determined by the VA

COR.

E. Workmen are subject to rules of Medical Center applicable to their conduct.

F. Execute work so as to interfere as little as possible with normal functioning of Medical Center as a whole, including operations of utility services, fire protection systems and any existing equipment, and patients, visitors, staff and/ or with work being done by others.

Provide unobstructed access to Medical Center areas required to remain in operation. Use of equipment and tools that transmit vibrations and noises through the building structure, are not permitted in buildings that are occupied, during construction, jointly by patients or medical personnel, and Contractor's personnel, except as permitted by VA COR where required by limited working space. Keep roads clear of construction materials, debris, standing construction equipment and

01 00 00 - 18 vehicles at all times. Do not block crosswalks and / or handicap access.

1. Do not store materials and equipment in other than assigned areas.

Storage of construction equipment and excess materials is prohibited within the workspace. Store all construction materials and other equipment only in lockable, watertight secure trailers.

2. Schedule delivery of materials and equipment to immediate construction working areas within buildings in use by Department of

Veterans Affairs in quantities sufficient for not more than two work days. Provide unobstructed access to Medical Center areas required to remain in operation. The Contractor shall be on site to receive all scheduled deliveries. The Medical Center Warehouse will not accept deliveries; do not use the warehouse as a shipping destination. The VA COR will assign routes for the delivery of materials and supplies to the jobsite if such routes are not designated in the Contract Document. Under no circumstances will

Government accept deliveries for the Contractor. The Contractor will advise the VA COR, in writing, 48 Hours in advance of delivery of materials or equipment requiring the blocking of any Medical Center

Road, street, walkway, or building egress and await a written reply prior to effecting any such blockage. Building loading docks and landings may be used to load and unload construction materials when requested by the Contractor in writing and approved by the VA COR.

Approval to utilize loading dock areas may contain restrictions as to areas which can be utilized by the Contractor. Loading Docks are not to be used as storage areas nor are the docks to be considered as a parking area for more than 20 minutes.

3. Provide unobstructed access to Medical Center areas required to remain in operation. Where access by Medical Center personnel to vacated portions of buildings is not required, storage of

Contractor's materials and equipment will be permitted subject to fire and safety requirements.

G. Utilities Services: Where necessary to cut existing pipes, electrical wires, conduits, cables, etc., of utility services, or of fire protection systems or communications systems (except telephone), they shall be cut and capped at suitable places where shown; or, in absence

01 00 00 - 19 of such indication, where directed by COR All such actions shall be coordinated with the COR or Utility Company involved:

1. Whenever it is required that a connection fee be paid to a public utility provider for new permanent service to the construction project, for such items as water, sewer, electricity, gas or steam, payment of such fee shall be the responsibility of the Government and not the Contractor.

H. Phasing:

The Medical Center must maintain its operation 24 hours a day 7 days a week. Therefore, any interruption in service must be scheduled and coordinated with the COR to ensure that no lapses in operation occur.

It is the CONTRACTOR'S responsibility to develop a work plan and schedule detailing, at a minimum, the procedures to be employed, the equipment and materials to be used, the interim life safety measure to be used during the work, and a schedule defining the duration of the work with milestone subtasks. The work to be outlined shall include, but not be limited to:

To ensure such executions, Contractor shall furnish the VA COR with a schedule of approximate phasing and dates on which the Contractor intends to accomplish work in each specific area of site, building or portion thereof. In addition, Contractor shall notify the VA COR two weeks in advance of the proposed date of starting work in each specific area of site, building or portion thereof. Arrange such phasing and dates to ensure accomplishment of this work in successive phases mutually agreeable to VA COR and Contractor as follows:

PHASE

ITEM

NO. CONSTRUCTION TASK

TBD

01 00 00 - 20

01 00 00 - 21

Phase I: Submittals: Contractor shall submit all required submittals in

Division No. 1 as required by the COR in the time stipulated by the COR to issue the Award Notification and Notice to Proceed. Submittals are to be submitted within 45 days of the Notice to Proceed and until approval no work shall commence on the job site. Delays and lack to progress work on schedule will be borne by the Contractor.

Phase II: VAHVHCS shall review submittals and return to contractor.

Submittals will be returned within 30 days of receipt of submittal.

Phase III: Due to needed use of these facilities by numerous medical clinics for procedures the work area will not be available to the contractor until the electrical work items are present and stored on the job site location. Contractor shall commence there-after and then complete construction for base bid in a period of 270 Calendar Days from the Notice to Proceed.

Phase IV: Contractor shall clean up site within 10 Calendar Days of the above-indicated completion. VAHVHCS shall perform a final inspection after site is cleaned by contractor.

01 00 00 - 22

Contract Completion shall be 280 Calendar Days from the Notice to

Proceed.

I. When a construction site is turned over to Contractor, Contractor shall accept entire responsibility therefore.

1. Contractor shall maintain a minimum temperature of 4 degrees C (40 degrees F) at all times, except as otherwise specified.

2.…