Scope of Work.pdf
PDF 1 MB Posted
- Solicitation number
- 36C24225B0018
About this file
This is a Scope of Work document for Project #620-15-111 to replace fused and obsolete electrical panels at the FDR Montrose Campus of the Hudson Valley Health Care System VA Medical Center in New York. The project involves replacing antiquated electrical panels and associated feeders and branch circuit wiring that are no longer VA compliant, including panels located in hallways/stairwells and aluminum wiring that must be replaced with copper.
The work encompasses 18 specific panelboards across Buildings 1, 3, 4, 5, 6, 7, 12, and 14 that must be relocated to suitable locations meeting NEC requirements. Key objectives include relocating hallway/electrical fused panels to dedicated electrical rooms or secured locations, replacing main feed and branch circuit wiring, and replacing fuse panels with circuit breaker panels. The contractor must furnish all new materials, equipment, supervision and labor, coordinate with the VA COR to minimize shutdown durations during construction, and comply with all VA, Federal, State and Local codes. Common issues documented across the panels include obsolete fuses, lack of proper grounding, undersized copper conductors, multiple circuits tapped off single fuses, abandoned conductors, and exposed openings requiring UL listed conduit plugs/caps.
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Project # 620-15-111
Replace Fused and Obsolete Electrical Panels
FDR Montrose Campus
Scope of Work (Construction)
Electrical panels and associated feeders and branch circuit wiring have been identified as antiquated and in need of replacement. Fuse panels are no longer
VA compliant nor are panels located in hallways and stairwells. In addition to fused panels needing replacement, aluminum wiring is no longer VA compliant and requires identification and replacement with copper. This project will correct safety deficiencies thereby enhancing patient care with a more reliable and robust power distribution network.
The objectives are as follows:
- Relocate hallway and electrical fused panels to dedicated electrical room or secured location.
- Replacement of main feed and branch circuit wiring.
- Replacement of fuse panels with circuit breaker panels.
The Contractor will furnish all new materials, equipment, supervision, and labor necessary to accomplish the work as described in the contract documents and any amendments issued prior to the Bid opening for Project 620-15-111, Replace fused and Obsolete Electrical panels at Montrose Campus of the Hudson Valley Health Care System, New York.
Work shall comply with VA Contract documents, VA regulations, all Federal, State and Local codes including specific regulations related to working at the VA Medical Center at Montrose, NY
Contractor shall be responsible to complete the work within the contractual period of performance, and within the work hours as defined in the contract.
Contractor will be responsible to coordinate and schedule work to minimize to short duration any shutdowns. Phasing shall be coordinated with the VA COR to ensure minimal shutdowns during construction. See associated phasing documentation associated with the Construction Documents. Refer to section 1.9 for phasing.
The Bidding Contractors shall inspect the areas of work prior to bidding.
Scope of Work for the Base Bid includes the following description of work, and as defined in the contract documents but not limited to the following:
The following panelboards shall be replaced throughout Buildings 1, 3, 4, 5, 6, 7, 12, and
14:
- Building 1; Panel ID B-1-1-112
- Building 3; Panel ID B-3-G-13-L
- Building 3; Panel ID B-3-G-7
- Building 3; Panel ID B-3-G-8A-F
- Building 4; Panel ID B-4-G-9A-X
- Building 4; Panel ID B-4-G-7-A
- Building 5; Panel ID B-5-G-5/7
- Building 6; Panel ID B-6-G-13
- Building 6; Panel ID B-6-G-X-9
- Building 7; Panel ID B-7-G-15
- Building 7; Panel ID B-7-G-X-9
- Building 7; Panel ID B-7-G-8A
- Building 7; Panel ID B-7-G-8
- Building 12; Panel ID B-12-G-8A-X
- Building 14; Panel ID B-14-G-17-G
- Building 14; Panel ID B-14-G-12B-E-R
- Building 14; Panel ID B-14-G-12B-X-L
- Building 14; Panel ID B-14-G-9-A
The noted panelboards under this scope of work are to be relocated to suitable locations meeting NEC requirements and as defined by this project drawings and specifications. The associated panelboard circuits shall be redirected to the new panelboard location where they are to be restored to their original state.
Panel Observations – For Reference only
Building 1 – Panelboard B1-1-112
Building 1, 1st Floor, Corridor 38Z.
o 70A panelboard with 100A MCB, 120/208V, single phase, 3- wire o Obsolete fuses o Stranded copper conductors (smaller than #8 conductors as allowable by VA Design Manual) o Lack of grounding for associated branch circuits o Potential multiple circuits fed from a single circuit breaker.
o Conductors are not securely fastened to fuse connections.
o Abandoned conductors within panelboard.
Building 3 – Panelboard B3-G-7
Building 3, Ground Floor, Corridor 19Z o 100A panelboard with 100A MLO, 208/120V, single phase, 3-wire o Obsolete fuses o Stranded copper conductors (smaller than #8 conductors as allowable by VA Design Manual) o Lack of grounding for associated branch circuits o Abandoned conductors within panelboard.
Building 3 – Panelboard B3-G-
8AF Building 3, Ground Floor, Corridor 19Z o 60A panelboard with 60A MCB, 208/120V, single phase, 3- wire o Obsolete fuses o Stranded copper conductors (smaller than #8 conductors as allowable by VA Design Manual) o Tap connections located within panelboard gutter.
o Lack of grounding for associated branch circuits o Abandoned conductors within panelboard gutter.
o Potential multiple circuits fed from a single circuit breaker.
Building 3 – Panelboard B3-G-13-
L Building 3, Ground Floor, Corridor 22Z o 60A panelboard with 100A MLO, 208/120V, single phase, 3-wire o Obsolete fuses o Stranded copper conductors (smaller than #8 conductors as allowable by VA Design Manual)
Building 4 – Panelboard B4-G-7-
A Building 4, Ground Floor, Corridor 22Z o 100A panelboard with 100A MCB, 208/120V, single phase, 3-wire o Obsolete fuses o Stranded copper conductors (smaller than #8 conductors as allowable by VA Design Manual) o Feeder tap connections located within panelboard gutter.
Building 4 – Panelboard B4-G-9A-X
Building 4, Ground Floor, Corridor
24Z o 60A panelboard with 60A MCB, 208/120V, single phase, 3- wire o Obsolete fuses o Lack of grounding for associated branches o Stranded copper conductors (smaller than #8
Building 5 – Panelboard B5-G-
5/7 Building 5, Ground Floor, Corridor 26Z o 125A panelboard with 200A MCB, 208/120V, single phase, 3-wire o Obsolete fuses o Stranded copper conductors (smaller than #8 conductors as allowable by VA Design Manual) o Lack of grounding
Building 6 – Panelboard B6-G-13
Building 6, Ground Floor, Corridor
22Z o 100A panelboard with MLO, 208/120V, 3-phase, 3-wire o Obsolete fuses o Stranded copper conductors (smaller than #8 conductors as allowable by VA Design Manual)
Building 6 – Panelboard B6-G-X-9
Building 6, Ground Floor, Corridor
24Z o 100A panelboard with 60A MCB, 208/120V, single phase, 3-wire o Obsolete fuses o Multiple conductors tapped off the same fuse.
o Lack of grounding o Panelboard openings exposed – require UL listed conduit plug/cap
Building 7 – Panelboard B7-G-8
Building 7, Ground Floor, Corridor 22Z o 100A panelboard with 100A MLO, 208/120V, single phase, 3-wire o Obsolete fuses o Lack of grounding.
Building 7 – Panelboard B7-G-8A
Corridor 22Z o 100A panelboard with 100A MLO, 208/120V, single phase, 3-wire o Obsolete fuses o Lack of grounding.
o Stranded copper conductors (smaller than #8 conductors as allowable by VA Design Manual) o Multiple conductors tapped off the same fuses.
Building 7 – Panelboard B7-G-15
Corridor 26Z o 100A panelboard with 100A MCB, 208/120V, single phase, 3-wire
Building 7 – Panelboard B7-G-X-9
Building 7, Ground Floor, Corridor
24Z o 100A panelboard with 60A MCB, 208/120V, single phase, 3-wire o Obsolete fuses o Lack of grounding o Stranded copper conductors (smaller than #8
Building 12 – Panelboard B12-G-8A-
X Building 12, Ground Floor, Corridor 20Z o 60A panelboard with 60A MCB, 208/120V, single phase, 3- wire o Obsolete fuses o Lack of grounding o Multiple conductors tapped off the same fuse.
Building 14 – Panelboard B14-G-9-A
Building 14, Ground Floor, Corridor
24Z o 125A panelboard with 200A MCB, 208/120V, single phase, 3-wire o Obsolete fuses o Multiple conductors tapped off the same fuse.
o Feeder tap connections located within panelboard gutter.
o Lack of grounding o Stranded copper conductors (smaller than #8
Building 14 – Panelboard B14-G-
12B-E-R Building 14, Ground Floor, Corridor 25Z o 80A panelboard with 80A MCB, 208/120V, single phase, 3- wire
Building 14 – Panelboard B14-G-
12B-X-L Building 14, Ground Floor, Corridor 25Z o 60A panelboard with 60A MCB, 208/120V, single phase, 3- wire
Building 14 – Panelboard B14-G-17-
G Building 14, Ground Floor, Corridor 25Z o 90A panelboard with 90A MCB, 208/120V, single phase, 3- wire o Obsolete fuses o Feeder tap connections located within panelboard gutter.
o Stranded copper conductors (smaller than #8 conductors as allowable by VA Design Manual) o Multiple conductors tapped off the same fuse.