This document is a Schedule Page (Attachment IV) detailing natural gas requirements for multiple Department of Defense and federal civilian installations across the southern United States. The solicitation (SPE604-24-R-0403) covers direct supply natural gas for 45 different installations in Arkansas, Florida, Louisiana, Mississippi, North Carolina, Oklahoma, South Carolina, Georgia, Tennessee, and Texas, with a 24-month performance period beginning June 1, 2025 (with a slightly different start date for Fort Jackson on April 1, 2025).
The total estimated gas volume is approximately 16,745,091 dekatherms, with individual installation requirements ranging from as low as 1,582 dekatherms (Harry Milton Kandell USARC) to as high as 2,616,000 dekatherms (Federal Corrections Complex Butner). The contract will be a fixed-price agreement with economic price adjustment, utilizing various pricing indices including Gas Daily Price Guide for different pipeline zones. Installations will be served by multiple local distribution companies such as Atlanta Gas Light, Centerpoint Energy, Dominion Energy, and others. Offers are due by 3:00 p.m. Eastern Daylight Time on September 5, 2024, with questions accepted via email by August 16, 2024. The solicitation is being issued by the Defense Logistics Agency Energy.
View the file
Other files
Show all 26
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Line Item Installation
Address
City State
Zip
Summit Utilities
218,440 108,740 109,700
Location
58,160 37,070 21,090 Jun Jul Aug Sep Oct Nov Dec
6,950 7,040 7,380 7,520 8,180 9,770 11,320
109,220 54,370 54,850 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
12,160 11,010 10,590 9,210 8,090 6,950 7,040 7,380 7,520 8,180 9,770 11,320
51,060 17,300 33,760 Jan Feb Mar Apr May
12,160 11,010 10,590 9,210 8,090
Curtailment Days Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
0 0 0 0 0 0 0 0 0 0 0 0
Overage & Shortage Volume Pricing Publication Location Methodology Include Adj. Factor
Overage Treatment Summer Volumes Yes
Winter Volumes Yes Shortage Treatment
Summer Volumes Yes Winter Volumes Yes
Note #1
Note #2 Note #3 Note #4
Schedule Page By Line Item Detail
John L McClellan Memorial Hospital Installation Address
0001-01 John L McClellan Memorial Hospital DODAAC/
FEDAAC:4300 W. 7th St.
Little Rock
AR
72205-0000
Delivery Point Telemetered Rate Class City Gate Yes LCS-1 TSO
Utility Account Information LDC or Pipeline
Total Contract Total Summer (Dths) Total Winter (Dths)
No None 0% Alternate Fuel Type Percent Load Limits on Use Notes
Year 2026 Annual Totals Summer Totals Winter Totals
Year 2027 Annual Totals Summer Totals Winter Totals
Estimated Usage Information (All volumes expressed in Dths)
City Gate
Year 2025 Annual Totals Summer Totals Winter Totals
06/01/25 05/31/27 INSIDE FERC'S Enable Gas, East (3) Monthly Order Firm
Solicitation Parameters
Period Beginning Period Ending Publication SIP Delivery Option Delivery Type
GAS DAILY PRICE GUIDE Enable Gas, East Simple Average 1-EOM GAS DAILY PRICE GUIDE Enable Gas, East Simple Average 1-EOM
GAS DAILY PRICE GUIDE Enable Gas, East Simple Average 1-EOM GAS DAILY PRICE GUIDE Enable Gas, East Simple Average 1-EOM
The Contractor is required to perform contractor consolidated billing in accordance with the statement of work. All pipeline capacity charges and LDC transportation charges will be billed as a pass through to the customer.
Address
City State
Zip
Summit Utilities
264,440 98,700 165,740
Location
58,630 27,960 30,670 Jun Jul Aug Sep Oct Nov Dec
6,000 5,000 4,790 4,710 7,460 13,890 16,780
132,220 49,350 82,870 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
19,210 17,150 15,840 12,990 8,400 6,000 5,000 4,790 4,710 7,460 13,890 16,780
73,590 21,390 52,200 Jan Feb Mar Apr May
19,210 17,150 15,840 12,990 8,400
Curtailment Days Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
0 0 0 0 0 0 0 0 0 0 0 0
Overage & Shortage Volume Pricing Publication Location Methodology Include Adj. Factor
Overage Treatment Summer Volumes Yes
Winter Volumes Yes Shortage Treatment
Summer Volumes Yes Winter Volumes Yes
Note #1
Note #2 Note #3 Note #4
Schedule Page By Line Item Detail
Eugene J Towbin Healthcare Center Installation Address
0001-02 Eugene J Towbin Healthcare Center DODAAC /
FEDAAC: FP4460220 Ft. Roots Dr.
North Little Rock
AR
72114-0000
Delivery Point Telemetered Rate Class City Gate Yes LCS-1 TSO
Utility Account Information LDC or Pipeline
Total Contract Total Summer (Dths) Total Winter (Dths)
No None 0% Alternate Fuel Type Percent Load Limits on Use Notes
Year 2026 Annual Totals Summer Totals Winter Totals
Year 2027 Annual Totals Summer Totals Winter Totals
Estimated Usage Information (All volumes expressed in Dths)
City Gate
Year 2025 Annual Totals Summer Totals Winter Totals
06/01/25 05/31/27 INSIDE FERC'S Enable Gas, East (3) Monthly Order Firm
Solicitation Parameters
Period Beginning Period Ending Publication SIP Delivery Option Delivery Type
GAS DAILY PRICE GUIDE Enable Gas, East Simple Average 1-EOM GAS DAILY PRICE GUIDE Enable Gas, East Simple Average 1-EOM
GAS DAILY PRICE GUIDE Enable Gas, East Simple Average 1-EOM GAS DAILY PRICE GUIDE Enable Gas, East Simple Average 1-EOM
The Contractor is required to perform contractor consolidated billing in accordance with the statement of work. All pipeline capacity charges and LDC transportation charges will be billed as a pass through to the customer.
Address
City State
Zip
Summit Utilities
437,630 149,740 287,890
Location
100,805 46,840 53,965 Jun Jul Aug Sep Oct Nov Dec
8,690 7,800 7,600 8,690 14,060 23,890 30,075
218,815 74,870 143,945 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
34,470 31,690 23,820 16,390 11,640 8,690 7,800 7,600 8,690 14,060 23,890 30,075
118,010 28,030 89,980 Jan Feb Mar Apr May
34,470 31,690 23,820 16,390 11,640
Curtailment Days Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
0 0 0 0 0 0 0 0 0 0 0 0
Overage & Shortage Volume Pricing Publication Location Methodology Include Adj. Factor
Overage Treatment Summer Volumes Yes
Winter Volumes Yes Shortage Treatment
Summer Volumes Yes Winter Volumes Yes
Note #1
Note #2 Note #3 Note #4
Schedule Page By Line Item Detail Little Rock AFB
Installation Address Little Rock AFB DODAAC/FE
DAAC:528 Thomas Ave
Little Rock AFB
AR
72099-5000
Delivery Point Telemetered Rate Class City Gate Yes LCS-1
Utility Account Information LDC or Pipeline
Total Contract Total Summer (Dths) Total Winter (Dths)
No None 0% Alternate Fuel Type Percent Load Limits on Use Notes
Year 2026 Annual Totals Summer Totals Winter Totals
Estimated Usage Information (All volumes expressed in Dths)
City Gate
Year 2025 Annual Totals Summer Totals Winter Totals
Delivery Type
06/01/25 05/31/27 INSIDE FERC'S Enable Gas, East (3) Monthly Order Quantities. Firm
Year 2027 Annual Totals Summer Totals Winter Totals
Solicitation Parameters Period Beginning Period Ending Publication SIP Delivery Option
GAS DAILY PRICE GUIDE Enable Gas, East Simple Average 1-EOM GAS DAILY PRICE GUIDE Enable Gas, East Simple Average 1-EOM
GAS DAILY PRICE GUIDE Enable Gas, East Simple Average 1-EOM GAS DAILY PRICE GUIDE Enable Gas, East Simple Average 1-EOM
The Contractor is required to perform contractor consolidated billing in accordance with the statement of work.
Government owns pipeline capacity of 1,700 dths per day on Enable Gas Transmission. The installation will utilize this capacity via its transportation agreement with the pipeline. The contractor will utilize the installation owned capacity and will provide transportation if the increased usage necessitates additional capacity.
The cost associated with the contractor provided transportation will be included in the adjustment factor.
Address
City State
Zip
Summit Utilities
297,380 146,100 151,280
Location
79,700 51,190 28,510 Jun Jul Aug Sep Oct Nov Dec
9,950 9,870 9,890 10,020 11,460 13,230 15,280
148,690 73,050 75,640 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
17,010 16,910 13,210 11,230 10,630 9,950 9,870 9,890 10,020 11,460 13,230 15,280
68,990 21,860 47,130 Jan Feb Mar Apr May
17,010 16,910 13,210 11,230 10,630
Curtailment Days Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
0 0 0 0 0 0 0 0 0 0 0 0
Overage & Shortage Volume Pricing Publication Location Methodology Include Adj. Factor
Overage Treatment Summer Volumes Yes
Winter Volumes Yes Shortage Treatment
Summer Volumes Yes Winter Volumes Yes
Note #1
Note #2
Note #3 Note #4
Schedule Page By Line Item Detail
FDA Jefferson Labs/NCTR Installation Address
FDA Jefferson Labs/NCTR DODAAC/FE
DAAC:3900 NCTR Road
Jefferson
AR
72079-9501
Delivery Point Telemetered Rate Class City Gate Yes LCS-1 TSO
Utility Account Information LDC or Pipeline
Total Contract Total Summer (Dths) Total Winter (Dths)
No None 0% Alternate Fuel Type Percent Load Limits on Use Notes
Year 2026 Annual Totals Summer Totals Winter Totals
Estimated Usage Information (All volumes expressed in Dths)
City Gate
Year 2025 Annual Totals Summer Totals Winter Totals
Delivery Type 06/01/25 05/31/27 INSIDE FERC'S Enable Gas, East (3) Monthly Order Quantities. Firm
Year 2027 Annual Totals Summer Totals Winter Totals
Solicitation Parameters
Period Beginning Period Ending Publication SIP Delivery Option
GAS DAILY PRICE GUIDE Enable Gas, East Simple Average 1-EOM GAS DAILY PRICE GUIDE Enable Gas, East Simple Average 1-EOM
GAS DAILY PRICE GUIDE Enable Gas, East Simple Average 1-EOM GAS DAILY PRICE GUIDE Enable Gas, East Simple Average 1-EOM
The Government owns pipeline capacity of 850 Dths per day. The installation will utilize capacity via its transportation agreement with the pipeline. The contractor will utilize this capacity and will provide transportation if increased usage necessitates additional capacity. The cost associated with the contractor provided transportation will be included in the adjustment factor.
The contractor is required to perform contractor consolidated billing in accordance with the statement of work.
Installation has one delivery point, CenterPoint Energy meter number 912410.
Address
City State
Zip
Black Hills Energy
140,540 65,080 75,460
Location
36,040 21,560 14,480 Jun Jul Aug Sep Oct Nov Dec
4,220 3,990 3,900 4,100 5,350 6,680 7,800
70,270 32,540 37,730 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
8,470 7,590 7,190 5,920 5,060 4,220 3,990 3,900 4,100 5,350 6,680 7,800
34,230 10,980 23,250 Jan Feb Mar Apr May
8,470 7,590 7,190 5,920 5,060
Curtailment Days Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
0 0 0 0 0 0 0 0 0 0 0 0
Overage & Shortage Volume Pricing Publication Location Methodology Include Adj. Factor
Overage Treatment Summer Volumes GAS DAILY PRICE GUIDE Yes
Winter Volumes GAS DAILY PRICE GUIDE Yes Shortage Treatment
Summer Volumes GAS DAILY PRICE GUIDE Yes Winter Volumes GAS DAILY PRICE GUIDE Yes
Note #1 Note #2 Note #3 Note #4
Schedule Page By Line Item Detail
VAMC Fayetteville Installation Address
VAMC Fayetteville DODAAC/FE
DAAC:1100 N. College Ave
Fayetteville
AR
72703-1944
Delivery Point Telemetered Rate Class City Gate Yes Sch B4 Trans (AR580)
Utility Account Information LDC or Pipeline
Total Contract Total Summer (Dths) Total Winter (Dths)
No None 0% N/A Alternate Fuel Type Percent Load Displaceable Limits on Use Notes
Year 2026 Annual Totals Summer Totals Winter Totals
Estimated Usage Information (All volumes expressed in Dths)
Meter
Year 2025 Annual Totals Summer Totals Winter Totals
Year 2027 Annual Totals Summer Totals Winter Totals
Solicitation Parameters Period Beginning Period Ending Publication SIP Delivery Option
Enable Gas, East Simple Average 1-EOM Enable Gas, East Simple Average 1-EOM
Enable Gas, East Simple Average 1-EOM
Delivery Type
06/01/25 05/31/27 INSIDE FERC'S Enable Gas, East (3) Monthly Order Quantities. Firm
Enable Gas, East Simple Average 1-EOM
Address
City State
Zip
TECO Peoples Gas
75,000 35,400 39,600
Location
17,600 11,200 6,400 Jun Jul Aug Sep Oct Nov Dec
2,590 2,090 2,070 2,210 2,240 2,810 3,590
36,900 17,100 19,800 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
5,110 4,500 3,790 3,310 2,590 2,590 2,090 2,070 2,210 2,240 2,810 3,590
20,500 7,100 13,400 Jan Feb Mar Apr May
5,110 4,500 3,790 3,310 3,790
Curtailment Days Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
0 0 0 0 0 0 0 0 0 0 0 0
Overage & Shortage Volume Pricing Publication Location Methodology Include Adj. Factor
Overage Treatment Summer Volumes
Winter Volumes Shortage Treatment
Summer Volumes Winter Volumes
Note #1 Note #2
Note #3
Note #4
Schedule Page By Line Item Detail
Tyndall AFB Installation Address
Tyndall AFB DODAAC /
FEDAAC:119 Alabama Stop 42 Tyndall AFB
FL
32403-5014
Delivery Point Telemetered Rate Class City Gate No NCTS
Utility Account Information LDC or Pipeline
Total Contract Total Summer (Dths) Total Winter (Dths)
No None 0% Alternate Fuel Type Percent Load Limits on Use Notes
Year 2026 Annual Totals Summer Totals Winter Totals
Year 2027 Annual Totals Summer Totals Winter Totals
Estimated Usage Information (All volumes expressed in Dths)
Meter
Year 2025 Annual Totals Summer Totals Winter Totals
06/01/25 05/31/27 INSIDE FERC'S FL Gas Zn3 (2) Full Requirements/Pool. Firm
Solicitation Parameters
Period Beginning Period Ending Publication SIP Delivery Option Delivery Type
Multiple meters will require a single consolidated invoice with a separate breakdown of monthly meter quantities and contractor charges.
Period of performance will start/finish in alignment with TECO Peoples Gas meter reading cycle following the period beginning and period ending cited on this schedule page.
Natural Choice Transportation Service for multiple accounts/meters on TECO-Peoples Natural Gas (supplier must adjust for new or closing accounts).
Address
City State
Zip
TECO Peoples Gas
58,640 31,120 27,520
Location
15,640 10,650 4,990 Jun Jul Aug Sep Oct Nov Dec
2,130 2,110 2,030 2,260 2,120 2,410 2,580
29,320 15,560 13,760 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
3,160 3,130 2,480 2,710 2,200 2,130 2,110 2,030 2,260 2,120 2,410 2,580
13,680 4,910 8,770 Jan Feb Mar Apr May
3,160 3,130 2,480 2,710 2,200
Curtailment Days Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
0 0 0 0 0 0 0 0 0 0 0 0
Overage & Shortage Volume Pricing Publication Location Methodology Include Adj. Factor
Overage Treatment Summer Volumes
Winter Volumes Shortage Treatment
Summer Volumes Winter Volumes
Note #1 Note #2
Note #3
Note #4
Schedule Page By Line Item Detail MacDill AFB
Installation Address MacDill AFB DODAAC /
FEDAAC:2606 Pelican Ave
MacDill AFB
FL
33621-5000
Delivery Point Telemetered Rate Class City Gate No NCTS
Utility Account Information LDC or Pipeline
Total Contract Total Summer (Dths) Total Winter (Dths)
Yes #4 Oil 35% Yes Emergency Back-up Alternate Fuel Type Percent Load Limits on Use Notes
Year 2026 Annual Totals Summer Totals Winter Totals
Year 2027 Annual Totals Summer Totals Winter Totals
Estimated Usage Information (All volumes expressed in Dths)
Meter
Year 2025 Annual Totals Summer Totals Winter Totals
06/01/25 05/31/27 INSIDE FERC'S FL Gas Zn3 (2) Full Requirements/Pool. Firm
Solicitation Parameters
Period Beginning Period Ending Publication SIP Delivery Option Delivery Type
Multiple meters will require a single consolidated invoice with a separate breakdown of monthly meter quantities and contractor charges.
Period of performance will start/finish in alignment with TECO Peoples Gas meter reading cycle following the period beginning and period ending cited on this schedule page.
Natural Choice Transportation Service for multiple accounts/meters on TECO-Peoples Natural Gas (supplier must adjust for new or closing accounts).
Address
City State
Zip
TECO Peoples Gas
36,780 15,300 21,480
Location
7,060 4,040 3,020 Jun Jul Aug Sep Oct Nov Dec
1,130 800 780 600 730 1,090 1,930
18,390 7,650 10,740 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2,440 2,880 2,400 2,050 1,560 1,130 800 780 600 730 1,090 1,930
11,330 3,610 7,720 Jan Feb Mar Apr May
2,440 2,880 2,400 2,050 1,560
Curtailment Days Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
0 0 0 0 0 0 0 0 0 0 0 0
Overage & Shortage Volume Pricing Publication Location Methodology Include Adj. Factor
Overage Treatment Summer Volumes
Winter Volumes Shortage Treatment
Summer Volumes Winter Volumes
Note #1 Note #2 Note #3
Note #4
Schedule Page By Line Item Detail
NSA Panama City (Main Lab) Installation Address
0007-01 NSA Panama City (Main Lab) DODAAC /
FEDAAC:101 Vernon Ave
Panama City Beach
FL
32407-0000
Delivery Point Telemetered Rate Class City Gate No NCTS
Utility Account Information LDC or Pipeline
Total Contract Total Summer (Dths) Total Winter (Dths)
No None 0% Alternate Fuel Type Percent Load Limits on Use Notes
Year 2026 Annual Totals Summer Totals Winter Totals
Year 2027 Annual Totals Summer Totals Winter Totals
Estimated Usage Information (All volumes expressed in Dths)
Meter
Year 2025 Annual Totals Summer Totals Winter Totals
06/01/25 05/31/27 INSIDE FERC'S FL Gas Zn3 (2) Full Requirements/Pool. Firm
Solicitation Parameters Period Beginning Period Ending Publication SIP Delivery Option Delivery Type
Natural Choice Transportation Service for multiple accounts/meters on TECO-Peoples Natural Gas (supplier must adjust for new or closing accounts).
Multiple meters will require a single consolidated invoice with a separate breakdown of monthly meter quantities and contractor charges.
Period of performance will start/finish in alignment with TECO Peoples Gas meter reading cycle following the period beginning and period ending cited on this schedule page.
A hard copy of the invoice must be mailed to the invoice certification office.
Address
City State
Zip
TECO Peoples Gas
12,100 3,480 8,620
Location
1,820 550 1,270 Jun Jul Aug Sep Oct Nov Dec 190 60 60 90 150 460 810
6,050 1,740 4,310 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 940 1,240 860 650 540 190 60 60 90 150 460 810
4,230 1,190 3,040 Jan Feb Mar Apr May 940 1,240 860 650 540
Curtailment Days Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
0 0 0 0 0 0 0 0 0 0 0 0
Overage & Shortage Volume Pricing Publication Location Methodology Include Adj. Factor
Overage Treatment Summer Volumes
Winter Volumes Shortage Treatment
Summer Volumes Winter Volumes
Note #1 Note #2 Note #3
Note #4
Schedule Page By Line Item Detail
NSA Panama City (Dive School) Installation Address
0007-02 NSA Panama City (Dive School) DODAAC /
FEDAAC:101 Vernon Ave
Panama City Beach
FL
32407-0000
Delivery Point Telemetered Rate Class City Gate No NCTS
Utility Account Information LDC or Pipeline
Total Contract Total Summer (Dths) Total Winter (Dths)
No None 0% Alternate Fuel Type Percent Load Limits on Use Notes
Year 2026 Annual Totals Summer Totals Winter Totals
Year 2027 Annual Totals Summer Totals Winter Totals
Estimated Usage Information (All volumes expressed in Dths)
Meter
Year 2025 Annual Totals Summer Totals Winter Totals
06/01/25 05/31/27 INSIDE FERC'S FL Gas Zn3 (2) Full Requirements/Pool. Firm
Solicitation Parameters Period Beginning Period Ending Publication SIP Delivery Option Delivery Type
Natural Choice Transportation Service for multiple accounts/meters on TECO-Peoples Natural Gas (supplier must adjust for new or closing accounts).
Multiple meters will require a single consolidated invoice with a separate breakdown of monthly meter quantities and contractor charges.
Period of performance will start/finish in alignment with TECO Peoples Gas meter reading cycle following the period beginning and period ending cited on this schedule page.
A hard copy of the invoice must be mailed to the invoice certification office.
Address
City State
Zip
Florida City Gas
20,440 11,360 9,080
Location
5,840 4,020 1,820 Jun Jul Aug Sep Oct Nov Dec 820 810 740 770 880 680 1,140
10,220 5,680 4,540 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
1,130 780 810 820 840 820 810 740 770 880 680 1,140
4,380 1,660 2,720 Jan Feb Mar Apr May
1,130 780 810 820 840
Curtailment Days Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
0 0 0 0 0 0 0 0 0 0 0 0
Overage & Shortage Volume Pricing Publication Location Methodology Include Adj. Factor
Overage Treatment Summer Volumes
Winter Volumes Shortage Treatment
Summer Volumes Winter Volumes
Note #1 Note #2 Note #3 Note #4
Schedule Page By Line Item Detail
Federal Bureau of Prisons, Miami Installation Address
Federal Bureau of Prisons, Miami DODAAC /
FEDAAC: VAMC5215801 SW 137th Ave
Miami
FL
33177-1297
Delivery Point Telemetered Rate Class City Gate Yes GS-25K
Utility Account Information LDC or Pipeline
Total Contract Total Summer (Dths) Total Winter (Dths)
No None 0% Alternate Fuel Type Percent Load Limits on Use Notes
Year 2026 Annual Totals Summer Totals Winter Totals
Year 2027 Annual Totals Summer Totals Winter Totals
Estimated Usage Information (All volumes expressed in Dths)
Meter
Year 2025 Annual Totals Summer Totals Winter Totals
06/01/25 05/31/27 INSIDE FERC'S FL Gas Zn3 (2) Full Requirements/Pool. Firm
Solicitation Parameters Period Beginning Period Ending Publication SIP Delivery Option Delivery Type
Installation Fort Moore
Address
City State
Zip
Liberty Gas
1,066,000 392,000 674,000
Location
241,000 129,000 112,000 Jun Jul Aug Sep Oct Nov Dec
23,000 23,000 23,000 25,000 35,000 50,000 62,000
533,000 196,000 337,000 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
93,000 75,000 57,000 37,000 30,000 23,000 23,000 23,000 25,000 35,000 50,000 62,000
292,000 67,000 225,000 Jan Feb Mar Apr May
93,000 75,000 57,000 37,000 30,000
Curtailment Days Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
0 0 0 0 0 0 0 0 0 0 0 0
Overage & Shortage Volume Pricing Publication Location Methodology Include Adj. Factor
Overage Treatment Summer Volumes
Winter Volumes Shortage Treatment
Summer Volumes Winter Volumes
Note #1 Note #2 Note #3 Note #4
Schedule Page By Line Item Detail
Fort Moore Installation Address
DODAAC/FE
DAAC:6650 Meloy Drive Attn: IMBE-PWB (Royer) Fort Moore
GA
31905-4500
Delivery Point Telemetered Rate Class City Gate Yes
Utility Account Information LDC or Pipeline
Total Contract Total Summer (Dths) Total Winter (Dths)
Yes Propane 95% Yes N/A Alternate Fuel Type Percent Load Limits on Use Notes
Year 2025 Annual Totals Summer Totals Winter Totals
Year 2027 Annual Totals Summer Totals Winter Totals
Estimated Usage Information (All volumes expressed in Dths)
City Gate
Year 2025 Annual Totals Summer Totals Winter Totals
06/01/25 05/31/27 INSIDE FERC'S SoNat LA (2) Full Requirements/Pool. Firm
Installation DODAAC/FEDAAC:
Address
City State
Zip
Centerpoint Entex
152,320 73,840 78,480
Location
39,630 25,020 14,610 Jun Jul Aug Sep Oct Nov Dec
4,920 4,730 4,800 4,910 5,660 7,020 7,590
76,160 36,920 39,240 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
8,810 8,130 7,690 6,440 5,460 4,920 4,730 4,800 4,910 5,660 7,020 7,590
36,530 11,900 24,630 Jan Feb Mar Apr May
8,810 8,130 7,690 6,440 5,460
Curtailment Days Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
0 0 0 0 0 0 0 0 0 0 0 0
Overage & Shortage Volume Pricing Publication Location Methodology Include Adj. Factor
Overage Treatment Summer Volumes
Winter Volumes Shortage Treatment
Summer Volumes Winter Volumes
Note #1
Note #2 Note #3 Note #4
Schedule Page By Line Item Detail
VAMC Shreveport Installation Address
VAMC Shreveport 510 East Stoner Ave
Shreveport
LA
71101-0000
Delivery Point Telemetered Rate Class City Gate No LCT-1
Utility Account Information LDC or Pipeline
Total Contract Total Summer (Dths) Total Winter (Dths)
No None Alternate Fuel Type Percent Load Displaceable Limits on Use Notes
Year 2026 Annual Totals Summer Totals Winter Totals
Year 2027 Annual Totals Summer Totals Winter Totals
Estimated Usage Information (All volumes expressed in Dths)
Meter
Year 2025 Annual Totals Summer Totals Winter Totals
06/01/25 05/31/27 INSIDE FERC'S Enable Gas, East (2) Full Requirements/Pool. Firm
Solicitation Parameters Period Beginning Period Ending Publication SIP Delivery Option Delivery Type
Contractor Consolidated Billing is required for VAMC Shreveport in accordance with the statement of work.
CenterPoint Energy Entex holds the upstream capacity on CEGT for the customer. The contractor is required to use the capacity for deliveries to VAMC Shreveport. The customer is billed directly from CenterPoint for the pipeline capacity.
Address
City State
Zip
Gulf South Pipeline
450,280 148,020 302,260
Location
99,633 46,774 52,859 Jun Jul Aug Sep Oct Nov Dec
10,507 8,539 7,656 8,304 11,768 22,837 30,022
225,140 74,010 151,130 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
39,560 34,868 23,843 15,610 11,626 10,507 8,539 7,656 8,304 11,768 22,837 30,022
125,507 27,236 98,271 Jan Feb Mar Apr May
39,560 34,868 23,843 15,610 11,626
Curtailment Days Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
0 0 0 0 0 0 0 0 0 0 0 0
Overage & Shortage Volume Pricing Publication Location Methodology Include Adj. Factor
Overage Treatment Summer Volumes Yes
Winter Volumes Yes Shortage Treatment
Summer Volumes Yes Winter Volumes Yes
Note #1
Note #2
Note #3
Note #4
Schedule Page By Line Item Detail Fort Johnson
Installation Address Fort Johnson DODAAC/FE
DAAC:DPW, BOID (Business Operations Div), 6661 Warrior Trail Bldg 350 Suite 230 Fort Johnson
LA
71459-5440
Delivery Point Telemetered Rate Class Burner Tip Yes
Utility Account Information LDC or Pipeline
Total Contract Total Summer (Dths) Total Winter (Dths)
No None Alternate Fuel Type Percent Load Displaceable Limits on Use Notes
Year 2026 Annual Totals Summer Totals Winter Totals
Year 2027 Annual Totals Summer Totals Winter Totals
Estimated Usage Information (All volumes expressed in Dths)
Burner Tip
Year 2025 Annual Totals Summer Totals Winter Totals
06/01/25 05/31/27 INSIDE FERC'S Henry Hub (3) Monthly Order Quantities. Firm
Solicitation Parameters Period Beginning Period Ending Publication SIP Delivery Option Delivery Type
GAS DAILY PRICE GUIDE Henry Hub Simple Average 1-EOM GAS DAILY PRICE GUIDE Henry Hub Simple Average 1-EOM
GAS DAILY PRICE GUIDE Henry Hub Simple Average 1-EOM GAS DAILY PRICE GUIDE Henry Hub Simple Average 1-EOM
The contractor shall be required to perform contractor consolidated billing in accordance with the statement of work. Gulf South Pipeline Company, LP, will forward each installation's transportation invoice to the contractor. In return, the contractor will include these transportation costs and its supply costs on the customer invoice. Therefore, Fort Johnson will receive one invoice from the contractor, which will include both supply costs and Gulf South Pipeline., LP, transportation costs.
The customer has 6,000 DTHs of capacity in its storage account. The storage account will be managed by the contractor to keep customer's supply balanced and provide additional gas in emergency situations or as needed and directed by the installation. Monthly invoices will have seperate line items documenting the starting balance, amount of gas that is either injected or withdrawn, and the ending balance for the storage account. The invoice will also include a seperate line item to reflect the quantity and the additional price and/or credit for any gas that is either injected or withdrawn from the storage account.
A. The customer owns excess capacity on the pipeline. The customer owns a total of 4,200 DTHs/day of FTS on the pipeline. Any excess capacity utilized by the contractor will be rebated to the customer at a rate of 50% of the nominal rate charged to the installation by Gulf South Pipeline for this capacity. The contractor's monthly invoice will include a seperate line item to reflect any credits due for the utilization of excess capacity.
B. The excess capacity will be handled in accordance with the statement of work, paragraph (L), the contractor shall manage the excess capacity.
A. Fort Johnson's total MDQ for Firm (Contract#16106) is 4,200 Dths and its MDQ for No-Notice (Contract #14583) is 800 Dths. Receipt points for Firm and No-Notice for Fort Johnson are SLN#0004708 and SLN#0003260 and delivery points are SLN#0002989 and SLN#002990. The term MDQ is not intended to communicate a maximim monthly order quantity. See clause C700 and 52.216-21.
B. The contractor shall deliver natural gas supplies FOB Burnertip. The contractor's obligation is to deliver gas supplies via Government's owned capacity on the pipeline.
Address
City State
Zip
Centerpoint Entex
369,660 116,550 253,110
Location
80,614 36,435 44,179 Jun Jul Aug Sep Oct Nov Dec
7,120 6,465 6,299 6,614 9,937 18,266 25,913
184,830 58,275 126,555 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
33,097 30,099 19,180 12,652 9,188 7,120 6,465 6,299 6,614 9,937 18,266 25,913
104,216 21,840 82,376 Jan Feb Mar Apr May
33,097 30,099 19,180 12,652 9,188
Curtailment Days Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
0 0 0 0 0 0 0 0 0 0 0 0
Overage & Shortage Volume Pricing Publication Location Methodology Include Adj. Factor
Overage Treatment Summer Volumes
Winter Volumes Shortage Treatment
Summer Volumes Winter Volumes
Note #1
Note #2
334 Davis Ave West, Ste 308 Barksdale
LA
71110-2078
Schedule Page By Line Item Detail
Barksdale AFB Installation Address
Barksdale AFB DODAAC/FE
DAAC:2d Civil Engineer Sqd
Utility Account Information LDC or Pipeline
Total Contract Est. Total Summer (Dths) Total Winter (Dths)
Alternate Fuel Type Percent Load Displaceable Limits on Use Notes
Delivery Point Telemetered Rate Class City Gate Yes LCS-1
Estimated Usage Information (All volumes expressed in Dths)
Meter
Year 2025 Annual Totals Summer Totals Winter Totals
No
Firm
Solicitation Parameters Period Beginning Period Ending Publication SIP Delivery Option Delivery Type
Year 2026 Annual Totals Summer Totals Winter Totals
Year 2027 Annual Totals Summer Totals Winter Totals
06/01/25 05/31/27 INSIDE FERC'S Enable Gas, East (2) Full Requirements/Pool.
Payment office is DFAS, but do not contact them before contacting the local payment office, Ms Ty'Kesha Williams-Saunders, (318) 456-2158. DFAS address is DFAS DEAMS - F87700 - PAYMENT, ACCTG DISB STATION 387700, 27 ARKANSAS RD, LIMESTONE, ME 04751-6216
Contractor consolidated billing is required in acordance with the statement of work.
Address
City State
Zip
Centerpoint Entex
485,700 239,200 246,500
Location
132,440 83,160 49,280 Jun Jul Aug Sep Oct Nov Dec
16,340 16,140 15,170 15,410 20,100 21,480 27,800
242,850 119,600 123,250 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
28,230 23,790 21,950 19,400 17,040 16,340 16,140 15,170 15,410 20,100 21,480 27,800
110,410 36,440 73,970 Jan Feb Mar Apr May
28,230 23,790 21,950 19,400 17,040
Curtailment Days Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
0 0 0 0 0 0 0 0 0 0 0 0
Overage & Shortage Volume Pricing Publication Location Methodology Include Adj. Factor
Overage Treatment Summer Volumes
Winter Volumes Shortage Treatment
Summer Volumes Winter Volumes
Note #1 Note #2 Note #3 Note #4
500 Fisher Street, Suite 244 Keesler Air Force Base
MS
39534-0000
Schedule Page By Line Item Detail
Keesler Air Force Base Installation Address
Keesler Air Force Base DODAAC/FE
DAAC:81st Civil Engineering Squadron
Delivery Point Telemetered Rate Class City Gate Yes MT-3
Utility Account Information LDC or Pipeline
Total Contract Total Summer (Dths) Total Winter (Dths)
No None Alternate Fuel Type Percent Load Limits on Use Notes
Year 2026 Annual Totals Summer Totals Winter Totals
Year 2027 Annual Totals Summer Totals Winter Totals
Estimated Usage Information (All volumes expressed in Dths)
Meter
Year 2025 Annual Totals Summer Totals Winter Totals
06/01/25 05/31/27 INSIDE FERC'S Henry Hub (2) Full Requirements/Pool. Firm
Solicitation Parameters Period Beginning Period Ending Publication SIP Delivery Option Delivery Type
Load data includes service to Base, Medical Center, Multi-family Housing via master meter.
Contractor Consolidated Billing is required for Keesler AFB in accordance with the Statement of Work.
Address
City State
Zip
Centerpoint Entex
173,600 92,100 81,500
Location
47,850 32,200 15,650 Jun Jul Aug Sep Oct Nov Dec
6,510 6,200 6,490 6,210 6,790 7,080 8,570
86,800 46,050 40,750 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
9,180 8,070 7,850 7,090 6,760 6,510 6,200 6,490 6,210 6,790 7,080 8,570
38,950 13,850 25,100 Jan Feb Mar Apr May
9,180 8,070 7,850 7,090 6,760
Curtailment Days Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
0 0 0 0 0 0 0 0 0 0 0 0
Overage & Shortage Volume Pricing Publication Location Methodology Include Adj. Factor
Overage Treatment Summer Volumes
Winter Volumes Shortage Treatment
Summer Volumes Winter Volumes
Note #1 Note #2 Note #3 Note #4
Schedule Page By Line Item Detail
VAMC Biloxi
Installation Address VAMC Biloxi DODAAC/FE
DAAC:400 Veterans Avenue
Biloxi
MS
39531-0000
Delivery Point Telemetered Rate Class City Gate Yes 49
Utility Account Information LDC or Pipeline
Total Contract Total Summer (Dths) Total Winter (Dths)
No Alternate Fuel Type Percent Load Displaceable Limits on Use Notes
Year 2026 Annual Totals Summer Totals Winter Totals
Year 2027 Annual Totals Summer Totals Winter Totals
Estimated Usage Information (All volumes expressed in Dths)
Meter
Year 2025 Annual Totals Summer Totals Winter Totals
06/01/25 05/31/27 INSIDE FERC'S Henry Hub (2) Full Requirements/Pool. Firm
Address
City State
Zip
Gulf South Pipeline
283,000 130,000 153,000
Location
73,000 41,500 31,500 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
9,000 9,000 7,500 8,500 7,500 15,500 16,000
141,500 65,000 76,500 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
17,000 15,500 12,500 12,500 11,000 9,000 9,000 7,500 8,500 7,500 15,500 16,000
68,500 23,500 45,000 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
17,000 15,500 12,500 12,500 11,000
Curtailment Days Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
0 0 0 0 0 0 0 0 0 0 0 0
Overage & Shortage Volume Pricing Publication Location Methodology Include Adj. Factor
Overage Treatment Summer Volumes
Winter Volumes Shortage Treatment
Summer Volumes Winter Volumes
Note #1 Note #2 Note #3 Note #4
Stennis Space Center
MS
39529
Schedule Page By Line Item Detail
Stennis Space Center Installation Address
Stennis Space Center DODAAC /
FEDAAC:1100 Balch Blvd
Utility Account Information LDC or Pipeline
Total Contract Total Summer (Dths) Total Winter (Dths)
Alternate Fuel Type Percent Load Limits on Use Notes
Delivery Point Telemetered Rate Class Burner Tip No FTS
Estimated Usage Information (All volumes expressed in Dths)
Meter
Year 2025 Annual Totals Summer Totals Winter Totals
No 0% No
Firm
Solicitation Parameters Period Beginning Period Ending Publication SIP Delivery Option Delivery Type
Year 2026 Annual Totals Summer Totals Winter Totals
Year 2027 Annual Totals Summer Totals Winter Totals
06/01/25 05/31/27 INSIDE FERC'S Henry Hub (2) Full Requirements/Pool.
Delivery Point is North Fee Area Boundary of Stennis Space Center (Gulf South Station Location Number 2568).
Contractor Consolidated Billing (Gulf South Pipeline charges) is required for Stennis Space Center in accordance with the Statement of Work.
All Voucher/Invoice submissions are to be sumbitted through the Invoice Processing Platform (ipp.gov) as per NASA FAR Supplement (NFS) 1852.232.80.
DLA Energy requires an emailed copy of supplier invoices and Gulf South Pipeline invoices.
Address
City State
Zip
Dominion Energy
317,094 139,304 177,790
Location
82,161 46,403 35,758 Jun Jul Aug Sep Oct Nov Dec
8,950 8,911 8,619 8,177 11,746 16,389 19,369
158,547 69,652 88,895 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
20,276 17,132 15,729 12,580 10,669 8,950 8,911 8,619 8,177 11,746 16,389 19,369
76,386 23,249 53,137 Jan Feb Mar Apr May
20,276 17,132 15,729 12,580 10,669
Curtailment Days Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
0 0 0 0 0 0 0 0 0 0 0 0
Overage & Shortage Volume Pricing Publication Location Methodology Include Adj. Factor
Overage Treatment Summer Volumes
Winter Volumes Shortage Treatment
Summer Volumes Winter Volumes
Note #1
P.O. Box 999 Butner
NC
27509-0000
Schedule Page By Line Item Detail
Federal Corrections Complex Butner Installation Address
Federal Corrections Complex Butner DODAAC/FE
DAAC:Old NC Hwy 75
Utility Account Information LDC or Pipeline
Total Contract Total Summer (Dths) Total Winter (Dths)
Alternate Fuel Type Percent Load Limits on Use Notes
Delivery Point Telemetered Rate Class City Gate Yes 175
Estimated Usage Information (All volumes expressed in Dths)
City Gate
Year 2025 Annual Totals Summer Totals Winter Totals
Yes #2 Oil 0% Yes Emergency Operations Only
Firm
Solicitation Parameters Period Beginning Period Ending Publication SIP Delivery Option Delivery Type
Year 2026 Annual Totals Summer Totals Winter Totals
Year 2027 Annual Totals Summer Totals Winter Totals
06/01/25 05/31/27 INSIDE FERC'S Transco Zn5 Del South (2) Full Requirements/Pool.
Five meters currently serve the Corrections Complex.
Address
City State
Zip
Piedmont Natural Gas
2,616,000 976,000 1,640,000
Location
625,000 315,000 310,000 Jun Jul Aug Sep Oct Nov Dec
62,000 56,000 56,000 58,000 83,000 135,000 175,000
1,308,000 488,000 820,000 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
205,000 155,000 150,000 98,000 75,000 62,000 56,000 56,000 58,000 83,000 135,000 175,000
683,000 173,000 510,000 Jan Feb Mar Apr May
205,000 155,000 150,000 98,000 75,000
Curtailment Days Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
0 0 0 0 0 0 0 0 0 0 0 0
Overage & Shortage Volume Pricing Publication Location Methodology Include Adj. Factor
Overage Treatment Summer Volumes Yes
Winter Volumes Yes Shortage Treatment
Summer Volumes Yes Winter Volumes Yes
Note #1 Note #2 Note #3 Note #4
Schedule Page By Line Item Detail
Fort Liberty Installation Address
Fort Liberty DODAAC/FE
DAAC:Directorate of Public Works (MSE-BRG-PWO)
Fort Liberty
NC
28310-5000
Delivery Point Telemetered Rate Class City Gate Yes LGST-113
Utility Account Information LDC or Pipeline
Total Contract Total Summer (Dths) Total Winter (Dths)
No Alternate Fuel Type Percent Load Limits on Use Notes
Year 2026 Annual Totals Summer Totals Winter Totals
Year 2027 Annual Totals Summer Totals Winter Totals
Estimated Usage Information (All volumes expressed in Dths)
Meter
Year 2025 Annual Totals Summer Totals Winter Totals
06/01/25 05/31/27 INSIDE FERC'S Transco Zn5 Del. South (3) Monthly Order Quantities. Firm
Solicitation Parameters Period Beginning Period Ending Publication SIP Delivery Option Delivery Type
GAS DAILY PRICE GUIDE Transco Zn5 Del. South Simple Average 1-EOM GAS DAILY PRICE GUIDE Transco Zn5 Del. South Simple Average 1-EOM
GAS DAILY PRICE GUIDE Transco Zn5 Del. South Simple Average 1-EOM GAS DAILY PRICE GUIDE Transco Zn5 Del. South Simple Average 1-EOM
Address
City State
Zip
Piedmont Natural Gas
1,577,000 693,000 884,000
Location
396,500 230,000 166,500 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
45,000 45,000 45,000 45,000 50,000 70,000 96,500
788,500 346,500 442,000 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
100,000 90,500 85,000 63,000 53,500 45,000 45,000 45,000 45,000 50,000 70,000 96,500
392,000 116,500 275,500 Jan Feb Mar Apr May
100,000 90,500 85,000 63,000 53,500
Curtailment Days Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
0 0 0 0 0 0 0 0 0 0 0 0
Overage & Shortage Volume Pricing Publication Location Methodology Include Adj. Factor
Overage Treatment Summer Volumes
Winter Volumes Shortage Treatment
Summer Volumes Winter Volumes
Note #1 Note #2 Note #3 Note #4
Schedule Page By Line Item Detail
Marine Corps Air Station-Cherry Point
Installation Address Marine Corps Air Station-Cherry Point DODAAC/FED
AAC: 30000PSC Box 8005
Cherry Point
NC
28533
Delivery Point Telemetered Rate Class City Gate Yes
Utility Account Information LDC or Pipeline
Total Contract Total Summer (Dths) Total Winter (Dths)
Yes #2 Oil 100% Yes Emergency Only Alternate Fuel Type Percent Load Displaceable Limits on Use Notes
Year 2026 Annual Totals Summer Totals Winter Totals
Year 2027 Annual Totals Summer Totals Winter Totals
Estimated Usage Information (All volumes expressed in Dths)
Meter
Year 2025 Annual Totals Summer Totals Winter Totals
06/01/25 05/31/27 INSIDE FERC'S Transco Zn5 Del. South (2) Full Requirements/Pool. Firm
Address
City State
Zip
Summit Utilities
323,350 59,792 263,558
Location
68,737 15,439 53,298 Jun Jul Aug Sep Oct Nov Dec
1,749 1,255 1,225 1,483 9,727 23,424 29,874
162,221 30,442 131,779 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
29,214 26,946 22,321 9,644 4,267 1,919 1,697 1,475 1,713 9,727 23,424 29,874
92,392 13,911 78,481 Jan Feb Mar Apr May
29,214 26,946 22,321 9,644 4,267
Curtailment Days Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
0 0 0 0 0 0 0 0 0 0 0 0
Overage & Shortage Volume Pricing Publication Location Methodology Include Adj. Factor
Overage Treatment Summer Volumes Yes
Winter Volumes Yes Shortage Treatment
Summer Volumes Yes Winter Volumes Yes
Note #1
Schedule Page By Line Item Detail
Altus Air Force Base Installation Address
Altus Air Force Base DODAAC/FE
DAAC:209 E Sir Dr
Altus
OK
75323
Delivery Point Telemetered Rate Class City Gate Yes LCS-1
Utility Account Information LDC or Pipeline
Total Contract Total Summer (Dths) Total Winter (Dths)
No Alternate Fuel Type Percent Load Limits on Use Notes
Year 2026 Annual Totals Summer Totals Winter Totals
Year 2027 Annual Totals Summer Totals Winter Totals
Estimated Usage Information (All volumes expressed in Dths)
City Gate
Year 2025 Annual Totals Summer Totals Winter Totals
06/01/25 05/31/27 INSIDE FERC'S Enable Gas East (3) Monthly Order Quantities. Firm
Solicitation Parameters Period Beginning Period Ending Publication SIP Delivery Option Delivery Type
GAS DAILY PRICE GUIDE Enable Gas East Simple Average 1-EOM GAS DAILY PRICE GUIDE Enable Gas East Simple Average 1-EOM
GAS DAILY PRICE GUIDE Enable Gas East Simple Average 1-EOM GAS DAILY PRICE GUIDE Enable Gas East Simple Average 1-EOM
There are two meters that will be served under LCS-1 on the contract. The 1866 W River Dr meter location will remain on utility service at a projected load of 500 dth per year.
Address
City State
Zip
Summit Utilities
1,053,000 288,000 765,000
Location
217,000 87,000 130,000 Jun Jul Aug Sep Oct Nov Dec
16,000 12,000 14,000 15,000 30,000 50,000 80,000
524,000 144,000 380,000 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
95,000 95,000 60,000 35,000 22,000 16,000 12,000 14,000 15,000 30,000 50,000 80,000
312,000 57,000 255,000 Jan Feb Mar Apr May
100,000 95,000 60,000 35,000 22,000
Curtailment Days Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
0 0 0 0 0 0 0 0 0 0 0 0
Overage & Shortage Volume Pricing Publication Location Methodology Include Adj. Factor
Overage Treatment Summer Volumes Yes
Winter Volumes Yes Shortage Treatment
Summer Volumes Yes Winter Volumes Yes
Note #1
Note #2
Note #3 Note #4
Building 1950 Fort Sill
OK
73503-5100
Schedule Page By Line Item Detail
Fort Sill Installation Address
Fort Sill DODAAC/FE
DAAC: W44DQ1Director Public Works, 1950 Barbour Rd.
Delivery Point Telemetered Rate Class City Gate Yes LCS-1
Utility Account Information LDC or Pipeline
Total Contract Total Summer (Dths) Total Winter (Dths)
No Alternate Fuel Type Percent Load Limits on Use Notes
Year 2026 Annual Totals Summer Totals Winter Totals
Year 2027 Annual Totals Summer Totals Winter Totals
Estimated Usage Information (All volumes expressed in Dths)
City Gate
Year 2025 Annual Totals Summer Totals Winter Totals
06/01/25 05/31/27 INSIDE FERC'S Enable Gas, East (3) Monthly Order Quantities. Firm
Solicitation Parameters Period Beginning Period Ending Publication SIP Delivery Option Delivery Type
GAS DAILY PRICE GUIDE Enable Gas, East Simple Average 1-EOM GAS DAILY PRICE GUIDE Enable Gas, East Simple Average 1-EOM
GAS DAILY PRICE GUIDE Enable Gas, East Simple Average 1-EOM GAS DAILY PRICE GUIDE Enable Gas, East Simple Average 1-EOM
CenterPoint Energy Gas Transmission (CEGT) Pipeline requires the contractor to add additional gas for fuel loss for the gas to be delivered to West Pooling Area 2. The cost for this gas will be included in the adjustment factor.
The Government has a rate rider 1 transport agreement with the LDC which includes a pipeline capacity of 7021 Dths per day with CEGT.
CenterPoint Energy Arkla holds the upstream capacity on CEGT for the customer. The contractor is required to use the capacity for deilveries to Fort Sill. The customer is billed directly by CenterPoint for the pipeline capacity.
Address
City State
Zip
Summit Utilities
760,240 275,200 485,040
Location
171,320 84,320 87,000 Jun Jul Aug Sep Oct Nov Dec
16,920 16,050 15,770 16,150 19,430 38,220 48,780
380,120 137,600 242,520 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
58,220 52,420 44,880 30,950 22,330 16,920 16,050 15,770 16,150 19,430 38,220 48,780
208,800 53,280 155,520 Jan Feb Mar Apr May
58,220 52,420 44,880 30,950 22,330
Curtailment Days Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
0 0 0 0 0 0 0 0 0 0 0 0
Overage & Shortage Volume Pricing Publication Location Methodology Include Adj. Factor
Overage Treatment Summer Volumes Yes
Winter Volumes Yes Shortage Treatment
Summer Volumes Yes Winter Volumes Yes
Note #1
Note #2
Note #3 Note #4
Bldg 6 McAlester
OK
74501-9002
Schedule Page By Line Item Detail McAlester AAP
Installation Address McAlester AAP DODAAC/FE
DAAC:1 C-Tree RD
Utility Account Information LDC or Pipeline
Total Contract Est. Volume (Dths) Total Summer (Dths) Total Winter (Dths)
Delivery Point Telemetered Rate Class
Yes #2 Oil 20% Yes For emergency use only
City Gate Yes LCS-1
Alternate Fuel Type Percent Load Limits on Use Notes
Year 2026 Annual Totals Summer Totals Winter Totals
Year 2027 Annual Totals Summer Totals Winter Totals
Estimated Usage Information (All volumes expressed in Dths)
Burner Tip
Year 2025 Annual Totals Summer Totals Winter Totals
06/01/25 05/31/27 INSIDE FERC'S Enable Gas, East (3) Monthly Order Quantities. Firm
Solicitation Parameters Period Beginning Period Ending Publication SIP Delivery Option Delivery Type
GAS DAILY PRICE GUIDE Enable Gas, East Simple Average 1-EOM GAS DAILY PRICE GUIDE Enable Gas, East Simple Average 1-EOM
GAS DAILY PRICE GUIDE Enable Gas, East Simple Average 1-EOM GAS DAILY PRICE GUIDE Enable Gas, East Simple Average 1-EOM
The contractor shall be required to perform contractor consolidated billing in accordance with the statement of work. Summit Utilities, Inc. and Enable Gas Transmission LLC will forward each installation's transportation invoice to the contractor. In return, the contractor will include these transportation costs and its supply costs on the customer invoice. Therefore, McAlester will receive one invoice from the contractor, which will include both supply costs and Summit Utilities, Inc. and Enable Gas Transmission LLC, transportation costs.
Contractor to submit invoices via the electronic payment system specified by the installation; Wide Area Workflow (WAWF) or its successor.
McAlester has pipeline capacity with Enable Gas Transmission LLC- November-March(2,225 dths/day); April (1,125 dths/day); May-October (1,000 dths/day)
Address
City State
Zip
Oklahoma Natural Gas
213,180 94,560 118,620
Location
54,450 31,410 23,040 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
5,930 5,540 5,550 5,840 8,550 10,610 12,430
106,590 47,280 59,310 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
13,780 12,190 10,300 8,500 7,370 5,930 5,540 5,550 5,840 8,550 10,610 12,430
52,140 15,870 36,270 Jan Feb Mar Apr May
13,780 12,190 10,300 8,500 7,370
Curtailment Days Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
0 0 0 0 0 0 0 0 0 0 0 0
Overage & Shortage Volume Pricing
Publication Location Methodology Include Adj. Factor Overage Treatment
Summer Volumes Yes Winter Volumes Yes
Shortage Treatment Summer Volumes Yes
Winter Volumes Yes
Note #1 Note #2 Note #3 Note #4
Schedule Page By Line Item Detail
VAMC Oklahoma City Installation Address
VAMC Oklahoma City DODAAC/FE
DAAC:921 NE 13th Street
Oklahoma City
OK
73104-0000
Utility Account Information
LDC or Pipeline
Total Contract Est. Volume (Dths) Total Summer (Dths) Total Winter (Dths)
Delivery Point Telemetered Rate Class City Gate Yes 391-T
Alternate Fuel Type Percent Load Limits on Use Notes
Estimated Usage Information (All volumes expressed in Dths)
Burner Tip
Year 2025 Annual Totals Summer Totals Winter Totals
No None
Firm
Solicitation Parameters Period Beginning Period Ending SIP Publication SIP Location Delivery Option Delivery Type
Year 2026 Annual Totals Summer Totals Winter Totals
Year 2027 Annual Totals Summer Totals Winter Totals
GAS DAILY PRICE GUIDE Oneok OK Simple Average 1-EOM GAS DAILY PRICE GUIDE Oneok OK Simple Average 1-EOM
06/01/25 05/31/27 INSIDE FERC'S Oneok OK (3) Monthly Order Quantities.
GAS DAILY PRICE GUIDE Oneok OK Simple Average 1-EOM
Address
City State
Zip
Oklahoma Natural Gas
172,200 83,180 89,020
Location
44,540 28,220 16,320 Jun Jul Aug Sep Oct Nov Dec
5,170 5,640 5,390 5,430 6,590 7,630 8,690
86,100 41,590 44,510 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
10,960 9,100 8,130 6,570 6,800 5,170 5,640 5,390 5,430 6,590 7,630 8,690
41,560 13,370 28,190 Jan Feb Mar Apr May
10,960 9,100 8,130 6,570 6,800
Curtailment Days Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
0 0 0 0 0 0 0 0 0 0 0 0
Overage & Shortage Volume Pricing Publication Location Methodology Include Adj. Factor
Overage Treatment Summer Volumes Yes
Winter Volumes Yes Shortage Treatment
Summer Volumes Yes Winter Volumes Yes
Note #1 Note #2 Note #3 Note #4
Schedule Page By Line Item Detail
VAMC Muskogee (Jack C. Montgomery) Installation Address
VAMC Muskogee (Jack C. Montgomery) DODAAC/FED
AAC:1011 Honor Heights Drive
Muskogee
OK
74401-0000
Utility Account Information LDC or Pipeline
Total Contract Est. Volume (Dths) Total Summer (Dths) Total Winter (Dths)
Delivery Point Telemetered Rate Class City Gate Yes 391-T
Alternate Fuel Type Percent Load Limits on Use Notes
Estimated Usage Information (All volumes expressed in Dths)
Burner Tip
Year 2025 Annual Totals Summer Totals Winter Totals
Yes #2 Oil 10% Yes Emergency Back-up Only
Firm
Solicitation Parameters Period Beginning Period Ending SIP Publication SIP Location Delivery Option Delivery Type
Year 2026 Annual Totals Summer Totals Winter Totals
Year 2027 Annual Totals Summer Totals Winter Totals
GAS DAILY PRICE GUIDE Oneok OK Simple Average 1-EOM GAS DAILY PRICE GUIDE Oneok OK Simple Average 1-EOM
06/01/25 05/31/27 INSIDE FERC'S Oneok OK (3) Monthly Order Quantities.
Address
City State
Zip
Dominion Energy South Carolina
1,247,484 637,692 609,792
Location
391,077 273,879 117,198 Apr May Jun Jul Aug Sep Oct Nov Dec
47,907 42,027 35,505 35,114 34,809 35,180 43,337 52,996 64,202
578,775 273,879 304,896 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
65,737 62,836 59,125 47,907 42,027 35,505 35,114 34,809 35,180 43,337 52,996 64,202
277,632 89,934 187,698 Jan Feb Mar Apr May
65,737 62,836 59,125 47,907 42,027
Curtailment Days Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Overage & Shortage Volume Pricing Publication Location Methodology Include Adj. Factor
Overage Treatment Summer Volumes
Winter Volumes Shortage Treatment
Summer Volumes Winter Volumes
Note #1
Note #2
Note #3
Note #4
Note #5
Schedule Page By Line Item Detail Fort Jackson
Installation Address 0024-01 Fort Jackson DODAAC/FE
DAAC: W913712601 Washington Rd.
Fort Jackson
SC
29207-5400
Delivery Point Telemetered Rate Class City Gate Yes 36
Utility Account Information LDC or Pipeline
Total Contract Total Summer (Dths) Total Winter (Dths)
No None 0% Alternate Fuel Type Percent Load Limits on Use Notes
Year 2026 Annual Totals Summer Totals Winter Totals
Year 2027 Annual Totals Summer Totals Winter Totals
Estimated Usage Information (All volumes expressed in Dths)
Meter
Year 2025 Annual Totals Summer Totals Winter Totals
04/01/25 05/31/27 INSIDE FERC'S Transco Zone 5 Del So (3) Monthly Order Quantities. Secondary Firm
Solicitation Parameters Period Beginning Period Ending Publication SIP Delivery Option Delivery Type
GAS DAILY PRICE GUIDE Transco Zone 5 Del So See Note 2 GAS DAILY PRICE GUIDE Transco Zone 5 Del So See Note 2
GAS DAILY PRICE GUIDE Transco Zone 5 Del So See Note 2 GAS DAILY PRICE GUIDE Transco Zone 5 Del So See Note 2
The pricing methodology for calculating the overage/shortage for Delivery Option 3 as stated in C700 par (e)(3) is revised as follows. The 10% allowance does not apply. The overage and shortage methodology will be applied on a daily basis. The monthly order quantity will be divided by the number of days in the month to determine the average daily order quantity.