SPE603-26-R-0533 Amend 0005 Attach A.pdf

PDF 219 KB Posted

Attached to
Government-Owned, Contract-Operated (GOCO) Fuel Storage Services in Patrick SFB, FL
Solicitation number
SPE603-26-R-0533
Issued by

About this file

This is a Questions and Answers (Q&A) document, specifically Amendment 0005 to solicitation SPE603-26-R-0533, addressing clarifications on a federal contract opportunity for fuel services operations at Patrick Space Force Base.

The contract is a Government-Owned, Contractor-Operated (GOCO) requirement with a 48-month base period (CLIN 0001) plus one 5-year option period (CLIN 0002), valued using the formula: (CLIN 0001 monthly × 48) + (CLIN 0002 monthly × 60) + (CLIN 0002 monthly × 6). This is a firm fixed-price contract with a contract start date of November 1, 2026, requiring a 10-working-day joint turnover period. The solicitation is a 100% 8(a) set-aside under the Small Business Administration, with CMMC Level 2 (Self) required for cybersecurity compliance. The government will not furnish contractor vehicles or special equipment; contractors must propose their own staffing approach and Computerized Maintenance Management System (CMMS). Key operational requirements include aviation and ground fuel refueling operations (approximately 3,650 annual refueling events and 1.7 million gallons of jet fuel issued annually), maintenance activities at the operator level, and coordination with government-performed system maintenance. Personnel require NACI-level security clearances, and the incumbent Collective Bargaining Agreement expires April 21, 2027, with FAR 52.222-43 price adjustment procedures applicable thereafter. The government will not provide incumbent staffing matrices, facility condition reports, or detailed equipment specifications; contractors must develop proposals based on PWS requirements, Appendix G military installation information, and UFM 3-460-03 maintenance standards. All-inclusive pricing must account for anticipated inflation and market fluctuations over the 114-month contract term with no economic price adjustment mechanism for non-labor elements.

View the file

Other files

Show all 16

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SPE603-26-R-0533

Amendment 0005

Attachment A

Question Number

Question Answer

1. CLIN 0001 covers a single 48-month base period at one fixed monthly rate. Will FAR 52.222-43 price adjustments be applied annually on the contract anniversary within the base period, or only at exercise of CLIN 0002 in year five? Given the CBA expires 21 April 2027, this materially affects pricing.

The incumbent CBA expires 21 April 2027. Will the successor contractor’s obligation under SCA 4(c) extend to a renegotiated successor agreement, and how will resulting increases be handled under 52.222-43?

For bidding purposes, offerors should base their pricing for CLIN 0001 on the wage and benefit rates stipulated in the current, incorporated CBA. After the current CBA expires, the successful awardee may negotiate a new CBA. Once that new CBA is effective, the contractor must notify the Contracting Officer in accordance with FAR 52.222-43.

The contractor may then submit a request for an equitable adjustment to the contract price to cover the change in labor costs for the remainder of the base period, effective from the date the new CBA is implemented.

2. Is any economic price adjustment mechanism contemplated for non-labor cost elements over the 114-month term? If not, please confirm that offerors should build full escalation into the fixed monthly rates.

As this is a firm fixed price contract, all expenses and proposed pricing should cover all costs to include profit, anticipated inflation and market fluctuations shall be included in the monthly price for the respective base and option period.

3. Please confirm the total evaluated price formula:

(CLIN 0001 monthly × 48) + (CLIN 0002 monthly × 60) + (CLIN 0002 monthly × 6).

Confirming the price formula is correct. Offerors must complete Attachment VII as instructed in the solicitation. The formula contained therein is the definitive method that will be used for price evaluation.

4. Will the government release the incumbent’s currently approved FTE count and staffing matrix by position and shift? Absent this, offerors cannot calibrate staffing to the government’s expectation under an Acceptable/Unacceptable standard.

The Government cannot provide the requested incumbent’s FTE count or staffing matrix by position and shift, as this information is specific to the incumbent contractor’s technical and business solution and is not the Government’s data to release.

PWS, Appendix D, provides the required staffing positions (Key and Service Personnel) for the performance tasks specified in the PWS. This allows each contractor the opportunity to propose their own quantitative staffing business approach, in meeting, all normal or contingencies missions, simultaneous-operation, and downtimes during maintenance or repair durations.

5. Appendix G Table M-3a lists an average of 6 refuels on day shift and 4 on night shift (approximately 3,650 annually), while Table M-3b totals 1,222 aircraft servicing’s per year. Please reconcile — does the daily figure include ground product, organizational tank, and support equipment servicing?

PWS, Appendix G, Table M-3a, identifies 6 refuels on day shift and 4 on night shift. In a separate line; it identifies an average annual jet fuel gallons issued of 1.7M. This figure does not include ground products or organizational tanks, as it only includes services applicable to Jet Fuel Sales (e.g., aircraft support equipment).

Ground product, organizational tank, and other product services are identified in a separate line, within Table M-3a.

6. Appendix D states an ATM "may" be employed.

Will a proposal without a dedicated ATM be rated Acceptable under Sub-factor 1, provided a qualified TM alternate is identified?

PWS, Appendix D, has been updated to reflect “the Contractor shall employ an ATM” and updated PWS provided via Amendment 0005.

7. Please confirm which positions require which security clearance level (Secret versus NACI/Tier 1), and whether the government will sponsor clearance processing for incoming contractor personnel prior to the 1 November 2026 start.

PWS, C-5.5, Security, paragraph and Appendix H, confirms NACI requirements. The PWS, Appendix G, Supplement to C- 5.5, applicable to Reporting Emergency Petroleum, Oils, and Lubricants (REPOL), DD Form 254, and classified/secret requirements have been removed from this PWS. See updated PWS via Amendment 0005. The government cannot start processing security requirements for incoming contractor personnel until after contract award date has been accepted.

8. What is the current headcount of employees covered by the CBA, by classification and shift?

The Government cannot provide the requested anonymized workforce roster. Offerors are responsible for developing their own staffing plan based on the current requirements of the solicitation, Performance Work Statement (PWS), and the labor classifications outlined in the provided CBA.

9. Appendix G shows no hydrant facilities and marks all hydrant entries N/A. Please confirm that hydrant servicing vehicles (R-12 type) are not required at Patrick SFB.

PWS, Appendix G, Table M-3a., has been updated and hydrant entries indicating Non-Applicable (N/A), have been removed from the table. Contractor furnished special purpose refueling vehicles are not required in this PWS, which includes (R-12 Type). See updated PWS via Amendment 0005.

10. What is the minimum acceptable quantity of aviation truck refuelers and ground product refuelers? Will a proposal of three aviation refuelers plus one spare be considered sufficient for Sub-factor 4?

The government does not provide offerors with minimum or maximum acceptable quantities of refueling vehicles for any product.

The contractor is provided with the opportunity to propose their own quantitative vehicle fleet business approach (e.g., new, used, rebuilt, or remanufactured).

The contractors proposed quantitative vehicle fleet shall meet all normal missions, contingencies, simultaneous-operation, and downtimes during maintenance or repair durations.

Appendix F has been removed entirely from PWS. Contractor furnished special purpose mobile refueling vehicles for aviation and ground products are not required.

See updated PWS via Amendment 0005.

11. Given the anticipated 1 November 2026 start and typical 9- to 18-month lead times for specification-compliant aviation refuelers, will the government consider a phased fleet delivery schedule with government-furnished assets bridging the gap? If not, will certified used or refurbished units meeting all Appendix F specifications be acceptable?

Will a letter of commitment from a refueler supplier (rather than executed purchase orders or proof of ownership) satisfy the Sub-factor 4 requirement at proposal submission?

Does the requirement for refuelers to issue at 600 GPM apply to all units, or is the 300 GPM filtration minimum the controlling specification for the aircraft mix at Patrick (predominantly HH-60 and C- 130)?

For LOS compliance under FAR 52.219-14, please confirm that contractor-furnished vehicle lease or purchase costs are excluded from the calculation of the amount paid to non-similarly-situated subcontractors.

PWS does not require the contractor to provide special purpose vehicles. Appendix F has been removed entirely from PWS.

Contractor furnished, special purpose, mobile refueling vehicles for aviation, and ground products are not required. See updated PWS via Amendment 0005.

12. Appendix G states that government refueling and defueling vehicles "will be turned back into LRS Vehicle Maintenance for redistribution." Please confirm the date this occurs relative to contract start.

Appendix G has been updated, vehicles "will not be turned back into LRS Vehicle Maintenance” and the government confirms, there is no set date. See updated PWS via Amendment 0005.

13. FAR 52.219-9 Alternate II and DFARS 252.219- 7996 Alternate I (Small Business Subcontracting Plan) are incorporated. Please confirm whether a subcontracting plan is required from a small business prime under this 8(a) set-aside, and if so, when it is due.

No, a formal subcontracting plan is not required from a small business prime contractor on this 8(a) set-aside. The clauses are included to address a different requirement: the Limitations on Subcontracting. The clause FAR 52.219-9, with its Alternate II, is included in this solicitation because it is the appropriate clause for 8(a) contracts. This clause requires the contractor to agree to comply with the Limitations on Subcontracting outlined in FAR 52.219-14, which specifies the percentage of work that must be performed by the prime contractor's own employees.

14. If proposing as a Mentor-Protégé Joint Venture, must the SBA-approved JV agreement be submitted with the offer, or may it be provided prior to award?

the SBA-approved Mentor- Protégé Joint Venture agreement must be submitted with your initial offer. It cannot be provided later, prior to award.

15. Since the site visit was limited to 6 August, will the government provide facility condition reports, tank inspection records (API 653), current environmental permits, the SPCC plan, and leak detection system status to all offerors?

The government cannot provide facility condition reports, tank inspection records (API 653), current environmental permits, the SPCC plan, and leak detection system status to offerors.

Historical maintenance data required for contract turnover shall be available during turnover.

PWS, Appendices, References, and UFM 3-460-03, Appendix C, Maintenance Table identifies the required fuel infrastructure, assets, equipment, and operating systems, associated with (Operator and System Maintenance), to ensure, the contractor can propose their own, contractor-furnished, Computerized Maintenance Management System (CMMS).

16. Appendix G lists no oil/water separators and no pre-identified confined spaces but notes the contractor shall validate confined spaces. Please confirm that no confined space entry program cost should be assumed at bid.

Appendix G confirms no pre-identified confined spaces.

However, it does require the contractor to establish a confined space program applicable to C-6.1.10 Training Plan. Offeror cost to confine space entry program remains applicable to training of contractor personnel and capabilities.

17. What is the current condition and remaining service life of the Veeder-Root ATG systems, Gasboy AMSS pedestals, and EPoS tablets, and who bears replacement cost when they fail?

The government cannot provide current condition and remaining service life of the Veeder-Root ATG systems, Gasboy AMSS pedestals, and EPoS tablets to offerors. Historical maintenance data required for contract turnover shall be available during turnover.

PWS, Section C-5.8.2, provides Incidental Equipment, Property, and Services to be operated and maintained by the Contractor under Operator Maintenance. The System Maintenance requirements applicable to replacement cost remain governmental responsibility, unless damaged by the contractor.

18. PWS C-5.3.3 references SRM/MILCON. What is the contractor’s expected role and cost responsibility for SRM projects during the performance period?

PWS C-5.3.3, SRM/MILCON is funded and executed by the Government. The contractor’s support is limited to operational contract control labor (e.g., stripping tank bottoms, system isolation, environmental and safety concerns)

19. Are there any known or pending environmental remediation actions (including PFAS/AFFF, common at Air Force and Space Force installations) within the contractor’s area of responsibility?

Currently there are no known or pending environmental remediation actions (including PFAS/AFFF, common at Air Force and Space Force installations) within the contractor’s area of responsibility listed in Appendix G.

20. Please confirm the anticipated award date, given the 1 November 2026 start and the requirement for a 10-working-day joint turnover.

We look forward to your response.

The Government has not established a firm date for contract award. However, the Government is fully aware of the 10-working-day joint turnover requirement.

The Government anticipates an award will be made in sufficient time to ensure the successful offeror can complete the mandatory transition period prior to the 1 November 2026 performance start date.

21. a. Will the Government confirm that an Alaska Native Corporation offeror may rely on the experience and past performance of

Yes, an offeror may rely on the experience of an affiliate and Teaming Arrangements if the its parent, sister company, affiliate, or other commonly controlled entity when the proposal clearly demonstrates the affiliated entity’s meaningful involvement in contract performance, including the commitment of relevant personnel, management, facilities, or other resources?

b. If so, will the solicitation identify how the Government will evaluate the proposed relationship, resources, and level of affiliate involvement?

PLEASE NOTE: The Government Accountability Office (GAO) permits Alaska Native Corporations to claim all the experience and work history of its affiliated corporations for the purposes of establishing performance capability in the context of a competitive acquisition. Reference: Ecompex, Inc., B-292865.4, B-292865.5, B-292865.6, June 18, 2004 (see page 5). Serco, Inc., B 406683, B- 406683.2, Aug. 3, 2012. AMI-ACEPEX, Joint Venture, B-401560, Sept. 30, 2009. Specifically, GAO has ruled that an ANC bidding on a government contract may rely on the past performance of an affiliated company when the proposal makes it clear that the resources associated with the affiliated company will have meaningful involvement in the execution of the present contract.

proposal demonstrates the affiliate’s meaningful involvement in contract performance. The solicitation's evaluation criteria, typically found in Section M, describe how the Government will assess this relationship.

b. Please see section M factor 2 Past Performance that details the evaluation of Past Performance.

22. Would the Government please clarify security-related requirements:

a. What level of personnel security clearance will be required for contractor staff under this effort?

Will the Government issue a draft DD Form 254 during the proposal stage to allow the contractor’s Facility Security Officer (FSO) to begin required planning and compliance activities?

PWS, C-5.5, Security, paragraph and Appendix H, confirms NACI requirements. The PWS, Appendix G, Supplement to C- 5.5, applicable to Reporting Emergency Petroleum, Oils, and Lubricants (REPOL), DD Form 254, and classified/secret requirements have been removed from this PWS. See updated PWS via Amendment 0005.

23. a) Can the Government confirm if this requirement is strictly Government-Owned, Contractor- Operated (GOCO), or if Contractor-Owned assets are expected for performance?

a) The Government confirms this requirement is strictly Government-Owned, Contractor- Operated (GOCO).

b) If the intent is GOCO, please confirm that all references to “Contractor-Owned in the solicitation are typographical errors and will be amended to read “Government-Owned.”

c)If Contractor-Owned elements are indeed required, please provide the specific facility/equipment baseline requirements.

b) A review of the solicitation documents was conducted in response to your question, and the Government did not identify any references to “Contractor- Owned”. As such, no amendment to the solicitation is necessary at this time.

c. This is a GOCO solicitation.

24. PWS Appendix G, Table M-1 marks C-5.3.2.1 (Contractor Performed Maintenance) as “N/A” and C-5.3.2.2 (Government Performed System Maintenance as applicable (“X”). However, the main body of the PWS references active Contractor responsibilities for system maintenance.

a) Can the Government clarify if the “X” and “N/A” designations in Table M-q are typographical errors, or if the main body text takes precedence?

b) To ensure accurate pricing and risk allocation, will the Government provide a specific, itemized System Maintenance Boundary Matrix detailing exactly which components/tasks are Contractor responsibility versus Government responsibility?

If unable to provide the System Maintenance Boundary Matrix, can the Government clarify which specific system maintenance tasks are the responsibility of the contractor versus the Government, especially for any items not explicitly listed in Appendix G?

a) PWS, Table M-1, C-5.3.2.1 has been updated as applicable. See updated PWS via Amendment 0005.

b) PWS, Appendices, References, and UFM 3-460-03 (Appendix C, Maintenance Table) identifies the required fuel infrastructure, assets, equipment, and operating systems, associated with (Operator and System Maintenance), to ensure the contractor can offer their own, contractor-furnished, Computerized Maintenance Management System (CMMS).

UFM 3-460-03 (Appendix C, Maintenance Table) identifies contractor responsibility versus government responsibility, in meeting PWS (Operator and System) maintenance requirements. A System Maintenance Boundary Matrix is not requested or required in this solicitation/contract, as each contractor is required to establish a new maintenance database from local maintenance records during turnover.

25. Several sections of the PWS indicate that tank-related maintenance and cleanings are performed by the Government, yet other sections reference contractor involvement in tank-cleaning tasks.

Fixed government real property (tanks) is reference within PWS, Section C-5.3.1 and UFM 3-460- 03 (Appendix C, Maintenance Table), to assist each contractor in

a) Can the Government confirm if the contractor is required to directly fund and subcontract full-scope industrial tank-cleaning operations (including API 653 inspections, degassing, sludge disposal, and interior washing)?

Alternatively, is full-scope tank cleaning funded and executed by the Government (or via the DLA RMMR program), with the contractor’s scope strictly limited to operational support labor (e.g., stripping tank bottoms, system isolation, and safety escorts)?

proposing their own, contractor furnished, Computerized Maintenance Management System (CMMS), towards understanding the difference between (Operator and System Maintenance), and Contractor verses DLA Energy responsibilities. The question does not address any specific PWS Section. That said, full scope tank cleaning is funded and executed by the government. The contractor’s support is limited to operational contract control labor (e.g., stripping tank bottoms, system isolation, and safety concerns).

26. E1.11-1 in the Quality Control Plan includes meter-proving requirements. However, meter proving at Patrick SFB is normally performed by the Government under recurring and annual system-maintenance programs. Would the Government please confirm whether the contractor is expected to perform (and fund) meter proving under this contract, or whether these requirements remain solely within Government system-maintenance responsibilities?

The government confirms, meter proving at Patrick SFB is performed by the Government.

Appendix F has been removed entirely from PWS. Contractor furnished, special purpose, mobile refueling vehicles for aviation, and ground products are not required. See updated PWS via Amendment 0005.

27. Paragraphs C-5.3.2 and C-5.3.2.2 specify that all system maintenance is performed by the Government. Would the Government please confirm that the contractor’s Maintenance Plan required under C-5.3 is intended to address only operator-level maintenance activities performed by the contractor, and not Government-executed system maintenance?

PWS, Section C-5.3 and C-5.3.1 stipulated contractor requirements for their Maintenance Plan. The contractor shall be responsible for obtaining all inspections by state and local authorities for any maintenance performed by the contractor (or other commercial vendors completing the maintenance or repair for the contractor) as required, to document in the Contractor Furnished, Computerized Maintenance Management System (CMMS). The Contractor is responsible for all operator maintenance to be executed and document, along with documenting all system maintenance in the computerized maintenance management system

(CMMS).

28. Appendix D imposes strict limitations on which duties specific personnel may perform (e.g., prohibiting the Laboratory Technician from serving as a collateral duty, and preventing the Assistant Terminal Manager from acting as the Fuels Accountant or Dispatcher/Computer Operator).

Given the small size of this contract and limited staffing requirements, would the Government please clarify whether exceptions, alternative staffing formats, or Government-accepted cross-utilization arrangements are permissible to meet mission needs without violating Appendix D restrictions

PWS, Appendix D, provides the required staffing positions (Key and Service Personnel) for the performance tasks specified in PWS. This allows each contractor the opportunity to propose their own quantitative staffing business approach. PWS, Appendix D, remains in effect, based on industry standards, with no exceptions.

29. Appendix G contains multiple discrepancies in the equipment and facilities listing, including items no longer in service and office equipment previously turned in. Please confirm whether the Government will issue an updated and corrected Appendix G, and whether contractors should base proposals on current onsite equipment inventories or on the existing (but outdated) Appendix.

Appendix G has been updated and will be provided via amendment 0005.

PWS, Section C-5.8.2.1, shall be executed at contract start, to allow the Contractor and COR to conduct a joint inventory of all on-site items applicable to Appendix G (Government Incidental Equipment and Property). Current government office equipment which is funded by the government does not impact contractors’ operations or firm-fixed price bids.

30. Will the Government allow the contractor to install commercial or proprietary maintenance tracking software on Government-furnished computers, or will the Government provide access to an existing Government system (e.g., Maximo, GFEBS) for this requirement?

No, Air Force, LAN (Local Area Network), systems or software are not managed or funded by DLA Energy.

PWS, Sections C-5.3 and C-6.1.5, specifically requires the contractor to furnish a computerized maintenance management system (CMMS). These systems are weblink services, easily managed, and operated with internet networks

31. Section C-6.1.5 requires tracking maintenance on facilities and systems not managed by the contractor. Please clarify if the contractor is responsible for tracking the execution and completion of maintenance performed by third parties or Government personnel, or if the requirement is strictly to log and report discovered deficiencies.

Yes, the contractor is required to track maintenance performed by external entities and the COR, along with other base representatives, will be available to the contractor, in obtaining the required maintenance data, to be documented in the Computerized Maintenance Management System

(CMMS).

PWS, Appendices, References, and as stipulated in Section C-5.3, C-5.3.1, C-6.0, C-6.1.1, and C- 6.1.5, identifies “Contractor Control” responsibilities in managing these facilities under this contract. The contractor shall be responsible for obtaining all inspections by state and local authorities for any maintenance performed by the contractor (or other commercial vendors completing the maintenance or repair for the contractor) as required, to document in the Computerized Maintenance Management System (CMMS).

32. If the contractor is required to track maintenance performed by external entities, how will the Government ensure the contractor receives timely, accurate maintenance completion data from those third parties to update the logs?

Yes, the contractor is required to track maintenance performed by external entities and the COR, along with other base representatives, will be available to the contractor, in obtaining the required maintenance data, to be documented in the Computerized Maintenance Management System

(CMMS).

Additionally, PWS, Sections C-5.4 (Safety), C-5.5 (Security), and C-

5.6 (Environmental Protection), provides the awardee, the responsibility to engage with external maintenance technicians or entities, before any maintenance is performed in the “Contractor Control” facilities.

33. Please provide a definitive list of specific facilities, equipment, and system components that the contractor is required to track under section C- 6.1.5.

PWS, Appendix G, Military Service Installation Information, provides contractors specific facilities, equipment, and system components that the contractor is required to track, as stipulated in PWS, Section C-5.3 and C-5.3.1.

Additionally, UFM 3-460-03 (Appendix C, Maintenance Table), will assist the contractor in determining the difference between (Operator and System Maintenance) requirements.

34. a) Please define the specific systems, equipment, and assets that fall under the new Corrosion Control requirements.

b) Are the facility storage tanks included in the Corrosion Control scope of work?

c) If tanks are included in the scope, please provide the height, diameter, capacity, and material composition of each tank to allow for accurate pricing.

Please provide historical data from the past 3 to 5 years detailing how often corrosion control services, mitigation, or treatments have been performed on these systems.

PWS, Appendices, References, and UFM 3-460-03 (Appendix C, Maintenance Table), provides each contractor, the previously established Corrosion Control requirements for all infrastructure, which includes (e.g., tanks, pumps, valves, etc.), known as equipment and systems, towards meeting PWS (Operator and System) maintenance requirements. The UFM 3-460-03 (Appendix C, Maintenance Table) provides the informative data required to understand, the scope of work for corrosion control tasks, as the tasks vary based on (e.g., tanks, pumps, valves, etc.), known as infrastructure, equipment, and systems.

Historical data shall be provided at turnover (post award) and UFM 3-460-03 (Appendix C, Maintenance Table), provides the required periodicities for each contractor towards establishing their own contractor furnished, computerized maintenance management system (CMMS).

35. What specific government, military, or industry technical standards (e.g., UFC, NAVFAC, Army Regulations) must the Corrosion Control program adhere to?

PWS, Appendices, References, and UFM 3-460-03 (Appendix C, Maintenance Table), provides each contractor with the previously established Corrosion Control requirements for all infrastructure, equipment, and systems, towards meeting PWS (Operator and System) maintenance requirements.

36. a) Please clarify whether the incoming contractor is responsible for providing all required refueling assets necessary to fulfill the contract requirements.

b) If so, will the Government furnish an approved facility at which the contractor may perform the required maintenance on those assets?

c) If no, can general maintenance be performed in the fuels yard?

a) No, awardee is not responsible for providing all required refueling vehicle assets necessary to fulfill the contract requirements. Appendix F has been removed entirely from PWS.

Contractor furnished special purpose mobile refueling vehicles for aviation and ground products are not required. See updated PWS via Amendment 0004.

b) There are currently no-known facilities for contractor vehicle maintenance, as identified in the Pre-Proposal Site Visit.

c) Yes, general maintenance can be performed on contractor furnished equipment, specifically required under this contract. PWS Section C-5.8.2.2 states the Contractor shall not utilize on-site equipment, property, or facilities for storage or repair of Contractor furnished vehicles and equipment not specifically required by the contract provisions.

37. DFARS 252.204-7025(b)(1): As the instructional fill-in language lists all four available levels in the clause, the required CMMC level is not clearly established. As this is a 100% 8(a) set-aside, and

See Amendment 0004 which defines the specific CMMC level as Level 2 (Self) for this solicitation.

CMMC Level 2 imposes a significant technical and financial burden on small business concerns, potentially narrowing the competitive pool, will the Government clarify the specific CMMC level required for award, and confirm whether CMMC Level 1 (Self-Assessment) would be sufficient given the scope of information involved?

38. Will DLA provide a detailed asset list of the components associated with fuel systems (i.e.

listing of the equipment on site that is to be maintained in terms of the number of pumps, filters, meters, etc.) so that we can develop a detailed PM schedule?

PWS, Appendix G, Military Service Installation Information, provides contractors specific facilities, equipment, and system components that the contractor is required to track, as stipulated in PWS, Section C-5.3 and C-5.3.1.

Additionally, UFM 3-460-03 (Appendix C, Maintenance Table), provides each contractor with the opportunity to determine the difference between (Operator and System Maintenance), along with required periodicities towards establishing their own contractor furnished, Computerized Maintenance Management System (CMMS). Historical maintenance data required for contract turnover shall be available during turnover.

39. Can we submit a CPAR in lieu of a PPQ? As instructed in the solicitation, the questionnaire must be completed by the reference point of contact and submitted directly to the Government by the deadline to be considered for evaluation.

While the Government may also review CPARs during its evaluation, this does not replace the requirement for offerors to submit completed Past Performance Questionnaires (PPQs).

40. It is understood that the References provided on the reference sheet can be more than the number of PPQs and CPARS submitted. Correct?

The Past Performance Reference List should identify the specific contracts you are submitting for past performance evaluation, up to the maximum number allowed in the solicitation. The purpose of the list is to identify which contracts the Government should evaluate.

The Past Performance Questionnaires (PPQs) you submit must correspond directly to the contracts identified on that list.

41. Do you require any resumes to be submitted in the proposal? Or is this only during the transition period?

Resumes are not required for submission with the proposal. All proposal submission requirements are detailed in Section L of the solicitation. Any requirements for personnel information during the transition period are specified in the Performance Work Statement

(PWS).

42. To develop Preventative Maintenance protocol and PM procedures that are asset specific, does DLA utilize Fuel Master Management Unit (FMU) maintenance guidelines?

No, PWS, Appendices, and References utilize UFM 3-460-03, Petroleum Fuel Systems Maintenance requirements applicable to (Operator and System Maintenance). To ensure, the contractor can propose their own, contractor-furnished, Computerized Maintenance Management System (CMMS).

Historical maintenance data required for contract turnover shall be available during turnover.

43. Since the contractor is required to provide a CMMS system, does our CMMS system have to be compatible and able to communicate with existing government CMMS systems?

No, PWS, Appendices, and References utilize UFM 3-460-03, Petroleum Fuel Systems Maintenance requirements applicable to (Operator and System Maintenance). To ensure, the contractor can propose their own, contractor-furnished, Computerized Maintenance Management System (CMMS).

Historical maintenance data required for contract turnover shall be available during turnover.

44. CMMS systems offer various modules to customize the system to customer requirements.

What are the minimal requirements for the contractor provided CMMS system?

The requirements for the contractor provided CMMS system are stipulated in PWS, Appendices, References, and UFM 3-460-03, Petroleum Fuel Systems Maintenance requirements applicable to (Operator and System Maintenance).

45. Will the contractor be responsible for dispensing LOX to aircraft or will this function be provided by aircrew staff?

No, Lox carts are filled at the cryogenics facility during the hours of operations specified in Appendix G.

File details come from the government source that posted it. Updated .