This document is an amendment to the solicitation for Contractor-Owned, Contractor Operated (COCO) fuel storage services in the Arabian Gulf area. The amendment provides clarifications to several questions received from offerors:
-
The solicitation requires all storage to be at a single location. The Port of Fujairah is not an acceptable location as it is outside the defined area of consideration.
-
The requirement is for two tanks per product, with each tank meeting the minimum receiving and shipping requirements. One large tank will not suffice.
-
Offerors may use a subcontractor to fulfill the ownership and operational requirements, but the prime contractor remains solely responsible for contract performance.
-
The area of consideration is limited to Kuwait, Saudi Arabia, Bahrain, Qatar, and the United Arab Emirates. Locations in Oman will not be considered.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| SPE60324R0507-0001 w Att A.pdf | ||
| SPE60324R0507 .pdf | ||
| Attachment V - PPQ.pdf | ||
| Attachment II - PPF.pdf | ||
| Attachment III - QAPS .pdf | ||
| Attachment I - PWS.pdf | ||
| Attachment IV - Consent Form.pdf | ||
| Attachment VI - PPRL.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
1. CONTRACT ID CODE
2. AMENDMENT/MODIFICATION NO.
See Block 14
4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicable)
6. ISSUED BY CODE SPE603 7. ADMINISTERED BY (If other than Item 6) CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
CODE FACILITY CODE
SPE60324R0507
X
2024 SEP 05
10A. MODIFICATION OF CONTRACT/ORDER NO.
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of OffersX is extended, X is not extended.
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
12. ACCOUNTING AND APPROPRIATION DATA (If required)
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO.
IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc. ) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A NAME AND TITLE OF SIGNER (Type or print)
NSN 7540-01-152-8070
Previous edition unusable
STANDARD FORM 30 (REV. 10-83)
Prescribed by GSA FAR (48 CFR) 53.243
16B. UNITED STATES OF AMERICA15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
(a) By completing Items 8 and 15, and returning
DLA ENERGY
BULK PETROLEUM SERVICES
8725 JOHN J. KINGMAN ROAD
FORT BELVOIR VA 22060
15C. DATE SIGNED 16C. DATE SIGNED
D. OTHER (Specify type of modification and authority)
01 OCT 2024
3. EFFECTIVE DATE
See Attached Continuation Sheet(s).
(X)
CHECK ONE
9A. AMENDMENT OF SOLICITATION NO.
9B. DATED (SEE ITEM 11)
13. THIS APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
CONTINUATION SHEET REFERENCE NO. OF DOCUMENT BEING CONTINUED: PAGE 2 OF 2 PAGES
SPE60324R0507 - 0002
This amendment 0002 is hereby issued to answer the following questions received in response to the solicitation:
1. We understand that solicitation as DLA is seeking one single location to perform this operation, is that correct?
DLA Energy Response: Correct, all storage must be at a single location.
2. What is considered an acceptable geographic location to best provide the services DLA requires? Can you tell us if the Port of Fujairah is considered within the acceptable geographic range for the purposes of the solicitation?
DLA Energy Response: Fujairah is not acceptable as it is not located within the area of consideration which can be found in section 1.2 of the Performance Work Statement (PWS).
3. Requirement for F76 is 465,000 BBLs, we have 1 tank with a Fill + pipeline capacity of 500,246 BBLs, will this 1 tank suffice for the requirement? As per the solicitation each product should have a minimum of 2 tanks, if this is a mandatory requirement, we can offer another tank of 12,822 BBLs (fill + pipeline). So for F76, capacity will be 500,246 + 12,822 which totals 513,068 BBLs for 2 tanks. Please advice if the 1 tank of 500,246 BBLs meet your requirement.”
DLA Energy Response: No, one tank will not suffice. The requirement is for two tanks as stated in PWS section 1.3.1.
The successful offer must demonstrate their ability to meet the requirements within the PWS. If the offer is only for 2 tanks and one of the tanks is out of service, the remaining tank must meet the receiving requirement (PWS section 1.8) and shipping requirement (PWS section 1.9).
4. We realize Technical/Management Evaluation Sub-factor 1 states the Area of Consideration to be along the Arabian Gulf, littoral south that includes Kuwait, Saudi Arabia, Bahrain, Qatar, and the United Arab Emirates. But would DLA Energy consider a facility located in Oman, just south of the Strait of Hormuz?
DLA Energy Response: DLA Energy will not consider a facility located in Oman as it is outside the area of consideration.
5. We are considering engaging in subcontractor to own and operate the bulk storage and handling facilities specified under the contract. I would like to confirm if it is acceptable for a subcontractor, rather than the prime contractor, to fulfill the ownership and operational requirements outlined for the contractor-owned, contractor-operated (COCO) services? Please advise if this arrangement is permissible under the terms of the contract or if further documentation is needed for this approach?
DLA Energy Response: It is acceptable for a subcontractor to fulfill the ownership and operational requirements of the COCO storage services but the prime contractor will need to confirm it is solely responsible for contract performance and the performance of its subcontractor. Both the prime and subcontractor must meet and adhere to the requirements in the solicitation and performance work statement.