Attachment_5_Special_Notes.pdf
PDF 66 KB Posted
- Attached to
- Afghanistan Direct Delivery Fuels Requirement Federal contract opportunity
- Solicitation number
- SPE600-17-R-0224
- Issued by
- Defense Logistics Agency
About this file
Attachment 5 Special Notes
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Amendment-0002.pdf | ||
| Amendment-0001.pdf | ||
| Attch_1_Questions_and_Answers.pdf | ||
| Attachment_4_Letter_of_Commitment_Instructions.pdf | ||
| SPE60017R0224.pdf | ||
| Attachment_6_Commercial_Lab_Test_Report_Example.pdf | ||
| Attachment_I_Price_Data_Sheet.pdf | ||
| Attachment_7_Sample_Certificate_of_Analysis_Test_Report.pdf | ||
| Attachment_3-Contractor_Past_Performance_Data_Sheet.pdf | ||
| Attachment_2_Past_Performance_Questionnaire.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Attachment 5
SPE600-17-R-0224
ADDITIONAL SPECIAL NOTES REGARDING ALL PRODUCTS IN THIS SOLICITATION:
1. Source, in this contract, as determined for government acceptance, is defined as the location of the storage tank(s) from which the product(s) will be loaded into trucks and directly delivered to the customer’s destination as stated in the schedule of this contract.
a. Acceptance storage tanks should be within the borders of the country for which the major requirements are located. However, delivery from an identified, outside of the country, storage location to end user locations can be used and acceptable as long as this delivery route is listed on the vendor’s supply chain map/plan and the proper certificates of quality or analysis are presented to the region Quality Manager or QAR for acceptance in accordance with below guidance.
b. Offeror will need to inform the contracting officer of the location in which the products will be stored and sampled, for acceptance purposes, along with the distance the storage location is from the delivery locations.
c. Offeror will also inform the contracting officer of their commercial laboratory which will be used to perform acceptance testing prior to acceptance by the government.
i. All commercial laboratories to be used for acceptance testing must be approved by the U.S. Government.
ii. The Government will be provided, for evaluation and acceptance, the name of the laboratory to be used, the expected capabilities of that lab (full specification, etc.) for each product, a good point of contact name, phone number, laboratory location address, and email address.
iii. Samples of their certificates of analysis (redacted) will be provided to the government for evaluation. Certificate of analysis should reflect the same information as that listed in section 14 below.
iv. Offeror can expect a quality visit to their proposed laboratory if the laboratory has not already been vetted and accepted by the Government in the past.
v. If the offeror possesses their own laboratory, it can perform full specification testing in accordance with the specification requirements and want to use that lab for this contract and acceptance purposes, the lab will have to be vetted and approved by use, by the U.S. Government, prior to the beginning of the performance period.
vi. The use of a third party inspection contractor may be used to assist DLA Energy Quality in witnessing and verification of laboratory testing and equipment calibrations/standardizations for contractor owned laboratories.
1. Contract awardee(s) that plan on using their own laboratories will allow entry to any DLA Energy, third party inspection contractors, just like they would any DLA Energy QAR or representative stated in contract provision(s) FAR 52.246.2 and E21.01.
2. Failure to do so will result in the awardee(s) to have to use an outside, commercial lab for all of their “acceptance” testing.
2. The Fuel Source Data Sheet attached will be used to show all of the refineries or terminal sources where the offeror is sourcing the fuel to be provided to the U.S. Government.
a. This requires not only the refineries or terminal sources but the contractor’s “acceptance” storage tanks as well.
b. Under “Country of Origin” on the Fuel Source Data Sheet, type or write “acceptance” beside the country name. Then under “Destination Country” please include any outside locations included in the schedule in which that source may deliver to.
3. Offeror will need to provide letters of commitments from all sources of supplies, transportation sub-contractors, laboratories, and any other sub-contractors (storage, operations, drivers, etc.)
from which they will require assistance in order to fulfill this contract and its requirements.
a. Letters of commitment will be on sub-contractor, lessor, and/or supplier’s letterhead and in the format listed in attachment # 4. The commitment letter must also state how soon before the start of the performance period the sub-contractor will be fully available for access and use by the offeror.
4. In order for the offeror to demonstrate that they possess the technical capability to provide the fuel (all products in the schedule) which meets the required specification(s), the offeror, with their supply commitment letters, must present either a current, full specification Refinery Certificate of Quality (COQ) or a recertification certificate of analysis (COA) if sourcing from a location which blends several batches from more than one refinery source (terminal). All COQ/COAs should be presented in a format which resembles that of the one listed in ASTM D1655, figure X3.2 or the commercial laboratory sample provided. These certificates will be on refinery or commercial laboratory letterhead and signed and dated like the certificates of analysis listed below.
a. Certificates of Analysis will contain the source information (location, tank number, lot or batch number, etc.), specification tested to, along with the test methods used for testing.
b. To be acceptable for evaluation, the certificate will also be signed and stamped by the laboratory manager and be within 30 days of submission from a batch out of the terminal storage tank(s) or refinery batch tank(s) to be used for actual supply.
c. If the supplier is purchasing products from a terminal that receives and blends several different refined products from multiple refineries/sources, a list of those refineries/sources as part of that batch blending will be submitted for traceability purposes and should be included on the Fuel Source Data Sheet, if room or on a separate attachment stating that these are refineries used in the blending of that product.
d. Partial quality certificates (with less than the required or listed characteristics tested, as listed in the specification) and manufacturer/product specification sheets will not be accepted.
e. All test certificates submitted shall be translated into English and will be in the same format as required by the original. The original, non-English version will need to accompany the translated version and the offer must ensure that they are one in the same.
f. Translated version must be signed and stamped by the person that translated and the method of translation included.
5. If the offeror is unable to provide full specification certificates of quality/analysis from the refinery or terminal or own storage, or if the offeror determines that certain test characteristics were not tested under specific specifications or find some characteristics do not meet specification limits, offeror will have samples, from all of their source(s), taken and tested to the full specification(s) listed in this solicitation and submitted with the offer.
a. This independent test will be to the full specification and meet the certificate of analysis requirements of section 14 above.
b. Offerors will need to submit exception or deviation requests for changes to the fuel specifications which they cannot meet or specific characteristic limits and/or test methods which their laboratory or country specification(s) cannot meet or test.
c. Offerors will have to provide a detailed reason behind the need for the exception or deviation request, along with their way forward with meeting the requirements of this contract, and the duration of the exception or deviation request.
6. All products, once received at the offeror’s “acceptance” storage tank(s) as stated above and prior to loading and trucks and delivering to the end user, will have to meet the product specification(s) listed in this contract and be submitted to the regional Quality Manager or QAR prior to being released for shipment.
a. DLA Energy Quality Assurance will be covered under Alternate Release Procedures (ARP) and requires all product(s) be inspected and approved (accepted) by a QAR prior to being released for shipment.
b. Contract awardee(s) will be provided with an ARP letter stating the requirements for product quality acceptance and other instructions to be followed during the performance period of this contract.
c. Once individual storage tank inventory, during the entirety of the performance period, is depleted and fresh product is received into that storage tank(s), a new batch sample and acceptance testing will need to be completed prior acceptance and release for delivery to the government.
7. The offeror must provide a map or chart showing the entire supply chain of the product(s), from source to final delivery. The offeror must also show this plan as part of their ability to supply on specification product(s) in their quality control plan (QCP) and/or standard operating procedures/statement of work (SOP/SOW) required below.
8. Offeror will provide transportation plans which shall include details as to how the offeror will move fuel through the entire supply chain. The emphasis will be on the details provided for transportation of the product from the in-country intermediate storage sites to the customer’s delivery location(s). Descriptions of leased or owned transportation modes for movement of product(s) from source to the intermediate storage locations should, at minimum, included the type of transportation, the numbers made available, the sub-contractor to be used and what areas of the supply chain they will cover.
9. Offeror will need to provide a list of the tank trucks which will be utilized for this contract.
a. Tank Truck list will include the make and model of the truck, capacities, the plate and registration/vehicle identification number (VIN) numbers, the model year, whether the tank is epoxy coated or not and if the trucks are dedicated to a specific grade of fuel and that grade of fuel it will carry.
b. Offerors will need to provide lists of drivers and the vehicles they will be assigned to after award. List will need to have drivers’ full names, identification numbers, and trucks they will be assigned to. Offeror may also have to provide further information to the Government and/or customer locations to allow entrance and do background checks.
c. For offeror owned assets, the list of assets with the information required under section 19 a. above, is the only thing required, no letter of commitment.
d. Except for the letters of commitment and the asset lists, the transportation plan can be submitted separately or be submitted as part of the QCP and/or the SOP/SOW. If part of the QCP and/or SOP/SOW, the offeror will state that in their offer.
10. Offeror will need to provide detailed descriptions/plans of all primary and alternate storage and distribution systems, both leased and owned, to be used for the entirety of the performance period.
a. To demonstrate the offeror’s ability for sufficient storage, the offeror will need to provide details of the storage facilities to be used, whether primary or alternate
i. Storage tank lists will include the tank numbers, max capacities each can hold, if they are rigid (steel, aluminum, etc.) or bladders, whether they are segregated or on common lines, and the grade of fuel each will hold. Offeror will also have to express the max quantity(s) of each grade made available to the government for the entirety of the period of performance.
b. The offeror will also show the storage facilities ability as to how many trucks it can up-load and/or down-load in a 24 hour period, if it can support filling customer tank trucks, and all laboratory capabilities, either owned or contracted out, and their testing capabilities for ensuring product quality is met prior to final delivery to the customer.
c. The offeror will provide their proposed storage capacity and proximity to each solicited location, and the offeror’s ability to provide operational storage and supply arrangements that are proposed to insure the intermediate reserve products are available throughout the term of the contract.
i. Proximities to be provided will include the distance and time to destination of all the customers listed in the solicitation schedule.
d. Except for the letters of commitment and the facilities asset lists, the supply/distribution plan can be submitted separately or be submitted as part of the QCP and/or the SOP/SOW. If part of the QCP and/or SOP/SOW, the offeror will state that in their offer.
11. A quality control plan (QCP) and/or standard operating procedure/statement of work (SOP/SOW) will be provided in the offer in order to show the offeror’s ability and capability to assure the quality of the product remains within contract specifications from origin to destination.
a. The quality control plan must meet the requirements of the solicitation/contract provision E1, section (b)(3). A QCP is required, for all products, if the attached schedule includes any aviation fuel (JA1, Avgas, etc.). If no aviation fuel, the offeror will only have to submit their standard operating procedures/statement of work.
i. These SOP/SOWs, at minimum, will describe how the offeror or its sub-contractors will ensure quality of the product throughout the supply chain.
ii. The QCP will be evaluated for its ability to show the steps to be taken for quality assurance and surveillance throughout the supply chain and how well it incorporates the elements required by the E1 provision.
iii. The contractor must also show that any sub-contractors will be utilizing and adopting those procedures and that the primary contractor understands that the QCP will be updated and revised to meet the unique requirements of this solicitation and approved and signed by the region’s quality manager prior to first order off this contract.
iv. The offeror must also provide standard operating procedures for the proposed operation of their transportation and storage distribution segments of this contract if those procedures are not incorporated into their QCP.
12. Offeror will submit a detailed description of their alternate supply chain, to include distribution and storage, from vendor source to final destination.
a. The offeror’s will need to show, through similar lists and plans to be submitted for their primary support listed in the above paragraphs, their ability to provide alternative sources of supply in the event of geo-political shifts, political uprisings, poor weather and road conditions, refinery constraints or any other contingency that would prevent delivery from the primary source of supply.
b. The alternate supply chain must be shown to be distinct and separate from their primary chain(s) and all items require in paragraphs 11 thru 19 above.
c. The offeror’s ability to provide alternative sources and the ability to continue contract requirements shall be shown on the same map or chart required above and must also be included in their QCP and/or SOP/SOW.
13. Offeror is responsible read and understand all of the requirements set in this solicitation and these special notes. Offeror is also responsible for submitting all attachments and offers that show that they understand these requirements and any specifications or instructions are going to be met. If the offeror discovers deficiencies or non-compliance to these solicitation requirements and/or specifications, the offeror must present an exception or deviation request similar to that stated in section 15 above and in accordance with solicitation provision E35. If offeror has some sort of “shortcoming” with meeting a portion or portions of the requirements and plan on having it resolved and meet the requirements as stated, the offeror should provide a “letter of intent” to the contracting officer with the offer.
a. Letter of intent will provide the portion of the requirement(s) unable to meet at the time, how and what the offero plans on putting in place to meet the requirement(s), and the date (before the start of the performance period) they plan on having in place and meeting the requirement, if awarded.
b. Letter of intent must be provided only to the contracting officer assigned to this contract. If pre-award survey is scheduled, offeror must provide the information with regard to their letter of intent but must not hand over any letters to the QAR conducting the survey.