2nd_Pre-Proposal_Q A_for_Gas-Cyl.doc

DOC document 68 KB Posted

Attached to
Compressed Gases and Cylinders RFP SPE4A615R0340
Solicitation number
SPE4A615R0340
Issued by

About this file

The questions and answers from both the May 28th and June 2nd 2015 teleconference Q A sessions are attached.

View the file

Other files

File Type Posted
Amendment_10_SPE4A615R0340_Signed.pdf PDF
CONUS_RECOMPETE_AMD_9REVISED.pdf PDF
amendment_09.pdf PDF
Amendment_0008_SPE4A615R0340.pdf PDF
Amendment_0007_SPE4A615R0340.pdf PDF
Amendment_0006_SPE4A615R0340.pdf PDF
Amendment_5_SPE4A615R0340.pdf PDF
SF30_SPE4A615R0340_Amendment_04_(2).pdf PDF
SF30_SPE4A615R0340_Amendment_04.pdf PDF
SF30_SPE4A615R0340.pdf PDF
Amendment_0003_SPE4A615R0340.pdf PDF
Updated_B6.xlsx XLSX spreadsheet
Amendment_2_SPE4A615R0340.pdf PDF
permit.pdf PDF
Email_Q A_for_Gas-Cyl.doc DOC document
Updated_Book2.xlsx XLSX spreadsheet
Updated_Section_L.doc DOC document
Updated_Inactive_NSN_PID_Data_(SPE4A615R0340).txt TXT text file
Updated_Active_NSN_PID_Data_(SPE4A615R0340).txt TXT text file
Updated_SOW.docx DOCX document
Updated_Book16.xlsx XLSX spreadsheet
Updated_Book15.xlsx XLSX spreadsheet
Updated_Section_M.doc DOC document
Updated_Book5.xlsx XLSX spreadsheet
Updated_Book1.xlsx XLSX spreadsheet
Updated_Book4.xlsx XLSX spreadsheet
New_Quality_Matrix.xlsx XLSX spreadsheet
SPE4A615R0340_RFP.pdf PDF
NSN_LIST.xlsx XLSX spreadsheet
PID_Data_File_(Active_NSNs).txt TXT text file
SPE4A615R0340_DRAFT_RFP.pdf PDF
Show all 31

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DEFENSE LOGISTICS AGENCY

AVIATION

8000 JEFFERSON DAVIS HIGHWAY

RICHMOND, VIRGINIA 23297-5100

Pre-Proposal Conference Follow-Up Question and Answer for Gas Cylinder Project SPE4A6-15-R-0340

Following are the follow-up questions that were asked during the Pre-Proposal conferences held by DLA Aviation regarding RFP SPE4A6-15-R-0340 on May 28 and June 2, 2015:

1) Q: During the current contract termination and subsequent transition period, what happens to full Government Cylinders (GFP) that remains on hand for the current Contractor?

A: The gas contained within the cylinders is still the property of the current Contractor. DLA does not pay for material until such time that we are invoiced for the delivery order; therefore, until that time it is considered Contractor property. The current Contractor will have to reclaim or evacuate the gas contained in the GFP before transition to the next Contractor. Only empty cylinders will be transferred from one Contractor to another. DLA Aviation will transition the GFP as we feel appropriate during the transition period. At the end of the transition period, all GFP on hand at the current Contractor will be moved to the next Contractor.

2) Q: In Section M, The Government mentions transactions in excess of 500 per month. Can you clarify this figure?

A: The current contract has an average of 500 orders per month.

3) Q: We remain unclear on how the proposed refurbishment prices will be evaluated according to Section M. Please provide further detail.

A: The Contractors will provide a price list on Schedule B15 for refurbishment services. These prices will then be multiplied by the EAD to calculate the overall refurbishment price used for evaluation. This calculation is strictly being used for evaluation purposes only. This formulation was chosen as the best way to evaluate these services even though the actual refurbishments and refurbishment rates will vary under the terms of the contract. The language in Section M will be changed to better clarify the evaluation.

4) Q: How do we price the outliers of the refurbishment process?

A: Refurbishment of NSN 6830-01-433-3717 (15-lb carbon dioxide fire extinguisher) to meet the requirements of NSN 8120-01-502-4379 is not considered a “standard” refurbishment because of the additional parts required. As described in 6.6.2.2 of the SOW, this shall be priced separately. The Contractor may choose to use a modified version of Schedule B15 or another way as long as it priced and the additional parts are covered in the price.

5) Q: Based on the POT for NSN 6830-01-392-0959, the cylinder is included. Shall we be pricing this NSN for both the gas and cylinder?

A: The POT describes both the gas and the cylinder requirements for this NSN. The Contractor’s price should include the cost of the gas and the cylinder since it won’t be provided as GFP for this NSN.

File details come from the government source that posted it. Updated .