CSC-26502 Questions and Answers.xlsx
XLSX spreadsheet 52 KB Posted
- Attached to
- SP4702-26-Q-0012 MEP
- Solicitation number
- SP470226Q0012
- Issued by
-
Defense Logistics Agency
About this file
This is a Questions and Answers document for federal contract solicitation SP4702-26-Q-0012, issued by the Defense Logistics Agency for comprehensive operation, maintenance, and repair services at the Defense Supply Center Columbus (DSCC) installation in Columbus, Ohio. The contract covers non-personal services including operation and maintenance of Electrical & Lighting Systems, HVAC, Plumbing, Kitchen Equipment, and Life Cycle Management Cyber Security across multiple facility buildings, with performance commencing November 1, 2026, through October 31, 2027 (base year), plus one option year.
The Q&A clarifies critical contract mechanics and performance expectations across 89 question responses. Key financial thresholds establish that Demand Maintenance Orders (routine corrective maintenance) are included in fixed-price scope when labor does not exceed 32 hours and combined labor-plus-materials cost does not exceed $2,000; work exceeding either threshold converts to separately funded Project Work Orders. The contract requires two full-time on-site Journeyman Electricians for Building 20 (0700-1600 hours Monday-Friday), with mandatory Saturday coverage 0700-1100 for basic operations checks and off-hours maintenance. Standard duty hours are 0700-1530, with on-call emergency response capability required 24/7, with one-hour response time for Priority 1 emergencies and 15-minute phone response. The contract distinguishes Government-Furnished Equipment (GFE)—including network infrastructure, servers, workstations, enterprise cybersecurity tools, and OS-level systems—from Contractor-Furnished Equipment (CFE), with the contractor responsible for vendor-specific applications, supervisory software, controllers, sensors, and field-level BAS components. Cybersecurity requirements under Section C.6 are comprehensive and continuous, requiring the contractor to support Zero Trust implementation aligned with NDAA 2022 and Executive Order 14028 through FY2030, with responsibility for STIG remediation on contractor-furnished systems and supporting the Government's RMF authorization and A&I (Assess & Incorporate) processes. The contractor must maintain a 30-day rolling spare parts inventory for HVAC, plumbing, and electrical systems, coordinate all OEM warranties, manage facility emergency response capabilities, and provide all vehicles and transportation for personnel and materials across the installation. Pricing is submitted via detailed bid sheets with separate tabs for CLINs 0001-0006, where CLIN 0003 covers maintenance labor (fixed-price) and CLIN 0004 covers maintenance materials (fixed-price), with CLIN 0006 functioning as the Time & Material vehicle for Project Work Orders. The contract includes technical exhibits providing 3-year historical demand maintenance order data, equipment lists spanning 14 chiller units from multiple manufacturers and extensive electrical distribution infrastructure (253 panels in Building 20 alone, 700,000 square feet), and the contractor must conduct comprehensive baseline assessments post-award to identify end-of-life systems and cybersecurity deficiencies. Evaluation criteria include Technical Quote (Factor A), Management Proposal (Factor B), Past Performance (Factor C), and Price (Factor D), with Key Personnel limited to Project Manager and Site Maintenance Manager positions only.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| SF30_SP470226Q00120004.PDF | ||
| PRICE_BID_SHEETS_PROTECTED_REV2.xlsx | XLSX spreadsheet | |
| SF30 SP470226Q0012 0003.pdf | ||
| PRICE_BID_SHEETS_PROTECTED_REV1.xlsx | XLSX spreadsheet | |
| CSC-26502 Evaluation Criteria L and M.pdf | ||
| SF30 SP470226Q0012P0002.pdf | ||
| CSC-26502 Updated Tech Exhibit Attachments.zip | ZIP file | |
| CSC-26502 PWS_REV1.pdf | ||
| SP470226Q0012 0001.pdf | ||
| CSC-26502 PWS 05-27.pdf | ||
| SP470226Q0012 0001.pdf | ||
| SF1449_SP470226Q0012.PDF | ||
| Evaluation Criteria L and M CSC-26502.pdf | ||
| SCA Wage Shortcuts.pdf | ||
| PWS CSC-26502.pdf | ||
| CSC-26502 Bid Sheet.xlsx | XLSX spreadsheet | |
| PWS CSC-26502 Tech Exhibit Attachments.zip | ZIP file |
Show all 17
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| Question | File | Section | Question | Government Response | Response from: |
| 1 | Evaluation Criteria L&M | Page #8 Section 3.2.1.b.iii | The key personnel description for Cybersecurity Systems Administrator is missing and there is no section C5.8.4 in the PWS document | With guidance from J6 it was determined that Cybersecurity Systems Administrator will not be considered key personnel. | Installation Management |
| 2 | PWS CSC-26502 | Page #50 Section C.6.3.2 ZT | Could the government clarify what is meant by the "(Future)" tag? Does it imply that ZT requirements are not part of the existing contract and instead will be part of a future contract? | Zero Trust (ZT) implementation is not categorized by a static list of capabilities mandatory solely at the time of award versus future-state objectives. Rather, the requirement is continuous. |
| The Contractor shall design, implement, and maintain their solution in a manner that enables DLA to meet all evolving requirements aligned with Zero Trust implementation and compliance. This ongoing support must ensure DLA remains in accordance with the mandates set forth in NDAA 2022 and Executive Order 14028, leading up to full ZT implementation by FY30. | J6 | |||||
| 3 | PWS CSC-26502 | C6.1–C6.4 | Please confirm that all references to 'Department of War' and 'DoW' throughout Section C.6 should read 'Department of Defense' / 'DoD,' and provide corrected instruction/regulation numbers where applicable. This affects interpretation of all cybersecurity compliance obligations under the contract. | Within the context of this contract and Section C.6, "Department of War (DoW)" and "Department of Defense (DoD)" are used synonymously. All cybersecurity compliance obligations, standards, and instruction/regulation references remain fully applicable as written under either term. No formal text revisions are required. | J6 | |
| 4 | SF1449 / PWS | PWS C2.3 / SF1449 pp.8–12 | Which period of performance dates are correct - the PWS (November 1, 2026 - October 31, 2027) or the SF1449 CLIN pages (September 1, 2026 - August 31, 2027)? This discrepancy affects pricing, staffing plans, and all post-award deliverable deadlines. | SF1449 will be updated to match the PoP listed in the PWS (Nov. 1 - Oct. 31). | KO | |
| 5 | SF1449 / Bid Sheet | SF1449 pp.8-12 / Bid Sheet | (a) What does each CLIN cover? Specifically, which CLIN covers: management labor, maintenance labor, cybersecurity, materials, subcontracts, and PWOs? (b) Please confirm that the CSC-26502 Bid Sheet.xlsx is the authoritative pricing document and that CLIN descriptions therein govern over the SF1449 label. (c) Is CLIN 0006 the sole T&M vehicle per FAR 52.216-31, and is the 325-hour ceiling a hard NTE for all labor categories combined? | The SF1449 will be updated to provide item description names for the CLINs instead of reference of see SoW document. FAR 52.216-31 does not apply to this solicitation and reference to it has been removed from the Bid Sheet. | KO | |
| 6 | PWS CSC-26502 | C4.4.7 / C4.5 | (a) Is the $2,500 threshold applied to materials cost only, or is it a combined labor plus materials cap? (b) Has this threshold been reviewed against current 2026 Columbus OH market rates? (c) What is the Government's expectation for the DMO-to-PWO conversion ratio? (d) Can the Government share historical data on the percentage of DMOs that were converted to PWOs under the prior contract? | Threshold updated from $2,500 to $2,000. |
The $2,000 threshold is a combined labor plus materials cap (total cost per work order). In accordance with PWS Section C4.4.7, a repair is considered a Demand Maintenance Order (DMO) and included in the fixed-price maintenance scope if it requires thirty-two (32) labor hours or less AND the total estimated cost (combined labor and materials) is $2,000 or less. If an individual repair exceeds 32 hours of labor OR exceeds $2,000 in total cost, the work must be converted to a Project Work Order (PWO).
2026 Columbus Ohio market rates were not reviewed. The thresholds are based off DFARS 222.402-70 Installation support contracts, 40 USC § 3142: Rate of Wages for Laborers and Mechanics and 41 USC Chapter 67 SERVICE CONTRACT LABOR STANDARDS.
The Government does not have a set expectation or mandated target ratio for DMOs converting to PWOs. DMOs are inherently unscheduled and corrective in nature; therefore, the conversion rate is driven by equipment condition and unpredictable failure events. It is the responsibility of the Contractor to manage the workforce and materials to meet the PWS objectives within these established thresholds.
| Offerors should refer to Technical Exhibit 07 (TE-07) – Legacy Demand Maintenance Data to review historical workload and service call volumes. The Government does not maintain or provide a specific historical percentage metric for DMO-to-PWO conversions, as previous contract scope thresholds and asset inventories may have varied. Offerors must base their proposals on the provided technical exhibits, the current equipment list, and their own industry expertise in maintaining similar facilities. | Installation Management | |||||
| 7 | PWS CSC-26502 | C6.5 Table 6.5-1 / C7.1.2 | Will the Government accept preliminary or draft versions of the C6.5 cybersecurity deliverables (items #4, #6, #7) within the 15-day window, with final versions submitted after the 90-day equipment inventory? Will DLA J6 provide existing OT system documentation or diagrams from the incumbent contractor to facilitate the incoming contractor's initial submissions? | Yes, with conditions. The Government will accept preliminary or draft versions of the specified deliverables within the 15-day window, provided the Contractor demonstrates a deliberate, ongoing effort and consistent progress to finalize these documents in a timely manner. Upon contract award, the Government will provide available existing documentation or diagrams to the incoming Contractor to facilitate these initial submissions. | J6 | |
| 8 | PWS CSC-26502 / Bid Sheet | C5.8.4 / C6.2.1-C6.2.2 | (a) What IT investigation level (Tier 1, Tier 3, or Tier 5/SSBI) is required for the Cyber Systems Administrator position? (b) Confirming this position requires a CAC? (c) What specific DoDM 8140.03 work role (e.g., System Administrator, Information Systems Security Manager) and associated baseline certification is required? (d) What is the current estimated adjudication processing time for this investigation level at DSCC? | Requirements for the Cyber Systems Administrator position depend on the Contractor's proposed technical solution and whether the role requires administrative (privileged) access: |
1. If Administrative/Privileged Access is Required:
(a) Investigation Level: IT-I or IT-II level of trust is required. Specifically, all CONUS Contractor personnel performing IT-II/Moderate Risk duties require a Tier 3 (T3) investigation. If IT-I duties are required, a Tier 5 investigation is necessary.
(b) CAC: Yes, a Common Access Card (CAC) is required.
(c) Work Role & Certification: This role maps to DoDM 8140.03 / DoD 8570.01-M IAT Level II or III baseline certification (e.g., Security+ CE, CISSP, or equivalent). Additionally, a Computing Environment (CE) certification applicable to the application is required: all contract employees must be certified in the operating systems of any system on which they perform system administration duties.
2. If Administrative/Privileged Access is NOT Required:
(a) Investigation Level: Standard IT-III/Tier 1 (National Agency Check with Inquiries - NACI) is typically required for basic network access.
(b) CAC: Yes, a CAC is required for network and physical facility access.
(c) Work Role & Certification: Standard non-privileged user rules apply; specific cyber work roles may not be triggered unless direct system configuration changes are within the scope.
3. (d) Processing Times:
| Adjudication processing times are determined by the Defense Counterintelligence and Security Agency (DCSA) and the Defense Industrial Security Clearance Office (DISCO). DLA J6/DSCC does not control these timelines, though interim clearances/access may be processed in accordance with standard DLA security protocols. | J6 | ||||
| 9 | PWS CSC-26502 / TE-03 | C7.4.9 / TE-03 | (a) When was the last eddy current test performed on each chiller, and which specific units are due within the base year (Sep 2026 -Aug 2027)? (b) Of the approximately 74 chiller-related items in TE-03, how many are complete refrigeration machines versus components, controls, or sensors? (c) How many distinct chiller manufacturers are represented on the installation? | TE-03 has been updated, 14 total Air Cooled and Centrifugal Chillers (DAIKIN, TRANE, MCQUAY, CARRIER, AIRSTACK, YORK). Perform eddy current testing as required by the TECHNICAL EXHIBIT - 04 in base year. |
| Installation Management | ||||
| 10 | PWS CSC-26502 / TE-03 | C7.4.7 / TE-03 | (a) What makes and models are the primary steam and hot water boilers on the installation? (b) When was the last State of Ohio third-party boiler inspection performed and what was the result? (c) Are any boilers under active manufacturer warranty that would restrict who may perform maintenance or tune-up services? | Hot Water: Cleaver Brooks ClearFire CE, Patterson Kelly Modu-Fire |
Steam: Cleaver Brooks CEW-700, CB-700 No record of 3rd party inspections.
Building 10 boilers are only boilers with restrictions
| Installation Management | ||||
| 11 | PWS CSC-26502 | C5.1.1.1 / C2.4.5 | (a) Are the two mandatory on-site electricians also responsible for after-hours and emergency electrical calls, or is after-hours electrical work handled separately and compensated through CLIN 0006? (b) Is there any medium or high-voltage electrical work (above 600V) that the contractor should anticipate anywhere on the installation? (c) What is the approximate square footage and number of electrical distribution panels within Building 20? | (a) The two mandatory on-site electricians are responsible for electrical maintenance during normal operating hours. For after-hours and emergency electrical calls, the Contractor must provide on-call coverage. If an after-hours electrical emergency is resolved within the Demand Maintenance Order limits (thirty-two labor hours or less, AND a total combined cost of $2,000 or less), the labor is included in the firm-fixed-price maintenance scope and is not separately reimbursable. If the after-hours electrical work exceeds wither the 32-hour or $2,000 total cost threshold, it will be converted, processed, and funded as a separate Project Work Order. |
(b) The distribution system for this site is fed from a 138kV Main Substation and is stepped down to a site distrition system of 13.2kV. The 13.2kV enters building transformers and is typically stepped down to 208V or 480V. Equipment that operates above 600V are the 3 centrifugal chillers in Bldg. 20A which operate at 4160V.
(c) 700,000 SF and 253 panels within Bldg. 20. Reoccuring preventative maintenance on panels handled under seperate contract effort.
| Installation Management | ||||
| 12 | PWS CSC-26502 / SF1449 | C4.2 / C6.2.1 / C5.8.4 | (a) Is there an incumbent contractor currently performing this work, and will they be required to cooperate with transition per an outgoing transition plan? (b) What is the current estimated adjudication processing time for security investigations at DSCC? (c) Will interim DLA network and EBS access be granted to key personnel while final adjudication is pending, to prevent delays in meeting the 30-day Phase-In and 120-day EBS PMO milestones? | There is an incumbent contractor and they will be required to cooperatte with the transition as stated in their current contract. |
| The Government cannot provide a specific estimated timeline for security adjudication processing, as background investigations are conducted by the Personnel Security Office and are subject to federal investigative agency workloads. Offerors must submit complete security packages for all personnel as early as possible to minimize potential administrative delays. The Governement will work with the contractor to obtain a waiver for intermin access. If delays caused by the Governemnt adjudication process occur or waivers are not granted then milestones can be adjusted acccordingly. | Installation Management | ||||
| 13 | Sections L & M / Bid Sheet | Section L 3.4.2 / CLIN 0005 | (a) For CLIN 0005 (Subcontracts), must each subcontractor exceeding the 10% threshold submit a separate detailed cost breakdown, or is the CLIN 0005 Bid Sheet tab sufficient? (b) Is there a required format for subcontractor cost breakdowns, or may offerors use their own format? (c) Are sole-source specialty subcontractors (e.g., factory-authorized OEM service) exempt from competitive comparison requirements? | CLIN 0005 Bid Sheet Tab is sufficient |
For PWOs Bidders may use their own format for these cost breakdowns, provided the proposal includes a transparent breakout of labor, materials, and equipment to allow the Contracting Officer to determine price reasonableness.
| Sole-source specialty subcontractors, such as factory-authorized OEM service providers, are not exempt from price justification requirements. While they are exempt from the standard three-quote competitive comparison, the Contractor must still submit a written sole-source justification and a detailed cost breakout. This information must be sufficient for the Contracting Officer to perform a price reasonableness determination. | Installation Management | ||
| 14 | PWS CSC-26502 | Please identify the standard duty hours applicable to this contract, including: | |
| • | normal operating hours, | ||
| • | onsite staffing hours, | ||
| • | facility access hours, | ||
| • | and any shift requirements. | ||
| Please specify whether all systems are expected to be supported during standard business hours only or on a 24/7 operational basis. If 24/7, is staffing required for all three shifts? If not, how are call-ins handled? | Please identify the standard duty hours applicable to this contract, including: | ||
| • | normal operating hours, 0700-1530 | ||
| • | onsite staffing hours, A combination of shifts shall cover 0700-1600, but all staff do not need to be present during all hours. i.e. some employees may work 0700-1530 while other would work 0730-1600. | ||
| • | facility access hours, The gate is open 24/7 and personnel will hvae 24/7 access for emergency calls. | ||
| • | and any shift requirements. | ||
| Please specify whether all systems are expected to be supported during standard business hours only or on a 24/7 operational basis. If 24/7, is staffing required for all three shifts? If not, how are call-ins handled? We do not expect employees to work outside of normal business hours unless there is an emergency. Contractor shall provide on call personnel (this typically is a 1-3 person phone tree) to respond 24/7 to mitigate an emergency but are not necessarily expected to completely resolve the problem. The intent is to come in and stop further damage and make the area safe. i.e. Personnel may need to come in and stop a water leak, but the cleaning up and remediation of damaged items will typically wait for normal business hours. This doesnt mean there wont be times we need full service but generally the emergency call is to stop further damage and then we deal with it on normal hours. | Installation Management | ||
| 15 | PWS CSC-26502 | Please clarify the required contractor coverage expectations for: | |
| • | HVAC systems, | ||
| • | BAS/FRCS systems, | ||
| • | electrical systems, | ||
| • | plumbing systems, | ||
| • | kitchen equipment, | ||
| • | and cybersecurity support. |
Please specify whether:
| • | continuous onsite coverage, | ||
| • | on-call coverage, | ||
| • | or dispatch-only coverage | ||
| is required outside normal duty hours. | The contractor shall provide appropiate staffing levels to be able to properly maintain and provide operational checks in accordane with the PWS. This may be done through prime contractor staff or subcontract. | Installation Management | |
| 16 | PWS CSC-26502 | Please identify required response times for after-hours service calls, including: | |
| • | emergency response, | ||
| • | urgent response, | ||
| • | routine response, | ||
| • | BAS outages, | ||
| • | utility failures, | ||
| • | and cybersecurity incidents. |
Please specify:
| • | phone response time, | |||
| • | onsite arrival time, | |||
| • | and restoration expectations. | Reference C4.4.7 and subsequent subsections following. Phone response should be nearly immediate, within 15 minutes and response for urgent/emergency work shall be within 1 hour. Also reference question #14 above for further infromation. | Installation Management | |
| 17 | PWS CSC-26502 | Please clarify whether: | ||
| • | overtime labor, | |||
| • | weekend work, | |||
| • | holiday work, | |||
| • | after-hours work, | |||
| • | emergency callback labor, | |||
| • | and off-shift support |
are included within the fixed-price scope or separately reimbursable when directed by the Government.
Please also clarify:
| • | approval authority, | |
| • | authorization procedures, | |
| • | and reimbursement methodology. | After-hours, weekend, or overtime labor for routine maintenance and Demand Maintenance Orders is not separately reimbursable. In accordance with the contract, all tasks falling under the thirty-two labor hours and $2,000 total combined cost thresholds are included in the firm-fixed-price scope. The costs associated with providing on-call coverage, executing Saturday shifts, and responding to off-shift emergencies must be fully burdened and absorbed within the Contractor's monthly firm-fixed-price proposal for maintenance labor. |
Premium labor rates or shift differentials are only applicable to separately funded Project Work Orders. If the Government initiates a Project Work Order for major repairs or upgrades that exceed the Demand Maintenance Order thresholds, and explicitly directs that the work be performed outside of normal operating hours, the Contractor may include negotiated premium labor rates in their Project Work Order cost estimate for Contracting Officer approval prior to execution.
| Installation Management | |||
| 18 | PWS CSC-26502 | Please clarify whether planned outages, shutdowns, or mission-sensitive work requiring after-hours execution will be: | |
| • | separately funded, | ||
| • | reimbursed at premium labor rates, | ||
| • | or included within the fixed-price scope. |
Examples include:
| • | electrical shutdowns, | |
| • | BAS cutovers, | |
| • | controls upgrades, | |
| • | cybersecurity maintenance windows, | |
| • | and utility interruptions. | The funding and reimbursement for planned outages, shutdowns, or mission-sensitive work requiring after-hours execution are determined by the category of the work being performed. |
Routine Maintenance and Minor Interruptions (Fixed-Price Scope) For routine preventative maintenance (PMO) or Demand Maintenance Orders (DMOs) that fall under the 32-hour and $2,000 total combined cost thresholds, after-hours execution is included within the fixed-price scope. In accordance with PWS Sections C4.4.1 and C2.4.7, the Contractor must arrange work to cause the least interference with Government business. If a minor electrical shutdown, cybersecurity patch, or utility interruption is required for a routine task, the labor is included in the fixed-price monthly maintenance CLINs, and premium labor rates are not separately reimbursed. The Contractor is expected to utilize the mandated Saturday shift (0700 to 1100) or other off-hours for these disruptive maintenance services.
Major Upgrades and Cutovers (Separately Funded PWOs) Major system modifications, such as controls upgrades, full BAS cutovers, or significant cybersecurity maintenance windows, generally exceed the DMO thresholds and are processed as Project Work Orders (PWOs) in accordance with PWS Section C4.4.8. PWOs are separately funded. If the Government explicitly directs these PWOs to be executed after hours to prevent tenant disruption, the Contractor may include negotiated premium labor rates or shift differentials in their PWO cost proposal for Contracting Officer approval prior to execution.
| Installation Management | |||
| 19 | PWS CSC-26502 | Please identify required contractor support expectations during: | |
| • | federal holidays, | ||
| • | weekends, | ||
| • | weather events, | ||
| • | and installation closures. | ||
| Please clarify whether premium holiday labor is reimbursable. | On-site presence is not required for routine work on Federal holidays. However, the Contractor must maintain standby status and be capable of physically responding on-site to emergency requisitions within two (2) hours, as defined in PWS Section C2.4.5. |
On-site coverage is required on Saturdays from 0700 to 1100 utilizing alternating FTE schedules (PWS Section C2.4.7). Outside of those hours, the Contractor must maintain standby status and respond on-site to Priority 1 (Emergency) DMOs within one (1) hour of receipt or after-hours approval (PWS Sections C5.1.1 & C4.4.7.1.1).
If the Contractor determines weather conditions are unsafe for continued operations, they must notify the KO/COR/ACOR within twelve (12) hours of the suspension. Operations must resume immediately upon weather clearance and KO/COR approval (PWS Section C2.4.3).
For DMOs and emergencies, premium holiday labor is not reimbursable. The cost of maintaining on-call/standby personnel on Federal holidays to meet the 2-hour emergency response requirement must be built into the Contractor's monthly firm-fixed-price proposal.
| For PWOs, if the Government explicitly directs a Project Work Order (PWO) to be executed on a Federal holiday, the Contractor may propose negotiated premium holiday labor rates within their PWO cost estimate for KO approval prior to execution | Installation Management | ||
| 20 | PWS CSC-26502 | Please clarify whether the contractor is required to maintain full-time onsite, or on-call staffing for: | |
| • | HVAC, | ||
| • | electrical, | ||
| • | BAS/controls, | ||
| • | plumbing, | ||
| • | kitchen equipment, | ||
| • | or cybersecurity personnel. |
If required, please specify:
| • | required labor categories, | |
| • | coverage periods, | |
| • | and response expectations. | The Government expects the Contractor's Staffing Plan to provide full-time, on-site coverage during normal duty hours for the core critical facilities disciplines: HVAC, Electrical, BAS/Controls, and Plumbing. Offerors must demonstrate how their proposed staffing model ensures uninterrupted performance, routine maintenance execution, and rapid response to daily operational needs across these specific systems. |
Full-time on-site coverage is not expected for Kitchen Equipment or Cybersecurity support. The Contractor may propose on-call, dispatch, or scheduled subcontractor support for these specific disciplines, provided all PWS performance metrics, regulatory certifications, and emergency response times are strictly met.
| Outside of normal duty hours, continuous on-site coverage is not required for any discipline. The Contractor must provide on-call and standby coverage capable of meeting the mandatory one-hour on-site response time for Priority 1 Emergency service calls, as established in PWS Section C4.4.7.1.1. | Installation Management | ||
| 21 | PWS CSC-26502 | Please identify any mission-critical facilities, systems, or operations requiring enhanced response capability or priority restoration. |
Please clarify whether:
| • | accelerated response times, | ||
| • | dedicated staffing, | ||
| • | or after-hours support | ||
| are required for these areas. | Building 20 takes priority of other facilities unless directed by COR/KO. However there is no additional support required. | Installation Management | |
| 22 | PWS CSC-26502 | Please clarify whether cybersecurity support under Section C.6 requires: | |
| • | after-hours monitoring, | ||
| • | off-shift patching, | ||
| • | emergency cyber response, | ||
| • | or weekend maintenance windows. | ||
| Please identify whether these activities are included within the fixed-price scope. | Operational hours, including any requirements for after-hours monitoring, off-shift patching, emergency response, or weekend maintenance, are site-specific and depend entirely on the operational needs of each individual DLA site. Offerors must review the specific site requirements and operational hours outlined in the PWS. Any required after-hours, maintenance, or emergency support specified for a given site is considered within the fixed-price scope of support for that site. | J6 | |
| 23 | PWS CSC-26502 | Please clarify the Government approval process for: | |
| • | overtime, | ||
| • | premium labor, | ||
| • | weekend work, | ||
| • | holiday work, | ||
| • | and emergency after-hours support. |
Please identify:
| • | approving authority, | |
| • | notification requirements, | |
| • | and funding authorization procedures. | The Contracting Officer is the sole approving authority who can bind the Government to additional costs. All premium labor, overtime, weekend, and holiday work must be authorized in writing by the Contracting Officer prior to execution. For standard Project Work Orders, funding is authorized via a formal contract modification. For emergency after-hours support, the Contracting Officer or COR may verbally authorize emergency response up to a specified Not-To-Exceed limit, which must subsequently be formalized and funded. The Government is not liable for premium or emergency labor costs incurred without prior proper authorization. |
All requests for planned premium labor, overtime, weekend, or holiday work must be submitted in writing to the COR and the Contracting Officer. This notification must include a justification of necessity, estimated labor hours, and an estimated cost breakout. For emergency after-hours support that exceeds the routine fixed-price thresholds, the Contractor must provide immediate notification to the COR, followed by an estimated cost of work within 24 hours for budgeting and Not-To-Exceed authorization purposes
| Installation Management | |||
| 24 | PWS CSC-26502 | Please clarify whether utility interruption work must be performed: | |
| • | after hours, | ||
| • | during weekends, | ||
| • | or during designated maintenance windows. | ||
| Please identify whether associated premium labor is separately reimbursable. | The Contractor shall schedule and arrange work to cause the least interference with the normal occurrence of Government business and mission. |
Premium labor for routine utility interruptions is not separately reimbursable. If the interruption is part of a routine preventative maintenance task or a Demand Maintenance Order that falls under the $2,000 total combined cost and thirty-two labor hour thresholds, the effort is entirely included within the fixed-price scope. The Contractor must absorb any after-hours or weekend labor costs associated with these routine shutdowns into their firm-fixed-price proposal.
| If the utility interruption is part of a major system upgrade or replacement that exceeds the $2,000 total combined cost or thirty-two labor hour thresholds, it is processed as a separately funded Project Work Order. If the Government explicitly directs the Project Work Order to be executed after hours to prevent tenant disruption, the Contractor may propose negotiated premium labor rates within their cost estimate for Contracting Officer approval prior to execution. | Installation Management | ||
| 25 | PWS CSC-26502 | Please identify whether maintenance activities affecting occupied or mission-critical spaces are restricted to: | |
| • | nights, | ||
| • | weekends, | ||
| • | holidays, | ||
| • | or other designated outage windows. | The Contractor shall schedule and arrange work to cause the least interference with the normal occurrence of Government business and mission. While standard maintenance should occur during normal operating hours, there may be times where off-hours execution will be necessary due to mission requirements. This work should be scheduled to the maximum extent possible during the designated Saturday shift from 0700 to 1100. |
| For routine maintenance and Demand Maintenance Orders that fall under thirty-two (32) labor hours and the $2,000 total combined cost thresholds, any necessary off-hours work must be absorbed within the firm-fixed-price contract. For major upgrades or replacements exceeding these thresholds, the work will be executed as a Project Work Order, and any required off-hours labor rates may be negotiated and separately funded. | Installation Management | ||
| 26 | PWS CSC-26502 | Please clarify whether minimum onsite staffing levels are required during: | |
| • | normal duty hours, | ||
| • | evenings, | ||
| • | weekends, | ||
| • | and holidays. | ||
| If so, please identify required labor categories and staffing quantities. | During normal operating hours, the Contractor must provide adequate staffing to ensure uninterrupted performance and full-time, on-site coverage for core critical facility disciplines, including HVAC, Electrical, Plumbing, and BAS/Controls. With the exception of the two (2) Electricians for Building 20, the Government does not dictate specific staffing quantities for these trades; rather, offerors must propose their optimal headcount and labor mix in their C5.1 Staffing Plan. |
The on-site staffing hours must be covered by a combination of shifts (for example, some employees working 0700 to 1530 and others working 0730 to 1600) to ensure continuous coverage throughout the day.
On Saturdays, the Contractor is required to maintain the minimal staffing necessary to successfully perform basic operations checks and execute any required off-hours maintenance, in accordance with PWS Section C2.4.7. The specific labor categories and quantities for this shift are not mandated by the Government but must be determined and proposed by the Contractor to satisfy this specific performance objective.
Outside of standard operating hours, there are no mandatory on-site staffing level quantities. The Contractor is not expected to have employees working unless there is an emergency. However, the Contractor must maintain on-call and standby coverage.
| On-site presence is not required for routine work on Federal holidays. The Contractor is not expected to have employees working unless there is an emergency. However, the Contractor must maintain on-call and standby coverage. | Installation Management | ||
| 27 | PWS CSC-26502 | Please clarify contractor support requirements during: | |
| • | snow events, | ||
| • | severe weather, | ||
| • | installation emergencies, | ||
| • | utility failures, | ||
| • | and continuity operations. | ||
| Please clarify whether extraordinary labor associated with these events is reimbursable. | Contractor personnel must report on-site and maintain operations during severe weather and snow events. If the Contractor determines conditions are unsafe to travel or continue operations, they must immediately notify the Contracting Officer or COR to request approval to suspend operations. If granted, operations must resume immediately upon weather clearance or Government direction. |
The Contractor is required to support installation emergencies and Continuity of Operations plans. This includes participating in exercises, executing emergency recall procedures, and maintaining personnel accountability. During an actual emergency or continuity activation, the Contractor must follow all procedures directed by the KO/COR to ensure critical facility systems remain operational.
In the event of an unplanned utility failure, the Contractor must act immediately to troubleshoot, check backup systems, and restore services, and must provide a verbal report to the KO/COR within one hour. The initial troubleshooting, system resets, and routine repairs associated with utility failures are included within the fixed-price scope.
| If severe weather, an emergency, or a utility failure causes physical damage requiring extraordinary labor that exceeds the Demand Maintenance Order thresholds (thirty-two labor hours or $2,000 in total combined costs), the repair work will transition into a separately funded Emergency Project Work Order to ensure rapid facility stabilization. | Installation Management | ||||
| 28 | PWS CSC-26502 | Please clarify whether remote diagnostics, BAS monitoring, or cybersecurity support may satisfy after-hours response requirements in lieu of onsite presence. | External remote access (i.e., from outside the physical installation or DLA network boundary) is highly restricted and not authorized as a standard operating procedure. Exceptions for external remote access require extraordinary justification and high-level security approval, which are typically reserved only for severe mission-critical emergencies. Therefore, Offerors should not propose or rely upon external remote support to satisfy standard after-hours response requirements; an onsite presence (or access from within the approved DLA boundary) remains the baseline expectation. | Installation Management | |
| 29 | PWS CSC-26502 | Please clarify whether shift differential or premium labor rates are reimbursable for Government-directed off-shift work. | No separate reimbursement or premium labor rates will be paid for work categorized as Demand Maintenance Orders (DMOs). In accordance with PWS Section C2.4.7, the Contractor is required to maintain varying schedules and provide personnel at all other times to handle emergencies (Priority 1) or scheduled after-hours work. The costs associated with responding to off-shift, weekend, or holiday DMOs (which are capped at thirty-two (32) labor hours and $2,000 in total combined costs per event) must be fully burdened and included within the Contractor's firm-fixed-price proposal for Maintenance Labor (CLIN 0003). |
If the Government initiates a Project Work Order (PWO) and explicitly directs that the work be performed outside of normal operating hours (e.g., to prevent tenant disruption per PWS Section C4.4.1), the Contractor may include applicable shift differentials or premium labor rates in their PWO cost estimate. Per PWS Section C4.4.8.1 (Execution of PWO Work), the Contractor must provide a detailed proposal addressing the scope, schedule, and proposed price, supported by detailed labor and material estimates. These rates will be reviewed, negotiated, and approved by the Contracting Officer on a case-by-case basis.
| The Government is not liable for any premium, overtime, or shift differential labor costs incurred by the Contractor without prior written authorization from the Contracting Officer. For routine operations under the fixed-price maintenance scope, the Contractor is expected to manage their staffing and scheduling to minimize the need for premium hours while still satisfying the mandatory response times. | Installation Management | ||
| 30 | PWS CSC-26502 | Please clarify the distinction between: | |
| • | routine corrective maintenance included in the fixed-price scope, and | ||
| • | repair/replacement work requiring separately authorized service orders or task orders. |
Please identify:
| • | dollar thresholds, |
| • | labor-hour thresholds, |
| • | equipment size thresholds, |
| • | or replacement criteria |
| used to determine when work becomes “additional work.” | The distinction between routine corrective maintenance (Demand Maintenance Orders - DMO) and separately authorized "additional work" (Project Work Orders - PWO) is determined by the specific labor-hour and dollar thresholds established in PWS Section C4.4.7. |
| Work is considered included in the fixed-price scope if it meets the definition of a DMO. Work becomes "additional work" (PWO) when it exceeds any one of the established criteria | Installation Management | ||
| 31 | PWS CSC-26502 | Is there a maximum individual material or repair-part cost that is considered included in the fixed-price contract? |
If so, please identify:
| • | per-part threshold, | |
| • | per-event threshold, | |
| • | annual threshold, | |
| • | or per-system threshold. | The distinction between routine corrective maintenance included in the fixed-price scope (Demand Maintenance Orders) and separately authorized "additional work" (Project Work Orders) is determined by the specific labor-hour and total cost thresholds established in PWS Section C4.4.7. Unscheduled corrective maintenance or repair is classified as a DMO and included in the fixed-price maintenance scope if the estimated labor does not exceed thirty-two (32) hours or the total estimated cost (combined labor and materials) does not exceed $2,000. |
There are no physical equipment size thresholds (such as tonnage, horsepower, or voltage) used to determine when a repair becomes additional work. The scope of a repair is evaluated solely by the estimated labor-hours and total combined cost required to resolve the specific failure, regardless of the physical size of the machine or system being repaired.
| Standard replacement of parts, components, and minor units is included in the fixed-price scope as long as the work stays within the 32-hour and $2,000 limits. However, major system replacements, facility modernizations, and new installations are excluded from the routine fixed-price scope because they naturally exceed these thresholds. If the Contractor determines during the execution of a DMO that the task will breach either limit, they must stop work immediately and follow the conversion procedures in PWS Section C4.4.8.2. | Installation Management | ||
| 32 | PWS CSC-26502 | Please confirm whether replacement of major equipment is excluded from the fixed-price scope and performed through separately authorized service orders/task orders. |
Examples include:
| • | chillers | |||
| • | compressors | |||
| • | boilers | |||
| • | pumps | |||
| • | cooling towers | |||
| • | VFDs | |||
| • | BAS servers | |||
| • | PLCs | |||
| • | transformers | |||
| • | switchgear | |||
| • | large motors | |||
| • | heat exchangers | The replacement of major equipment is excluded from the routine firm-fixed-price scope based on the cost and labor thresholds defined in the PWS, rather than by a categorical list of equipment. | Installation Management | |
| 33 | PWS CSC-26502 | Please clarify whether compressor replacements and motor replacements are considered: | ||
| • | routine corrective maintenance, | |||
| • | repair work under fixed fee, | |||
| • | or separately authorized additional work. | |||
| If included, please define applicable size/HP/value thresholds. | The replacement of major equipment is excluded from the routine firm-fixed-price scope based on the cost and labor thresholds defined in the PWS, rather than by a categorical list of equipment. | Installation Management | ||
| 34 | PWS CSC-26502 | Please clarify which BAS/FRCS/ICS hardware components are included in the fixed-price scope. |
Specifically:
| • | controllers |
| • | sensors |
| • | actuators |
| • | gateways |
| • | network switches |
| • | servers |
| • | workstations |
| • | firewalls |
| • | licensing |
| • | supervisory software |
| Please identify which items are Government Furnished versus Contractor Furnished. | The division of responsibility for the listed components is generally as follows: |
1. Standalone (Non-Networked) Systems:
If the Contractor's proposed solution requires a standalone, non-networked system, the Contractor is fully responsible for furnishing and maintaining the entire system, including both the Operating System (OS) and all applications.
2. Networked Systems / General Division of Responsibility:
For systems residing on the Government network, responsibility is divided between the OS/Infrastructure layer and the Application layer:
Contractor Furnished/Responsible (Application Layer - Included in fixed-price scope):
Controllers Sensors Actuators Vendor application licensing Vendor-specific supervisory software and applications
Note: The Contractor is responsible for maintaining and applying STIGs to all vendor-specific applications.
Government Furnished Equipment/Responsible (OS & Infrastructure Layer):
Gateways Network switches Servers Workstations Firewalls
Note: The Government is responsible for furnishing, upgrading, updating, and applying STIGs for these GFE items, including the underlying Operating Systems.
Exceptions: While rare and highly unlikely, if a specific site or networked solution requires Contractor-furnished servers, the Contractor would then assume full responsibility for those servers. Otherwise, the baseline assumption is that servers and standard network infrastructure are GFE.
| Installation Management | ||||
| 35 | PWS CSC-26502 | C.6 | Please clarify whether cybersecurity-related hardware/software required for compliance with Section C.6 is: | |
| • | Government Furnished, | |||
| • | contractor provided within the fixed fee, | |||
| • | or separately funded through service orders/task orders. |
Examples:
| • | antivirus licensing | |
| • | vulnerability scanning tools | |
| • | OT monitoring tools | |
| • | network segmentation hardware | |
| • | switches/firewalls | |
| • | cybersecurity software renewals | Responsibility for cybersecurity-related hardware and software is aligned with the standard GFE/CFE boundaries, specifically based on network connectivity and the OS vs. Application layer: |
1. Standalone (Non-Networked) Systems:
If the solution is standalone, both the Operating System (OS) and all applications (including any required local cybersecurity tools) are maintained by the vendor.
2. Networked Systems / General Division of Responsibility:
Government Furnished / Funded (OS & Infrastructure Layer):
Antivirus Licensing & Vulnerability Scanning Tools: Provided by the Government for systems on the network (e.g., ACAS, enterprise host-based security tools).
Network Segmentation Hardware, Switches, and Firewalls: Furnished and maintained by the Government.
Software Renewals (Government-owned): The Government is responsible for renewing licenses for all Government-provided (GFE) software, OS licenses, and enterprise tools.
Contractor Furnished / Funded (Application Layer - Within Fixed-Price Scope):
Vendor-Specific Software & Applications: The Contractor is responsible for the provisioning, licensing, maintenance, and renewals of any contractor-proposed or vendor-specific applications/supervisory software.
Clarification Required from Offeror:
| OT Monitoring Tools: To provide a definitive response on "OT monitoring tools," the Offeror must clarify what specific monitoring tools are being referenced. If they monitor the network/OS, they fall under Government purview; if they are vendor-specific application performance monitors, they fall under the Contractor's purview. | J6 | ||
| 36 | PWS CSC-26502 | Please clarify whether refrigerant costs are included in the fixed-price scope. |
If included:
| • | are there quantity thresholds, | |
| • | leak-loss thresholds, | |
| • | or major-event exclusions? | Yes, refrigerant costs are included in the firm-fixed-price scope, subject to the Demand Maintenance Order (DMO) thresholds. In accordance with PWS Section C4.4.7, all materials, including refrigerants, and labor required to make systems function properly are included in the fixed price for CLIN 0003 and CLIN 0004, provided the individual repair event does not exceed thirty-two (32) labor hours and the total combined cost of labor and materials does not exceed $2,000. If a repair requiring refrigerant exceeds either of these thresholds, the quantity required exceeds the fixed-price scope, and the event must be processed as a separately funded Project Work Order (PWO). |
The Contractor must strictly adhere to the EPA refrigerant management requirements detailed in PWS Section C9.5.5. The Contractor is required to identify and repair leaks that exceed applicable EPA thresholds, such as ten percent for comfort cooling, twenty percent for commercial refrigeration, and thirty percent for Industrial Process Refrigeration, within thirty days of adding refrigerant. Furthermore, per PWS Section C9.5.5.7, the Contractor must notify the COR and DPW Environmental if any appliance leaks one hundred twenty-five percent or more of its full charge in one calendar year.
A major refrigerant loss event caused by a catastrophic equipment failure that exceeds the $2,000 total combined cost or 32 labor-hour DMO thresholds will be excluded from the fixed-price scope and treated as additional work via a PWO. However, this exclusion only applies if the loss was not the direct result of Contractor negligence, such as a failure to perform scheduled preventative maintenance, a failure to repair a known leak within the mandated thirty-day window, or the improper handling of refrigerants by Contractor personnel.
| Installation Management | ||
| 37 | PWS CSC-26502 | Please clarify whether catastrophic equipment failures or major utility events are considered additional work. |
Examples:
| • | major refrigerant loss | |
| • | flood damage | |
| • | fire damage | |
| • | catastrophic pump failure | |
| • | major electrical faults | |
| • | BAS network failure | Yes, catastrophic equipment failures and major utility events (such as the examples provided) are considered additional work, provided they exceed the routine maintenance and repair thresholds defined in the contract and are not the result of Contractor negligence. |
In accordance with PWS Section C4.4.7, routine corrective maintenance covers work where the estimated labor does not exceed thirty-two (32) hours and the total estimated combined cost of labor and materials does not exceed $2,000. Because catastrophic failures and major utility events naturally require repairs or replacements that exceed these thresholds, they fall outside of the fixed-price DMO scope and must be processed as Project Work Orders (PWOs) or Emergency PWOs in accordance with PWS Section C4.4.8 and Section C4.4.8.3. Emergency PWOs are separately funded, and the Contracting Officer or COR can immediately authorize the Contractor to begin stabilization and repair work under a Not-To-Exceed budget to protect personnel and property.
| The Contractor will be held fully liable for the costs of repairing or replacing equipment damaged during a catastrophic event or utility failure if the incident is determined by the Government to be the direct result of Contractor negligence. If the failure or damage occurred because the Contractor failed to perform required preventative maintenance, failed to safeguard the facilities, or ignored documented system alarms, the entire cost of the emergency response and repair must be borne by the Contractor at no additional cost to the Government. | Installation Management | ||
| 38 | PWS CSC-26502 | Please identify: | |
| • | systems currently at end-of-life, | ||
| • | unsupported BAS platforms, | ||
| • | obsolete controllers, | ||
| • | unsupported firmware/software, | ||
| • | or systems requiring modernization. | ||
| Please clarify whether lifecycle replacement costs are separately funded. | The Government does not provide a pre-compiled list of end-of-life systems, unsupported BAS platforms, obsolete controllers, or unsupported firmware/software. The successful Contractor is required to conduct a comprehensive baseline assessment post-award to identify these components. |
The labor associated with performing this baseline assessment is included within the Contractor's fixed-price scope. Physical lifecycle replacement and modernization costs for Government-furnished (GFE) systems and hardware identified during the baseline will be funded separately by the Government (subject to availability of funds), as the procurement of new GFE is not within the Contractor's fixed-price scope.
Ongoing Maintenance of Replaced/Modernized Systems:
Following any modernization or replacement, ongoing maintenance responsibilities are divided as follows:
Standalone Systems: If the system is standalone, both the Operating System (OS) and all applications are maintained by the vendor.
| Networked Systems: If the system is on the network, anything OS or infrastructure-related is maintained by the Government, while anything application-related is maintained by the vendor. | Installation Management | |||
| 39 | PWS CSC-26502 | C.6 | Please clarify whether Section C.6 cybersecurity requirements are intended as: | |
| • | compliance sustainment only, | |||
| • | RMF package maintenance, | |||
| • | continuous monitoring, | |||
| • | vulnerability remediation, | |||
| • | or active cybersecurity operations. | The cybersecurity requirements in Section C.6 are comprehensive. The scope includes all listed activities—compliance sustainment, RMF package maintenance, continuous monitoring, and vulnerability remediation—as they are integral components of maintaining the overall cybersecurity posture for the covered systems | J6 | |
| 40 | PWS CSC-26502 | Please clarify whether the contractor is responsible for: | ||
| • | obtaining ATOs, | |||
| • | maintaining ATOs, | |||
| • | updating RMF packages, | |||
| • | conducting scans, | |||
| • | producing artifacts, | |||
| • | or only supporting Government cybersecurity personnel. | The Contractor serves in a supporting role to Government cybersecurity personnel. Specifically: |
ATOs & RMF Packages: The Contractor does not directly obtain or "own" the ATO. The Contractor is responsible for supporting the Government team that leads the ATO effort by providing the required deliverables and artifacts as outlined in the PWS and awarded contract.
| Scanning: The Government conducts routine vulnerability scans for all networked equipment currently in operation. However, the Contractor is responsible for scanning their own systems and equipment prior to installing them and bringing them to the site, regardless of whether the system will be networked or standalone. | J6 | ||
| 41 | PWS CSC-26502 | Please clarify the scope of contractor responsibility for STIG compliance. |
Specifically:
| • | Does the contractor perform remediation? | |
| • | Does the Government provide scanning tools? | |
| • | Are contractor personnel expected to remediate all findings? | |
| • | Are there existing POA&M items? | Contractor responsibility for STIG compliance aligns with established maintenance boundaries: |
Remediation & Scope:
Networked Systems: The Government handles STIG remediation for the Operating System (OS) and network infrastructure. The Contractor is responsible for remediating all findings related to vendor-specific applications and software.
Standalone Systems: The Contractor is fully responsible for remediating all STIG findings for both the OS and the applications.
Note: Occasional Government assistance may be provided if Government applications or hardware are determined to be the root cause of an issue impacting Contractor systems.
Scanning Tools: As previously noted, the Government provides vulnerability scanning (and tools) for active networked/GFE equipment. The Contractor is responsible for scanning their own systems prior to implementation and site installation.
Existing POA&Ms: If applicable, the Government maintains the Plan of Action and Milestones (POA&M). Currently, there are no existing POA&M items for this requirement.
| J6 | |||
| 42 | PWS CSC-26502 | Please clarify the intended use of service orders/task orders for: | |
| • | corrective maintenance, | ||
| • | emergency repairs, | ||
| • | replacement work, | ||
| • | and modernization projects. |
This is the start of the file's text. The full file is on GovTribe.