Attachment 8 -KTR Removal Empty ROB or Vac Box.pdf

PDF 45 KB Posted

Attached to
Regional Hazardous Waste Disposal Contract for Columbus, Campbell, Knoxville
Solicitation number
SP450024R0004
Issued by

About this file

This document contains a contractor surveillance checklist for the placement or removal of empty roll-off boxes or vacuum boxes, as well as information on a related regional hazardous waste disposal solicitation. The checklist is used to inspect contractor work and equipment for jobs involving empty rental container exchange. It addresses arrival time and equipment, weight tickets, container condition, operation and safety.

The combined synopsis/solicitation seeks hazardous and non-hazardous waste disposal services for military installations in Kentucky, Ohio, Tennessee and West Virginia, or within 50 miles of listed pickup points. Services include waste removal, transportation and disposal. The solicitation number is SP450024R0004 and was issued by the Defense Logistics Agency for a regional hazardous waste contract serving Columbus, Campbell and Knoxville.

View the file

Other files

Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Contractor Work Surveillance Checklist

Placement or Removal of Empty Rented Rolloff Box (ROB) or Vacuum Box

Date(s) of Work Surveillance: _________________ Start Time: ___________ Stop Time: ___________

Contract Number: SP4500-______-D-___________ TO #: ________________ CLIN: ______________

Name of Designated Government Representative: ___________________________________________

Title of Designated Government Representative: ____________________________________________

Phone Number of Designated Government Representative: (______) _______-___________ Ext.______

Yes No N/A Description of Contractor Work Surveillance: [ROB] or [Vac Box] (Circle one)

Did the Contractor arrive on site at the scheduled time and date?

Did the Contractor arrive on site with all of the requisite equipment, including

- One ROB or Vacuum Box container of the appropriately ordered size, with

- One plastic liner of sufficient size and thickness to adequately contain the waste for which it was intended (ROB only), and

- One watertight tarp cover that was generally free of rips and tears (ROB only)?

Does the Contractor have an approved weight ticket showing the empty (tare) weight of the container?

Was the container inspected by a Designated Government Representative upon arrival at the designated location?

Was the container of acceptable appearance and integrity, with minimal evidence of corrosion, visibly void of waste residue and legible/offensive graffiti upon delivery?

Was the ROB, bows and cover free of any defects or damage, other than those attributable to normal wear and tear, and determined acceptable for Government use? Please document below any noteworthy defects or damage and have driver initial for acknowledgment.

Note: Failure of the driver to acknowledge any existing noteworthy defects or damage will be cause for rejection of the ROB and liner.

Did the equipment operate properly without causing a delay in work?

Was the work performed safely and did the equipment meet the satisfaction of the Designated Government Representative?

Comments:

Signature of Designated Government Representative Date