About this file

This document is an amendment to a solicitation for inspection, maintenance, and repair services for fire protection systems at the Defense Distribution Center in Susquehanna, Pennsylvania. The amendment answers two questions from vendors regarding qualifications for the project manager and quality control manager positions. For the project manager, the prime contractor must employ the individual and they must have a NICET level III certification in fire protection, along with other requirements. The quality control manager is not required to have any cybersecurity certification. All other terms and conditions of the original solicitation remain unchanged.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

1. CONTRACT ID CODE

2. AMENDMENT/MODIFICAITON NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicble)

7. ADMINISTERED BY (If other than Item 6) CODE

STANDARD FORM 30 (REV. 10-83)

Prescribed by GSA FAR (48 CFR) 53.243

FACILITY CODE

9A. AMENDMENT OF SOLICIATION NO.

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NO.

10B. DATED (SEE ITEM 11)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended, is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a)By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment your desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPIRATION DATA (If required)

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15C. DATE SIGNED

15A. NAME AND TITLE OF SIGNER (Type or print)

16C. DATE SIGNED

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

PAGE OF PAGES

6. ISSUED BY CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) (X)

CODE

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

NSN 7540-01-152-8070

Previous edition unusable

SP3300-21-R-0001

Amendment 0001

Amendment 0001 is incorporated into solicitation SP3300-21-R-0001.

Amendment 0001 is being issued to answer vendor questions seen below.

Vendor Questions:

Question 1: Reference page 26 of the SOW paragraph 12.1.1 12.1.2. Can a GC Project Manager manage the operations of the contract while the Fire Protection Specialist PM hold the NICET level III and manage the onsite work?

Answer 1: No, the Project Manager must be employed by the prime contractor and must have the referenced NICET certification (as well as meeting the other requirements in 12.1).

Question 2: Reference page 29 of the SOW paragraph 12.3.1. Does the QCM need any level of Cyber security certification?

Answer 2: No, the only position requiring the cybersecurity certification is the ‘IT Personnel’ required in Section 12.5, which is the position performing work under Section 17.0. The QCM will oversee this position but is not required to hold any level of Cybersecurity certification.

All other terms and conditions remain unchanged.

Amendment 0001
Amendment 0003
Amendment 0002
Amendment 0001
Amendment 0001
Amendment 0001
Amendment 0001

Amendment 0001 wording

IDCode:
Page: 1
Pages: 2
AmendNo: 0001
EffDate: 30-Aug-2021
ReqNo: N/A
ProjNo:
IssCode: SP3300
IssuedBy: DLA DISTRIBUTION

ACQUISITION OPERATIONS J7-AB

5404 J AVENUE BUILDING 404

NEW CUMBERLAND PA 17070-5059

AdmCode: SP3300
AdminBy: JOSHUA WOODWORTH

717-770-4192 joshua.woodworth@dla.mil

ContName:
ContStrt:
ContCnty:
ContSt:
ContZIP:
Code:
FacCode:
SolChgYs: Yes
SolChgNo: Off
SolAmdNo: SP3300-21-R-0001
AmendDate: 06-Aug-2021
ModNo:
ModDate: 05 JUL 20
NoCopies: 1
Amended: Yes
OffrExt: Off
OffrNoEx: No
ApprData:
ChgeOrd: Off
ChgeOrder:

File details come from the government source that posted it. Updated .