SP330018R0002
AMENDMENT 0001
ATTACHMENT 9 - REVISED - STATEMENT OF WORK
STATEMENT OF WORK
Extend Arms Room – Public Safety Center
Building 235 - DLA San Joaquin, Tracy Site
16 June 2017
REVISED – 4/25/2018
1. PROJECT DESCRIPTION:
This Statement of Work (SOW) details the requirements associated with the project to Extend Arms
Room inside the Public Safety Center, Building 235. Contractor shall furnish and provide all labor, material, equipment, and supervision to extend the Arms Room at DLA Defense Distribution Depot San
Joaquin in accordance with plans and specifications.
2. OBJECTIVES:
The purpose of this project is to renovate the existing Arms Room at DLA – San Joaquin Public Safety
Center, Building 235. The renovation will provide a larger Arms Room, a Weapon’s Cleaning Room, and new offices for Police and Security personnel.
3. BASE BID REQUIREMENTS:
3.1. CLIN 0001 – Extend/Renovate Arms Room, Building 235
3.1.1. Demo exiting metal stud wall separating Copy Room 194 and Storage Room 195. Casework in Copy Room 194 shall be remove and reset. Laminate counter top, three (3) base cabinets and three (3) wall cabinets to be reused. The remaining shall be disposed.
3.1.2. Remove existing sheetrock from walls Per Appendix 1 Sheet AD-101. Sheetrock in Section
MGR Room 197 connecting to Arms Room CMU walls need not be removed.
3.1.3. Remove doors, doorframes, openings, and hardware per Appendix 1 Sheet AD-101. Door panel and hardware shall be salvage for reuse. REX, BMS, and LENEL Card Reader at
Room 195 shall also be removed and reused. Coordinate with Proposed Floor Plan, A-101.
3.1.4. Remove existing 2’x4’ light fixture. Light fixture shall be turned over to the government.
3.1.5. Relocate supply diffuser in Copy Room 194. Coordinate with Mechanical Plan, M-101.
3.1.6. Remove and Relocate occupancy sensor. Coordinate with Lighting Plan, E-101.
3.1.7. Remove and relocate light switch. Coordinate with Lighting Plan, E-101.
3.1.8. Remove existing floor finish in Copy Room 194, Section Mgr 197, and Arms Room 196. All flooring base and subbase in Room 197 and Arms Room 196 shall also be remove.
3.1.9. Reconfigure sprinkler heads and piping. Coordinate with Proposed Floor Plan and Fire
Protection Plan, A-101 and F-101 respectively.
3.1.10. Relocate existing fire extinguisher and cabinet. Coordinate location with new floor plan.
3.1.11. Construct new metal stud wall and door at north wall (plan north) of Room 195. Install salvaged door panel, hardware, REX, BMS, and LENEL Card Reader to Door 195. Door frame to be new metal frame.
3.1.12. Arms Room 196B walls and floors shall be constructed with new 3/16” expanded metal, 4.27
PSF Min. grid opening 1” x 3” Max fasten to metal stud and floor slab. Expanded metal to extend and secured to roof deck above. Sheetrock and finish per schedule.
3.1.13. Arms Room 196A floors shall be constructed with new 3/16” expanded metal, 4.27 PSF Min.
grid opening 1”x3” Max fasten to floor slab. Expanded metal to extend and secured to intersecting wall stud. Floor finish per schedule.
3.1.14. Provide and install drop ceiling tiles and grids for Room 194 to match existing drop ceiling in Room 195.
3.1.15. Provide and install five (5) stools for Room 195.
3.1.16. Provide and install new metal shelving with lockable cage doors in Room 195 per A-102.
3.1.17. Provide new LED light fixture per Lighting Plan, E-101.
3.1.18. Provide new electrical duplex receptacle (quadplex where occur) and data outlet per Power
Plans, E-101.
3.1.19. Provide and install new fully recessed sprinklers per Fire Protection Plan, F-101.
3.1.20. Provide and install new plumbing fixture per Plumbing Plan and mechanical equipment/devices including two (2) new exhaust fan and hood above weapon cleaning station per Mechanical Plans, M-101. Exhaust fan may be one (1) each per hood or two (2) each per hood so long as the CFM requirements are met.
3.1.21. All penetrating conduits, ducts, or pipes through walls shall be sealed per details provided in
Sheet A-503.
3.1.22. Provide one (1) new FM approve flammable liquid safety storage cabinet. Capacity shall be
12 gal minimum and the height shall be 32” max to fit under the stainless steel counter height.
4. DESIGN REQUIREMENTS:
1. Architectural - Develop design drawings, plans and details, of new walls, ceilings, floors, doors, frames, door hardware, finishes, casework, shelving, exhaust fan and hood, and the connection to existing structures.
2. Structural – Develop design and structural details, of new walls and connection to roofs and floors.
3. Mechanical - Develop design drawings, plans and details, of air distribution for new Arms Room and Weapon Cleaning, ductworks, penetrations, and diffuser/grilles. Contractor to determine
CFM requirements. New exhaust hood needs to have details drawings and show connections.
Contractor to verify wall support is able to handle the load of new exhaust hood.
4. Electrical/Telecom – Develop design drawings, plans and details, of new lighting, receptacle, IDS and data outlets; and configuration of existing light switch and occupancy sensors. Also, ensuring panels have enough load capacity.
5. Plumbing – Design of new water and waste lines for new sink. Provide plans and details of plumbing fixtures, pipping, valves, waste, vents, penetrations, and connection to existing pipping.
6. Fire Protection – Provide plans and details, for the reconfiguration of the sprinkler piping, new recessed sprinklers, horns/strobes, connection to the existing system. Ensure the new devices integrate and operable with existing system.
7. Develop demolition plans for the removal of the existing walls, floors, ceilings, casework, doors, frames, door hardware, lighting fixtures, switches, sensors, sprinkler heads, and air diffusers, etc.
to facilitate the installation of new equipment.
NOTE: The provided RFP drawings are for engineering use ONLY and NOT for construction.
Contractor is responsible to provide design drawings and submitting for approval.
DESIGN SCHEDULE:
1. Submit 95% document, including the calculations stated in the Design Requirements, within 8 weeks of written Notice To Proceed
2. In-house review within 2 weeks of 95% Document Submission
3. Submit 100% document within 2 weeks of first in-house review
4. In-house review within 2 weeks of 100% Document Submission
5. Submit final documents within 2 week of in-house final review
DESIGN AFTER AWARD DOCUMENTATION: Refer to specification section 01 33 16, Design
After Award for required documentation to be submitted after award. The Contractor shall provide a design schedule showing the duration of each section of the design process as defined in the referenced specification. The schedule shall include the number of days after Notice To Proceed until the 95% design review is to be held. Included in this duration is the allotted period of time that the
Government will have prior to the meeting for review of the submittal documents. The schedule shall show progress through Final Submission. After all Final Design Submission documents have been issued, the preconstruction meeting shall be scheduled not later than 14 days after this submission.
The Contractor shall coordinate the time and date of this meeting with the Contracting Officer.
Preconstruction meeting and submittal requirements are provided below.
5. SUBMITTALS:
5.1. Submittals are required for all material to be utilized and/or installed and shall be in compliance with the
Unified Facilities Guild Specifications (UFGS) and the basic contract. All submittals shall be approved prior to commencement of work. Submittals shall include but are not limited to the following:
5.1.1. Task Specifics: Quality Control Plan, Hazard Analysis, and Safety/Health Plan.
5.1.2. Submittal Registers, Form 4288
5.1.3. Drawings: 2 hard copies half size (11”x17”) and 2 full size (22”x34”) sets of drawings; 1copy of
AutoCAD 2017 or newer drawings with all Xref files attached in each drawing and 1copy of the drawings and specifications in PDF format on CD/DVD.
5.1.4. Product data sheet and specifications.
5.1.5. Construction Schedule.
5.1.6. Waste Prevention Spreadsheet.
5.1.7. Others as required by specifications.
5.2. Preconstruction Meeting
5.2.1. Prior to the initiation of work, a meeting will be held with the Contractor, COR and Depot PM/PE to discuss matters of mutual interest concerning the task order. General conditions, work schedule, phasing and coordination, security, safety, permits, and other matters pertinent to work accomplishments will be discussed in this meeting.
6. GENERAL REQUIREMENTS:
6.1. All demolished materials shall be disposed of off DLA Defense Distribution Depot San
Joaquin property.
6.2. Contractor shall adhere to the specification attached as part of this project.
6.3. Job site shall be left in a clean and orderly condition, and all construction debris and excess materials shall be removed upon completion of the job. Contractor shall not use Government trash cans, dumpsters, or other waste receptacles.
6.4. Contractor is subject to all DLA Distribution Depot San Joaquin health and safety regulations, security requirements, and environmental requirements. Additional information will be provided at the time of a pre-construction meeting prior to any work.
7. ENVIRONMENTAL REQUIREMENTS:
7.1. Contractor to comply with attached Appendix 2 - Environmental Checklist.
7.2. Contractor shall complete the attach Appendix 3 - Waste Prevention Worksheet
8. SCHEDULE:
8.1. HOURS OF WORK: Contractor's working hours, which do not require a power outage, will coincide with working hours of Defense Logistics Agency, DDJC, a normal five (5) day, forty (40) hour week, Monday through Friday, from 7:00 A.M. to 4:30 P.M., except Federal holidays. Federal holidays are those days officially observed by the Federal Government.
Saturday holidays are observed on the preceding Friday and Sunday holidays the following Monday. New Year's Day, Martin Luther King Day, President's Day, Memorial Day, July Fourth, Labor Day, Columbus Day, Veterans Day, Thanksgiving Day, Christmas Day, and any other day as may be declared by the President to be a Federal holiday.
8.2. PERIOD OF PERFORMANCE: The Contractor shall complete work described in Section 3 of this Statement of Work 270 days after Notice to Proceed (NTP).
9. SECURITY AND BADGE REQUIREMENTS:
The Contractor shall be required to comply with all DLA Tracy entrance and security requirements. The installation will vet all contractors, including subcontractor, for criminal warrants before a contractor will be allowed to enter the installation or garrison.
9.1. Contractor’s Badge Requirements:
9.1.1. A minimum of one week prior to entry and initiation of work on Tracy Facilities, the Prime
Contractor shall submit a list of all prime and subcontractor employees including any other personnel required to perform work on the installation during the contract performance period. The list will include the name, driver’s license number, and state of issuance to the
Contracting Officer Representative who will request badges at the Security Operations Pass
& ID Office located in Building 29A. If personnel are added or changed during the contract performance period, a revised list is to be submitted 72 hours prior to any new employees’ arrival for work at the Tracy Facility.
9.1.2. Badges will be issued for the contract performance period not to exceed 179 day increments.
A check will be made periodically by Security on the status of these badges. Normally, on projects longer than 180 days, the COR will submit a request to Pass and ID and request new badges to ensure contract personnel are vetted semi-annually.
9.1.3. The Prime Contractor will be required to escort suppliers, vendors, or other one-time or occasional visitors to the project site. Notification will be given a minimum of 3 working days prior to arrival and include the name of the company, the Prime Contractor Company name responsible for the vendor, and the vendor representative if available. Security may refuse entry without this notification.
9.1.4. The Prime Contractor will ensure that all access control requirements are adhered to per the
DLA Defense Distribution Depot San Joaquin Physical Security Plan. Any questions or concerns will be routed through the COR to the Security Services Branch for clarification.
9.1.5. Any additional requirements from Physical Security and Emergency Installation Management will be addressed during the pre-construction meeting conducted by the COR.
9.2. Contractor shall comply with attached Security and Fire Department Checklist, Appendix 4 & 5 respectively.
10. DELIVERABLES: All Submittals shall be submitted to the Contracting Officer within 30 days after completion of work. All submittals shall be in both electronic and hard copies.
10.1. Product data sheet and Specifications.
10.2. Drawings and As-Built, PDF and CAD.
10.3. Relevant Calculations (i.e. structural, foundation, wind, earthquake, etc.)
10.4. Warranty
10.5. Operation and Maintenance Data
10.6. Final Inspection
11. AUTHORITIES
Only a warranted Contracting Officer (either PCO or ACO) acting within their delegated limits has the authority to issue modifications or otherwise change the term and conditions of this contract. If an individual other than the Contracting Officer attempts to make changes to the term and conditions of this contract the Contractor shall not proceed with the change and shall immediately notify the Contracting
Officer.
12. POINT OF CONTACT (POC):
DLA Project Manager: Phuoc Dang, PE / 209.839-4220 / Phuoc.dang@dla.mil
DLA COR: Joseph Orpilla / 209.839.4522 / Joseph.Orpilla@dla.mil
DLA COR: Douglas Betz / 209.839.4232 / Douglas.Betz@dla.mil
Attachments:
1. Appendix 1: RFP Drawings
2. Appendix 2: Environmental Checklist
3. Appendix 3: Waste Prevention Worksheet
4. Appendix 4: Security Department Checklist
5. Appendix 5: Fire Department Checklist
6. Appendix 6: Performance Management Checklist
7. Appendix 7: Specifications
8. Appendix 8: Public Safety Center As-Built
-END STATEMENT OF WORK-