About this file

Joint Base Charleston New Bulk Fuel Facility Schematic and background information.

View the file

Other files

File Type Posted
Amendment_0008_Question_SP0600-13-R-0526.pdf PDF
Amendment_0008_to_SP0600-13-R-0526.pdf PDF
DFSP_Charleston_-_JBC_-_PWS_-_Final_(As_of_22_Aug_2013).pdf PDF
Amendment_0007_Question_SP0600-13-R-0526.pdf PDF
Amendment_0007_to_SP0600-13-R-0526.pdf PDF
Operator_Qualification_Program_Plan.pdf PDF
Charleston-Pre_Proposal_Confer_Sign-in_Sheet.pdf PDF
SWPPP_DFSP _Charlestion _SC.pdf PDF
Amendment_0006_to_SP0600-13-R-0526.pdf PDF
Amendment_0005_Question_SP0600-13-R-0526.pdf PDF
Amendment_0005_to_SP0600-13-R-0526.pdf PDF
DLA_Energy_CY13_Pest_Management_Plan(amend_4).pdf PDF
Amendment_0004_Questions_SP0600-13-R-0526.pdf PDF
Amendment_0004_to_SP0600-13-R-0526.pdf PDF
Amendment_0003_to_SP0600-13-R-0526.pdf PDF
Amendment_0002_to_SP0600-13-R-0526.pdf PDF
Charleston_05-2473_rev_15.pdf PDF
Charleston_SSP_13-R-0526 _revised.pdf PDF
Attachment_6-_Joint_Venture _revised.pdf PDF
Attachment_2_WD_2005-3473_Rev_14.pdf PDF
Evaluation_Provisions _revised.pdf PDF
Attachment_5-_Past_Performance_Questionnaire _revised.pdf PDF
Attachment_1_DFSP_Charleston_-_JBC_-_PWS_-_Final__(06_Jun_2013).pdf PDF
Commerical_Sol__13R0526-revised.pdf PDF
Attachment_3_Offers_Submission_Package__13R0526-revised.pdf PDF
Attachment_4-_PP_Quest_and_Ref _revised.pdf PDF
Show all 26

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Jet A MILCON Project

Background

- Tanks 1-4 were originally constructed in the 1950s (Attach 1). Tanks 1 and 2 were the

Hydrants tanks with a capacity of 387K gallons. Tanks 3 and 4 were Maytag storage tanks with a capacity of 314K gallons. The total capacity of JB Charleston was 3.7M gallons of Jet A.

MILCON Project

- MILCON contract# N69450-12-C-1757 was awarded to on Mid-Eastern Builders (MEB) on 28

Sep 12 to with an estimated completion date of May 14 (Attach 2). The actual construction began Jan 13 with the demolition of Tanks 1-4. The project includes the new construction of:

three Jet A tanks, a pumphouse, a 10” transfer line, ground product tanks and offloading header, Jet A tank truck offloading headers, and an Operations building for DLA-Energy. New security fencing will be constructed to expand the controlled area around the new tank and facilities.

Tanks

- MEB will construct three new tanks. Tanks 1 and 2 will be the new Air Force operational tanks with a combined capacity of 40Mbbls (Attach 3). Tank 4 will be the new DLA-Energy storage tank with a capacity of 80Mbbls (Attach 4). Tank 5 is currently the DLA-Energy storage tank with a capacity of 50Mbbls. It is being used as an operational tank as well until project completion. This will change JB Charleston’s total shell capacity to 8M gallons, including the two flightline operating tanks.

Pumphouse

- DLA-Energy will get a new receipt/transfer pumphouse (Attach 5a - 5b). This pumphouse will filter the fuel coming in from the DFSP receipt line. It will also be capable of transferring fuel through the new 10” transfer line to the two flightline operating tanks. It will also be equipped with a pig receiver and a pig sender.

Transfer line

- A new 10” fuel transfer line will be constructed along Taxiway D (Attach 6). This will replace the existing line that runs under the new CES buildings currently being constructed. It will also be equipped with a pig receiver at Pumphouse 2.

Ground Product tanks and offloading header

- The existing ground product tanks and offloading system have been demolished. It will be replaced by two 12K gallon tanks and new offloading headers for each grade (Attach 7a-7b).

Jet A tank truck offloading header

- The existing headers will be replaced with three skid-mounted offloading headers (Attach 8).

DLA-Energy Operations building

- A new operations building will be constructed to house the DLA-Energy contractors (Attach 9).

There will be an office room, bathroom and a storage/workshop.

Attachment 1 (Tanks 1-4)

Attachment 2 (Tanks 1, 2, 4, Pumphouse (blue) and Operations building (red))

2 1

Attachment 3 (Tanks 1 and 2)

Attachment 4 (Tank 4)

Attachment 5a (Pumphouse schematic)

Attachment 5b (Pumphouse components)

Attachment 6 (Map showing new 10” transfer line)

Attachment 7a (Ground product tanks and offloading headers)

Attachment 7b (Ground Product tanks)

Attachment 8 (Jet A tank truck offloading header)

Attachment 9 (Operations building schematic)