SOW Repair Replace Roofs 9 Aug 2023 (2 pages).pdf

PDF 80 KB Posted

Attached to
Z1DA--656-19-314, Repair/Replace Roof Systems 2019 36C263-23-AP-4135
Solicitation number
36C26323B0003
Issued by

About this file

This scope of work document outlines requirements for a roof repair and replacement project at multiple buildings on the St. Cloud VA Health Care System campus. The contractor will furnish all labor, materials, tools and equipment to repair and replace several roofing systems, including shingles, flat roofs, insulation, fall protection, flashing, gutters and parapet walls. Standard work hours are 8am to 4:30pm Monday through Friday excluding federal holidays, though some work areas require different hours including nights and weekends. The period of performance is 270 calendar days from notice to proceed, with a cost range between $1,000,000 to $2,000,000. Contractor employees must comply with St. Cloud VA Health Care System COVID-19 requirements when working on or traveling to VA locations. The related federal contract opportunity is solicitation number 36C26323B0003 for roof repair and replacement services issued by the Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 23.

View the file

Other files

Show all 17

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SCOPE OF WORK

CONSTRUCT “REPAIR/REPLACE ROOF SYSTEMS 2019”

PROJECT #656-19-314

ST CLOUD VA HEALTH CARE SYSTEM

A. PART I – GENERAL

1. Base Project: The Contractor shall furnish all labor, materials, tools and equipment required to repair and replace several roofing systems on campus. Including but not limited to Building 51, Building 50, Building 95, Building 48, Building 2, Building 1, Building 69, Building 37, Building 30 & Building 100. Roofing systems include but are not limited to shingles, flat roofs, insulation, fall protection, flashing, gutters, parapet walls, etc. All work completed in accordance with the specifications and contract drawings.

2. Deducts:

a. None

3. Work includes, but is not limited to:

a. Demolition: Bldg. 51, 50, 95, 48, 2, 1, 69, 37, 30 & 100.

b. Contractor shall remove from the VA site and dispose of all equipment and materials not scheduled to be reused.

c. Standard Contract working hours are 8am to 4:30pm Monday through Friday, excluding Federal Holidays unless otherwise specified in the drawings. Some work areas require different hours of work (including off hours, nights, weekends). Adhere to the drawings and specification for specific work area requirements.

d. Contractor shall furnish the COR with a schedule of approximate dates on which the

Contractor intends to accomplish work in each building.

B. Schedule:

Task Order Award D+0

Pre-Construction Conference D+14

Notice to Proceed (NTP) D+14

Construction Start D+28

Construction Completion D+284

C. Period of Performance (PoP)

The PoP for this project is 270 calendar days from the NTP.

D. Cost Range

The magnitude of construction for this project is between $1,000,000 and $2,000,000.

E. Requirements for Combating COVID-19

Contractor employees who work in or travel to VHA locations must comply with COVID-

19 requirements as established by the St Could VA Health Care System.

- - - E N D - - -

File details come from the government source that posted it. Updated .