SOW Maintain MSA Paint-VTS Smyrna.pdf
PDF 127 KB Posted
- Attached to
- MAINTAIN MUNITION STORAGE AREA VOLUNTEER TRAINING SITE Federal contract opportunity
- Solicitation number
- W50S9723B0002
- Issued by
- Department of the Army National Guard
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| W50S97-23-B-0002 Bid Open Roster_001.pdf | ||
| 1419 Abstract.pdf | ||
| W50S9723B0002 PRE-BID CONFERENCE AND SITE VISIT MINUTES.pdf | ||
| SOW Amenndment 1_SUSTAIN AMMO OFFICE CONTAINER PAINT-VTS SMYRNA 5.18.23.pdf | ||
| W50S97-23-B-0002 Maintain MSA Paint.pdf | ||
| BAR-RUST 235.pdf | ||
| Vicinity Map BKTZ232002.pdf | ||
| MSA Measurements.pdf | ||
| DEVPREP 88.pdf | ||
| DEVTHANE 379UVA info_ALL.pdf | ||
| BAR-RUST 235 MSDS.pdf | ||
| DEVPREP 88 MSDS.pdf |
Show all 12
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DEPARTMENT OF THE AIR FORCE
UNITED STATES AIR FORCE
118th Wing Tennessee Air National Guard
Berry Field Air National Guard Base, Nashville, TN
STATEMENT OF WORK
MAINTAIN MUNITION STORAGE AREA
VOLUNTEER TRAINING SITE
SMYRNA, TN.
BKTZ 232-002
10 February 2023
1.0 STATEMENT OF WORK
1.1. The contractor shall provide, unless otherwise noted, all management, tools, equipment, transportation, supervision, and labor necessary to clean, prepare all surfaces, prime, and paint the facilities as shown on the vicinity map of building 1008 (B1008) and building 1009 (B1009) located at Smyrna Volunteer Training Site (VTS) within negotiated period of performance. A
Vicinity map is attached for reference purposes. Contractor shall perform all work in accordance with this Statement of Work
(SOW). Contractor shall coordinate all work with the Contracting Officer and Civil Engineer office and is subject to the work schedule as stated in this document. Upon completion, the facility must be complete and usable for entire base populace. Period of performance will be thirty (30) days.
1.2. These requirements, together with the technical specifications, standards, specified in the contract documents, cover the requirements for all work associated with Maintain B1008 and B1009 located at Smyrna VTS. The following is a general description of the work involved:
1.1. Provide all material and services required to perform the following services:
1.1.1. Clean, prepare surfaces, prime and paint exterior sides and roof on building 1008 with dimensions of 40’ long by 20’ wide by 9’ tall and building 1009 with dimensions of 43’ long by 27’ wide by 9’ tall.
1.1.2. Furnish and apply Devprep 88 or similar product for surface preparation prior to priming and painting.
1.1.3. Furnish and install insulation primer with BAR-RUST 235 epoxy paint or equivalent
1.1.4. Furnish and install ICI Devoe DC349FR3501 gloss enamel or equivalent
1.1.5. Paint color to match existing
2.0 SPECIFICATIONS – B1008 and B1009 Repairs: Contractor SHALL comply with the following items:
2.1. Work shall be performed as described in this document.
2.1.1. Contractor will provide material for and perform all work to clean, prepare, prime and paint surfaces listed in this statement of work.
2.1.2. Coordinate with base authorities to obtain all passes required to enter the work site.
2.1.3. Contractor to complete Antiterrorism Level 1 Training and provide documentation of completion upon request.
2.2. MATERIALS:
2.2.1. Provide all services to clean, prepare, prime, and paint all B1008 and B1009 surfaces with anti-corrosion materials in accordance with the installation environmental requirements. MSDS sheets are attached for example products.
2.3. . INSTALLATION:
2.3.1. Installation shall meet or exceed all applicable federal, state and local requirements, referenced standards and conform to codes and ordinances of authorities having jurisdiction.
2.3.2. All installation shall be in accordance with manufacturer's published recommendations.
2.3.3. Contractor shall furnish all parts and assembly during construction.
2.4. PRODUCTS
2.4.1. GENERAL: All materials shall meet or exceed all applicable referenced standards, local requirements, and conform to codes and ordinances of authorities having jurisdiction to include UFC 3-190-06 Protective Coatings and Paints dated 1
March 2021. Contractor must provide submittals of materials to the Civil Engineer. (See Submittals Section Below.)
2.5. EXECUTION
2.5.1.1. Surface preparation, prime, and paint w o r k shall meet or exceed all applicable federal, state and local requirements, referenced standards and conform to codes and ordinances of authorities having jurisdiction to include UFC 3-190-06 Protective Coatings and Paints dated 1 March 2021.
2.5.1.2. Contractor shall furnish all parts and assembly during construction.
3.0 SPECIFICATIONS - Contractor shall comply with the following items:
3.1. PART 1 - GENERAL
3.1.1. SUMMARY: Perform all work to provide material, transport, and perform all work to clean, prepare all surfaces, prime and paint munitions storage facilities. Contractor must submit dust/debris plan and cleaning plan that describes measures to prevent the entrance of dust/debris in the areas where work is to be performed.
3.1.2. SUBMITTALS: Manufacturer’s product literature, data, and warranty information.
3.2. PRODUCTS
3.2.1. Substitutions: Requests for substitutions will be considered in accordance with provisions of Section 01 60 00 Product
Requirements.
When Submitting requests for substitution, provide complete product data specified above under Submittals, for each substitute product.
3.2.2. Acceptable Manufacturer:
The Sherwin-Williams Company
101 Prospect Avenue NW
Cleveland, OH 44115
Tel: (800) 321-8194 www.sherwin-williams.com
3.2.3. All materials shall meet or exceed all applicable referenced standards, local requirements, and conform to codes and ordinances of authorities having jurisdiction.
3.3. SUBMITTALS
3.3.1. Product Data: Manufacturer’s data sheets on each paint and coating product should include:
1. Product characteristics
2. Surface preparation instructions and recommendations
3. Primer requirements and finish specification
4. Storage and handling requirements and recommendations
5. Application methods
6. Cleanup Information
3.3.2. Selection Samples: Submit a complete set of color chips that represent the full range of manufacturer’s color samples available.
3.3.3. Coating Maintenance Manual: upon conclusion of the project, the contractor or paint manufacturer/supplier shall furnish a coating maintenance manual, such as Sherwin-Williams “Custodian Paint Manual” report or equal. Manual shall include an Area Summary with finish schedule. Area detail designating where each product/color/finish was used, product data pages, Safety Data Sheets, care and cleaning instructions, touch-up procedures, and color samples of each color and finish used.
3.4. EXECUTION
EXAMINATION
1. Do not begin application of coatings until substrates have been properly examined and prepared. Notify Contracting
Officer of unsatisfactory conditions before proceeding.
2. Proceed with work only after conditions have been corrected and approved by all parties otherwise application of coatings will be considered as an acceptance of surface conditions.
3. Previously Painted Surfaces: Verify that existing painted surfaces do not contain lead-based paints, notify Contracting
Officer immediately if lead based paints are encountered.
3.4.1. MATERIALS:
3.4.1.1. Devprep 88 Power wash solution
3.4.1.2. BAR-RUST 235 epoxy paint or similar
3.4.1.3. ICI Devoe DC349FR3501 gloss enamel or similar