SOW_EEPZ254664-B972 UOQ_06July2026.pdf

PDF 622 KB Posted

Attached to
B972 Renovate UOQ Community Commons
Solicitation number
FA302226R0024
Issued by

About this file

This is a Design-Build Statement of Work for the renovation of the Unaccompanied Officer's Quarters Commons (Building 972) at Columbus Air Force Base in Mississippi, with a project number EEPZ254664 and an effective date of June 6, 2026.

The scope encompasses comprehensive interior renovation and expansion of Building 972, including demolition of existing finishes, construction of new interior partition walls, installation of new doors and hardware, flooring systems (LVT plank and porcelain tile), ceiling systems (acoustic tile and drywall), electrical and lighting upgrades, HVAC modifications, plumbing work including new washer boxes and drinking fountains, fire sprinkler system modifications, and construction of a lean-to patio extension. Specific work areas include transforming the bulk storage room into a study room and game room with a kitchenette, renovating the laundry room with new washer stations and cabinetry, creating a new mail room with custom parcel storage shelving, and establishing a food kiosk room. The contractor must provide all design services including sealed professional drawings, photometric and psychrometric analyses, and Furniture, Fixtures, and Equipment (FFE) packages. Design submittals are required at 35%, 65%, 95%, and 100% completion stages with 30, 21, 21, and 14 days between submissions respectively. The total period of performance is 365 calendar days from Notice to Proceed. The government furnishes no equipment or materials; the contractor is fully responsible for all costs. The contractor must establish a Quality Control Plan, maintain a project office on-site, coordinate all submittals and material approvals within 21 days of 100% design approval, and provide one-year standard warranty on all work with extended warranties where specified. Key personnel requirements include a Contractor Project Manager with minimum five years' experience, a Site Superintendent with minimum five years' project superintendent experience, and a Quality Control Manager, all subject to government approval. Weekly progress meetings are mandatory, and the contractor must maintain detailed records, provide daily status reports, and submit progress reports twice monthly. The work must comply with applicable UFC standards, Columbus AFB Installation Facility Standards, NFPA codes, and all federal, state, and local regulations regarding safety, environmental protection, and hazardous materials management.

View the file

Other files

File Type Posted
RFIs_B972_FA302226R0024.pdf PDF
Sign-in Sheet_Site Visit.pdf PDF
AF Form 66_EEPZ254664-B972 UOQ.xlsx XLSX spreadsheet
Solicitation - FA302226R0024.pdf PDF
EAL Form 2026.pdf PDF
Contractors CUI Training Slides.pptx PPTX presentation
MFR CUI Contractor Training Acknowledgment July 2024.pdf PDF
Appendix A - Cost Breakdown.xlsx XLSX spreadsheet

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DESIGN-BUILD STATEMENT OF WORK

PROJECT NUMBER: EEPZ254664

RENOVATE UOQ COMMUNITY COMMONS, B972

COLUMBUS AFB, MISSISSIPPI

06 JULY 2026

COLUMBUS AFB, MS PROJECT NUMBER: EEPZ254664

RENOVATE UOQ COMMONS, B972

TABLE OF CONTENTS

NOMENCLATURE

1.1 ACRONYMS & ABBREVIATIONS

1.2 BASIC TERMS

DESCRIPTION OF PROJECT

2.1 SUMMARY

2.2 BACKGROUND

2.3 SCOPE OF PROJECT

2.4 GOVERNMENT FURNISHED EQUIPMENT/MATERIALS

2.5 SALVAGE

DESIGN REQUIREMENTS

3.1 SUMMARY

3.2 NATURE/EXTENT OF DESIGN

3.3 RESPONSIBILITY

3.4 DESIGN STANDARDS

3.5 DRAWINGS

3.6 DESIGN SUBMITTALS

3.7 DESIGN REVIEWS

3.8 CONFERENCES

ADMINISTRATION OF CONSTRUCTION

4.1 PERFORMANCE CAPABILITIES

4.2 COMMENCEMENT, PROSECUTION & COMPLETION

4.3 SCHEDULING

4.4 MANAGING

4.5 MATERIAL SUBMITTALS AND SHOP DRAWINGS

4.6 WORK BY GOVERNMENT

4.7 PRE-FINAL AND FINAL INSPECTION

4.8 WARRANTY

4.9 CONTRACTOR OFFICE

4.10 CONSTRUCTION SITES

4.11 CONSTRUCTION EQUIPMENT

4.12 AVAILABILITY OF UTILITY SERVICES AT JOB SITES

4.13 TEMPORARY UTILITIES

4.14 CONSTRUCTION SECURITY

QUALITY REQUIREMENTS

5.1 QUALITY CONTROL PLAN

5.2 TESTING AND INSPECTION SERVICES

5.3 MANUFACTURERS' FIELD SERVICES

5.4 PRODUCT REQUIREMENTS

5.5 CLOSEOUT PROCEDURES

SAFETY, HEALTH AND ENVIRONMENTAL PROTECTION

6.1 SAFETY AND HEALTH

6.2 GENERAL

6.3 HAZARDOUS MATERIAL

6.4 PROJECT EXECUTION

6.5 HAZARDOUS WASTE GENERATION/DISPOSAL

6.6 RECYCLING

6.7 PROHIBITED MATERIAL/ACTIONS

6.8 SPILLS AND CLEANUP

6.9 AIR CONSIDERATIONS

6.10 AFFIRMATIVE/GREEN PROCUREMENT/BIO-BASED/ENERGY

6.11 ASBESTOS/LEAD BASED PAINT

6.12 DRINKING WATER

6.13 EMS

6.14 HISTORICAL AND CULTURAL ARTIFACTS

6.15 NATURAL RESOURCES

6.16 NOISE

6.17 PESTICIDES/FERTILIZERS

6.18 STORM WATER PROTECTION

6.19 REQUEST FOR CE SERVICE/ACTION/CLEARANCE; AF FORMS 332/813

6.20 TANKS

6.21 LIMITS AND EXCEPTIONS

6.22 LEGAL AUTHORITY

NOMENCLATURE

1.1 ACRONYMS & ABBREVIATIONS

AF Air Force AFI Air Force Instruction AFM Air Force Manual AFUE Annual Fuel Utilization Efficiency AHU Air Handling Unit ATFP Anti-terrorism/Force Protection BCE Base Civil Engineer CAD Computer Assisted (or Aided) Design CAFB Columbus Air Force Base CDs Construction Documents CEPM Civil Engineering Project Manager CES Civil Engineering Squadron cfm cubic feet per minute CFR Code of Federal Regulations CHW Chilled Water CMI 14CES Construction Manager Inspector CO Contracting Officer COR Contracting Officer Representative Comm Communications CPM Contractor’s Project Manager CSS Contractor’s Site Superintendent DP Design Professional EMCS Energy Management & Control System EMI Electromagnetic Interference EPA Environmental Protection Agency ETL Engineering Technical Letter FAR Federal Acquisition Regulation FCU Fan Coil Unit FM Factory Mutual

FOD Foreign Object Debris fps feet per second

ft. foot or feet GFCI Government Furnished Contractor Installed gpm gallons per minute Hazmat Hazardous Materials HMW Hazardous Material or Waste HTW Hazardous and Toxic Waste HVAC Heating, Ventilating and Air Conditioning NEC National Electrical Code NTP Notice to Proceed O&M Operation and Maintenance OSP Originally Specified Product PDF Portable Document Format PE Professional Engineer Ph Phase (electrical) PM Project Manager psi pounds per square inch QCP Quality Control Plan RFP Request for Proposal SOW Statement of Work TI Technical Instruction TL Technical Letter TM Technical Manual UFC Unified Facilities Criteria UPS Uninterruptible Power Supply VAV Variable Air Volume V Volts W Watts

1.2 BASIC TERMS

The following table provides many of the meanings of words or phrases commonly used in this document.

All directives, informative, etc. statements are directed to the Contractor even if the term “contractor” or the contractor name is not included (e.g. “Provide a nail.” is equivalent to “The contractor shall provide a nail.” And “remove” is equivalent to “The Contractor shall remove”). Also, the Contractor shall ably and competently execute all directives including all directly or indirectly related tasks required to safely and legally perform the directive (e.g. “remove debris from CAFB” includes “safe and legal removal, disposal and obtaining all necessary permits, etc.)

A device, equipment or system referred to in the singular (e.g. “the pump”, or “the ___ system”) includes all related devices, elements and components required to Provide (see below in this table) that device, equipment, or system.

The Term Shall Mean (*=Shall in Addition Mean) Approved (by CAFB) *without waiving or suspending the full force of Contractor obligation to fulfill the CDs Aspect Distinct feature or element of the project CAFB Government contracting Authority on Columbus Air Force Base

Construction Documents

Drawings, specifications and their references including all Design Criteria and Design & Construction Requirements for this Project.

Contractor The Design-Build entity holding a current Government contract including all personnel in direct or indirect employ of same entity servicing same contract including partners, consultants, subcontractors, suppliers, and manufacturers.

Design Professional (Abbreviated: DP) Professionals including Architects, Engineers and Landscape Architects licensed to practice in one or more states of the U.S.

Day Calendar day unless noted otherwise.

DP Licensed Design Professional fully responsible for all professional design on this project.

Engineer DP For example (e.g.) One among many possible examples Government Columbus Air Force Base Contracting Officer Including [Includes] Including, but not limited to [Includes, but is not limited to] Provide Furnish and install complete, functional, and ready for use without added government action Provision Furnishing & installation complete, functional, and ready for use without added government action Will, must, shall & similar Terms are mandatory directives whereby ‘Term’ = ‘Term + to CAFB satisfaction’ Work The whole or any part, product, system or subsystem of this project Replace Demolish and dispose of existing element. Provide new element of equal or greater value.

Review Review and, if and when acceptable to the government, approval Subcontractor Subcontractor and all personnel in Subcontractor’s direct or indirect employ on any given

Project including suppliers and manufacturers

DESCRIPTION OF PROJECT

2.1 SUMMARY

The Contractor must provide all plant, labor, equipment, transportation, and tools required to complete the renovation of the Unaccompanied Officer’s Quarters Commons, B972. Work includes replacing interior finishes, upgrading electrical fixtures, demolishing and erecting interior partition walls and doors, mechanical and plumbing work, among others. Perform all work according to this Statement of Work (SOW), the Concept Plan, and all related AF requirements and other codes and references.

2.2 BACKGROUND

Building 972 serves as the central commons building for the residents of Buildings 971 and 973. This facility houses several centralized amenities including central laundry facilities, vending machines, a front office, centralized mechanical equipment, game areas, and large bulk storage. This project intends to transform the underutilized Bulk Storage Room into a large Study Room, Game Room, and Kitchenette. Work also includes a renovation of the existing laundry room to create a small storage closet and new Mail Room.

2.3 SCOPE OF PROJECT

2.3.1 Within the existing Laundry Room and existing Mail Room, demolish the interior finishes including all built in cabinetry, dryer exhaust ductwork and chases, porcelain tile flooring, walls and door surrounding existing mail room, acoustical drop ceilings, and architectural flourishes surrounding window and door frames. Demolish the windows separating the Laundry Room from the Corridor, demolish the existing door and frame to the Corridor, and prepare the wall for the new door location. Demolish the window and the portion of the exterior wall at and prepare the opening for the new door.

2.3.2 Within the existing Game Room, demolish the interior partition wall separating the space from the existing Bulk Storage Room. Demolish all architectural flourishes surrounding window and door frames within the existing Game Room and within the Corridor at the entrance to the existing Game Room. Demolish acoustical drop ceilings, flooring, and cove base within the existing Game Room. Demolish and cap HVAC ductwork.

2.3.3 Within the existing Bulk Storage Room, demolish all wooden storage cabinets and demolish the cove base.

Demolish the hydronic unit heaters, hot water piping, controls components, mounting components, and all cabling and conduit back to the electric panelboard. Demolish the exhaust fan, intake air louver, controls components, mounting components, and all cabling and conduit back to the electric panelboard. Demolish the portion of the exterior wall at the back of the room and prepare the opening for the new door.

2.3.4 Within the existing Conference Room, demolish the drinking fountain and water filter mounted along the wall. Install an aluminum utility access panel into the drywall at the location of the water and waste lines. Cap and abandon water and waste utilities.

2.3.5 Furnish and install all materials required to construct the new interior partition walls as shown in the Concept Drawings. Materials include, but are not limited to, metal framing, insulation, 5/8” drywall, wall surface preparation materials, and paint, to achieve a level 4 finish. The wall separating the Study Room and the Game Room is intended to be built up to the roof deck. This wall must also be filled 10ft high with insulation designed to deaden sound transfer between the two spaces.

2.3.6 Furnish and install new interior and exterior doors, metal doorframes, associated door hardware including mortise hinges, handles, mortise locksets, kickplates, automatic door closers, and any other necessary components accordingly:

• Two (2) interior 3’x7’ solid-core wood doors: Mail Room and Storage Closet

• Two (2) interior 6’x7’ solid-core half-lite wood double-doors: Laundry Room and Game Room

• One (1) exterior 3’x7’ insulated metal door: Mail Room

• One (1) exterior 6’x7’ aluminum stile commercial-storefront double-door: Game Room

2.3.7 Furnish and install all materials necessary to repair the existing interior walls. Areas requiring repair include, but are not limited to, water and moisture damage, holes, peels/cracks/chips, among others. Repair walls with materials that match existing. All repairs shall have an uninterrupted, flat wall surface transition with existing. This only applies to the following rooms:

• Mail Room

• Laundry Room

• Storage Closet

• Study Room

• Game Room

2.3.8 Paint new interior walls and existing interior walls. At a minimum, painting should include one (1) coat of primer, two (2) coats of paint, sanding and prepping of all surfaces, and placing drop cloths on the floor. This only applies to the following rooms:

• Mail Room

• Laundry Room

• Storage Closet

• Study Room

• Game Room

2.3.9 Lightly sand, clean, and pre-treat all existing exposed ceiling surfaces, roof framing members, and exposed piping/conduit within the new Game Room. Apply two (2) coats of paint to all prepped ceiling surfaces, roof framing, and exposed utility piping/conduit utilizing professional airless spray application to ensure uniform coverage in recessed and hard-to-reach areas.

2.3.10 Any repaired or replaced wall surfaces shall achieve level 4 finish. painting should include one (1) coat of primer, two (2) coats of paint, sanding and prepping of all surfaces, and placing drop cloths on the floor.

2.3.11 Install new ceiling systems throughout the project areas accordingly:

• Install heavy-duty, commercial-grade, 15/16” tee grid system. Provide minimum 12-gauge galvanized carbon steel hanger wire. Center the ceiling grid layout in each room to avoid narrow border tiles (borders must be greater than half a tile width where possible). Install the main runners and cross tees level and securely tied and braced. Secure hanger wires directly to the building's structural deck using approved fasteners. Hanger wires shall not be attached to pipes, conduit, or HVAC ductwork. Provide standard 2'x2' mineral fiber acoustic tegular tiles. This only applies to the following rooms:

o Laundry Room o Storage Closet o Study Room

• Install a complete drywall ceiling system utilizing 5/8" Type X gypsum board attached to a suspended metal framing grid. Work includes mudding, taping, and sanding to a seamless Level 4 finish, as well as coordinating all ceiling penetrations with mechanical, electrical, and plumbing (MEP) fixtures prior to final finishing. This only applies to the following rooms:

o Mail Room

• Reinstall and properly align all previously removed ceiling-mounted devices into the new ceilings.

Ensure all heavy ceiling-mounted devices are independently supported to the structural deck with their own hanger wires. Ensure all reinstalled devices fit flush with the new ceiling. Restore all electrical and low-voltage connections to the reinstalled ceiling devices. Replace any damaged flexible conduit or wiring discovered during the reinstallation process. Ensure all penetrations through the ceiling grid are finished with professional-grade trim kits.

2.3.12 Install new flooring systems throughout the project areas accordingly:

• Install commercial-grade LVT plank flooring (20 mil wear layer, 5mm thick) and associated installation materials. Work includes preparing the concrete subfloor, including leveling the floors in certain sections of the existing Laundry Room where LVT flooring is intended to be installed. Furnish and install new transition strips at locations with differing floor types. Furnish and install new 4” vinyl wall base. This only applies to the following rooms:

o Mail Room o Storage Closet o Study Room o Game Room

• Install commercial-grade 2' x 2' (24-inch by 24-inch) porcelain tile flooring, matching 6-inch sanitary tile cove base (including pre-formed inside and outside corners), and non-slip grout; work includes preparing the concrete subfloor, applying a waterproof/crack-isolation membrane, and sealing all finished grout joints. This only applies to the following rooms:

o Laundry Room

2.3.13 Demolish existing light fixtures and fixture whips back to the nearest junction box. Furnish and install new 2’x2’ flat panel LED light fixtures with new fixture whips. Provide all new material including, but not limited to, conduit, conductors, junction boxes, light switches, and dimmers to supply the new room layout with lighting. Recess mount the light fixtures in the new suspended ceiling system. Light fixtures shall comply with ASHRAE 90.1 power and lighting standards and with base, local, and national emergency lighting codes. Light fixtures shall have necessary seismic support. Place new light fixtures in locations necessary for optimal lighting qualities for essential daily functions and occupant comfort. Light fixtures shall be placed in locations that ensure minimal disruptions (i.e. relocating, demolishing, performance, etc.) to new and existing HVAC, fire detection and alarms, and electrical systems. Design, furnish, and install new ceiling occupancy sensors or wall switch sensors and accompanying power pack relays. Components shall be compatible and connect with the new lighting circuits and light switches of each room. Furnish and install emergency exit signs and egress lighting in accordance with NFPA 101. This only applies to the following rooms:

• Mail Room

• Laundry Room

• Storage Closet

• Study Room

• Game Room

2.3.14 Reuse existing communication components to the maximum extent possible. Extend the system as required for the new room layouts. Furnish all new components, except for conductors, required for extension.

Government communications personnel will install new conductors. New components shall be placed in locations that ensure minimal disruptions (e.g. relocating, demolishing, performance, etc.) to new and existing communication and electrical systems. Demolish and remove existing communication faceplates and jack.

Furnish and install new faceplates and jacks in existing locations. Components shall be compatible and reconnect with existing conductors. Contractor shall test and modify the system as required. This only applies to the following rooms:

• Mail Room

• Laundry Room

• Storage Closet

• Study Room

• Game Room

2.3.15 Reuse existing electrical components to the maximum extent possible. Extend the system as required for the new room layouts. Furnish all new components required for extension. New components shall be placed in locations that ensure minimal disruptions (e.g. relocating, demolishing, performance, etc.) to new and existing communication and electrical systems. Furnish and install new receptacles, outlets, switches, and faceplates in existing locations. Modified rooms shall receive duplex receptacles spaced appropriately. Components shall be compatible and reconnect with existing conductors. Contractor shall test and modify the system as required. This only applies to the following rooms:

• Mail Room

• Laundry Room

• Storage Closet

• Study Room

• Game Room

2.3.16 In the new Study Room, provide 2 dedicated 20amp circuits to locations above the ceiling indicated on the concept drawings. Terminate all conduit and conductors into a junction box concealed above the ceiling tiles, for future connection to user installed equipment. At each of these locations, also provide conduit for communications wiring, and terminate at a junction box concealed above the ceiling.

2.3.17 Relocate existing detectors, strobes and alarms, and mass notifications that obstruct locations of the new interior partition walls, suspended ceiling system, and electrical and HVAC components. Extend items to include the new room layout. Furnish and install items in accordance with NFPA 101 and Air Force Occupational Safety and Health Standards 91-118, reusing existing components to the maximum extent possible and reprogram fire control panels accordingly (if applicable). If these items are required in additional areas and/or existing items cannot be relocated to extend in these additional areas, furnish and install new detectors, strobes and alarms, and mass notifications to match those existing within the project’s construction area. If this occurs, furnish and install conduit, wiring, associated components, and anything else required. Primary and secondary power for the smoke detectors must be provided from the fire alarm control panel. The facility’s fire alarm system must always remain operational throughout this project.

2.3.18 Construct a kitchenette space within the back corner of the new Game Room to include rough-ins for one electric oven and cooktop, one 36” wide refrigerator, one dishwasher, one ice maker. Provide a stainless-steel undermount double compartment sink with manual two-handle faucet. Provide overhead microwave with built in exhaust ducted to the exterior. Provide these rough-ins and equipment along with lower cabinets along the wall as indicated in the concept drawings. Install a 10ft long bar top with lower cabinets where indicated in the concept drawings. All countertops shall be solid surface.

2.3.19 Construct and install custom parcel storage shelving within the Mail Room along the back 3 walls.

Provide wooden shelving boxes of varying dimensions along the upper walls and provide countertop space below. Block off the exterior windows from the interior of the room and cover utilizing the parcel shelving. All countertops shall be solid surface.

2.3.20 Demolish existing supply registers and grilles. Furnish and install all new white supply registers and return grilles. Install new sections of flexible ductwork where needed. New components shall be placed in locations that ensure minimal disruptions (e.g. relocating, demolishing, performance, etc.) to new and existing HVAC, fire detection and alarms, and electrical systems. Components shall be aluminum with a factory finish to match the new ceiling. This only applies to the following rooms:

• Mail Room

• Laundry Room

• Storage Closet

2.3.21 Install a new air handling unit to supply conditioned air into the new Study Room and Game Room.

Mount the air handling unit from the roof structure and locate above the Game Room. Utilize the chilled-water loop that enters the Mechanical Room for cooling. Utilize the existing boiler that serves building 972 and re-pipe the existing system to integrate the new air handling unit. The air handling unit shall have a preheat, cooling, and reheat coil. The air handling unit shall be constant volume, ducted into both the Study Room and Game Room.

Install temperature sensors in each room and average reading to control spaces. Provide roof cap for outside air.

Connect controls components to the existing facility wide EMCS system, for centralized control and monitoring.

2.3.22 Install a dedicated exhaust system within the new Mail Room. System shall run continuously and be balanced with the supply air to maintain a negative pressure.

2.3.23 Install new exhaust ductwork for the row of stacked drying machines within the laundry room. Utilize the existing exterior building wall and soffit penetrations. Ductwork can either be routed up and over the mailroom or concealed within lower cabinets of the mailroom. Modify the supply air ductwork from the existing HVAC system to provide supply air to the new layout for the Laundry Room, Mail Room, and Storage Closet.

2.3.24 Relocate natural gas lines for the new drying machine locations.

2.3.25 Within the Laundry Room, provide five (5) new recessed washer box with cold- and hot-water lines, shut-off valves for each water line, waste lines, and associated components required for fixture connection hookups.

Reuse existing plumbing components rough-ins, stubs, hot and cold-water lines, among others to the maximum extent

2.3.26 Within the Laundry Room, construct a 10ft long set of lower cabinets and a solid surface countertop.

Provide electric receptacles located at working height above table.

2.3.27 Relocate the complete food kiosk setup from the existing Laundry Room into the new Food Kiosk Room.

Center all kiosk modules along the wall of the demolished water fountain. Plug power into existing receptacles.

Install communications conduit and boxes in order to extend the network access point for the food kiosk into its new location. Provide a recess mounted 4 square box into the wall behind the food kiosk. Government personnel will pull and terminate the communications conductors. Prep and paint the entire wall directly behind the food kiosk.

2.3.28 Install six (6) new ABA compliant wall-mounted drinking fountains, filters, with bottle fillers at the locations indicated in the concept drawings. Furnish and install all new plumbing components as required to supply the fountains with complete and functional supply and waste plumbing systems. Provide single union valves at each drinking fountain. Install dedicated electric receptacles for the drinking fountains. Drinking fountains shall have chilled water capabilities. Repair and paint disturbed wall surfaces.

2.3.29 Modify the existing wet-pipe fire sprinkler systems for new wall layouts, new ceiling heights, and changes in room types.

2.3.30 Construct a lean-to style patio extension off the back side of the building as indicated in the concept drawings. Provide all metal construction and attach to the existing roof structure. Provide gutters, 4” concrete slab, exterior lighting, exterior power receptacles, and a wooden privacy fence along the side nearest electrical transformer. The patio dimensions are limited by the electric transformer on the left side, and the high-voltage buried electric lines and manholes located along the back and the right side. The maximum dimensions as drawn are 7ft deep by 40ft long.

2.3.31 Repair or replace disturbed building components impacted by construction actions of this project, match existing.

2.3.32 Provide a third-party certified testing, adjusting, and balancing (TAB) report for air and water flow of new HVAC equipment.

2.3.33 All door hardware must be Best 7-pin core compatible.

2.4 GOVERNMENT FURNISHED EQUIPMENT/MATERIALS

The Government will not furnish any equipment or materials for this project.

2.5 SALVAGE

The Government will not salvage anything for this project.

DESIGN REQUIREMENTS

3.1 SUMMARY

Design will consist of all site investigations and design work associated with preparing complete contract documents for this project as described in this SOW. The design documents must be developed from the functional and technical data contained in this SOW and include construction drawings, schedules, and design analysis. The Contractor will also be required to submit design documents for review as described in Paragraph 3.6 as well as final contract documents. The Contractor will be required to attend review and conference meetings as needed and requested by the Government.

3.2 NATURE/EXTENT OF DESIGN

This project requires the services of licensed Design Professionals. Professionally sealed drawings are required. Design/shop/coordination drawings, materials and equipment submittals, and final as-built record drawings are required for this project. Contractor must maintain accurate redline As-Builts throughout construction and must submit final As-Built drawings (with any of the redline changes updated on the drawings) upon project completion (see paragraph 4.7.2 for more information). Provide photometric analysis of all renovated lighting systems detailing compliance with all applicable codes and standards. See UFC 3-530-01 for details on the required photometric analysis. Photometric analysis is to be provided at the 35% design. Provide psychrometric/load design analysis of all renovated HVAC systems detailing the system’s compliance with all applicable codes and standards. See UFC 3-401-01 and UFC 3-410-01 for details on the required HVAC design analysis. Psychrometric/load design analysis is to be provided to the Government at the 35% design. Provide a FFE (Furniture, Fixtures, and Equipment) package for the renovated spaces as part of the design package.

3.3 RESPONSIBILITY

3.3.1 Contractor must perform all services, including travel, required to prepare and to furnish complete design documents consisting of drawings, analysis, and addenda as required, for the construction of the project in accordance with this SOW.

3.3.2 Record drawings (attached) are provided to the Contractor as a courtesy at the discretion of the Government, but their accuracy is not guaranteed. The Contractor is responsible for doing his own field investigations of the utilities, existing conditions, and other items in the area.

3.3.3 The Government may provide conceptual drawings to the Contractor, but their accuracy is not guaranteed. The Contractor must do his own field investigations of the utilities, existing conditions, and other items in the area and base his design accordingly.

3.3.4 Although the sizing and specification of equipment is suggested by this SOW, the Contractor is responsible for all remaining design and coordination to provide an acceptable final product that meets intent of this SOW. Contractor is responsible for ensuring constructability and code compliance.

3.3.5 The Contractor must immediately notify the contracting officer and secure any documents found with “Classified”, “Controlled Unclassified Information” (CUI) or personal information. The Contracting Officer will direct disposition of these documents.

3.4 DESIGN STANDARDS

All design and construction must be accomplished in accordance with applicable UFC’s, ETL’s, (UFC’s and ETL’s may be found on-line at www.wbdg.org.) local and national codes, Columbus AFB Installation Facility Standards (IFS) and all Appendices (Special Construction, Mechanical, and Electrical) and other guidance as modified by this SOW. The IFS document may be found at the following location:

https://www.wbdg.org/airforce/ifs/columbus-afb-ifs. The list of documents includes, but is not limited to, the latest editions of the following https://www.wbdg.org/airforce/ifs/columbus-afb-ifs

• UFC 1-200-01 DoD Building Code (General Building Requirements)

• UFC 1-200-02 High Performance and Sustainable Building Requirements

• UFC 3-401-01 Mechanical Engineering

• UFC 3-410-01 Heating, Ventilating, and Air Conditioning Systems

• UFC 3-410-02 Direct Digital Control for HVAC and Other Building Control Systems

• UFC 3-410-04 Industrial Ventilation

• UFC 3-501-01 Electrical Engineering

• UFC 3-520-01 Interior Electrical Systems

• UFC 3-530-01 Interior and Exterior Lighting Systems

• UFC 4-010-01 DoD Minimum Antiterrorism Standards for Buildings

• NFPA 101

• NFPA 72

• NEC 70

• ACGIH: Industrial Ventilation Manual

• Columbus AFB IFS

• CAFB Base Standards

The Contractor must submit a written request for approval of any deviations from the Government's established standards. No deviations from the Government's established standards will be permitted unless the Contracting Officer has issued prior written approval of such deviation.

3.5 DRAWINGS

Drawings under this Contract must be well prepared, complete, and accomplished in accordance with the best professional practice to show clearly and concisely the type and extent of work to be performed.

3.5.1 Drawings must be drawn to appropriate scales and dimensioned completely and accurately.

Lettering must be large enough to ensure legible half-size reduction and each dimensioned drawing must have a graphic scale. Use of fractions less than 1/8-inch for building dimensions must be avoided. Use standard building material indications and symbols for architectural items and for mechanical, electrical and plumbing equipment.

3.5.2 The Contractor will use paper sheets, 24" x 36". Each sheet will be numbered consecutively beginning with "1 of (x) Sheets" and continue to the last sheet. Number individual drawing sheets as follows:

Drawing Sheet Subject Notation Additional Sheets

Cover (Title Sheet, Map and Index)

T1 and following

Civil/Site Work C1 and following Demolition D1 and following Landscaping L1 and following Architectural A1 and following Structural S1 and following Plumbing P1 and following Mechanical M1 and following Electrical E1 and following Interior Furnishings I1 and following

Note: All sheet subjects above may not be necessary for this project

3.5.3 Drawings must be prepared electronically in both AutoCAD (Release 2020) and PDF formats.

3.6 DESIGN SUBMITTALS

3.6.1 DELIVERY: Deliver two (2) hard copies of each submittal and one (1) digital copy via DoD SAFE containing each drawing sheet in PDF file format directly to the CO, along with AF Form 3000. For uploading to DoD SAFE, the Contractor must request an upload link from the CO and then upload the files using the details in the subsequent email from DoD SAFE. For the final design submittal (As-Builts in most cases), the contractor is to provide, in addition to the hard copies and digital copies via DoD SAFE, containing the PDF file as well as the associated CAD files in AutoCAD (Release 2020) .dwg file format. Hard copy submittals must be delivered to:

14th Contracting Squadron 495 Harpe Blvd, Suite 293 Columbus, MS 39710

3.6.2 SUBMITALS AT INTERMEDIATE STAGES OF DESIGN COMPLETION: To facilitate review and feedback throughout the design process, designs are submitted at various stages of completion as follows:

1. 35% DESIGN SUBMITTAL: Contractor must submit 35% design documents within 30 days after Notice to Proceed (NTP). The 35% design must include complete and thorough detailing to leave no question as to how demolition and construction is intended. All design documents must be clearly annotated (in both title block and revision block of drawings) with “35% REVIEW SET” and the date.

2. 65% DESIGN SUBMITTAL: Contractor must submit 65% design documents within 21 days after receipt of the “Approved” 35% design. The 65% design must include complete and thorough detailing to leave no question as to how demolition and construction is intended. All design documents must be clearly annotated (in both title block and revision block of drawings) with “65% REVIEW SET” and the date.

3. 95% DESIGN SUBMITTAL: Contractor must submit 95% design documents within 21 days after receipt of the “Approved” 65% design. The 95% design (essentially complete design and drawings, pending review and acceptance by Government as the 100% APPROVED CONSTRUCTION SET) must include complete and thorough detailing to leave no question as to how assembly is intended. All design documents must be clearly annotated (in both title block and revision block of drawings) with “95% REVIEW SET” and the date.

4. 100% DESIGN/APPROVED CONSTRUCTION SET: Contractor must submit the 100% DESIGN APPROVED CONSTRUCTION SET within 14 days after Contractor receipt of the “Approved” 95% design. The construction set must incorporate and/or address any Government comments on the 95% design and should leave no question to how demolition and construction will be done. If professionally stamped and sealed drawings are required for this project (paragraph 3.2), the approved construction set must include all stamped drawings. All final design documents must be clearly annotated (in both title block and revision block of drawings) with “APPROVED CONSTRUCTION SET” and the date.

5. For each holiday or extraordinary event in a submittal period, increase the required days for submittal by one day for each day in the event. Deliver no submittals within (before or after): one week of Thanksgiving; two weeks of Christmas; or one week of New Year’s Day. Extraordinary Events include: unscheduled holidays for base personnel;

base-wide training exercises; etc. The Government may prohibit work during such events.

3.6.3 PARTIAL SUBMISSIONS: Partial submissions normally will not be accepted. However, under some circumstances, to expedite project execution, the Government may accept design/shop drawings or material submittals for major elements or long-lead-time equipment for review and approvals prior to 95% design submittal. Government approval of such items does not relieve the Contractor of his responsibility to ensure a complete, constructible, code-compliant design.

3.6.4 CONSTRUCTION PRIOR TO 100% DESIGN: Construction may not commence until Government approves the 100% design. Exception: To expedite contract completion, Contractor may petition CO for an Interim Notice to Proceed with specific elements of construction. Government review does not constitute approval or acceptance of any variations from this SOW, the Contractor’s Proposal, or the Contract unless authorized in writing by the CO. The Interim Notice to Proceed, if exercised, will in no way mitigate the responsibility of the Contractor to provide a complete, constructible, code-compliant design.

All drawings, specifications, design analyses and other project materials become the property of the Government.

3.7 DESIGN REVIEWS

3.7.1 DESIGN PHASE REVIEWS: Government review of each XX% design submittal (where XX = 95 or 100 as required per 3.6.2) will require up to fourteen (14) days after Government receipt. The Government will determine the sufficiency of each XX% design submittal as follows:

6. Approved as Submitted. If design is sufficient to proceed without correction to the next phase submittal, one (1) copy of AF FORM 3000 marked "Approved" will be returned to the Contractor. Contractor must advance to the next stage design submittal.

7. Approved - Except as Noted. Design submittals that have only minor errors or deficiencies will be marked in red to indicate necessary corrections. Marked materials, along with one (1) copy of AF FORM 3000 indicating "Approved - Except as Noted" will be returned to the Contractor. Contractor must revise the design documents, making the necessary corrections, and advance to the next stage design submittal.

8. Disapproved. Design submittals that are incomplete or require more than minor corrections will be marked in red to indicate necessary corrections. Marked materials, along with one (1) copy of AF FORM 3000 marked “Disapproved” will be returned to the Contractor. Contractor must revise the design documents, making the necessary corrections, and re-submit as the current stage “XX% Design – 2nd (or subsequent) Submittal”.

9. Disapproved – Major Deficiency. Examples include, but are not limited to, design submittals that fall significantly short of indicated level of completion, grossly deviate from or misinterpret the SOW, or contain errors of a nature or quantity that indicate failure of Contractor to review submittals for completeness, correctness, and coordination between trades. For such submittals, the Government will not complete a comprehensive review or provide an exhaustive list of needed corrections. Rather, one (1) copy of AF FORM 3000 marked “Disapproved – Major Deficiency” along with general reason(s) for disapproval will be returned to the contractor. The CO will issue a written warning to the Contractor that any subsequent grossly incorrect/incomplete submittals constitute evidence of inability to complete the project and may result in declaring the Contractor “In Default.” Contractor must correct deficiencies and resubmit as current stage “XX% Design – 2nd (or subsequent) Submittal”.

3.7.2 100% DESIGN REVIEW: The Government will have fourteen (14) days to verify that all review comments have been addressed and no unapproved changes have been made. Upon Government approval of the 100% design documents, the Contractor may begin construction.

3.7.3 IMPACT OF REVIEW ON PERIOD OF PERFORMANCE: Contract completion time includes time for Government review of drawings, specifications, and material submittals. Unless otherwise noted, the Government will use no more than 14 calendar days for review of each design submittal and each subsequent re-submittal of “Disapproved” submittals (paragraph 3.7.1, c or d). There will be no increase in the period of performance for review of re-submittals.

3.7.4 RESPONSE TO REVIEW COMMENTS: The Contractor is required to respond to all review comments and submit their annotated comments as a design analysis appendix in the subsequent design submittal. All comments must either be accepted and incorporated into the next design submittal or satisfactorily rebutted.

3.7.5 DESIGN ACCOUNTABILITY: The Contractor is solely responsible for accurately designing and constructing everything necessary to provide a fully functional product. Government approval of any design or design-related submittal does not waive or remove full liability from the Contractor to provide a design, facility, or final product that meets the intent of this SOW, performs as intended, and adheres to all applicable codes and standards.

3.8 CONFERENCES

3.8.1 PRECONSTRUCTION CONFERENCE: A Preconstruction Conference (Pre-Con) will be held at the Contracting Office as indicated.

3.8.2 COORDINATION/REVIEW CONFERENCES: Coordination/review conferences may be held from time to time as required. The Contractor may request such conferences when it is deemed necessary by both parties to clarify the work or expedite the preparation of plans, specifications or construction.

3.8.3 REVIEW/CONFERENCE MINUTES: The Contractor will be responsible for making memoranda of record of any conversations and minutes of any meeting with Government personnel concerning this project and forward one copy of these memoranda/minutes to each party concerned and one copy to the Contracting Officer within seven (7) days. The final version of the meeting minutes will be approved and filed at the CO’s discretion. Each copy will be numbered consecutively and chronologically.

3.8.4 MEETING LOCATIONS: Meetings will be held in person at Columbus Air Force Base.

Contractor transportation costs for attending all conferences/reviews and meetings must be included in the Contractor’s Proposal. There will be no teleconferences unless permitted otherwise by the Contracting Officer.

End of Design Requirements

ADMINISTRATION OF CONSTRUCTION

4.1 PERFORMANCE CAPABILITIES

4.1.1 One week prior to the start of work under this contract, Contractor must submit in writing to the CO for review and possible approval the names and credentials of Contractor Project Manager, Contractor Site Superintendent, and Quality Control Manager. Subsequent proposed changes of approved personnel must be submitted in writing to and receive prior approval from the CO before working on the project. Each of these personnel may upon CO approval hold additional onsite duties which must not diminish their required performance. Contractor must demonstrate to the Government’s satisfaction that proposed personnel exceed education, technical and experience levels of personnel described in this Contract including the following:

10. Contractor Project Manager (CPM) - Provide management of the prime contract to include subcontract purchasing and administration, review of material submittals and shop drawings. CPM must have full authority to develop cost proposals, negotiate with Government and subcontractors, sign awards and modifications, supervise project superintendents, attend weekly CO/CE/PM Contractor status meetings as well as pre-performance site visits, pre-final and final inspections. The CPM must have a minimum of 5 years previous experience as primary contract manager or equivalent experience as a primary estimator and negotiator with a contracting firm engaged in similar multi-discipline commercial construction projects. CPM must also have not less than 5 years’ experience managing subcontractors.

11. Contractor Site Superintendent (CSS) - Provide on-site construction superintendent(s) to oversee all work under this contract. Site supervision must be daily (constant throughout each day) and includes submission of detailed weekly progress reports, scheduling and coordination of subcontractors and material suppliers, and attendance at all construction progress meetings, CO site visits, and pre-final and final inspections. Superintendents must have a minimum of 5 years previous experience as a project superintendent (exclusive of time employed as a tradesman or working foreman) for a general contracting firm overseeing one or more multi-discipline commercial construction projects. The superintendent must be available within 15 minutes during all normal working hours, except for such incidental errands as required by his duties. The superintendent must be responsible for the proper coordination and timeliness of the work, and for the proper workmanship of all trades; therefore, his absence from the project site without a suitable substitute Contractor representative must be considered as damaging to the Government.

12. Quality Control Manager (QCM) - Provide quality control management for the project.

QCM must continually (constant throughout each day) ensure full compliance with all safety requirements, verification that work and materials in place and stored on site are in accordance with the approved construction documents, shop drawings and material submittals. QCM must submit daily status reports recording activities at each project site, prepare and coordinate material submittal sheets and shop drawing submittals, schedule and coordinate testing procedures, prepare quality control reports for construction progress and other required meetings, and attend all pre-final and final inspections. QCM must have a minimum of five years’ experience in Quality Control Management of multidiscipline construction projects.

4.1.2 Contractor must have additional personnel including management, technical, service, labor or subcontractor, available as necessary to fulfill all construction contract requirements. The Government may restrict employment under this contract of any personnel identified as a potential threat to the health, safety, security, well-being, or operational mission of CAFB and its population.

4.1.3 Contractor must be available by telephone 24-hours a day, 7-days a week and upon 15 minutes’ notice during normal duty hours and 30 minutes’ notice during non-duty hours must meet the CO at a CO designated location.

4.2 COMMENCEMENT, PROSECUTION & COMPLETION

4.2.1 Contractor must start design and various construction phases at times specified by CO issued Notice(s) to Proceed (NTP), prosecute the work, and complete the entire work within the Period of Performance.

4.2.2 Contractor must provide a Submittal Log (Schedule of Material Submittals), Progress Schedules, Progress reports and Status Reports.

13. Submittal Log: See Material Submittals and Shop Drawings below.

14. Progress Schedule: (AF Form 3064) Submit the progress schedule to the CO within 10 days after contract award, unless otherwise specified by the CO. Subdivide total schedule into individual work items. Show completed work percentages at the end of each two-week reporting period. Progress schedule should only be resubmitted during the project duration if there’s an issue with Period of Performance or if deemed necessary by the CO as described in 4.2.2.3.

15. Progress Reports: (AF Form 3065) Submit Project Progress reports to the CO minimum twice per month on the first working day of each month and again on the 15th. Describe the percentage of work completed during the report period. If behind schedule, report in writing what actions will be taken to regain the schedule. If the CO agrees to add days to the contract performance period, Contractor must provide an amended schedule.

16. Status Reports: Submit to the CO daily reports of the work status. In each report, list the tasks accomplished for that day, any deliveries received, equipment currently on-site, weather conditions for that day, and number of personnel working on each area listed by trade. Photos may be included.

4.2.3 Period of Performance: Is the period between the issuance of the NTP and the time all construction is complete, including all punch list items, and final inspection is approved by the Government. The total Period of Performance for this project is 365 days.

4.2.4 Contract Completion: At contract conclusion, vacate all work areas, including: Contractor offices, storage and staging areas, and individual work sites. Restore these areas to their condition prior to Contractor occupancy not more than 14 days from the earlier of: approved final inspection or CO notification.

4.2.5 Coordination and Project Conditions: Schedule and manage submittals, materials, products, equipment, manpower, etc. to control all parts of the work efficiently and orderly. Verify compatibility of existing building utilities with new operating equipment. Coordinate required space, supports, and mechanical and electrical work shown (even if via diagrams) on Drawings. Follow routing shown for pipes, ducts, and conduit; place runs parallel with building lines. Use space efficiently to maximize maintenance and for repair accessibility for other systems. Conceal wiring behind finish surfaces and locate fixtures and outlets with finish elements. Coordinate pre-Substantial Completion clean-up in separate building areas.

After CAFB occupancy, coordinate site access to correct defective (or non-compliant with CDs) to minimize disruption of Government activities.

4.2.6 Cutting and Patching: Only employ skilled and experienced workers to cut and patch. Report in writing to the CO wherever cutting and patching might degrade: safety; appearance, structure, weatherproofing, O&M, or separate Contractor or government construction. Prevent damage to existing or new construction and provide proper surfaces to receive patching and finishing. Match new finishes to existing adjacent surfaces unless noted otherwise. Maintain integrity of existing walls, ceilings, or floors;

completely seal voids. Refinish entire assemblies and continuous surfaces to nearest intersection. Cut, fit, and patch where CDs require e.g.: mechanical and electrical penetrations; integration of new components with one another or with existing construction; removal and replacement of defective and non-conforming elements; remove samples for testing.

4.2.7 Special Procedures: Employ skilled and experienced tradespersons to perform alteration work.

Remove debris from open work areas and concealed spaces. Remove, cut, and patch to minimize damage and provide means of restoring products and finishes to original or specified condition. If a change of plane of 1/4 inch or more is discovered, submit recommendation to the CO for providing a smooth transition.

Patch or replace portions of existing surfaces which are damaged or showing other imperfections. Finish surfaces as specified.

4.2.8 Airfield Waiver: Airfield waiver is not required for this project.

4.2.9 Welding Permits: No cutting or welding will be permitted without first obtaining a permit issued by the Base Fire Department. All fire and safety regulations are to be followed stringently. Contractor’s failure to obtain a cutting or welding permit may not be reason for extending the contract performance period. Any damages incurred while welding work is done without a permit are the responsibility of Contractor.

4.3 SCHEDULING

4.3.1 Contractor must coordinate all work schedules and manage progress of work with the CO and CEPM prior to start of work. Weekly progress meetings will be conducted with the CO, CMI, and Contractor’s team which may require corporate management representation at CAFB discretion.

4.3.2 Contractor must schedule all work. Performance periods must not be established or extended to accommodate insufficient personnel resources. Contractor will not move crews on and off the project while making minimal progress on concurrent projects as this must be construed as having an inadequate work force to fulfill the contract requirements. Contractor’s CPM and CSS must not change more than two (2) times during project construction as this would demonstrate an inadequate management force to fulfill contract requirements.

4.3.3 Before construction begins, Contractor must agree with CO on a sequence of procedures; means of access to…