SoW.pdf

PDF 125 KB Posted

Attached to
FY25 Airfield Rubber Removal and Painting
Solicitation number
FA466125Q0003
Issued by

About this file

This Statement of Work dated September 12, 2024 outlines requirements for rubber removal and airfield markings at Dyess AFB under project FNWZ 24-0129. The work involves rubber removal and painting of airfield markings on runways 16/34 and 164/344 (Tye LZ), with specifications detailed in drawings C1 through C7.

The project must be completed in two phases over 210 calendar days, with Phase 1 involving rubber removal at both runways during weekends only, and Phase 2 requiring rubber removal at runway 16/34 to be completed 6 months after Phase 1. The contractor must coordinate with the Contracting Officer and Airfield Manager 45 days in advance for approved weekend work periods. Due to the location being in a controlled airfield area, access requires coordination with the Contracting Officer, Airfield Management, and 7 CES. Tower contact and radio communication with Airfield Management are required during work in controlled movement areas.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FOR OFFICIAL USE ONLY

Statement of Work September 12, 2024

Project #: _FNWZ 24-0129 Rubber Removal & Airfield Markings

Civil Engineering Point of Contact (Name/phone #): Davis Matschek 325-696-5620__

Scope of Work: 1- Perform rubber removal as indicated in attached drawings C1 through C7 and per specifications at runways 16/34 and 164/344. 2- Paint airfield markings as indicated in the attached contract drawings C1 through C7 and specifications.

Phasing Requirements: This contract shall be performed in several phases on coordination with the Contracting Officer (CO), Airfield Management (AM), and Civil Engineering (CE). Access to all work areas is limited by ongoing airfield operations. Contractor shall coordinate work at each location with the Airfield Manager. Rubber removal shall be completed in two phases:

Phase 1: Perform rubber removal at runways 16/34 and 164/344 (Tye LZ); weekend work only Phase 2: Perform rubber removal at runway 16/34, must be completed 6-months after the completion of Phase 1.

Special Requirements/Security/Submittals: Contractor shall coordinate with the Contracting Officer and Airfield Manager, at least 45 days prior, for approved weekends when rubber removal and markings will be allowed.

Project is in a General/Controlled Area: Work under this contract is located on the airfield.

Access to it is subject to operations requirements and only after it has been coordinated with the CO in conjunction with the AM and 7 CES. Airfield Markings - Contact with the Tower is required during work in controlled movements areas. Contractor to request radio from Airfield Management.

Performance Time/Desired Project Completion Date: 210 calendar days